How to Perform Project Risk Management for Oil and Gas Projects Intaver Institute Inc. 303, 6707,...

24
How to Perform Project Risk Management for Oil and Gas Projects Intaver Institute Inc. 303, 6707, Elbow Drive S.W, Calgary, AB, Canada Tel: +1(403)692-2252 Fax: +1(403)459-4533 www.intaver.com

Transcript of How to Perform Project Risk Management for Oil and Gas Projects Intaver Institute Inc. 303, 6707,...

How to Perform Project Risk Management for Oil

and Gas Projects

Intaver Institute Inc.303, 6707, Elbow Drive S.W, Calgary, AB, CanadaTel: +1(403)692-2252Fax: +1(403)459-4533www.intaver.com

Introduction

• Intaver Institute Timeline– 2002: Established

– 2004: V.1 RiskyProject

– 2009: v 3 Integrated Risk Register

– 2012: v 5

• RiskyProject– Full Project Risk Management

Lifecycle

– Integrated Risk Register

– Risk Matrix, Risk Planning

+– Quantitative Monte Carlo Cost and

Schedule Risk Analysis

04/20/23 2013 Intaver Institute 2

Clients

Gorgon Natural Gas Project

04/20/23 2013 Intaver Institute 3

Project Cost Estimate in Billions A$

Date of cost estimate

A three-train liquefied natural gas (LNG) facility on Barrow Island (Australia) that will produce 15.6 million metric tons of LNG per year.

Corporate Portfolio Management Process

04/20/23 2013 Intaver Institute 4

Project Cost and Schedule risks and

uncertainties

Geological and other Uncertainties affecting

production

Price Uncertainties

Other Risks and Uncertainties:

-Political risks-Uncertainties in Royalties regimes-….

Economic Analysis of the

Projects

Corporate Portfolio

Management

Strategic Decision

Quantitative cost and schedule risk analysis is an important component of portfolio management

Risk Management Affects Project Profitability

04/20/23 2013 Intaver Institute 5

Full circle cost of gas$/Mcf

Quantitative risk analysis provides realistic risk adjusted and risk mitigated cost estimates

Identifying and Managing Critical Risks is Key

04/20/23 2013 Intaver Institute 6

Risk

Quantitative risk analysis identifies and prioritizes critical risks

Which risks are critical?

04/20/23 2013 Intaver Institute 7

Risk 3Risk 3

Risk 4Risk 4

Risk 1Risk 1

Risk 5Risk 5

Risk 2Risk 2

Risk 1Risk 1

Risk 2Risk 2

Risk 3Risk 3

Risk 4Risk 4

Risk 5Risk 5

Sche

dule

ris

k

Cost

Ris

k

Safe

ty R

isk

Lega

l Ris

k

Qua

lity

Risk

……

……

…..

Risk

Envi

rom

enta

l Ris

k

Time Dependent C

osts

Cost

Ris

k

Time is Money: Cost and Schedule Risks

04/20/23 2013 Intaver Institute 8

• Schedule risk drives Costs due to time dependent resource costs

• 40% -70% cost risk is schedule driven

Sche

dule

ris

k

Input 1: Project Schedule

Input 2: List of Risks (Risk Register)

Assign Risks to Project Tasks and Resources

Perform Analysis

Risk Events Approach

Schedule

04/20/23 2013 Intaver Institute 10

Import project schedule from project management tool (Primavera, MS Project, etc..

Costs

04/20/23 2013 Intaver Institute 11

Schedules can include cost data for quantitative risk analysis of fixed costs

Resources

04/20/23 2013 Intaver Institute 12

Resources with rates are loaded with the project schedule to allow for risk analysis of time dependent costs

Risk Register

04/20/23 2013 Intaver Institute 13

Project risk register is integrated to the project schedule and cost

Risk Assignment

04/20/23 2013 Intaver Institute 14

Task R1 R2 R3 R4 R5 R6

Installing Microsoft Seismic monitoring

x x

Deliver frac fleet and install equipment

x

Deliver rig and equipment x

Well 1,2,3 (share common risks) x

Rig Mobilization x

Drilling x x x x

Installing Service Rig x

Completion (8 stages fracing) x x

Risks are assigned to project activities

Risk Assignment Interface

04/20/23 2013 Intaver Institute 15

30 % chance that risk causes a delay and

increase in cost of drillingRisk Assigned to task

‘Drilling’

Risk probability and cost and schedule impact are assigned to activities

Run Monte Carlo Simulation

04/20/23 2013 Intaver Institute 16

Monte Carlo simulation prioritizes risk based on impact on cost, schedule or other parameters

Results of Analysis

04/20/23 2013 Intaver Institute 17

Monte Carlo simulation results for cost and schedule can be viewed as histograms or cumulative probability

Risk Adjusted Project Schedule

04/20/23 2013 Intaver Institute 18

Schedule with risks

Schedule without risks

Arrows show risk assignments

Project Cost

04/20/23 2013 Intaver Institute 19

Schedule with risks

Schedule without risks

Results of quantitative cost risk analysis are shown on the Cost view

Risk Planning – Mitigation Plan

04/20/23 2013 Intaver Institute 20

Risk response plans can be plotted on a Risk Mitigation Waterfall chart

Pre and Post Mitigation Risk Scores

04/20/23 2013 Intaver Institute 21

Pre-mitigation

Post-mitigation

Risk Planning

Risk: Mechanical Problem with instrument

04/20/23 2013 Intaver Institute 22

Post Mitigation $16, 734, 906Pre-Mitigation Cost 17, 178, 397

Risk response plans can reduce the expected cost of the project

RiskyProject Enterprise

04/20/23 2013 Intaver Institute 23

Enterprise Risk Database:Schedules,

Risks,Mitigation Plans

RiskyProject Professional

RiskyProject Lite

RiskyProject Web

Future Reading

• Virine, L. and M. Trumper. 2007 Project Decisions: The Art and Science. VA: Management Concepts

• Virine, L. and M. Trumper. 2013. Project Think: Why Good Managers Make Poor Project Choices. England: Gower Publishing

• P. Leach. 2005. Late and Over Budget: Why Projects Always Seem to Take Longer and Cost More Than Planned. Projects & Profits, Vol. V Issue - XI, November 2005

• http://www.project decisions.org

• http://www.intaver.com/index-whitepapers.html

• http://www.risk-doctor.com/

• http://www.projectrisk.com

Contact Michael [email protected] Institute Inc.www.intaver.com

04/20/23 2013 Intaver Institute 24