    Contents

    01 Introduction 04

    02 Design 08 Design Guidelines 12

    Area Schedule 26

    03 Cost 32

    Cost Drivers 36

    Cost Planning 46

    Cost Models 52

    04 Procurement 66

    05 Summary 76

    06 Contact Details BackCover

  • 7/21/2019 Hotel Build Cost Guide

    4/80

    Introduction

    At AECOM we offer a range

    of services that meet the

    development and asset

    management needs of

    hotel owners, operators and

    developers from initial feasibility

    through to planning, design,construction and operation.

    Before there is a design, there isan idea for a hotel. Assessing thefeasibility of a hotel developmentrequires you to understand whatthe market opportunity, needs

    of the market and cost of thedevelopment are.

    This guide explainsthe relationshipbetween thedesign and the

    costs of hoteldevelopment anddemonstratesthe benefits ofobtaining cost

    advice throughouteach stage ofthe developmentlifecycle.

    4: INTRODUCTION

  • 7/21/2019 Hotel Build Cost Guide

    5/80

  • 7/21/2019 Hotel Build Cost Guide

    6/80

  • 7/21/2019 Hotel Build Cost Guide

    7/80

    Based on outline informationabout the type and size of hotelproduct and the amenities that

    the market requires, the costconsultant is able to provide aninitial cost estimate to informthe development appraisal.

    During the design phase,understanding the way in which

    the design of a hotel can influencethe cost can help ensure that thecorrect choices are made at theearliest stages of a project andwill avoid expensive re-design andcost in use.

    By providing an analysis of cost

    by area and function, the costconsultants advice will ensurethat costs are being allocatedto those parts of the hotel thatwill deliver the best return oninvestment over the lifecycleof the asset.

    Once the design is completethe next step is to procure acontractor to undertake the

    construction of the hotel. Thisrequires an understanding ofthe various procurement optionsavailable to achieve the rightbalance between price and risk.

    This guide does not provide all

    of the answers but it will providethe reader with an understandingof the important relationshipbetween the design and thecost of a hotel and the benefitsof obtaining cost advice at eachstage of the development process.

    INTRODUCTION :7

  • 7/21/2019 Hotel Build Cost Guide

    8/80

    DESIGN

  • 7/21/2019 Hotel Build Cost Guide

    9/80

  • 7/21/2019 Hotel Build Cost Guide

    10/80

    Understanding the way inwhich the design of

    a hotel influencesthe cost means that

    the correct choices are

    made at the earliest

    stages of a project

    and avoids expensivere-design and cost in use.

  • 7/21/2019 Hotel Build Cost Guide

    11/80

  • 7/21/2019 Hotel Build Cost Guide

    12/80

    Design guidelines

    Food and beverage outlets

    Food and beverage outlets andrestaurant requirements vary bylocation and hotel type. However,

    a good rule of thumb is to providerestaurant seats ranging from0.75 to 1.2 times the number ofguestrooms. This does not takeinto account specific requirementsfor conferences, functions orbanqueting, for which additional

    provision will need to be made in,or adjacent to, the function suites.

    Most luxury hotels will have atleast two restaurants but somehotels operating at the upper levels

    of the market can offer up to four orfive different types of restaurants.Generally, there will be a main all-day dining area that serves as themain breakfast area in the morningand can be converted into lunchand dinner venues with different

    settings. The restaurant diningarea is calculated on the basis ofan area-per-seat allowance. Thisallowance varies between about1.5 to 2.5m per seat, dependingon the style and mode of operationof the venue. Further allowancesshould be made for the service

    stations and circulation spacewithin restaurants.

    12: DESIGN

  • 7/21/2019 Hotel Build Cost Guide

    13/80

  • 7/21/2019 Hotel Build Cost Guide

    14/80

  • 7/21/2019 Hotel Build Cost Guide

    15/80

    Lounges and bars

    A hotel is also likely to have anumber of lounges and bars. Theseating capacity allowance for

    these ranges from 0.5 to 0.9 timesthe number of hotel guestrooms.The area calculation is made on anarea-per-seat basis.

    Kitchens, storage and supportareas are excluded from thesearea calculations. Kitchens are

    calculated as food preparationareas and form part of the backof house and support areas.

    Meeting and function rooms

    Ballroom / banquet hallWhile many major hotel chainshave their own design and area

    guidelines for the capacitiesof a ballroom / banquet hall, aminimum size would be in theregion of 750m. The generalallowance for calculation of thenet area of the ballroom / banquethall is in the region of 1.20m per

    seat. The minimum total number ofseats is the equivalent of 1.5 to 2.0times the number of guestrooms.

    DESIGN :15

  • 7/21/2019 Hotel Build Cost Guide

    16/80

    Junior ballroomand function rooms

    In addition to a main ballroom /banquet hall, the hotel may havea junior ballroom and smaller

    function rooms. A junior ballroomtypically has a seating capacityof 400 to 500 people.

    Function rooms that double up asmeeting rooms should be a seriesof rooms catering for groups of20 to 50 people. There should be at

    least three of this type of functionroom. In addition, there may bea provision for a boardroom witha size of around 50m. The totalcapacity of the function / meetingrooms should be in the proportionof approximately 0.5 times the

    number of hotel rooms.Essential for all function suitesis the concept of flexible meetingspaces, allowing for changesin shape, and size by meansof acoustic, sliding / foldingpartitions. Each potential

    function area must be able to beserviced separately.

    Pre-function areas /break-out space

    These should be approximately33% of the area of the ballroom,banquet hall, junior ballroom,

    function and meeting rooms.

    Support areas

    All of the above areas excludesupporting areas such as furniturestores, restrooms, general storage,

    AV control rooms, interpretersrooms and so on. As a rule ofthumb, these would be allowed ona square metre per seat basis.

    16: DESIGN

  • 7/21/2019 Hotel Build Cost Guide

    17/80

    General public areas

    The general public area of a hotelmay include:

    (a) Business centre, including A reception / waiting area

    A secretarial area

    A small conference /meeting room

    Small booths / ofces

    (b) Health club / fitness centreSpace should be allocated for:

    An entry area

    Common facilities such as

    reception, examining room andnurses room

    A beauty centre

    A mens and womens spa

    A tness centre and gymnasium

    A spa restaurant / juice bar

    Employee facilities such as

    lockers, lounge and restroom

    (c) Commercial spaceThese spaces are often let out.Often there are around four to five

    such outlets in the hotel.

    (d) Front lobby and front officeThis covers the main entrancelobby, which should be a generousspace. The area allowance iscalculated on the basis of a squaremetre per hotel room. Supporting

    the main entrance lobby is thelobby waiting area. An allowanceis made for 20 people on the basisof 2.3m per person. These areasgenerally have higher or double-volume ceilings and pricing shouldtake this into account.

    DESIGN :17

  • 7/21/2019 Hotel Build Cost Guide

    18/80

    Provisions should be made formale and female restrooms, withthe female restroom slightly

    larger to allow extra space for avanity area. A janitors room isalso required to store cleaningequipment. A further allocationis made for a reception desk areatogether with a front office. As aguide, 1.75m length is assumed for

    each workstation at the receptiondesk. One workstation is requiredfor every 75 rooms. A width of1.5m is allowed for working spacebehind the counter and a width of4m is allowed for guest queues infront of the counter.

    Back of house, supportand services areas

    These are the non-public areas ofthe hotel. There should be minimalinterior designers input for these

    areas, except for some of theoffices. The spaces occupied underthis category include:

    (a) Administration andservice areasThe administration andservice areas include various

    departmental offices, such as:

    Front ofce support containing

    the office of the front officemanager and credit manager,telephone operators room,cashiers room and counting room.

    Safe-deposit box, stationerystorage, general office and pantry.

    18: DESIGN

  • 7/21/2019 Hotel Build Cost Guide

    19/80

  • 7/21/2019 Hotel Build Cost Guide

    20/80

  • 7/21/2019 Hotel Build Cost Guide

    21/80

    Executive ofces containing

    the offices of the generalmanager, resident manager,

    food and beverage manager,assistant food and beveragemanager, general office areas,executive boardroomand storage.

    Sales ofces containing the

    office of the sales director,

    sales manager, market analyst,sales executives, group salesco-ordinator, public relationsmanager, reservations manager,general office, conference roomand storage.

    Catering / banquet ofces

    containing the offices of thecatering manager, banquet

    representatives, conventionservices and secretarial area.

    Accounting ofces containing

    the offices of the financialcontroller, assistant financialcontroller, accounting workarea, payroll manager, general

    office and storage and mensand womens restrooms.

    DESIGN :21

  • 7/21/2019 Hotel Build Cost Guide

    22/80

    (b) Food preparation, supportand service areas

    Food preparation and service areasinclude support spaces for variousdepartments, such as:

    Food preparation, main and

    support kitchens containingproduction kitchens supportingthe banquet hall and function

    rooms, kitchens for the variousrestaurants, bakery / pastryshop and offices for theexecutive chef and roomservice manager. Areacalculations are generallymade on the basis of area perseat. Alternatively, as a general

    guide, an area equivalent to 40%of restaurant net areas wouldmake up the kitchen areas.

    Storage areas containing

    storage for dry food, refrigeratedfood (cold rooms), beverages,

    refrigerated beverages,ballroom liquor, the service bar,silverware, chinaware,glassware, utensils andstewards and janitors rooms.Area calculations are generallymade on the basis of an

    area per seat for food storagesupporting the kitchens, andarea per key for general storage.Generally, storage areas will bein the region of 30 to 50% of nettotal food preparation areas.

    22: DESIGN

  • 7/21/2019 Hotel Build Cost Guide

    23/80

    Service entrance areas

    containing areas for the loadingdock and truck parking bays,

    receiving areas, receiving office,office for the purchasingmanager, purchasingdepartment, security /timekeeper, flower shopstorage, trash holding area, wetgarbage refrigeration area, can

    wash, garbage compactor,empty bottle storage,refrigerated storage forfood, employee entrance area,compressor rooms and the like.

    Housekeeping areas

    containing offices of theexecutive and assistant

    housekeeper, housekeepingclerks, seamstress, fittingrooms and storage for linen,supplies, lost and found, uniformand uniform-issue rooms.

    Laundry areas containing the

    laundry and valet office, laundry

    room, soiled linen sortingarea, guest laundry area, valetservice room, supplies storageand compressor room.

    DESIGN :23

  • 7/21/2019 Hotel Build Cost Guide

    24/80

    Area calculations for

    housekeeping and laundryareas are generally made on

    the basis of area per key ofthe hotel. Requirements forlaundry facilities will varybetween locations and betweenoperators. In many instances,the laundering of bedsheetsand towels is outsourced. If so,

    the requirements for in-houselaundries are limited to a smallnumber of domestic machines.

    Engineering areas containing

    offices of the engineeringdirector, assistant engineer,general maintenance and

    secretary, paint shop, carpentryshop, upholstery shop, plumbing /refrigeration shop, electricalshop, key shop, TV repair shop,parts storage, energymanagement computer roomand janitors store.

    Mechanical areas usually cover

    two major locations, one ofwhich is normally in the

    basement, the other on theupper level or roof space ofthe hotel.

    Mechanical areas in the

    basement contain theengineers control room,engineers office, toilet and

    locker, janitor room, boilerrooms, fire control pump rooms,electrical sub-stations,electrical rooms and wet risertanks.

    Mechanical areas in the

    upper levels can contain the

    air handling units, domesticwater tanks, sprinkler tanks,wet riser tanks, condenserwater storage tanks, electrical,switch and power rooms,although these may also behoused at the basement level if

    space allows.

    24: DESIGN

  • 7/21/2019 Hotel Build Cost Guide

    25/80

    (c) Employee facilities

    Employee facilities areas include

    spaces for: Human resources ofce

    containing rooms for thepersonnel manager, assistantpersonnel manager,interviewing, training manager,training, first aid application

    and storage. Employee areas containing

    staff lockers and shower areas,toilets, dining and recreationareas. If not provided in thefeasibility study or the businessplan, the number of employees

    can be calculated on thebasis of employees per key. Forfive-star hotels, the range canbe from 1 to 1.5 employees perkey. The changing and lockerareas are generally based onarea per employee.

    DESIGN :25

  • 7/21/2019 Hotel Build Cost Guide

    26/80

    Using functional area datafrom previous projects and fromoperators standard requirements,

    it is possible to create a reasonablyaccurate assessment of the spacerequirements for a hotel.

    This can form the basis ofpreliminary budget calculationsfor a hotel of a particular standardwith a stated number of rooms and

    ancillary functions (restaurants,fitness, spa, banqueting and so on)in advance of the development ofany design.

    The hotel area schedule must,therefore, be based on realisticnumbers. Any gross over or under

    allowance of areas would cause adistortion of the forecast cost.

    The area allowances must ofcourse be tested against otherhotels of similar standard in the

    geographical region, to checkthat it is competitive. Ideally, themarket feasibility study provides asuggested high level area programbased on market requirements.

    A preliminary budget costingfor a hotel development can

    be generated quite quickly andefficiently, based on data forsimilar existing hotels, designcriteria of major hotels andknowledge of the market. Thisincludes setting the number ofhotel room bays and keys and

    the total seating capacitiesfor food and beverage outlets,entertainment lounges, banquet,ballroom and meeting facilities. Itshould also cover the capacity ofthe health club facilities and thesize and number of retail outlets.

    Area schedule

    26: DESIGN

  • 7/21/2019 Hotel Build Cost Guide

    27/80

  • 7/21/2019 Hotel Build Cost Guide

    28/80

    Worked example based on a luxury hotel

    Bays Keys Total bays

    A. Standard guest rooms1. King rooms 1 200 200

    2. Queen rooms 1 100 100

    3. Accessible rooms 1 20 20(circa 5% of total room count)

    4. Other standard rooms 1 55 55(eg twin)

    B. Suites1. Junior suites 2 40 80

    2. Executive suites 3 10 30

    4. Presidential suites 5 2 10

    5. Club lounge 5 - 5

    Total 427 500

    Based on the above configuration, the total number of bedroom bays is500 and the total number of keys is 427 about 85% of the total numberof bays.

  • 7/21/2019 Hotel Build Cost Guide

    29/80

    Typical total area allowancesfor luxury hotels vary aroundthe world, from circa 80m to

    over 120m of gross floor area(excluding parking and externalareas) per bay. Hotels in moreWestern locations tend to havesmaller bedrooms than thosein the Middle East or Asia. A500-bay five-star hotel could

    therefore be expected to havea range of gross floor area ofbetween 40,000 to 60,000m.

    DESIGN :29

  • 7/21/2019 Hotel Build Cost Guide

    30/80

    The breakdown between thebedroom zone, public areas andback of house for a notional 500-

    bay, 50,000m hotel would be:

    A. Guestrooms and suites 22,500 to 30,000m 55 - 60%

    B. Public area 10,000 to 15,000m 20 - 30%

    C. Back-of-house 7,500 to 12,500m 15 - 25%administrative, supportand services areas

    Hotel total gross area40,000 - 57,000m 100%

    Based on the above hotel floorareas, the gross area per bayranges between 80 to 115m.

    The net areas of the bedrooms(including bathrooms) variesaccording to geographical location,from a low of about 35m up toabout 55m but typically between40 and 50m net bedroom area is

    a good guide

  • 7/21/2019 Hotel Build Cost Guide

    31/80

  • 7/21/2019 Hotel Build Cost Guide

    32/80

    COST

  • 7/21/2019 Hotel Build Cost Guide

    33/80

  • 7/21/2019 Hotel Build Cost Guide

    34/80

    By providing an analysisof cost by area and

    function, the costconsultant is able to

    ensure that costs are

    allocated to those parts

    of the hotel that deliver

    the best return oninvestment over the

    lifecycle of the asset.

  • 7/21/2019 Hotel Build Cost Guide

    35/80

  • 7/21/2019 Hotel Build Cost Guide

    36/80

    The major cost drivers of a hoteldevelopment include:

    a. Site location, shape, conditions,means of access and visibility

    b. Position of the hotel inthe development

    c. The shape and form of thebuilding

    d. The external facades,particularly the extent ofglazing and cladding

    e. The level of sophisticationof building services and fire-protection systems

    f. Particular requirements of the

    chosen hotel operator

    g. Shape and layout of theguestrooms zone, particularly ifthis is a tower

    h. The level of provision andfacilities of rooms

    i. The storey height ifexceptionally high, it willneed a heavier structure,more complex foundations,additional lifts and fire-fighting installations

    j. Location of function rooms.

    One major impact on the costof the structure is the locationof the main function room orballroom. The ballroom shouldnot be located directly belowthe hotel guestrooms tower,as it requires column-freespace that is difficult and

    expensive to accommodate andis likely to require theintroduction of transferstructures at the base of theguestroom tower

    Cost drivers

    36: COST

  • 7/21/2019 Hotel Build Cost Guide

    37/80

  • 7/21/2019 Hotel Build Cost Guide

    38/80

    The choice of guest

    room configurationcan affect area

    efficiency by as

    much as 20%

    of the grossfloor area.

    Another area for carefulconsideration is the location ofthe bank of guest and service

    lifts rising up to the guestrooms.These should be located centrallyto the guestroom block and theguest lifts should descend into theentrance lobby, where pedestriantraffic can be monitored by thefront desk.

    A third major consideration is theconfiguration of the guestroomblock, particularly if this is inthe form of a tower. Analysisshows that some shapes andconfigurations of a guestroomtower yield more cost-effective

    solutions than others. In fact, thechoice of configuration can affectthe area efficiency by as much as20% of the gross floor area.

    38: COST

  • 7/21/2019 Hotel Build Cost Guide

    39/80

    Ideally, the efficiency of theguestroom zone should be inthe region of 75%for a tightly

    designed, double-loadedcorridor layout. However, for asingle- loaded corridor or atriumlayout, the efficiency can dropas low as 60%. Obviously, thehigher the efficiency, the moreeconomical the construction cost.

    It is critical to ensure the designis economical without sacrificingthe design intent. Due to themultiplier effect of having manyfloors in the guestroom zone,minor differences or inefficienciescan have a major impact on theconstruction cost.

    The following factors must beconsidered:

    a. Number of guestroomsper floor

    b. Lift location and escape

    staircase cores

    c. Shape of guestroom tower, as itaffects the wall-to-floor ratios

    d. Corridor configuration

    COST :39

  • 7/21/2019 Hotel Build Cost Guide

    40/80

    A limiting factor of the number ofguestrooms per floor is the localauthority building code requirement

    for fire evacuation, which iscontrolled by the distance betweenfire-escape stairs. In a tower, anoptimum number of guestroomswould be in the region of 16 to 24rooms per floor if only two fire-escape stairs are envisaged.

    This ratio also facilitates efficienthousekeeping. Increases in thenumber of rooms per floor cantrigger the need for additionalfire-escape stairs and additionallifts. This in turn may require thelift core to be increased in size,

    with its corresponding increasein gross floor and elevationareas leading to an increase inconstruction costs.

    A guestroom tower may takevarious plan shapes, ranging fromrectangular to circular, triangular,

    curved or offset. It has beenproven that the most efficientshape is generally rectangular,with a double loaded corridorconfiguration.

    Curved and circular shapedtowers will involve higher costs

    because of non-standard roombays and panelled or facetedglazing. Architects may opt for anapproach to maximise views fromthe guestrooms to accommodatethe often narrow site, but there isa cost premium to this and this

    choice should be scrutinised.

    40: COST

  • 7/21/2019 Hotel Build Cost Guide

    41/80

  • 7/21/2019 Hotel Build Cost Guide

    42/80

    The single-loaded corridor configuration is

    less efficient as the corridor serves only oneset of guestrooms. Efficiency is in the region of

    65% or less.

    The double-loaded corridor configuration

    is efficient, with one single corridor serving

    guestrooms on both sides. Efficiency is in the

    region of 70 to 75%.

    Typical guestroom layoutGuestroom sizes are generallystandardised. For a five-star hotelit would be rectangular in shape,

    in the region of 40 to 50m netarea inclusive of sleeping area andbathroom. Some developers ordesigners may attempt to providelarger and odd-shaped roomswhich may not be economical.

    Good workable dimensions are

    approximately 4.5m by 9.1m. Thewidth should not be excessive,as it increases the length of thecorridors, the cost of the structureand affects the external walls ofthe bedroom zone.

    Examples of differentconfigurations are shown below.

    42: COST

  • 7/21/2019 Hotel Build Cost Guide

    43/80

    The offset configuration is the most efficient

    configuration in terms of accommodatingmore rooms per floor, with minimum effect on

    external walls and finishes. Efficiency is in the

    region of 75%

    The rectangular configuration is not efficient,as it requires additional corridor lengths to

    serve end rooms. Efficiency is in the region of

    65% or less.

    COST :43

  • 7/21/2019 Hotel Build Cost Guide

    44/80

    The triangular configuration providesinefficient space for the central core. The

    corner rooms are odd-shaped. Efficiency is

    likely to be below 65%. The atrium configuration is served by single-

    loaded corridors, which reduce efficiency.

    Though it may provide an opportunity for

    glass elevators, there is a cost premium.

    Smoke extraction and an extra premium for

    roof construction is a major consideration.

    Efficiency is likely to be around 60%.

    44: COST

  • 7/21/2019 Hotel Build Cost Guide

    45/80

    The circular configuration may have shorter

    corridors but it is a challenge to design

    efficient room space, especially in relation to

    the location of the bathroom. The central core,

    where the lifts, housekeeping and fire-escape

    stairs are located, will determine the floor area.

    It is unlikely to achieve efficiency beyond 70%

    COST :45

  • 7/21/2019 Hotel Build Cost Guide

    46/80

    Cost planning

    Cost planning is typically done intwo stages. The first stage involvesan initial order of magnitude

    costing or cost appraisal. Thisusually takes place before anydesigns have been produced,and is based on available costdata and past experience of hotelprojects of comparable standard,together with an understanding of

    the current market trends.The second stage involvesmore detailed cost planningbased on design informationprocured specifically for theparticular project.

    46: COST

  • 7/21/2019 Hotel Build Cost Guide

    47/80

    Initial order ofmagnitude costing

    Using benchmarked areadata, a preliminary scheduleof all functional areas in

    the hotel is made based onoutline information about thehotels market position, therecommended type of hotelproduct, and the amenities themarket requires. This produces areasonably accurate estimate of

    overall gross constructed area.Based on this preliminaryarea schedule, the estimatedconstruction cost for the hotelis calculated. This is usuallydone both on a cost per squaremetre basis and on the basis

    of a cost per bedroom or key,using historical benchmark datacollated from similar projects.Assuming that both calculationsproduce answers in the sameballpark, it is likely the hoteldesign is reasonably efficient.

    Our cost consultants are wary ofhotels with, for example, unusuallylarge or extensive restaurants,

    conference facilities, health clubs,suites or other unusual facilitiesthat skew the comparativecalculation by increasing thecost per key without perhapssignificantly affecting the cost persquare metre.

    For any such unusual hotels,further discussion with thedeveloper is advisable to ensurethat his requirements have beenaccurately captured. An initialcost prepared on a $/m should,however, be more reliable.

    COST :47

  • 7/21/2019 Hotel Build Cost Guide

    48/80

    With the preliminary costings inplace, a construction cost cash-flow forecast is prepared, based

    on the estimated time required tocarry out the design, procure theright contractor and then build andfit-out the hotel. The results of thiscash-flow study give an indicationof the likely draw-down of thefunds throughout the construction

    of the hotel to allow developersand investors to assess the needfor, and cost of, funding.

    The construction cost consultantthen works with the developerand the design team to reviewand modify the scope and nature

    of the hotel design, and thecorresponding construction cost.

    This review process may berepeated a number of timesuntil the developer arrives at

    a financially viable schemethat yields the required targetprofitability. In this way, a budgetis refined and set for constructionof the hotel and the developeris given the confidence in hisviability calculations to give the

    go-ahead to proceed to the nextstage of the project.

    48: COST

  • 7/21/2019 Hotel Build Cost Guide

    49/80

    Detailed cost planning

    The developers design teamshould design the hotel toprovide the functional areas

    necessary to meet the hoteloperators requirements withinthe constraints of the approvedbudget. The construction costconsultant costs the design andprepares an initial cost plan thatbreaks down the cost of each

    element of the building intosmaller, more identifiable andmanageable items.

    The cost plan is fine-tuned to tryto make sure that firstly, overallcosts fall within the targetedbudget and secondly, that the

    spread of the expenditure is aboutright ie the money is beingspent on those elements whichare customer facing or affect theoperating costs of the building and therefore improve thepotential viability of the scheme.

    This may involve a value-engineering (VE) process, carriedout with the construction cost

    consultant guiding the designersby using analyses and benchmarkcomparisons with other hotelprojects. All cost elements arescrutinised for efficiency in designand whether they add value tothe hotel. Our construction cost

    consultants, who are well-versedwith the various cost drivers of ahotel development, share theirknowledge and experience withthe design team, challengingand being challenged, therebymaximising the value andeffectiveness of the hotel building.

    COST :49

  • 7/21/2019 Hotel Build Cost Guide

    50/80

    The construction cost consultantmay suggest alternativeconstruction methods and

    advise on the range of productsand materials available in themarket that are within theallowable budget, from which thearchitects and interior designerscan then select.

    Once the preliminary designs

    are completed and have beenchecked to remain within budget,the construction cost consultantcompiles all the information intoa final detailed cost plan thatis distributed to the developerand consultants. This defines

    the design intent and the agreedbudget to which the developer anddesign team should adhere.

    The initial budgeting processminimizes time spent pursuingdesign options that are either not

    affordable or do not produce therequired financial return.

    50: COST

  • 7/21/2019 Hotel Build Cost Guide

    51/80

    Constructioncost consultantsshare theirknowledge andexperience withthe design team,challenging andbeing challenged,thereby maximisingthe value andeffectiveness ofthe hotel building.

    COST :51

  • 7/21/2019 Hotel Build Cost Guide

    52/80

    Spain

    TOTAL USD USD/m2(GBA) USD/key % 8,544 m2 153 keys

    6,072,299 711 39,688 19%

    1,667,432 195 10,898 5%

    11,027,489 1,291 72,075 35%

    7,062,250 827 46,158 22%

    5,819,339 681 38,035 18%

    263,350 31 1,721 1% 31,912,160 3,735 208,576 100%

    Structure and envelope

    Internal fit-out

    Building services

    On-cost

    FF&E

    External worksTotal

    Cost models*

    Europe

    * Cost models based on a mid-market product

    52: COST

  • 7/21/2019 Hotel Build Cost Guide

    53/80

    Russia

    TOTAL USD USD/m2(GBA) USD/key % 8,544 m2 153 keys

    6,493,440 760 42,441 29%

    358,848 42 2,345 2%

    5,510,880 645 36,019 24%

    3,740,300 438 24,446 17%

    5,615,579 657 36,703 25%

    854,400 100 5,584 4% 22,573,447 2,642 147,539 100%

    COST :53

  • 7/21/2019 Hotel Build Cost Guide

    54/80

    United Kingdom

    TOTAL USD USD/m2(GBA) USD/key % 8,544 m2 153 keys

    7,800,037 913 50,981 26%

    3,785,507 443 24,742 12%

    7,543,701 883 49,305 25%

    5,197,200 608 33,969 17%

    5,819,339 681 38,035 19%

    263,350 31 1,721 1% 30,409,134 3,559 198,753 100%

    Structure and envelope

    Internal fit-out

    Building services

    On-cost

    FF&E

    External worksTotal

  • 7/21/2019 Hotel Build Cost Guide

    55/80

  • 7/21/2019 Hotel Build Cost Guide

    56/80

    Dubai

    TOTAL USD USD/m2(GBA) USD/key % 8,544 m2 153 keys

    5,885,147 689 38,465 23%

    3,022,309 354 19,754 12%

    6,289,284 736 41,106 25%

    4,250,100 497 27,778 17%

    5,356,243 627 35,008 21%

    351,767 41 2,299 1% 25,154,850 2,944 164,411 100%

    Structure and envelope

    Internal fit-out

    Building services

    On-cost

    FF&E

    External worksTotal

    Cost models*

    Middle East

    * Cost models based on a UK mid-market product.

    The equivalent product in the Middle East is a budget product

    56: COST

  • 7/21/2019 Hotel Build Cost Guide

    57/80

    Qatar

    TOTAL USD USD/m2(GBA) USD/key % 8,544 m2 153 keys

    8,116,800 950 53,051 24%

    3,844,800 450 25,129 11%

    8,116,800 950 53,051 24%

    3,844,800 450 25,129 11%

    9,825,600 1,150 64,220 29%

    427,200 50 2,792 1% 34,176,000 4,000 223,373 100%

    COST :57

  • 7/21/2019 Hotel Build Cost Guide

    58/80

    Saudi Arabia

    TOTAL USD USD/m2(GBA) USD/key % 8,544 m2 153 keys

    5,002,375 585 32,695 23%

    2,568,963 301 16,791 12%

    5,345,891 626 34,940 25%

    3,612,585 423 23,612 17%

    4,552,807 533 29,757 21%

    299,002 35 1,954 1% 21,381,623 2,503 139,749 100%

    Structure and envelope

    Internal fit-out

    Building services

    On-cost

    FF&E

    External worksTotal

    58: COST

  • 7/21/2019 Hotel Build Cost Guide

    59/80

  • 7/21/2019 Hotel Build Cost Guide

    60/80

    South Africa

    TOTAL USD USD/m2(GBA) USD/key % 8,544 m2 153 keys

    3,875,822 454 25,332 24%

    1,380,676 162 9,024 9%

    5,598,122 655 36,589 35%

    2,808,660 329 18,357 18%

    2,136,503 250 13,964 13%

    146,327 17 956 1% 15,946,110 1,866 104,223 100%

    Structure and envelope

    Internal fit-out

    Building services

    On-cost

    FF&E

    External worksTotal

    Cost models*

    Africa

    * Cost models based on a mid-market product

    60: COST

  • 7/21/2019 Hotel Build Cost Guide

    61/80

    Nigeria

    TOTAL USD USD/m2(GBA) USD/key % 8,544 m2 153 keys

    6,965,981 815 45,529 24%

    2,496,952 292 16,320 9%

    10,076,620 1,179 65,860 35%

    5,055,780 592 33,044 18%

    3,845,742 450 25,136 13%

    263,389 31 1,721 1% 28,704,464 3,360 187,611 100%

    COST :61

  • 7/21/2019 Hotel Build Cost Guide

    62/80

    Nairobi

    TOTAL USD USD/m2(GBA) USD/key % 8,544 m2 153 keys

    3,978,504 466 26,003 24%

    1,243,969 146 8,131 8%

    5,080,700 595 33,207 31%

    2,821,440 330 18,441 17%

    3,281,781 384 21,450 20%

    160,960 19 1,052 1% 16,567,354 1,939 108,283 100%

    Structure and envelope

    Internal fit-out

    Building services

    On-cost

    FF&E

    External worksTotal

    62: COST

  • 7/21/2019 Hotel Build Cost Guide

    63/80

  • 7/21/2019 Hotel Build Cost Guide

    64/80

    UK

    Spain

    Russia

    Dubai

    Qatar

    SaudiArabia

    South

    Africa

    Nige

    ria

    Nairobi

    250,000

    200,000

    150,000

    100,000

    50,000

    0

    Cost per key analysisBased on a mid-market hotel

    FF&EExcluding FF&E

  • 7/21/2019 Hotel Build Cost Guide

    65/80

    UK

    Spain

    Russia

    Dubai

    Qatar

    SaudiArabia

    South

    Africa

    Nige

    ria

    Nairobi

    4,000

    3,500

    3,000

    2,500

    2,000

    1,500

    1,000

    500

    0

    Cost/m2analysisBased on a mid-market hotel

    FF&EExcluding FF&E

  • 7/21/2019 Hotel Build Cost Guide

    66/80

    PROCU

  • 7/21/2019 Hotel Build Cost Guide

    67/80

    EMENT

  • 7/21/2019 Hotel Build Cost Guide

    68/80

    Selecting a contractorto undertake the

    construction of thehotel requires an

    understanding of the

    procurement options

    available to ensure

    that the right balancebetween price and risk

    is achieved.

  • 7/21/2019 Hotel Build Cost Guide

    69/80

  • 7/21/2019 Hotel Build Cost Guide

    70/80

    Procurement

    Having completed the cost

    planning process, agreed a

    budget and scope of work and

    received the go-ahead fromthe developer to proceed to the

    next stage, the construction

    cost consultant advises on the

    most appropriate procurement

    approach for the particular blend

    of time, cost and quality that

    relates to the hotel project.Every project is different,and it is important that thechoice of the most appropriateprocurement route and theselection and pre-qualificationof potential contractors for the

    project is carefully considered.Even the best cost plans will beundermined if the wrong choice ofcontract or contractor is made orif the design information on whichthe contract is let is incomplete orof poor quality.

    70: PROCUREMENT

  • 7/21/2019 Hotel Build Cost Guide

    71/80

  • 7/21/2019 Hotel Build Cost Guide

    72/80

    The three most commonlyencountered forms ofprocurement for hotels are briefly

    described below:

    Traditional lump sum

    Traditional lump-sum contracts,based on full bills of quantities orpriced schedules of work, provide

    an essential means of lettingand cost managing the work asit proceeds. However, they dorequire all design to be finalisedand detailed, and completedocumentation to be preparedbefore going to tender, whichtakes time and the overall life of a

    project is therefore usually longerusing this route. Careful planningand interfacing of, for example,the interior design with the mainbuilding works can reduce theimpact on the master programme.

    The main advantage of completingthe design before constructioncommences is the fact that the

    contract cost is established inadvance of entering into thecontract and work starting on site.The cost risk to the developer istherefore relatively low. Control ofdesign and quality remains largelyin the hands of the developer and

    the design team.If properly set up andadministered, this can be a goodform of contracting to produce ahigh-quality hotel.

    72: PROCUREMENT

  • 7/21/2019 Hotel Build Cost Guide

    73/80

    Design and build

    The design and build (d+b) approachneeds a clearly stated set ofrequirements, setting out in detail

    those parts of the finished hotelthat are important to the developeror hotel operator (for example,the finishes to the public areas orthe performance of the servicesinstallations, but not necessarily thedetail of how the main structure is

    put together) but without producingfull design documentation.

    The contract price is based onthe contractor satisfying theserequirements while leaving a

    significant part of the design,particularly the detailed designdevelopment, to the contractor.The perceived lack of control bythe developer over quality issuesmay lead to compromises bythe builder despite the design

    team often being novated tothe contractor. This is a goodand usually cost-efficient formof contracting for reasonablystandard, repetitive types ofhotel such as budget lodges andbranded mid-market hotels. It isless often used for luxury, five-

    star hotels.

    PROCUREMENT :73

  • 7/21/2019 Hotel Build Cost Guide

    74/80

    Construction management

    The construction management(CM) approach, where the workis let under a series of smaller

    individual trade contracts underthe management of a specialistconstruction managementcompany, can provide programmeadvantages but may expose thedeveloper to greater cost risks.This is because the out-turn cost

    (end cost) is not known until thelast trade package is agreed.

    This construction managementapproach also does notprovide the developer with asingle point of responsibilityfor the construction works,

    which developers might seeas a disadvantage. It requires amuch greater involvement bythe developer, in dealing withindividual trade contracts andpackage contractors.

    This approach is often used onlarge or complex hotel projectswhere making a quick start on

    site, before the whole designis completed, is important inorder to minimise the overallduration of construction. Carefulconsideration of all factors isneeded before proceeding downthis procurement route.

    A modified version of thismethod can be used where,part way through the designand procurement process, thecontractor warrants the cost byproviding a guaranteed maximumprice (GMP), usually including

    a premium cost to reflect theadditional risk he is taking on.Any savings achieved within theGMP are shared between thedeveloper and the contractorin a predetermined proportion,thereby creating an equitable risk-sharing arrangement.

    74: PROCUREMENT

  • 7/21/2019 Hotel Build Cost Guide

    75/80

    Procurement management

    The cost consultant will be activelyinvolved in establishing detailedprocurement strategy to cope with

    the clients master programme.

    If some packages of work needto be procured at an early stageto meet the programme, the costconsultant will actively participatein the pre-qualification andselection of suitable contractors,

    including sourcing internationally,if required. AECOMs experienceand global presence allows us toput together the necessary tenderdocumentation and recommendthe appointment of appropriatecontractors for these packages in

    a timely manner

    PROCUREMENT :75

  • 7/21/2019 Hotel Build Cost Guide

    76/80

    SUMMA

  • 7/21/2019 Hotel Build Cost Guide

    77/80

    RY

  • 7/21/2019 Hotel Build Cost Guide

    78/80

    Summary

    This guide explains the

    relationship between the

    design and the costs of hotel

    development and demonstratesthe benefits of obtaining cost

    advice throughout each stage of

    the development lifecycle.

    Successful hotel developmentrequires not only anunderstanding of the market,

    but also the ability to design andprocure the right product at theright price.

    To achieve this you need tounderstand the relationshipbetween design and cost andhave knowledge of the latest

    technologies, materials, pricesand construction methods.Combined with the knowledge ofhow hotels operate, this ensuresthat you have the right balancebetween capital expenditureand operating costs.

    From initial feasibility throughdesign, procurement andconstruction, the role of the

    construction cost consultant is key.

    We hope that you have foundthis guide a useful source ofinformation and guidance for yourhotel projects. We would welcomethe chance to discuss it with youin greater detail.

    At AECOM we offer a range ofservices that meet the developmentand asset management needsof hotel owners, operators anddevelopers from initial feasibilitythrough to planning, design,construction and operation.

    78: CONCLUSION

  • 7/21/2019 Hotel Build Cost Guide

    79/80

  • 7/21/2019 Hotel Build Cost Guide

    80/80

    About AECOMAECOM is a global provider of professional technicaland management support services to a broad range ofmarkets, including hospitality, leisure, culture, facilities,environmental, energy, transportation, water andgovernment. With approximately 45,000 employees aroundthe world, AECOM is a leader in all of the key markets that

    it serves. AECOM provides a blend of global reach, localknowledge, innovation and technical excellence in deliveringsolutions that create, enhance and sustain the worlds built,natural and social environments. A Fortune 500 company,AECOM serves clients in more than 130 countries.

    More information on AECOM and its services can be foundat www.aecom.com.

    Kevin Underwood

    Global Leader, Leisure + Culture

    m: +44 (0) 7768 877382

    [email protected]

    Paul Nash

    Project Management, EMEA

    m: +44 (0)7876 396338

    Philip Churchman

    Cost Consultancy, Europe

    m: +44 (0) 7795 043872

    [email protected]

    Paul Ralph

    Cost Consultancy, Middle East

    t: +971 4 439 1000