How to manufacture a conveyor for pcb handling
-
Upload
shenzhen-southern-machinery-sales-and-service-co-ltd -
Category
Technology
-
view
403 -
download
0
Transcript of How to manufacture a conveyor for pcb handling
www.smthelp.com
Design as your require:-Conveyor length: 0.5m;1.0m;1.5m or other- Working lighting- Power supply
www.smthelp.com
*Note: The component providing 'contact closure' may be a relay or a transistor. 'contacts open' will always be infinity but 'contacts closed' may not be 0 ohms. In the case of a transistor it will be approximately 10K ohms and polarity of pins 1 and 3 are positive. Wrong polarity while testing will give false readings.
This conveyor communicates with other machines through a SMEMA (Surface Mount Equipment Manufacturers Association) interface. SMEMA is an equipment standard for single board transfer for manufacturing systems of surface-mounted printed circuit boards. Reference the following chart for interface function
SMEMA Communication/Interface
www.smthelp.com
Buffer Conveyor S-350C• PCB Conveyor rail length: 0.5m;1.0m;1.5m• Rail Fix mode: Front Fix (Option: Rear fix)• PCB Conveyor direction: L→R (Or R→L)• Control System: Relay Board (2 sensor without stopper)• PCB Conveyor Height: 900±20 mm• PCB Conveyor Width: 50-250/300/400/500mm• PCB Conveyor Speed: 0-2M/min• Available to communications with other devices by
SMEMA signal plug• Exact thread shaft structure to ensure the adjustment
of rail Width parallel• Used durable Anti-static belt with strengthen
Aluminum Alloy rail to be reliable• Power Consumption: Approx. 40W• Power Supply: Single Phase 220V, 50HZ • Weight: Approx. 70kg
www.smthelp.com
Installation Procedure 1) Set conveyor height
2) Locate in Position
3) Set final transfer height
4) Connect power to enclosure
5) Connect air (if required)
• Adjust to approximate transfer height (+1.00” with telescoping leg). (Hardware located on the backside of leg and control box.) • 0.38” – 0.50” gap between rails of adjacent equipment. • Ensure level transfer by adjusting leveling pads. • Ensure fixed rails are aligned.
• Adjust leveling feet to achieve final height (maintain level). • Tighten lock nuts on leveling pads.
• Connect power to disconnect via provided entry holes. - Line (brown or black) to position #1. - Neutral (blue or white) to position #3. • Connect the ground conductor to the ground block. (Note: It is the user’s responsibility to ensure that power wiring from the customer source to control enclosure meets all applicable local and national wiring codes.)
• 6 ft of ¼” diameter tubing is provided for air hookup.
5 Steps for installation
www.smthelp.com
Welcome inquiry
1,Please visit : www.smthelp.com
2, Find us more: https://www.facebook.com/autoinsertion
3, Know more our team: https://cn.linkedin.com/in/smtsupplier
4, Welcome to our factory in Shenzhen China
5, See more machine working video, please Youtobe: Auto Insertion
6, Google: Auto+insertion, to get more informations
7,Looking forward to your email: [email protected]