Http://nodal.ercot.com 1 Market Trials Phase 3.0 RTM / LFC, Outage Scheduling, CRR Kick Off Meeting...

74
http://nodal.ercot.com 1 Market Trials Phase 3.0 RTM / LFC, Outage Scheduling, CRR Kick Off Meeting January 28, 2010

Transcript of Http://nodal.ercot.com 1 Market Trials Phase 3.0 RTM / LFC, Outage Scheduling, CRR Kick Off Meeting...

http://nodal.ercot.com 1

Market Trials Phase 3.0 RTM / LFC, Outage Scheduling, CRR

Kick Off Meeting

January 28, 2010

http://nodal.ercot.com 2

Agenda

• Nodal Phase 3.0 Kick-Off

– Market Trials 2.1 Connectivity Testing – How’d We Do?

– Phase 3.0 Objective and Scope

– Nodal Production Environment • ERCOT Support

• Access / URLs

• Common Information Model / Data Set

• Known Issues

– Communications Plan / Issue Management

– Reports / MIS Review• Phase 3.0 Handbook Review

– Outage Scheduler– Real Time Market / LFC

• Nodal Telemetry Outreach Update• Handbook Review

– Congestion Revenue Rights

QSE Qualification Call Overview: Market Trials 2010 Roadmap

http://nodal.ercot.com 3

Market Trials 2.1 Connectivity Testing – How’d We Do?

• QSE MMS Submission Qualification Statistics:– 160 / 292 Total QSEs Qualified as of 6:30 pm 1/27/2010

• 64 / 114 QSEs w/ Resources (includes sub-QSEs)– 78.77% of generation currently qualified– MPs unqualified by today will continue to work with ERCOT Account Managers and

the Market Trials support team– Note that the scorecard will not be updated until 2/10/2010 – there is still time to

prevent going amber / red on the qualification metric

• CRRAH Qualification Statistics– 41 / 80 Total registered CRRAHs Qualified as of 6:30 pm 1/27/2010

• Common Issues– Listener set ups– Connectivity (e.g. security)– MPs implementing new Certifying Authorities (CAs) not in the ERCOT supported list

• Note that ERCOT is now in a position to add CAs on a by request basis– Incorrect role assignments

http://nodal.ercot.com 4

http://nodal.ercot.com 5

Phase 3.0 Testing Objective and Scope

• Scope: Phase 3 of Market Trials will exercise the following functionality in the NPROD, Market facing environment:– SCED inputs and outputs– Outage Scheduling (OS) submittals (for purposes of qualification)– CRR auction, trading and invoicing– LFC generator tests– RTM / LFC / CRR / OS related reports

• Objective of Market Trials Phase 3:– LMPs: Establish reasonable LMPs and start 6 Month LMP posting– Qualify QSEs and TSPs on their ability to submit, update and query

outages – Begin CRR monthly auctions and invoicing– Qualify QSEs ability to move generation based on ERCOT

instructions (individual generator LFC tests)– Post reports to MIS related to in scope activities

http://nodal.ercot.com 6

Phase 3.0 Testing Objective and Scope

• Scope of Phase 3.0 MMS (Market Management System) will be limited to the following transactions and MMS Phase 1 validations (which are detailed in the Explanation of Market Submission Items document found at http://nodal.ercot.com/readiness/mt21/index.html):– Real-Time

• Current Operating Plan• Energy Offer Curve• Output Schedules• Incremental / Decremental Offer Curves• getReports• See RTM / LFC handbook for available market information queries

• Additionally, ERCOT will also support the following transactions in MMS in support of continued qualification activities– Day-Ahead / Other submission

• Three Part Offers• Ancillary Service Offers• Energy-only Offers and Bids• Trades (Energy, Ancillary Service, Capacity)• Self-Arranged Ancillary Services• CRR Offers• PTP Obligation Bids• Self Schedules• Resource Parameters

Phase 3.0 Testing Objective and Scope

• Outage Scheduler will support the following transaction submittals:TSP

• Planned• Remedial Switching Action• Forced• Maintenance 1• Maintenance 2• Maintenance 3• Simple• Group

QSE• Planned • Forced• Maintenance 1• Maintenance 2• Maintenance 3

• CRR will support all transaction submittal types for bidding and trading

http://nodal.ercot.com 7

http://nodal.ercot.com 8

Phase 3.0 Connectivity Testing Objective and Scope (continued)

• Telemetry Support

– Focused Input Testing Windows have ceased as of 1/4/2010

– Telemetry will be reviewed on a daily basis for missing points and data quality

– A periodic dashboard will be posted to the ERCOT Nodal Readiness Center under Real Time Market / LFC for point in time telemetry issues http://nodal.ercot.com/readiness/markettrials/rtm/index.html

http://nodal.ercot.com 9

Release 3.0 Connectivity Testing Objective and Scope (continued)

• Out of Scope (not limited to the following) :

– Functionality not related to in-scope Market Trials activities• Examples of out of scope features

– Running Day Ahead Market (DAM)

– Reports not listed in the Market Trials Handbooks under Phase 3

– Areas of MIS not related to Phase 3 scope as defined in the Market Trials Handbooks• Although other systems and features may be included in the release for this phase, ERCOT

continues to perform testing on these and will not be supported• Additionally, ERCOT will continue performance testing

– There may still be performance related issues– ERCOT will communicate these via the Friday Market Calls– If necessary (frequently occurring issues) a market notice will be sent to the Nodal PMs

contact list

– Settlements (with the exception of CRR Auction invoices)– Examples of data that will be stubbed in and not yet integrated

• Credit • Verifiable costs• Some registration data not impacting Phase 3 scope• Dynamically Scheduled Resources (DSR) and AS Qualification status

http://nodal.ercot.com 10

Nodal Production Environment - ERCOT Support

• Nodal Production Environment Status– Phase 3 is the second major release of the Nodal Production Environment– ERCOT continues to perform Integration and Performance Testing– It is expected that issues will be found during Phase 3 by both, ERCOT and

Market Participants

• Supported days / hours for Market Trials Phase 3– The Nodal Production environment is still considered a test environment,

consequently it will be necessary to bring the environment down periodically to perform maintenance and patch releases to the software

– The following bullets details the supported days and hours ERCOT is actively supporting and monitoring the environment

– The Nodal Production environment will remain accessible outside of these support windows, however there is no guarantee of system stability or accessibility

– February 2010• ALL SYSTEMS: Monday through Friday from 8:00 am to 6:00 pm

– March 2010• CRR, Outage Scheduler, MMS (as it related to market submissions): Monday through Friday

from 8:00 am to 6:00 pm• Telemetry / EMS, SCED: 7x24

http://nodal.ercot.com 11

Nodal Production Environment - ERCOT Support

• Outage and Restoration

– In the event of an outage or significant degradation in performance during an active support window, ERCOT will send a market notice followed by periodic status updates as they are available.

– The expected restoration time for outages will be on a ‘as soon as possible’ basis

Note that planned environment outages outside the active support window will be communicated as appropriate on a weekly basis during the Friday Market Participant calls

http://nodal.ercot.com 12

Nodal Production Environment – Access / Location

• Following are the URL’s to be used during Phase 3– Market Information System (MIS)

https://mis.ercot.com/pps/tibco/mis – Market Manager User Interface:

https://mis.ercot.com/pps/tibco/mis/Pages/Applications/Applications Navigate to the Applications Link and select “Market Manager” from the ERCOT Applications Portlet

– Outage Schedulerhttps://mis.ercot.com/pps/tibco/mis/Pages/Applications/Applications Navigate to the Applications Link and select “Outage Scheduler” from the ERCOT Applications Portlet

– Web Services Endpoint URL:https://misapi.ercot.com/2007-08/Nodal/eEDS/EWS

Nodal Production Environment – Access / Location

• Authentication– Users that currently have an ERCOT production digital certificate, will

continue to use this certificate in the Nodal Production Environment – Users that do not have an ERCOT production digital certificate should

request one from their company’s USA (User Security Administrator)– New Market Participants will obtain certificates via the ERCOT registration

process

• Authorization (Roles)– Nodal Roles are currently available in the production Market Participant

Identity Management (MPIM) system– Market Participant USAs must assign the appropriate role to users that will

be testing in the Nodal Production environment– See next slide for a list of Nodal Roles

http://nodal.ercot.com 13

Nodal Production Environment – Access / Location

• Authorization (Roles) – continued– Note that we will discuss which roles will apply to each functional area during the

handbook discussion– Note that certificates to be used for the Web Services Interface need to have the API

Certificate checkbox checkedDisplayName Description

CRR_EXTRACTS Views CRR certified Extracts

MMS Reviewer Reviews market submissions on behalf of the QSE

MMS Trader Creates and reviews market submissions on behalf of the QSE

MP CRR Account HolderParticipates in CRR market activities; including nominating, buying, sell ing or trading of CRRs

MP_SERVICEREQUESTS Create/Find eService Service Requests

MP_CRR_Credit_Manager Assigns credit l imit to upcoming CRR market activities

MP_SETTLEMENTS Create/Find eService Service Requests and Disputes

NMMS Planning User Submits modifies and views any PMCRs for the TSP

NMMS Remote Users Submits, modifies and views any NOMCRs for the TSP

QSE_EXTRACTS Views QSE certified Extracts

Qualified Scheduling Entity

Submits, modifies any Outage of the Resource Category for which the Requestor's Organization is the Resource's master owner; can view any Outage of the Resource Category for which the Requestor's Organization is at least a partial owner but not the Master

Qualified Scheduling Entity Read Only Views Outages of the Resource Category for which the Requestor's Organization is the Resource's master owner of partial owner.

REAL TIME OPERATIONS MAPSituation Awareness FERC and NERC Allows the user to view a snapshot of the Grid.

TDSP_EXTRACTS Views TSP certified Extracts

Transmission Service ProviderSubmits, modifies, and views any Outage of the Transmission Category the requestor's organization submits. Can view any Outage.

Transmission Service Provider Read Only Views any Outage

RTDMS_M_Phasor This role will allow TSPs to access an application through Citrix

http://nodal.ercot.com 15

Nodal Production Environment – Common Information Model / Data Set

• Network Model / Common Information Model (CIM) Loads– ERCOT starts Phase 3.0 with the CIM loaded on

1/22/2010– This version of the CIM will reflect data as of 1/6/2010– ERCOT currently has ~3 weeks verification process when

a new CIM is “cut”– The next scheduled CIM model will be on 2/5/2010– The 2/5/2010 version of the CIM will reflect data as of

1/20/2010– ERCOT is working on implementing a schedule that is in

lock step with zonal database loads. Updates on this will be shared at the weekly

– Settlement Points and Market Participant Short Names extracted from the 1/22/2010 CIM have been posted to the Phase 3 readiness Market Trials front page: http://nodal.ercot.com/readiness/markettrials/index.html

http://nodal.ercot.com 16

Communications Plan / Issue Management

• Weekly Conference Calls: – ERCOT’s primary tool for communicating updates, status and general

information will occur on the weekly Market Trials Market Calls.– Note that there will be multiple calls, each focused on a specific functional

area:– Calls scheduled for Phase 3 are:

• Real Time Market / LFC: Fridays at 9 am – 10 amhttp://www.ercot.com/committees/nodal/mt/rtm/index

• Congestion Revenue Rights: Fridays 10:30 am – 11:30 amhttp://www.ercot.com/committees/nodal/mt/crr/index

• Outage Scheduler: Thursdays 10:00 am – 11:00 amhttp://www.ercot.com/committees/nodal/mt/os/index

– Note for QSEs still working on qualification, the last QSE Qualification call will take place on 1/29/2010 (tomorrow)

• ERCOT will continue to work with those that have not completed qualifications on an individual basis.

• The Qualification dashboard will continue to be posted to the readiness center at: http://nodal.ercot.com/readiness/markettrials/connectivity/index.html

– ERCOT will also be hold an additional call every Monday from 10am – 11am open to all Market Participants

• We will briefly review that week’s coming activities• The remainder of the call will be an open forum for all MPs to ask questions or raise

concerns

Communications Plan / Issue Management

• Emails / Phone Calls to Individual Market Participants: – All general communications from ERCOT regarding Market Participant –

specific information will be routed through your Nodal Project Manager as identified in the “Nodal Contact Declaration Form”

– For specific topics, we will contact the individual for that area (e.g. ICCP issue reaches out to the ICCP contact) as identified in the “Nodal Contact Declaration Form”

– A copy of that spreadsheet may be found at: http://nodal.ercot.com/readiness/rq/documents/index.html

– If you wish to view what contacts are currently on file, please send an email to [email protected] to request populated version of the spreadsheet

http://nodal.ercot.com 17

http://nodal.ercot.com 18

Communications Plan / Issue Management

• Emails to ERCOT: – At any point during the testing questions can be emailed to

[email protected] – Note that this has changed from the 2.1 testing; the eds3 email address will

continue to be supported for hold over activities from 2009– All Market Participants should start using the [email protected] email

address immediately going forward for new issues / questions

• Nodal Market Trials Readiness Center Website– The Nodal Readiness Center will continue to be leveraged for any required

documents MPs will need to reference– All functional areas have a specific subsection under the Market Trials front

page:• Real-Time Market/LFC• Congestion Revenue Rights• Outage Scheduler• DAM/RUC• COMS/Settlements

– For documents that apply to all functional areas, those will be posted to the Market Trials Front Page under Key Documentshttp://nodal.ercot.com/readiness/markettrials/index.html

http://nodal.ercot.com 19

Communications Plan / Issue Management

• Issue Management – Market Participants will report all issues using the [email protected] email

address– Business oriented issues

• Initially reviewed by the ERCOT Wholesale Client Services Account Managers• If required, issues are escalated to the Market Trials Lead responsible for that functional area• More complex or indepth questions will be ultimately escalated to a Subject Matter Expert (SME)

– Technical issues • Initially reviewed by the Market Trials Technical Generalist for initial triage• If required, issues will be escalated to IT Production Support• If determined to be a variance / defect, ERCOT will leverage our existing defect management process to

estimate, analyze and prioritize the resolution

– Our target turn-around time on questions is 24 hours– ERCOT will maintain a known issues spreadsheet for each functional area on the

Nodal Readiness center• Will be updated every Friday by EOB (note that if no new known issues are discovered or

closed, the spreadsheet will remain static)• Will only detail those issues affecting the scope of Release 3.0 and any work-arounds

available to avoid issues• Known issues will be added as a standing agenda item on each of the weekly Market

Trials Calls

http://nodal.ercot.com 20

Market Trials Core Team

Matt MerenessMarket Trials Business Lead

Scott MiddletonMarket Trials Project

Manager

Stacy BridgesRTM / LFC Lead

Carrie TuckerDAM / RUC Lead

Steve ReedyCRR Lead

Robert MatlockOutage Scheduling

Lead

Jamie LavasReporting Lead

Kim DecuirMarket Support

Analyst

Balaji Krishnaswamy

Tech Generalist

Matthew TozerSettlements Lead

04/20/23

http://nodal.ercot.com 21

Market Information System (MIS) / ReportJamie Lavas

Handbook Information Provided

• High level list of functions and activities being provided across all phases of MTs broken out by functional area.

• Market Trials Timeline• Digital Certificates

– Nodal Roles• Introduction to MIS

– What is MIS– What is available on MIS– What is in scope for MT3– General Information– Limitations/Known Issues– Navigation

Slide 22

Items Available on MIS UI/ Web Services

• Report Links available for MT3• Alerts/Notices available for MT3• Applications available via MIS• EWS Web Services available for MT3

Slide 23

Market Participant Engagement

• Market Participant Engagement• Reports Extracts populated with Market Trial data will be aligned and

released with phase/functionality

Slide 24

http://nodal.ercot.com

• Readiness Center has an area dedicated to reports:• http://nodal.ercot.com/readiness/reports/index.html

Slide 25

Readiness Center

Readiness Center contains:• Reports• Data Definition Language (DDL) instructions• Statements & Invoices• Report & Extract Specifications• XML Schema Definitions (XSD)

Slide 26

Key Documents

ERCOT Market Information List (EMIL)

Required Postings - documents, reports, extracts, web services, alerts and notifications required by Protocol or Market Guides

Non-required Postings - available on the ERCOT website

Slide 27

ERCOT Market Information List (EMIL)

• EMIL can be used for a variety of reasons including:• Sorting and Filtering as needed • Viewing new Nodal required deliverables• Details on Protocol section or Market Guide requirements for each

published item• Finding EMIL Index # to locate relevant specifications in appropriate

documentation• Acquiring Report ID for the ‘Get Report’ Web Services• Currently adding information for Market Trial Available deliverables

Slide 28

04/20/23

http://nodal.ercot.com 29

Market Trials Handbooks ReviewOutage Scheduler

Robert Matlock

http://nodal.ercot.com 30

Agenda

• Introduction• System Requirements• Overview of Roles• Supporting Documents• Entry Criteria• Timeline• Overview of Activities• Reports• Dashboard• Exit Criteria• Question and Answers/General Discussion

http://nodal.ercot.com 31

Introduction

Market Trials Phase 3 Outage Scheduler Qualification consist of:

• MPs will test connectivity to the OS using the External Web Services (EWS)

and/or the Outage Scheduler User Interface (OS UI)

• MPs will test their ability to submit various outage types as well as updating

outages

• Testing will be self directed unless the MP would prefer to schedule a

conference call with ERCOT

• Note that new MPs (since 2008) will be contacted by ERCOT and a Market

Trials team member will hold a conference call to walk through the

qualification checklist

Supporting Documents

Some important documents you may need:

• External Interfaces Specification v1.19

– http://nodal.ercot.com/readiness/sandbox/index.htm

• OS User Guide TSP

– http://nodal.ercot.com/readiness/markettrials/os/index.html

• OS User Guide QSE

– http://nodal.ercot.com/readiness/markettrials/os/index.html

• OS Requirements v2.0

– http://nodal.ercot.com/docs/pd/mms/index.html#req

• ERCOT Market Information List (EMIL)

– http://nodal.ercot.com/readiness/reports/index.html

• OS Known Issues List

– http://nodal.ercot.com/readiness/markettrials/os/index.html

http://nodal.ercot.com 32

Entry Criteria

For the MP to participate in MT3 they must:

• Be registered as a TSP or QSE and operate Transmission Elements

• Possess an ERCOT production certificate with the appropriate role

• Must have access to the OS through EWS and/or the OS UI

http://nodal.ercot.com 33

Timeline

http://nodal.ercot.com 34

Phase 3 Outage Scheduler Market Trials begins Feb. 1and runs until March 30

Overview of Activities

MP’s will need to download the Outage Scheduler Qualification Checklist from: http://nodal.ercot.com/readiness/markettrials/os/index.html

http://nodal.ercot.com 35

DATE CONDUCTED: 1/0/00 12:00 AM

QSE REPRESENTATIVE: MP NODAL PMThe checklist below represents the transactions required for qualification. The Comments column will specify whether the transaction applies to QSEs, TSPs or both. Market Participants may elect to use Web Services or the ERCOT Nodal OS UI.

Scenario - Description Outage ID Date / Timestamp CommentsPlanned outage on a Single piece of equipment QSE and TSP

Submit Planned Outage QSE and TSPCancel Planned Outage QSE and TSP

Submit Planned outage derate QSESubmit Remedial Switching Action on a single piece equipment TSP OnlySubmit Forced Outage on a single piece of equipment QSE and TSP

Submit Opportunity OutageCurrently Unavailable / Not Required - QSE and TSP

Maintenance Level 1 on a group (QSE's w/ only one resource submit single outage) QSE and TSP

Submit outage at least 4 hours from current time (during business hours only) QSE and TSPEnter Actual Start Date/Time once ERCOT Approves (must be within 2 hours of Planned Start) QSE and TSPExtend Outage by entering new Planned End Date / Time (Include New Latest End as well) for Web Services only) QSE and TSPEnter Actual End Date / Time QSE and TSPEnter supporting information for extension QSE and TSP

Submit Simple Outage on a single piece of equipment TSP OnlySubmit Maintenance Level 2 on a single piece of equipment QSE and TSPSubmit Maintenance Level 3 on a single piece of equipment QSE and TSP

Testing Checklist

Overview of Activities continued

• MP’s will be required to submit at least one outage of each type applicable to the user:

http://nodal.ercot.com 36

TSP QSE

PlannedRemedial Switching ActionForcedM1M2M3Simple

PlannedForcedM1M2M3

• MP’s will also be required to take a Maintenance 1 outage all the way through completion.

• Once an MP has completed the Checklist, they will need to send it to ERCOT for verification.

ERCOT Activities

ERCOT will:• Periodically throughout the day, Approve/Accept the outages

submitted by the MP’s.• Work to resolve any issues the MP’s encounter.• Verified each MP has completed the required activities

http://nodal.ercot.com 37

Reporting Outputs

ERCOT will post on the MIS Secure area: • All Proposed• Approved/Accepted• Rejected• Withdrawn Transmission outages

Please Note, the following reports will not be available until MT4:• Advanced Transmission Outage Schedule Statistics• Advance Resource Outage Statistics• Planned vs. Actual

http://nodal.ercot.com 38

Dashboard/Tracking

During Phase 3, ERCOT will post Dashboard/Tracking documents to the Readiness Center.

http://nodal.ercot.com/readiness/markettrials/os/index.html

http://nodal.ercot.com 39

Phase 3 Exit Criteria

ERCOT Exit Criteria• 95% Operatorship of the Transmission system has completed and

passed qualification and testing• 95% Operatorship of the QSE’s have completed and passed

qualification and testing

MP’s Exit Criteria

• Successful completion of the required Scenarios

http://nodal.ercot.com 40

04/20/23

http://nodal.ercot.com 41

Nodal Telemetry OutreachStacy Bridges

Nodal Telemetry Outreach

42

Background:• The current Nodal Telemetry Outreach effort has two tracks:

• Missing Telemetry Effort:• ERCOT is working with QSEs and TSPs to help resolve issues

related to missing telemetry• Point lists identifying missing telemetry are queried and

distributed to QSEs/TSPs following each nodal database load (~bi-weekly)

• Quality Telemetry Effort:• Customized reports identifying quality issues are taken from a

daily SCED Telemetry Report and communicated to QSEs• Communications identifying quality issues are going to the QSE

ICCP contacts and nodal Project Managers• ERCOT is requesting that ICCP contacts respond to quality

issues within 24 hours

Nodal Telemetry Outreach

43

Missing Telemetry Update (QSEs):

• Status of requested State Estimator Telemetry:– Only 6 out of 3649 requested SE points remain unresolved (99% SE

points provided)• Status of requested SCED Telemetry:

– 634 requested SCED points remain unresolved

Progress measurement toward State Estimator Telemetry

# QSERs

JAN 5 JAN 13 JAN 21 JAN 29 (estimated)

100% 28 30 40 42

>=80% but <100% 0 0 0 0

<80% 4 0 0 0

In Review 14 16 6 4

http://nodal.ercot.com 44

Nodal Telemetry Outreach Update

Common Data Quality Issues:Common quality issues identified on the SCED Telemetry Report:

• Telemetry that remains to be mapped at ERCOT• Incorrect Resource Status• Generation>HSL; Generation<LSL• Negative Ancillary Service values (primarily for Responsive and Non-

Spinning Reserve)• Stale telemetry values 

Data Quality Inquiries Welcome:QSEs that have yet to receive a data-quality outreach from ERCOT may still have

quality issues that need to be addressed. QSEs may inquire about any issues reflected in the daily SCED Telemetry Report by submitting an email to [email protected] (please include “SCED Telemetry Report” in the subject line).

As common telemetry-quality issues continue to be reported, ERCOT will work to identify a tracking mechanism to support progress indicators and/or scorecard metrics.

Nodal Telemetry Outreach

Slide 45

Date ERCOT ActivitiesJan 29 • ERCOT begins distributing the next series of point lists

identifying missing nodal points (based upon the Jan 22 nodal database load)

• ERCOT updates the QSE Telemetry Dashboard on the Readiness Center (will include measurements for SCED as well as State Estimator)

• ERCOT posts the first TSP Telemetry Dashboard to the Readiness Center

Feb 1 • ERCOT’s goal is to have all nodal telemetry completed by Feb 1, 2010

Reminder of Upcoming Dates:

04/20/23

http://nodal.ercot.com 46

Market Trials Handbooks ReviewReal Time Market / LFC

Stacy Bridges

Real-Time Market / LFC

47

Topics:• Objectives• Entry Criteria• Schedule / Key Dates• Activities• Individual QSE Tests for LFC• Dashboards & Status Artifacts• Exit Criteria• Supplemental Materials

Objectives

48

Real-Time Market Timeline - Market Trials Phase 3.0

Objectives:• Execute SCED• Begin 6-month posting of LMPs• Schedule / Conduct individual QSE Tests for LFC

Objectives

49

Objectives – continued:• Execute SCED:

• Execute SCED and Real-Time system components continuously in Market Trials environment (February and March)

• Produce Base Points and LMPs (February and March) • Begin 6-month posting of LMPs:• Perfect the data and processes needed to support SCED in calculating

reasonable LMPs (February)• Begin Posting LMPs (March)• Schedule / Conduct individual QSE Tests for LFC:• Schedule individual QSE tests for LFC (February)• Conduct individual unit tests for LFC (March)

Entry Criteria

Entry Criteria:• Market Participants

• Meet system requirements:• Internet Explorer 6• Production digital certificate with MMS Trader role enabled

• Meet nodal ICCP requirements• Complete Phase 2.1 qualification testing

• ERCOT• Complete Nodal database mapping for all available Nodal ICCP

points• Complete required testing for Phase 3.0 functionality • Publish all known, market-relevant defects to Market Participants

Slide 50

Schedule / Key Dates

Slide 51

Schedule / Key Dates

Date ERCOT Activities QSE with Resources ActivitiesFeb 1 Begin SCED execution

Begin LFC and LMP analysis Begin posting Real-Time outputs, reports,

and extracts

Begin daily support of SCED with market submission items and quality ICCP

Feb 5 Begin weekly Real-Time Market calls Begin publishing MMS Transaction

Dashboard on the Readiness Center

Begin attending weekly Real-Time Market calls

Feb 26 Complete scheduling individual QSE tests on the LFC testing calendar

Mar 1 Begin six-month postings of LMPs Begin conducting individual QSE tests for

LFC

Begin conducting individual QSE tests for LFC

Schedule / Key Dates:

Activities

Market Participant Activities:• Verify ability to receive Resource Base Points via ICCP• Download and review Real-Time Report postings• Provide continuous nodal ICCP data to ERCOT • Submit/Update/Cancel daily Real-Time market submission items:

• Three-Part Supply Offers *• Inc/Dec Offers *• Output Schedule• Current Operating Plan (COP)

• Schedule / Conduct individual QSE LFC test windows (QSEs with Resources)

* Note: During Phase 3.0, Offer Curves should initially reflect 80-120% costs

Slide 52

Activities

ERCOT Activities:• Execute and monitor Real-Time system components• Run SCED every five minutes using ICCP and market submission data• Run LFC every four seconds• Verify QSE Submission Activities• Work with Market Participants to resolve ICCP telemetry issues• Generate Base Points, LMPs, SPPs, and Shadow Prices• Review Base Points, LMPs, and SPPs for reasonability using price

validation software• Publish Real-Time outputs/reports to the market via MIS and ICCP• Schedule / Conduct individual QSE tests for LFC

Slide 53

Individual QSE Tests for LFC

Individual QSE Tests for LFC:• Tests will confirm that QSEs providing Regulation Service and

Responsive Reserve Service (RRS) in the nodal market can exchange SCADA data with LFC/RLC components of ERCOT’s Nodal EMS system

• Tests will be scheduled January 25 – February 26• Tests will be conducted March 1 – April 16• Test Participation will be required from:• QSE with Resources that did not participate in EDS 3 Release 6.2

testing during 2008 • New QSEs with Resources planning to provide Regulation service in

the Nodal Market • 80% of system-wide generation

Slide 54

Dashboards & Status Artifacts

Slide 55

Artifact Description Availability

QSE Telemetry Dashboard

Communicates completion status of ICCP telemetry from QSEs

• Refreshes after each Nodal database load

• Currently available

TSP Telemetry Dashboard

Communicates completion status of ICCP telemetry from TSPs

• Refreshes after each Nodal database load

• Available January 29, 2010

MMS Transaction Dashboard

Communicates daily statistics for SCED submission items

• Refreshes weekly on Fridays • Available February 5, 2010

Dashboards & Status Artifacts• http://Nodal.ercot.com/readiness/markettrials/rtm/index.html

Dashboards & Status Artifacts

QSE Telemetry Dashboard Example:

Slide 56

Dashboards & Status Artifacts

TSP Telemetry Dashboard Example:

Slide 57

Dashboards & Status Artifacts

MMS Transaction Dashboard Example:

Slide 58

Exit Criteria

Exit Criteria - QSEs with Resources• A target of 98% of QSEs with Resources are successfully

submitting daily Real-Time market transactions as tracked on the MMS Transaction Dashboard

• QSEs with Resources have scheduled Individual QSE tests for LFC• QSEs have begun conducting individual QSE tests with ERCOT

Exit Criteria - ERCOT• Reasonable LMPs have been established• Six-month posting of LMPs has begun• ERCOT has scheduled Individual QSE tests for LFC• ERCOT has begun conducting individual QSE tests with QSEs

Slide 59

Supplemental Materials

Slide 60

Reference and Description Location Version

Market Connectivity Testing Market Participant Handbook

http://Nodal.ercot.com/readiness/markettrials/connectivity/index.html

0.97

External Interfaces Specification http://Nodal.ercot.com/readiness/sandbox/index.html 1.19d

Explanation of Market Submission Items

http://Nodal.ercot.com/readiness/markettrials/connectivity/index.html

0.26

ERCOT Nodal ICCP Communication Handbook

http://Nodal.ercot.com/readiness/markettrials/rtm/index.html

3.0

MMS Requirements http://Nodal.ercot.com/docs/pd/mms/index.html#req Various

EMS Requirements http://Nodal.ercot.com/docs/pd/ems/index.html#req Various

ERCOT Market Information List http://Nodal.ercot.com/readiness/reports/index.html N/A

Market Manager User Guide http://Nodal.ercot.com/readiness/markettrials/connectivity/index.html

0.06

Real Time Market Known Issues http://Nodal.ercot.com/readiness/markettrials/rtm/index.html

N/A

Web Services XSDs http://Nodal.ercot.com/readiness/sandbox/index.html 1.3.19d

Sample Reports, Extracts, and DDLs

http://Nodal.ercot.com/readiness/reports/index.html Various

04/20/23

http://nodal.ercot.com 61

Market Trials Handbooks ReviewCongestion Revenue Rights

Steve Reedy

Agenda

Topics:

I. Overview of CRR Market Trials Phase 3.0

II. Entry Criteria (including System Requirements)

III. CRR Qualification

IV. Allocations/Auctions in CRR Market Trials 3.0

V. Known Issues

VI. ERCOT And Market Participant Activities

VII. Highly Recommended Training

VIII. Dashboard/Metrics

IX. Supplemental Materials

Slide 62

Overview

• CRR Market Trials Phase 3.0• Perform CRR Account Holder Qualification• Run Allocations/Auctions with “First 6 months” data

scenario– NOIEs nominate for allocations each month

• Follow Nodal Protocol timelines when possible– Compressed timeline for first allocation/auction

• Integrated with – Settlements and Billing (auction invoices/payment

confirmation)– Network Model Management System

Slide 63

ERCOT Entry Criteria

• ERCOT Entry Criteria• Integration testing for functionality exposed in Market

Trials Phase 3 completed to ERCOT satisfaction with all market-relevant defects published to market participants via the known issues list.

• CRR Auction Application performance testing for functionality exposed in Market Trials Phase 3 completed with results deemed as acceptable by CRR business owner.

Slide 64

Market Participant Entry Criteria

• Market Participant Entry Criteria• Registered as CRR Account Holder• Met all CRR system requirements

a) Internet Explorer 6

b) Must have a CRRAH (CRR Account Holder) Digital Certificate installed with appropriate roles assigned

(USA certificates were issued Nov 16 and are available for download)

c) Must have a CP (Counterparty) Digital Certificate with appropriate roles assigned

d) Sun Java 1.5 JRE and IE Plug-in (or more recent version)

e) Keyhole Markup Language (KML) viewer (e.g. Google Earth) (for phase 4.0)

Slide 65

Counterparty vs. CRR Account Holder certificates

• Two types of digital certificates needed for CRR• Counterparty

– assigns credit• CRRAH

– submits bids/offers – views results– performs bilateral trades– can further limit any credit assigned by Counterparty, but can’t increase

CRR Qualification

• CRR Qualification from 1/4/2010-1/29/2010• Qualification Activities (all below activities must be

completed)– Log-in and access the CRR system – Download a CRR Network Model– Upload a bid/offer portfolio– Edit a bid/offer portfolio– Complete a bilateral trade

Slide 67

Allocations/Auctions in CRR Market Trials 3.0

• Auctions/Allocations for March & April 2010• Allocation for May • Allocation for Balance of Year (June – Dec 2010)

(note: Auctions for May, Balance of Year in Phase 4.0)

Slide 68

Known Issues

• JAN2010 CRR Monthly Network Model report file (Report ID 11204) does not contain all the required network files.

• Monitored Lines and Transformers contains no data• Portfolio upload - Portfolio Editor becomes unusable when

uploading a "targeted" bid portfolio containing a valid source/sink that is not biddable for that specific auction

Market Participant Activities

• Qualify• Submit Credit (Using Counterparty Certificate)• Submit Bid/offer portfolio• View/verify postings• Bilaterally trade

Slide 70

ERCOT Activities

• Create Models• Run Qualification• Run Auctions• Post Notices/Results/Invoices

Slide 71

Highly Recommended Training

• CRR MUI Training– Available on LMS

(https://www.ercottraining.com/lms/default.asp )

– Nodal Market Training• CRR Market User Interface Training • Will answer many questions regarding the mechanics of the CRR User

Interface

Slide 72

Dashboard

Slide 73

Dashboard will be posted on CRR section of Market Trials/Readiness Centerhttp://nodal.ercot.com/readiness/markettrials/crr/index.html

Supplemental Materials

Slide 74

Description Location Version

CRR Known Issues List http://nodal.ercot.com/readiness/markettrials/crr/index.html

N/A

ERCOT Market Information List (EMIL)

http://nodal.ercot.com/readiness/reports/index.html

N/A

CRR Requirements Doc http://nodal.ercot.com/docs/pd/crr/index.html#req

4.4

CRR - Market User Interface User Manual

http://nodal.ercot.com/readiness/markettrials/crr/index.html

1.0

CRR - Explan of Mkt Sub. Retrieval Items

http://nodal.ercot.com/readiness/markettrials/crr/index.html

.12

CRR MUI Training https://www.ercottraining.com/lms/default.asp

N/A