HOSPITAL LIAISON GROUP
HOSPITAL DEVELOPMENTSUPDATE
1st June 2015
![Page 2: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/2.jpg)
3rd Cardiac Theatre, RSCH
New Cardiac Theatre including Image Intensifier
Programme: Opened January 2014
Contract value: £5.6 Million
![Page 3: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/3.jpg)
Macmillan Horizon Centre
Information and Support Centre for those touched by Cancer
Programme: January 2016
Contract value: £ 5.4 Million
![Page 4: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/4.jpg)
3Ts Decant Programme: Work stream: FRONT CAR PARK
6 Storey modular building to house: Nuclear Medicine OPDPhysiotherapy OPDRheumatology OPD
Contractor: Laing O’Rourke
Completion: December 2015.
Contract value: £12.1 Million
Objective: To relocate clinical services off the 3Ts Stage 1 Site.
![Page 5: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/5.jpg)
3Ts Decant Programme: Work stream: COURTYARD
3 Storey modular building to house: Wards from Jubilee buildingfor Oncology and Infectious diseases
Contractor: Laing O’Rourke
Programme: September 2015
Contract value: £ 9.4 Million
Objective: To relocate clinical services off the 3Ts Stage 1 Site.
![Page 6: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/6.jpg)
3Ts Decant Programme: NORTH ROAD BUILDING
3 Storey modular building to house:Offices and clinical support functions from Stage 1 site area, Electrical infrastructure and Clinical support offices including A&E.
Contractor: P21+ Galliford Try HPS Limited
Programme: November 2015
Contract value: £ 8.2 Million
Objective: To relocate clinical services off the 3Ts Stage 1 Site.
![Page 7: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/7.jpg)
3Ts Decant Programme: NORTH ROAD BUILDING
![Page 8: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/8.jpg)
3Ts Decant Programme
Further work in progress:
RACH to house: Paediatric Audiology
Building 545 to house: Refurbishment for ENT OPD and replace waste compound
Sussex Cancer Centre: Internal refurbishment to decant OPD & impression room
Service roads: Linen Store relocation
Contract value to go: £ 3.1m
PROGRAMME COMPLETION: DECEMBER 2015
Objective: To relocate clinical services off the 3Ts Stage 1 Site.
![Page 9: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/9.jpg)
Site Reconfiguration: Neurosurgery to RSCH
Refurbished Operating Theatres and Recovery areas
Programme: opens 22nd June 2015
Contract value: £ 2.1 Million
![Page 10: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/10.jpg)
Site Reconfiguration: Neurosurgery to RSCH
New Bi-Planar Interventional Radiology suite
Programme: opens June 2015
Contract value: £ 1.9 Million
![Page 11: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/11.jpg)
Site Reconfiguration: Neurosurgery to RSCH
New MRI suite, RSCH
Programme: opens June 2015
Contract value: £ 2.2 Million
![Page 12: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/12.jpg)
Site Reconfiguration: Neurosurgery to RSCH
Refurbishment for expanded ITU facilities, RSCH & PRH
Programme: opens June 2015
Contract value: £ 0.9 Million
RSCH PRH
![Page 13: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/13.jpg)
Site Reconfiguration
Further work in progress:
Millennium Wing, RSCH L8A to house: Neurosurgery ward
Millennium Wing RSCH, L6 to house: Mortuary facilities
Twineham & Albourne wards, PRH to house: Trauma & Orthopaedics ward
Ansty ward, PRH to house: Urology OPD & ward
Hurstwood Park, PRH to house: Day Case theatres
Contract value to go: £ 1.2 m
PROGRAMME COMPLETION: JULY to MARCH 2016
![Page 14: HOSPITAL LIAISON GROUP HOSPITAL DEVELOPMENTS UPDATE …](https://reader031.fdocuments.us/reader031/viewer/2022012019/6168700dd394e9041f6f9446/html5/thumbnails/14.jpg)
Any Questions?