Older Toddler AreaHouse and Bridge
Instructions for building the house and bridge
Tools needed:Measuring tape
Sharpie MarkerCircular saw
HammerElectric Drill
Philips head driver bitExtension cord
Sabre saw or SawzallMetal shears
Bridge Materials needed:6 treated 2x4x8 boards
24 treated 1-1/4x6 deck boards4 concrete post bases
1-1/2 deck screwsHouse Materials needed:13 treated 2x4x8 boards22 treated 1-1/4x6 deck boards
3 pine 1x4x8boards1 treated 2x6x10 board
3-1/4 20D galvanized Nails1-1/2 deck screws
Hurricane plate ties1-5/8 sheetrock screws
2 galvanized x4 long lag bolts
-
7/27/2019 House and Bridge Instructions
2/11
Older Toddler AreaHouse and Bridge
Instructions for building the house and bridge
1. The first step is to layout the concrete deck bases. These
will be the supports for our bridge. The bases should be 96apart and 36 wide.
2. Place two eight-foot long 2x4s on the concreteblocks
3. Cut four of the eight-foot long2x4s as shown.
Place them like so.
-
7/27/2019 House and Bridge Instructions
3/11
Older Toddler AreaHouse and Bridge
Instructions for building the house and bridge
4. Cut the 24 of the eight-foot long 1-1/4 deck boards in half. When you are done, you shouldhave 48 boards.
5. Next, we will attach the deck boards to the 2x4s. Start in the middle span. Mark the middle of
each 2x4 with the Sharpie. Place a board on either side of this mark. Adjust the boards so thatthey are centered on the bridge (the boards should hang over about 5-1/4 on each side).
6. Now you can keep attaching boards until the bridge is complete.
-
7/27/2019 House and Bridge Instructions
4/11
Older Toddler AreaHouse and Bridge
Instructions for building the house and bridge
7. Now time to build the house. First thing is to use the circular saw to cut the 2x4s.
Cut the following from the treated 2x4s:18 boards at 3-10-1/2 long that we will use as studs
2 boards at 4-0 long that will be top plates in the wall4 boards at 7-1/2 long that will be bottom plates in the wall
4 boards at 3-10-1/2 two will be top, and two will be bottom platesRefer to cut plan;
-
7/27/2019 House and Bridge Instructions
5/11
Older Toddler AreaHouse and Bridge
Instructions for building the house and bridge
8. Now it is time to frame the walls. Do this with the wall lying flat on the ground.
There will be two of each of the walls shown above.
3-5 Top Plate
3-5 Sill Plate
Stud
Stud
Stud
Stud
Stud
Stud
Stud
48 Top Plate
7 Sill Plate 7 Sill Plate
SIDE WALL ENTRY WALL
Use two nails at
each location.
-
7/27/2019 House and Bridge Instructions
6/11
Older Toddler AreaHouse and Bridge
Instructions for building the house and bridge
9. Carry one of the Side Walls to the bridge. Center it onthe span. Tip the wall into place and nail the bottom plate
to the bridge. Have someone hold it in place.
10. Bring one of the Entry Walls. Tip it into place and nail
the corner studs of the two walls to one another.
11. Bring the second Side Wall to the bridge. Make sure
that it is centered on the span. Nail the bottom plate to thebridge. Nail the corner studs to the Entry Wall.
NAIL
NAIL
NAIL
NAIL
NAIL
NAIL
NAIL
NAIL
-
7/27/2019 House and Bridge Instructions
7/11
Older Toddler AreaHouse and Bridge
Instructions for building the house and bridge
12 Bring the second Entry wall to the bridge. Place it inposition and nail the corner studs together with both side
walls.
Now nail the bottom plate of the two Entry Walls to thebridge.
13. The next step is to cut the 1-1/4 deck boards to use
for the siding on the house. We will need to cut thefollowing:
32 boards at 7 long16 boards at 48 long
Refer to the cut plan on the next page
NAILN
AIL
-
7/27/2019 House and Bridge Instructions
8/11
Older Toddler AreaHouse and Bridge
Instructions for building the house and bridge
The boards will be screwed on using the 2 deck screws.Use four screws at the 7-1/4 boards and six at the 48
boards
Screws top andbottom at stud
location
-
7/27/2019 House and Bridge Instructions
9/11
Older Toddler AreaHouse and Bridge
Instructions for building the house and bridge
14. Attach six hurricane ties to the top plate of the houseside walls. The middle ties go at the half-way mark and the
ties at the ends go with the vertical flange in-line with theedge of the stud below. The side must be bent down before
it is attached (or before you attach the uppermost deckboard, attach the tie and bend it, then screw the last deck
board on over the flange). Screw the ties down with the 1-5/8 sheetrock screws
15. Use a pair of metal shears to cut off the left flange oftwo hurricane ties. Then, use a pair of metal shears to cut
off the right flange of two more hurricane ties.
16. Cut a 2x6 to 48 in length.
17. Screw the trimmed hurricane ties to the ends andmiddle of the 2x6x4 ridge beam. Bend the flange over the
ends of the 2x6 with a hammer.
Bend edge of tiedown before it is
screwed in
CutLine
Hammer these
flat
-
7/27/2019 House and Bridge Instructions
10/11
Older Toddler AreaHouse and Bridge
Instructions for building the house and bridge
18. Cut the rafters from the 2x4 as shown in the cuttingplan of step 7 (shown partially here)..
19. With one person holding the ridge beam, screw the rafters into the hurricane ties of the ridgebeam and then to the hurricane ties on the top plates. This will be awkward and annoying.
20. Attach the deck boards at the
gable.Refer to the deck board cut plan on
step 13.
An alternative to cutting the angle onthe boards is to cut the boards square,
and then trim the excess after theboards are screwed on. There is
sufficient extra deck board for this.
Rafter extendsjust to end of
hurricane tie
-
7/27/2019 House and Bridge Instructions
11/11
Older Toddler AreaHouse and Bridge
Instructions for building the house and bridge
21. Attach the deck board roof.
22. Cut the 1x4x8 boards using this cut plan.
Attach the rake boards with the 1-5/8 Sheetrock screws. The 1x4s are likely to split and thesmaller screws make this less likely. If the 1x4s still are trying to split, pre-drill the holes in the
1x4s. The rake board should extend beyond the gable siding.
23. Attach the under soffit trim boards. Use the 1-5/8 sheetrock screws for this.
24. The decorative ridge isin several parts. Follow the
true-size cutting plan. A
hole will be drilled verticallythrough the decorative ridgeboard. A x 4 lag bolt
will be screwed down intothe actual ridge beam. The
curved trim will be drilled,screwed and glued using the
2 deck screws.
This is the rake. Itattaches to the ends of
the rafters