Hse Risk Assessment - 006 Ra -Hdpe Duct Laying
-
Upload
binunalukandam -
Category
Documents
-
view
342 -
download
10
description
Transcript of Hse Risk Assessment - 006 Ra -Hdpe Duct Laying
CSIN-25 - Client Instruction
RISK ASSESSMENT
Activity
ROAD CROSSING DUCTS FOR HV/EHV CABLES
Method Statement No:
EXW-P015-0000-EE-LNT-MT-00094 REV CB
Risk Assessment No:006/PP
Date of Assessment
26 Jan 15
Review Date
25 Jan 2016
Revision 0
Act No.
Activity
Potential Hazards
Consequence
Risk Level
Control Measures
Residual Risk
P
S
R
1
Survey,
Marking layer/level
Working in and around excavation
Working near plant and vehicle
Injury from falling in to excavation or
Being hit by a moving vehicle/plant
3
3
9
Open edge of excavation shall be barricaded and no one shall work close to the edge of excavations
Marking out areas near plant vehicle movement area shall be isolated via physical barriers or controlled by banks man
PPE such as safety shoe, reflective jacket and helmet must be worn by all those involved in the activities
3
2
Excavation
Underground utilities
Working with moving plants
Noise
Dust
Personal injury /property damage from
Collusion with moving plants and vehicle
Striking underground services
Slip, trip and fall
3
5
15
The project engineer shall make sure that all required NOCs from concerned authorities are obtained and available with him prior to start removal of trees.
Obtain excavation work permit from HSE department before commencing the work and site supervisor shall make sure the permit, Method statement and TBT on method statement/risk assessments are available at site.
Competent supervision must be available during work
Identify and mark the underground utilities before starting the excavation and protect the utilities (If any) during work
Provide adequate protection for open pits such as hard barrier, adequate hazard warning signs (Danger Deep Excavation), mini flash lights if the trench is near to live road.
Only manual excavation to be done in areas where there is presence of underground utilities.
Equipment operation shall only be under the guidance of a competent banks man.
PPE such as safety shoe, reflective jacket, dust mask. goggles and helmet must be worn by all those involved in the activities
3
3
Welding & Laying of HDPE ducts
Manual handling
Use of HDPE fusion welding machine, Sharp cutting tools
Slip, trip and fall hazard
Hot surface
Flying particles
Electrical Powered Equipment
Crane associated Hazard
Injury from
Use of sharp tools, pipe handling
Health hazard from use of COSHH Material
Burn from potential melted pipe and heating elements
2
2
4
HDPE fusion work will be carried out by competent operator only
Maintain distance from heating elements on fusing machine-heat plate, pipe beads, etc.
Manual handling technique must be taught to all operatives involved in the activities
All tools must be used by trained workers
Good housekeeping shall be maintained to minimise trip hazards and contact with sharp objects such as protruding nails, sharp steel and tools....etc.
COSHH material shall be stored and handles as per MSDS of the material and the MSDS shall be communicated to all users
Control measures given in the crane operation for all lifting activity(11)
2
4
Concrete
pouring
Contact with wet concrete
Reversing trucks
Vibration
Health hazards from
contact with
Skin
Eye injury,
Slip and trip,
3
3
9
All work to be carried out as per approved MS
If anyone gets concrete on cloth or skin flush immediately with lots of water.
Washing facilities should be provided.
Banks man shall guide the reversing trucks
Use appropriate PPE s such as Hand gloves, safety glasses, gumboots...etc.
3
5
Backfilling
Vibrating Plants under operation.
Reversing tipper truck
Falling materials or plant
Falls of persons into excavation
Unsafe access/egress
Cave ins
Noise
Vibration
Dust
Personal injury /property damage from
Collusion with moving plants or vehicle
Cave inns
Fall into excavation
Material/equipment fall from height
Slip, trip and fall
4
3
12
All activities shall be carried out as per approved MS and risk assessments
All plants and vehicles shall be guided by a competent banks man
Stop blocks shall provide near edge of excavation to avoid vehicle/plants falling in to excavation
Adequate safe access to excavation shall be provided
Personnel working with vibrating equipment will be trained to operate the equipment
PPE such as heavy duty hand gloves, ear plugs/defenders dust mask and all other mandatory PPE shall be used by all involved in the activity.
Compaction machines will be inspected daily to ensure they are in good working condition
Reversing alarms to be fitted to all plant machinery.
3
6
Construction of precast Chambers
Unsafe working platform
Use of hand tools and power tools
Manual Handling
protruding nails, sharp edges
Ladder use
Personal injuries from
Fall from height
Striking by falling objects
Manual handling
Use of power tools
3
3
9
Safe and suitable working platform with suitable access/egress shall be provided for all work at height
Good housekeeping shall be maintained to minimise trip hazards and contact with sharp objects such as protruding nails, sharp steel and tools....etc
Only competent operatives will use the power tools such as angle grinder, jack hammer...etc
The operator/supervisor will check the tools for its inspection tag/colour coding; guards are in place, cable...etc while collecting the tool from store and before starting the work.
The foreman must make sure that no one uses loose clothing when working with grinder or any rotating machinery.
Trailing cables should not be in the path of other workers.
Plugs and sockets should be water resistant and colour coded. Not domestic appliances.
Adequate PPE must be used by the operatives using power tools, such as eye, respiratory protection, hand gloves, face shield while working with grinders...etc
Manual handling technique must be taught to all operatives involved in the activities
If ladders used as access/egress it must be secured top and bottom
2
7
Erection of precast chambers
Crane associated hazards
Injury/fatality by crane failure, dropped load, load striking other object/personal
3
4
12
Lifting permit must be obtained from HSE Department and implement the permit requirements
Only competent crane operator will operate the crane
Competent lifting supervisor and rigger will present during lifting
Crane and lifting gears shall be suitable and certified, valid certificates must be available with crane
3
8
Working close to Live Road
Moving traffic
Operatives and plants/vehicle close to the live traffic
Dust
Foreign object particles
Material falling from moving vehicles.
Personal injury,
Fatality, Property damage from traffic accident
4
5
20
All Road diversions, Detour and working close to live road shall be carried out as per approved detour plan and permit
All activity shall be carried out under competent supervision only.
A competent banks man must be present in the vehicle/plant movement area
Pedestrian and vehicle routes shall be segregated so far as reasonably practical and shall be clearly marked with signs and barriers
All work shall be carried out within the work zone (hard barrier) no one will be allowed to go to live road.
All employees shall follow instruction and attend training on site traffic management and logistics
Avoid reverse movement
All employees should wear high visibility jacket at all times
No workers shall be allowed to cross live roads, always be away from live road and adjacent barriers
Do not move any barrier or signs from its locations
Ensure adequate lighting provided during night activities
Do not store or keep any loose materials close to live road, Do not throw any materials on live road
Heavy equipment such as cranes, boom loaders, excavators, back hoes should not swing/extend their booms/arms towards live road direction at any time. Banks man must control/guide the operators
3
9
Working with moving plants and vehicle
Unauthorized operation of plants and machinery
Reversing heavy vehicle/plants
Pedestrian/workers on the blind spot of operators/drivers
Tipping at uneven/loose sand or poorly compacted ground
Operatives/vehicle close to the tripping trucks
Working during poor visibility
Vibrating plants under operation
Noise
Dust
Serious injury/fatality and/or property damage from vehicle hit, collusion, overturning and/or topplingetc
4
5
20
Operatives should be kept away area of operation by the provision of suitable barrier and maintain a pedestrian exclusion area.
The site supervisor shall make sure only competent drivers and operators are allowed to drive/operate on site
Speed limit of 30 KMPH shall be implemented at site
Plant and equipment should be inspected daily for any defect or oil leakage and routine maintenance to be carried out.
Competent banks men shall be assigned to guide the plants and vehicle
Reversing heavy vehicles shall be restricted at site and all plants and vehicle shall be fitted with reverse alarm
Site Engineer shall identify safe entry/ exit route for filling trailers/truck and communicated to drivers and foremen on a daily basis
Driver is responsible for covering the load if they enter highway or municipal Roads
Supervisor and banks men shall make sure all plants such as wheel loader, compactors, trucksetc maintain a safe clearance from edge of excavation
Plant operator shall make sure their visibility all around, no window curtains are allowed and all rear view mirrors and window glass/wind shield must be kept clear all time
PPE such as reflective Jackets, safety shoe, helmet, safety goggles and dust mask must be worn by all working in the area
Makes sure safe access available for truck, trailers and all reversing trucks are controlled by competent banks man
Make sure tipping area is level, compacted to avoid toppling hazards and make sure no overhead power lines in the tipping areas.
3
10
Use of Plate compactor
Unauthorized operation
Un guarded Rotating parts
Vibration
Noise
Dust
Use of fuel
Injury from unguarded moving parts
Health hazard from Vibration, Noise, dust
2
3
6
Compactors will be operated by competent operator
The supervisor and operator shall make sure the plant is equipped with guards on all rotating parts
Operator shall use heavy duty hand gloves, ear protection and dust mask in addition to his mandatory PPEs.
2
11
Use of crane/
Lifting operation
Structural failure
Erection of lifting equipment at poor ground condition, close to edge of excavation
Proximity Hazards such as OH electric line, Excavation, mobile equipments
Underground utilities
Use of damaged lifting gears
Unauthorized operation
Absent of competent rigger/supervisor
Manual Handling
Inclement weather
Death or Major Injury/ property damage from lifting equipment failure
3
5
15
Site Engineer shall make sure that the crane, lifting equipment, gears are suitable for the load and visually inspected by HSE team and Lifting Permit is obtained from HSE department.
The site and/or lifting supervisor and the crane operator must check the ground condition and the surrounding of operation for any proximity hazard such as excavation, manholes, overhead electrical line, mobile equipment etc.
All lifting activities shall be carried out by competent operator under a competent supervisor and rigger.
Ensure sufficient illumination if operating at night.
The lifting area shall be demarked provide sufficient hazard warning signs to avoid unauthorized entry of people/vehicle.
Ensure load is secured properly, remove if any loose material.
Use tag line of sufficient length to prevent unwanted swinging of the load.
Provide PPE such as hand gloves, goggles, safety shoes & hard hat to the workers engaged.
Stop the activity in case of bad weather such as sand storm affecting visibility, heavy wind 35 KMPH or more and heavy rainetc.
3
Risk Matrix
Severity
Consequence
Likelihood(probability) of occurrence
Very Low
Low
Medium
High
Very
High
H
Human
(injury)
A
Asset(s)
(Damage or loss of any kind)
E
Environment
R
Reputation
1
2
3
4
5
Never heard of the incident
The incident is known
Occurred in the company/ project
Occurred 5 times in a year times in the company/ project
Occurred more than 5 times in a year in the Company/ project
1
Insignificant
FAC
Insignificant
(QR 1 to 500)
Minor impact/ damage
Minor
Impact
1
2
3
4
5
2
Minor
(MTC/ RWC)
Moderate
(QR 501 to 5000)
Moderate Impact-reportable to authority
Limited Impact
2
4
6
8
10
3
Moderate
(LTI/ PPD/ reportable injuries)
Considerable
(QR 5001 to 50000)
Localized Impact- authority involvement
Considerable Impact
3
6
9
12
15
4
Major
Single Fatality/ PTD
Major
(QR 50001 to 100000)
Major Impact
Country wide impact.
4
8
12
16
20
5
Catastrophic
Multiple PTDs/ Fatalities
Heavy
(above QR 100000)
Massive Impact
Worldwide impact
5
10
15
20
25
Risk Rating Criteria
Risk= Severity X Likelihood
Low Risk: Risk Rating from 1 to 3
Medium Risk: Risk Rating from 4 to9
High Risk: Risk Rating from 10 to 25
Assessed By
Designation
Signature
Date
1. R. Srinivasan
Construction Manager
01.02.2015
2. Polaprakasan
HSE Manager
01.02.2015
3. Ethirajan.R
Deputy Project Director
01.02.2015
L&T/HSE/27 Rev 00 Page 6 of 6