How to Measure and Report PUE and DCiE

download How to Measure and Report PUE and DCiE

of 42

Transcript of How to Measure and Report PUE and DCiE

  • 7/30/2019 How to Measure and Report PUE and DCiE

    1/42

    SMSM

    Power Usage Effectiveness (PUE)& Data Center Infrastructure

    Efficiency (DCiE) Progress

    Dan Azevedo, Symantec

    Jon Haas, Intel

    Jud Cooley, Sun Microsystems, Inc.Mark Monroe, Sun Microsystems, Inc.

    Pam Lembke, IBM

  • 7/30/2019 How to Measure and Report PUE and DCiE

    2/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Agenda

    PUE / DCiE Background & Next Steps

    DCiE Detailed Analysis PUE / DCiE Usage & Public Reporting Guidelines

    PUE / DCiE Calculation Tool

    Free Cooling Map Power Configuration Calculator

    22

  • 7/30/2019 How to Measure and Report PUE and DCiE

    3/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    PUE / DCiE Background & NextSteps

    3

    3

  • 7/30/2019 How to Measure and Report PUE and DCiE

    4/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    DCiE Detailed AnalysisDan Azevedo, Symantec

    4

  • 7/30/2019 How to Measure and Report PUE and DCiE

    5/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Executive SummaryThe DCiE Detailed Analysis is to support and

    strengthen the Data Center infrastructureEfficiency (DCiE) metric. The intent is to enabledata center managers collectively to derive anduse DCiE as a global standard metric.

    55

  • 7/30/2019 How to Measure and Report PUE and DCiE

    6/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    DCiE Detailed AnalysisThis White Paper represents the first in a series that will

    provide a more detailed analysis of the PUE / DCiEMetric and represents the Basic level in the below tablewith the assumption of a dedicated data center facility:

    Level 1(Basic) Level 2(Intermediate) Level 3(Advanced)

    IT Equipment PowerMeasurement From

    UPS PDU Server,.

    Total Facility PowerMeasurement From

    Data Center inputpower

    Data Center inputless shared HVAC

    Data Center inputless shared HVACplus buildinglighting, security

    Minimum Measurement

    Interval

    Monthly/Weekly Daily Continuous(xx min)

    66

  • 7/30/2019 How to Measure and Report PUE and DCiE

    7/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    DCiE Detailed Analysis

    77

  • 7/30/2019 How to Measure and Report PUE and DCiE

    8/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    DCiE Detailed Analysis

    88

  • 7/30/2019 How to Measure and Report PUE and DCiE

    9/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    DCiE Detailed Analysis

    Table of Contents

    Introduction Type of Data Center

    Background and Assumptions Climate and Location

    DCiE Overview Data Center Design and Operation

    DCiE Subcomponents Measurement Period

    Obtaining Required Data Sometimes DCiE Seems To Go The

    Wrong Way

    Estimating Power Consumption Driving DCiE Efficiency

    Measuring Power Consumption DCiE and Future TechnologyAdvancements

    Power Metering Requirements Multiuse Facilities

    Factors Affecting DCiE Summary

    Dynamic Data Center Conclusion

    99

  • 7/30/2019 How to Measure and Report PUE and DCiE

    10/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    SummaryThis paper provides:

    Prescriptive information on how to calculate the

    efficiency metrics Multiple levels of implementation which enables a

    very simple basic approach to as much depth and

    complexity as desire Equipment categorization: infrastructure vs. ITequipment

    Power metering requirements

    Guidance on interpreting the metrics High-level guidance on multi-use facilities

    1010

  • 7/30/2019 How to Measure and Report PUE and DCiE

    11/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Usage And Public Reporting Guidelines forThe Green Grids Infrastructure Metrics

    Jon Haas, Intel

    11

  • 7/30/2019 How to Measure and Report PUE and DCiE

    12/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Reasons for Guidelines PUE/DCiE have become commonly used metrics for data center efficiency

    Factors such as environmental conditions, a data centers physicalcharacteristics, and timing and frequency of measurements can play a

    significant role in final results In addition, some individuals and organizations have used these metrics to

    promote design ideas that, while valuable, can provide misleading results

    Standard guidelines for the use and reporting of these metrics will:

    Enable a common language and nomenclature to compare results

    provide a process to support accurate, consistent results

    Provide additional transparency and accountabilitly in the process of measurementfor public claims

    In addition, these guidelines will support The Green Grid in:

    develop an auditing/certification process for the industry around these metrics

    develop a recognition program for those organizations showing strong resultsand/or improvements in data center energy efficiency

    1212

  • 7/30/2019 How to Measure and Report PUE and DCiE

    13/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Publicly reporting your Data

    The Green Grid will provide a means for organizations to publicly report theirmeasurements

    record their PUE/DCiE measurement data to The Green Grid

    provide background information about the data center, reporting the results andthe manner in which, and conditions under which, that data was collected

    provide a means to report any issues or difficulties in following TGGs proscribeprocesses and guidelines

    The Green Grid will also provide a portal through which organizations canview summary details on publicly reported PUE and DCiE results

    This portal will provide summary data on all registered reported results

    All reported results meeting TGG guidelines will be given a registration number that canbe referenced

    A subset of provided data will be publicly visible (see appendix 2 of WP or consent form)

    TGG will offer members the opportunity to provide a link to additional informationabout their result or data center via additional optional reporting

    Organizations reporting results have the option to participate in TGG awards orrecognition programs by complying with additional requirements

    1313

  • 7/30/2019 How to Measure and Report PUE and DCiE

    14/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum14

    Classes of Measurement Results

    Class Description Benefit to Reporting Organization

    Unrecognized A publicly reported result with noclaims of following TGGs guidelines.TGG will not comment on unrecognized

    results.

    Reported A publicly reported result by thereporting organization claiming theyfollowed TGGs measurementrecommendations and nomenclature

    guidelines. TGG will not comment onReported results.

    Reporting organization canuse standard materials fromThe Green Grid to explainprocess and results to

    audience.

    Registered A publicly reported result, with keyreport contextual data provided to TGGby the reporting organization to TGGsdata center performance database.

    Official registration ofreported result. Receipt of aregistration number from TGG.Link to public report data fromTGGs website.

    Certified A publicly reported result, with keyadditional data required for third-partyvalidation or certification of results,provided to TGG by the reporting

    organization.

    All benefits applicable toregistered results, plus,consideration of reportedresults in future TGG award or

    recognition programs.

  • 7/30/2019 How to Measure and Report PUE and DCiE

    15/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Usage and Reporting

    GuidelinesTo receive a PUE or DCiE registration number from The Green Grid: Follow The Green Grids measurement guidelines in the most recent revision of DCiE

    Detailed Analysis

    Report the process through which the data was collected (L1, L2, L3) using the

    nomenclature in the most recent revision of Usage and Public Reporting Guidelinesfor The Green Grids Infrastructure Metrics

    Report your measurement data and input the required information into the GreenGrids Metrics Data Collection Database (www.thegreengrid.org)

    Agree to The Green Grids metrics public reporting consent form

    If requesting to be considered for a TGG award, provide the extended dataset information into the Green Grids Data Collection Database forcertified measurements

    Additionally

    Report to The Green Grid any issues or difficulties in following TGGsproscribed processes and guidelines

    (optional, co-promotion) send the PUE or DCiE registration number, along with alink to any original source material or publication, to TGG [email protected]

    1515

  • 7/30/2019 How to Measure and Report PUE and DCiE

    16/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    PUE/DCiE Nomenclature

    Structure All PUE and DCiE measurements should be reported with subscripts that

    identify:

    The accuracy level of the measurement

    See The Green Grids Metrics: Data Center Infrastructure Efficiency Detailed Analysis The timeframe of the measurement

    E.g. yearly, monthly, weekly, daily

    The granularity of the measurement

    Frequency with which the data was collected

    E.g., monthly, weekly, daily, continuous Official PUE/DCiE reports will provide these information with subscripts

    appended to the Metric

    i.e. PUEx,y or DCiEx,y, where

    x describes the Level of the measurement (L1, L2, L3) L1, L2, and L3 are defined in the TGG White Paper: The Green Grid Metrics: Data Center

    Infrastructure Efficiency (DCiE) Detailed Analysis

    y describes the Timeframe and Granularity of the measurement

    y = timeframe identifier + frequency identifier

    1616

  • 7/30/2019 How to Measure and Report PUE and DCiE

    17/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Measurement Accuracy Reporting

    (from DCiE Detailed Analysis WP)Level 1(Basic) Level 2(Intermediate) Level 3(Advanced)

    IT Equipment PowerMeasurement From

    UPS PDU Server,.

    Total Facility PowerMeasurement From

    Data Center inputpower

    Data Center inputless shared HVAC

    Data Center inputless shared HVACplus buildinglighting, security

    Minimum Measurement

    Interval

    Monthly/Weekly Daily Continuous(xx min)

    1717

  • 7/30/2019 How to Measure and Report PUE and DCiE

    18/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Measurement Timescale and

    Granularity Reporting

    The y subscript on PUE or DCiE denotes the Timeframe and

    Granularity of the measurement y = timeframe identifier + frequency identifier [M, W, D, C]

    Frequency identifier:

    M for measurements taken monthly

    W for measurements taken weekly D for measurements taken daily

    C for measurements taken continuously (with frequency one hour orless)

    Except for those measurements collected with continuous data, alldata points that are averaged in the final measurement must betaken at the same time of day

    Single measurements are reported with no frequency identifier

    1818

  • 7/30/2019 How to Measure and Report PUE and DCiE

    19/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Example Reported Results

    0.45 DCiEL1,-- Single DCiE measurement (0.45) taken using a Level 1 meter placement

    0.51 DCiEL1,YM Yearly average DCiE (0.51), using data points gathered monthly with aLevel 1 meter placement

    1.6 PUEL1,MWMonthly average PUE (1.6) using data points gathered weekly with a Level

    1 meter placement

    0.43DCiEL1,WDWeekly average DCiE (0.43), using data points gathered daily with a Level

    1 meter placement

    1.8 PUEL2,WC Weekly average PUE using data points gathered continuously with a Level2 meter placement.

    2.1 PUEL3,YCYearly average PUE (2.1) using continuous measurements with a Level 3

    meter placement.

    19

  • 7/30/2019 How to Measure and Report PUE and DCiE

    20/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Specific Reporting Issues

    PUEs of < 1.0 and DCiEs of > 1.0 are *not* allowed

    Elements that go into the calculation

    Power consumed by IT equipment

    Power lost in distribution

    Power consumed by cooling equipment

    These elements are always 0

    Accounting for re-use of waste heat

    Waste heat re-use *does not* get included in either PUE or DCiE

    TGG will look into creating an additional metric to cover this

    Accounting for power generated on site PUE / DCiE is meant to cover areas of energy use in the data center

    Generation of power on-site is not incorporated into either the powerdistribution losses or cooling equipment requirements

    As such, it should not be considered in the PUE/DCiE calculation2020

  • 7/30/2019 How to Measure and Report PUE and DCiE

    21/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Conclusion We are driving the right behaviour!

    The Green Grid Metrics for data center efficiency are

    gaining widespread adoption, use and visibilityOrganizations are publicly reporting theirmeasurements and claiming highly efficient operations

    The Green Grid is implementing public reportingguidelines that includes standard processes andnomenclature to make the measured resultsmore transparent and consistent

    Stay away from PUEs of < 1.0 and DCiEs of >1.0, they are not viable

    2121

  • 7/30/2019 How to Measure and Report PUE and DCiE

    22/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    PUE Calculation Tool

    Jud Cooley, Sun Microsystems, Inc.

    2222

  • 7/30/2019 How to Measure and Report PUE and DCiE

    23/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Rationale and Objectives

    Sponsor: Container Assessment Task Force to allow casestudy comparisons

    Easily and accurately compute PUE In a consistent manner

    Allowing for apples-apples comparisons

    Container boundaries

    Building or room boundaries

    Web based One sheet printed report

    Data archival/retrieval

    2323

  • 7/30/2019 How to Measure and Report PUE and DCiE

    24/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    PUE with Physical boundaries

    Management reporting to visualize overhead

    Power: Transfer Switch, UPS, Transformer, Generator, Lighting, etc.

    Cooling: Tower, Condenser, Chiller, Pumps, etc.

    Other: Fire Supression, Control, Security, etc.

    IT Equipment: Servers, etc.

    Facility BoundaryContainer or RoomBoundary

    Facility equipment: air movers, powerdistribution, UPS, etc.

    IT Equipment: Servers, etc.

    2424

  • 7/30/2019 How to Measure and Report PUE and DCiE

    25/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Web screen shot example(Spreadsheet Prototype, artificial data)

    Seq Class Type Detail

    1 Facility Power Transfer Switch

    2 Facility Power UPS 5.0

    3 Facility Power DC Batteries / Rectifiers (non UPS Telco Nodes)

    4 Facility Power Generator

    5 Facility Power Transformer (step down) 5.0

    13 Facility HVAC Chillers 25.0

    19 Facility HVAC Return Fans 2.0

    ...30 IT Equipment Compute Devices Servers 50.0

    31 IT Equipment Network Devices Switches

    32 IT Equipment Network Devices Routers40 IT Equipment Other Other 2.0 2.0

    ...Total Facility + IT Power 32.0 59.0

    Total IT Power 2.0 52.0

    Total Facility Power (kW) 91.0

    Total IT Power 54.0

    PUE 1.69

    DciE 0.59Total Power (kW) at Container Boundary 59.0

    Total IT Power in Container 52.0

    Partial PUE (Container Boundary) 1.13

    Partial DciE (Container Boundary) 0.88

    Facility(kW)

    Container(kW)

    2525

  • 7/30/2019 How to Measure and Report PUE and DCiE

    26/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Output

    Single page PDF output Fileable report identifying configuration, date, data

    Useable for direct apples-apples comparisons

    Data saved in csv or a Data Base format TBD based on development discussion

    Consistent with other Green Grid tools

    Importable into spreadsheet

    Re-loadable

    2626

  • 7/30/2019 How to Measure and Report PUE and DCiE

    27/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Controversy over air movers

    Fan-less servers with rack fans rely on those fans

    Rack-based air movers might be considered either IT or

    facility depending on your point of view Proposed position is that the air mover power is part of

    the IT equipment

    Needs to be discussed in Committees

    PUE Calculator Tool will allow a separate line to enter airmover power that is not included inside the physicalboundary of the server, yet is required for the IToperation (to expose the ambiguity). That power will beallocated to IT, but will be left visible in the tool and theoutput.

    2727

  • 7/30/2019 How to Measure and Report PUE and DCiE

    28/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Status and Timing

    Consultants hired

    In development now

    Alpha version to be tested by Green Grid Task Forcemembers in Q1 2009

    Beta and release target is for Q2 2009

    2828

  • 7/30/2019 How to Measure and Report PUE and DCiE

    29/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Free Cooling Map/Web Tool

    Mark Monroe, Sun Microsystems, Inc.

    2929

  • 7/30/2019 How to Measure and Report PUE and DCiE

    30/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Concept and Features

    Estimate the number of hours of free cooling that maybe possible based on weather data at any location in

    the U.S. Consider European and APAC data in the design so that data

    can be added in the future without major changes to theapplication or database.

    Climate data will be analyzed to determine the numberof hours per year that either fresh air or evaporativecooling might be used in a data center.

    30

  • 7/30/2019 How to Measure and Report PUE and DCiE

    31/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Concept and Features (contd)

    Two colorful maps must be produced; one showing the U.S. color-coded to show the number of hours

    of fresh air cooling possible,

    the second map will show the U.S. color-coded to show thenumber of hours of evaporative cooling possible.

    31

  • 7/30/2019 How to Measure and Report PUE and DCiE

    32/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Concept and Features (contd)

    32

  • 7/30/2019 How to Measure and Report PUE and DCiE

    33/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Concept and Features (contd)

    A web tool must be produced which allows auser to enter their own location, via zip code,

    and the data center set points for temperatureand humidity that they which to examine forhours of free cooling

    33

  • 7/30/2019 How to Measure and Report PUE and DCiE

    34/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum34

  • 7/30/2019 How to Measure and Report PUE and DCiE

    35/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    RFP Responses

    weatherbank.com selected to implement

    Response within budget estimates

    Approved by Board 21 Jan 09

    Prototype ready now

    Seek approval from TC and Board in Feb Release in March

    35

  • 7/30/2019 How to Measure and Report PUE and DCiE

    36/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Roadmap/Futures

    Individual maps available for $150 direct fromweatherbank.com

    Feedback page allows users to consult directly

    Review in 3 months, determine enhancements

    Possibilities: European and APAC data/locations/calculations

    Simple model for water used by evaporative cooling

    Input location by latitude/longitude Redisplay map with user-input parameters

    Connect with DSIRE and other incentive databases

    More complex models, more accurate results36

  • 7/30/2019 How to Measure and Report PUE and DCiE

    37/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Power Distribution ConfigurationsOnline Efficiency Estimator Tool

    Pam Lembke, IBM

    37

  • 7/30/2019 How to Measure and Report PUE and DCiE

    38/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Tool Purpose

    The tool:

    Is for use as a companion to

    Qualitative Analysis of Power Distribution Configurations forData Centers, TGG WP #4 and

    Quantitative Efficiency Analysis of Power DistributionConfigurations for Data Centers, TGG WP #16

    Reduces the need for paper rewrites, as the tool can beeasily updated regularly

    Allows readers and users to test their own components

    and proposed system architectures

  • 7/30/2019 How to Measure and Report PUE and DCiE

    39/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Features

    Users are able to:

    Compare two topologies at a time

    Input data points (load vs efficiency) of their own componentsfor the calculations

    Create their own topologies based on their components or pre-defined TGG components

    Save components and topologies Print input and results in PDF

    Tool will automatically calculate full efficiency curves for

    components

    end-to-end efficiency curves for the two topologies

    T l

  • 7/30/2019 How to Measure and Report PUE and DCiE

    40/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Tool

    Mock Up

  • 7/30/2019 How to Measure and Report PUE and DCiE

    41/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum

    Availability

    The tool is scheduled to be available around Q22009

    It will be accessible to members only via TheGreen Grid website

  • 7/30/2019 How to Measure and Report PUE and DCiE

    42/42

    SMSM

    Copyright 2009, The Green Grid The Green Grid Technical Forum42

    Thank you for attending

    The 2ndAnnual Green Grid Technical Forum

    For more information, please visitwww.thegreengrid.org