    DREDGING AND SHIPPING

    HOW TO MAXIMIZE THE LOAD OF A HOPPERDREDGER.

    This artcle describes step-by-step, how to maxim ize payload of a tide bound hopperdredger. This specialised article requires some knowledge of terms like

    "squat" and "UKC" .

    Sooner or later, every hopperdredger is squeezed through a shallow navigation channel, with tide-restrictions.

    Every idiot can load a hopperdredger to the gunwales, but to get that load safely to the discharge area, time and again; a

    thousand times... and to maximize that load, with minimal risks,... need some reflection.

    Through calculation and assesment, tidebound dredgers can both have minimal risks and maximal loads, under the

    prevailing conditions.

    The method described below is rather specific for hopperdredgers. Merchant vessels will make an occasional port call,

    having limited info on tides, waterdepths, etc... Merchants often wait for the next high water to make a safe passage over

    shallow area's.

    A dredger cycles through the same passage several times a day at the same project -often for months.

    Dredgers have access to excellent bathymetric data of their site.

    Dredgers don't wait for highwater, if tides do not rise faster (allowing deeper draughts) than cycle production. Time

    is money

    We developed this method with "Leiv Eiriksson" in Malaysia, and fine-tuned it in Oman.

    It's just a squat-formula (http://www.theartofdredging.com/vsquat.htm), turned inside out, and further accounting for all possible

    errors and uncertainties.

    We attempt 10 cm vertical accuracy... with modern sensors and systems, this accuracy can be reached.

    w_to_load_max - The Art of Dredging http://www.theartofdredging.com/howtoloadmax.htm

    10 06/03/2013 07:58

  • 7/27/2019 how_to_load_max - The Art of Dredging.pdf

    2/10

    How ?

    Check draughts (http://www.theartofdredging.com/howtoloadmax.htm#812335925)(http://www.theartofdredging.com/howtoloadmax.htm#785099280)

    1.

    Check tidal data (http://www.theartofdredging.com/howtoloadmax.htm#785099280)2.Check surveydata of the channel (http://www.theartofdredging.com/howtoloadmax.htm#843645206)

    3.

    UKC ? (http://www.theartofdredging.com/howtoloadmax.htm#845650093)4.

    CHECK DRAUGHTS

    Check if draught readouts on the bridge are correct, or -if we find an error- is this a fixed error ?

    Quick draught checks can be done from deck, measuring freeboards. This should be done regularly, to detect any

    hickup with draught sensors. Paranoia pays.

    Checking water salinity .... With a draught of 15 meter (like TSHD "Leiv Eiriksson"), the difference between

    freshwater or seawater amounts to 37 cm of draught.

    Roll and list are two different things. A vessel can have a permanent list of 1 degree, and roll for another extra six

    degrees...

    List: formula to calculate extra draught by list: shows that list is a decisive factor, especially for the modern

    wide-beamed dredgers. List must be controlled during loading, or be corrected during sailing. (On Leiv Eiriksson we

    found out that hanging the 600 ton dredgepipe overboard adjusts for 1 degree of list. Lucky us.)

    Roll angle of the ship has to be determined before entering the channel. Clearly, no mariner can read the future, but

    by monitoring previous trips, roll can be reasonably "guesstimated" and accounted for.

    Trim affects draughts; and a loaded ship with some trim, clearly does not use it's full payload capacity. Trim can be

    manipulated by shifting weights onboard; bunkers throughout the bunkercycle, or on "Leiv Eiriksson" shifting the

    travelling deckcrane forward. Every idea may work.

    w_to_load_max - The Art of Dredging http://www.theartofdredging.com/howtoloadmax.htm

    10 06/03/2013 07:58

  • 7/27/2019 how_to_load_max - The Art of Dredging.pdf

    3/10

    Other effects can influence draught: heel angle with turning ship, heaving and pitching motion in waves. All these

    effects can be observed, and taken in account.

    CHECK TIDAL DATA

    On a dredge project, tides may be measured, and transmitted realtime to the dredgers.

    If realtime tidal data is missing; we can use the method with harmonic tidal constituents (http://en.wikipedia.org

    /wiki/Theory_of_tides), resulting in calculated ("astronomical") tides.

    Astronomical tides introduce three problems:

    1. Astronomical tides have no corrections for wind, rainfall or barometric pressure. Every mariner knows that tidal lows

    or highs may be completely flattened out or peaking, due to meteo conditions.

    w_to_load_max - The Art of Dredging http://www.theartofdredging.com/howtoloadmax.htm

    10 06/03/2013 07:58

  • 7/27/2019 how_to_load_max - The Art of Dredging.pdf

    4/10

    Tidal data receiver display onboard: black graph is calculated tide, red and green graphs are measured tides. A tidebound dredger can load 20 cm less

    draught on the first low tide of the day, if he enters that time. By presenting measured tidal data in graphs, anomalies can be easily detected.

    2. Global warming causes sea levels to rise; most of the harmonic tidal analysis need reviewing. Example: a recent

    article in Knack(http://www.knack.be/nieuws/planet-earth/belgie-nu-al-slachtoffer-van-opwarming-aarde/article-4000007206755.htm)

    states that -over a timespan of 40 years, for the port of Zeebrugge- tidal heights were found to have risen by 13 cm.

    3. Accuracy is a major problem, especially outside Europe. British Admiralty has -historically- always been interested

    in its own turf first. This is reflected in coverage of nautical charts, but also in tidal data. Example: in Duqm, Oman,

    tidal heights had a fixed correction of 20 cm, compared to Admiralty data. By datalogging tidal data over a longer

    period of time (say: one year), harmonic constituents can be recalculated and compared with historical data.

    Differences found are often significant.

    w_to_load_max - The Art of Dredging http://www.theartofdredging.com/howtoloadmax.htm

    10 06/03/2013 07:58

  • 7/27/2019 how_to_load_max - The Art of Dredging.pdf

    5/10

    Admiralty Tide Tables are arranged in 4 volumes: one volume serves the British Isles, the other three volumes cover the rest of

    the world.

    The benchmark was to have an accuracy of 10 cm, and Admiralty tidal data are simply not able to deliver that

    accuracy.

    Another method -however not yet commonly used on dredgers- is a GPS-receiver, working in RTK-mode

    (http://en.wikipedia.org/wiki/Real_Time_Kinematic). The vertical resolution of this system may be accurate enough

    (centimeter-level) for tidal height measurements (read here (http://www.hydro-international.com/productsurvey/id10-

    RTK_DGPS_Receivers.html)).

    RTK-technology is also a solution for jobs requiring exact knowledge of tidal heights, but located far away from

    reference ports or tidal height transmitters.

    The problem with GPS-antenna's heigth is that ship's draughts have to be taken into the calc, introducing errors

    from that side.

    CHECK SURVEYDATA OF THE CHANNEL

    Survey data accuracy can vary wildly, from 0.05 m up. Accuracy mostly depends on survey quality assurance.

    w_to_load_max - The Art of Dredging http://www.theartofdredging.com/howtoloadmax.htm

    10 06/03/2013 07:58

  • 7/27/2019 how_to_load_max - The Art of Dredging.pdf

    6/10

    Here are some things to consider:

    Multibeam or single beam ? Clearly: multibeam (http://www.nauticalcharts.noaa.gov/staff

    /education_animations.htm)carries the day. With single beam; shallow spots as wide as the interval betweensurvey lines can remain undetected. This is especially scary in area's with a rocky seabed.

    Does the survey platform pitches, rolls, etc... ? And what about accuracy of their motion-reference unit

    (MRU (http://www.km.kongsberg.com/ks/web/nokbg0240.nsf/AllWeb

    /61118F926CD5A6E5C125700B0033CF55?OpenDocument)) ? Top-of-the-line systems, functioning in a strict

    QA-system, can reach consistent accuracies of 0.15 meter; with small survey boats opearting in waves up

    to Hs = 2 m. To reach this accuracy however, interpretation and manual "cleaning up" of survey-data

    may be necessary, to remove "noise" and "spikes".

    By all means: if you look at a survey chart: check the date of the survey. Channels are liable to

    sedimentation, sandbanks move around, other dredgers dump loads... Bathymetry is constantly

    changing, and what you see on the survey chart, is notwhat you get after a couple of weeks or months.

    Multibeams gather a lot of depth data per square meter. For site management purposes; survey charts

    often displaymean values per grid cell (typically 1 sq.m.). Mariners are more interested in the shallowest

    values of a multibeam survey.It may be the difference between a safe passage in shallow water, or the

    keel of the ship ripped open by a protruding rock.

    w_to_load_max - The Art of Dredging http://www.theartofdredging.com/howtoloadmax.htm

    10 06/03/2013 07:58

  • 7/27/2019 how_to_load_max - The Art of Dredging.pdf

    7/10

    Survey & navigation display onboard TSHD Leiv Eiriksson. Navigation with a 15m draught is always a 3-D-, and often a 4-D- mind game.

    Draughts and sailing speed must be strictly controlled in shallow area's.

    UKC ?

    If we allow for all possible errors and uncertainties, as explained above, there remains an important question:

    "What dynamic ("nett") UKC do we choose ?"

    w_to_load_max - The Art of Dredging http://www.theartofdredging.com/howtoloadmax.htm

    10 06/03/2013 07:58

  • 7/27/2019 how_to_load_max - The Art of Dredging.pdf

    8/10

    In ship manoeuvring textbooks, we often find the rule of thumb: "UKC is minimal 10% of deepest

    ship's draught". Or sometimes "12.5%", or a very prudent "15 %"

    Some ports have their own guidelines, as do some shipping companies, often in ISM-procedures.

    PIANC (http://www.pianc.org/) has developed standards:

    Muddy seabed UKC = 0.3 m

    Sandy seabed UKC = 0.5 m

    Rocky seabed UKC = 1.0 m

    Small high spots in the seabed do not affect the ship hydrodynamically. But how large may be a shallow

    patch, before the ship experiences squat over that position ? This is beyond knowledge.

    In the end, it is still the mariner who picks a nett UKC, observes the ship, the tell-tale signs of squat, the

    vibrations in the ship, the changing wave patterns at the stern...

    Running aground is not an option.

    REFERENCES

    http://www.1902encyclopedia.com/T/TID/tides.html (http://www.1902encyclopedia.com/T/TID/tides.html)

    http://web.vims.edu/physical/research/TCTutorial/tideanalysis.htm?svr=www(http://web.vims.edu/physical/research/TCTutorial/tideanalysis.htm?svr=www)

    http://www.co-ops.nos.noaa.gov/about2.html#ABOUT (http://www.co-ops.nos.noaa.gov/about2.html#ABOUT)

    w_to_load_max - The Art of Dredging http://www.theartofdredging.com/howtoloadmax.htm

    10 06/03/2013 07:58

  • 7/27/2019 how_to_load_max - The Art of Dredging.pdf

    9/10

    Marc Van de Velde, february 2012

    Subscribe to our newsletter:

    Write us:

    reply.to.artofdredging (at) gmail.com

    - a sailor's fifth column

    w_to_load_max - The Art of Dredging http://www.theartofdredging.com/howtoloadmax.htm

    10 06/03/2013 07:58