How the NCSX Project Does Business
-
Upload
isabella-walsh -
Category
Documents
-
view
22 -
download
1
description
Transcript of How the NCSX Project Does Business
1/18/2005 Module 4 2
Purpose Provides review of how the NCSX Project does business
This module will focus on: Work Planning Processes on NCSX, including:
Work Plans Jobs/WAFs WP to WAF mapping
Later modules to will address other parts of how the NCSX Project will do business
Modules 1 & 2 are intended to provide overview of the NCSX Project Web and the NCSX Engineering Web
Modules 4-10 will focus other aspects of how the NCSX Project will do business
The NCSX Engineering Web is, to a major extent, the electronic NCSX filing system
Exceptions are the models and drawings contained in the Pro/INTERALINK data base and the hard copy supplier and other PPPL documents stored in the PPPL Operations Center
However – bulk of files stored electronically on this web
1/18/2005 Module 4 3
Work Planning
Work Plans
Per ENG-032
Jobs (WAFs)
• Essentially P3 resource loaded schedules
• Provides authorization to start work
WP to WAF Mapping
• Ensures that every WP has at least one job/WAF associated with it
1/18/2005 Module 4 4
PPPL Work Planning Processes Defined by PPPL Engineering Procedure ENG-032
Applicable to all activities at PPPL involving physical changes to engineering, facilities, control computing, and technical infrastructure and equipment or involving collaborations for others
NCSX Project will follow ENG-032 Purpose of ENG-032, Work Planning Procedure, is to:
Establish criteria by which work planning will proceed Integrates safety into work planning Organizes the systematic avenues by which changes will be planned,
prepared, reviewed, implemented, and documented Key decision maker in this process is the Responsible Line
Manager (RLM) List of RLMs found at: < http://engineering.pppl.gov/RLMs.doc > RLM will approve Work Plans (WPs)
As required, the PPPL Deputy Director shall convene a Work Planning Review Board to review WPs in process to ascertain whether they comply with the graded approach guidelines contained in ENG-032
1/18/2005 Module 4 5
When is a WP Required? RLM, in consultation with the Cognizant Engineer (usually Job
Manager), will determine whether or not a WP is required Graded approach provides options that balance priorities,
identify ES&H requirements, ensures proper controls, and provide an auditable package upon which to base authorization
Graded approach permits alternative procedure to be utilized vs. WP to plan work and mitigate hazards, but the default it to require a WP
Regardless to graded approach, a WP is always required if the change:
Is large or complex or represents a new installation into a usable space
Has a significant ES&H impact Involves Tritium or other radioactive contaminated or activated
equipment Impact multiple projects, systems, or groups Changes the scope or intent of the original design
1/18/2005 Module 4 6
Guides to Preparing a WP Work Planning Form is electronic
Will need to authenticate to get to this web page: http://workplanning.pppl.gov
Electronic submittal and signatures PROC-004 provides good
guidelines to assist in preparing WP (especially for PDR or FDR)
WP leads to preparation of a Job in the Primavera (P3) database
1/18/2005 Module 4 7
What Does a WP Achieve? Systematic way to plan the anticipated
requirements of a job Defines the scope of the job Performs Hazard Analysis Factors into planning all potential
environmental, safety, and health issues Establishes procedural and testing
requirements Establishes clear approval indicating
ownership of the work
1/18/2005 Module 4 9
NCSX Design Review Process Design reviews are performed to clarify and verify
compliance with functional, project, ES&H, and quality requirements
NCSX Project will follow ENG-033 Peer Reviews, Conceptual Design Reviews (CDRs),
Preliminary Design Reviews (PDRs), and Final Design Reviews (FDRs) will be conducted and follow requirements of ENG-033 – Design Review Reports, CHITs, etc.
In general, all CHITs should be resolved prior to the next design review, and in some instances much sooner
Major difference is that on NCSX, all the design review documentation will be stored in an electronic format vs. in hard copy in the Ops Center
1/18/2005 Module 4 10
Guidelines for Conducting Design Review Both ENG-033 and PROC-004
contain design review objectives and design review input documentation The input documentation should be
completed and provided to the Design Review Board prior to the review
Until all prerequisite design review documentation is completed, the review will NOT be scheduled or held
1/18/2005 Module 4 13
Summary This training module has focused on the work planning
and design review processes The NCSX Project is committed to following the
requirements and processes contained in: PPPL ENG-032 – Work Planning PPPL ENG-033 – Design Verification (as it pertains to
Design Reviews) NCSX PROC-004 augments and supplements ENG-032 and
ENG-033 No exceptions or modifications from compliance with
ENG-032 No exceptions or modifications from compliance with
ENG-033 with the exception that NCSX design review records will be stored electronically on the NCSX Engineering Web vs. in the Ops Center