How to Solve Project Crashing, Project Management Calculations

download How to Solve Project Crashing, Project Management Calculations

of 14

description

Project Crashing Calculator, This is an Excel Sheet which provides you an easy way to calculate the Project Crashing Schedule

Transcript of How to Solve Project Crashing, Project Management Calculations

Step 1

Activity Normal Days A 7B 5C 14D 5E 11F 7G 11H 4I 18

A(7)B(5)C(14)D(5)E(11)F(7)H(4)G(11)I (18)ABC- Project Paths AvailableA-C-E-H-I = 54 (Critical Path)A-D-F-H-I = 41B-G-I = 34

Step 2

Activity Normal Days Normal Cost Crash Time Crash Cost Max reduction of daysCost to Crash / dayabcde = (a-c)A 75,00047,0003667B 56,00036,5002250C 1412,0001015,0004750D 512,000216,00031,333E 1118,000825,00032,333F 715,000418,00031,000G 117,000910,00021,500H 49,000312,00013,000I 1814,0001522,00032,6675440Cost to crash/period( d - b ) / ( a - e )

Step 3Crash the Project to 42 DaysFor crashing the schedule select only the activities on the critical pathA-C-E-H-IStart crashing the schedule from first selecting the least expensive activity and gradually select other activities

Current Time (Days)54Crash Schedule to (Days)42Difference12

Step 4

Activity Normal Days Normal Cost Crash Time Crash Cost Max reduction of daysCost to Crash / dayDays to Crash 12Incurred Crash CostTotal Costabcde = (a-c)A 75,00047,000366732,0007,0001B 56,00036,50022500.00.06,000C 1412,0001015,000475043,00015,000D 512,000217,50031,8330.012,000E 1118,000825,00032,33337,00025,000F 715,000418,00031,0000.015,000G 117,000910,00021,5000.07,000H 49,000312,00013,0000.09,000I 1814,0001522,00032,66725,33319,3335498,00040Days to Crash017,333115,333

Revised CPM after Crashing

Activity Normal Days Crash ScheduleA 74B 55C 1410D 55E 119F 77G 1111H 44I 1816Revised PathsA-C-E-H-I43A-D-F-H-I36B-G-I32

A(7)B(5)C(14)D(5)E(11)F(7)H(4)G(11)I (18)ABC- Project Paths AvailableA-C-E-H-I = 54 (Critical Path)A-D-F-H-I = 41B-G-I = 34