Block 7&3 Oil Fields Project
PalougePower Plant
40MW
Central Processing Facilities
Palouge FPF
Crude OilExport Pipeline
Adar Pipeline76km,)
PS #2
AIRPORTAdar FPF
Adar existingCamp and airstrip
Palogue OBC
CPF Power Plant
10 MW Al-JabalaynOBC
PS #1
PS #3
PS #4
PS #5
PS #6
PORT SUDANMarine Terminal
RED SEAMOUNTAIN
Second River Crossing
First River Crossing
Palouge FSF
Adar FSF
Project Components Supplier European CountriesGERMANYUNITED KINGDOM
NORWAY FINLAND
BULGARIA
ITALY TURKEY
FRANCE
SPAIN
HOLLAND
BELGIUM
SWITZERLAND
Project Components Supplier Asian Countries
CHINAMIDDLE EAST(UAE) JAPAN
MALAYSIA
KOREA
INDIA
INDONESIA
SINGAPORE
LEBANON
Project Components Supplier American Countries
VENEZUELA
BRAZIL
Foreign Companies working in the Project
CANADA
SOUTH AERICA
UNITED KINGDOM
OMAN
FINLAND
ITALY
FRANCE GERMANY
CHINA
RUSSIA
JAPAN
INDIA MALYSIA
EYGPET
Line Pipe Supply
Line pipes at storage yard in Port Sudan
Loading of pipes onto ship at Port in China
Export Pipeline Segment A1 – CPPE
Welding
Welding
Line Pipe Transport
Construction Camps
Export Pipeline Segment A2 – STG/Troytransgaz
Stringing
Transport
Office and accommodation for OWNER
ADAR FSF
Completed RMU building, wellhead & transformer @ Yale-1
Flowline inlet to common manifold.
OGM 3 common manifold
Wellhead and sand-trap RMU Building
ADAR FPF
Trunkline & Flowline@ receiver area
Overview of Train 1 (1st Stage Separators, 2nd Stage Separatorsand Heat Exchangers)Crude Oil Storage Tank (2 nos). One
is undergoing painting.
Diesel storage & FW TanksSub station Building Overview of Tank Area
ADAR PIPELINE
Fitting up riser at Receiver Palogue
Installation of pig into NPS 20 Pig Launcher at FPF
POWER PLANT - PALOGUE
PALOGUE FSF
Piping connected to Christmas Tree at wellhead
The pigging flowline activity. The dust come out from receiver at OGM.
Flowline connected to piping at the wellhead.
PALOGUE FPF
INSTRUMENT AIR SYS
Installed 2nd stage separator
Sub station building From left: Tank A, B & C
Piperack No 1Piperack No 2
Piperack No 4
Heat Medium Package
CPF AL JABALAYN
Pipe Spool & Cable TrayCold vent Knock our drum TANK C & D
Gas Boot
Surge Vessel
Instrument Air Water Treatment Package CHEMICAL INJECTION SKID & TANK
PIPELINE SEGMENT A1
Block Valve Installation & Tie-in
Block Valve Installation
PIPELINE SEGMENT A2
Linepipe ready for tie-in at Blue Nile River crossing
Blue Nile River crossing
Exit of – 28” Rimmer drill for HDD at Blue NileNew HDD Rig
PIPELINE SEGMENT B1
Scraper trap at PS4
Scraper Receiver installation at PS5
Scraper Launcher installation at PS4
PIPELINE SEGMENT B2-1
Welding of incoming pipeline to MT Scraper Receiver at MT
PUMP STATION1 (PS1) - Palogue
MCC Building
Air Cooler
Pump & Drivers on its foundations with shelter
PUMP STATION 2 (PS2) – Al Jabaleen
Main Pump Area
Flanges
Crude oil treatment package
PUMP STATION 4 (PS4) – El Fon
Overview of PS4- Main Pump, Air Cooler, MCC, Genset Areas
Air Cooler
Main Pump Foundations
MCC BuildingSump PitPumps & Genset Foundations
PUMP STATION 5 (PS5) – Jabal Umm Ali
PUMP SHELTER
Air Cooler Area
Crude Oil Treatment SystemCrude Oil Treatment System
EXPORT MARINE TERMINAL – Port Sudan
Rebars Works In Progress – Tank 30101B
HIEDYC – For soil improvement & compaction
Plate Bending - Tankage Concreting [Truck Ready Mixer ] of the Ring Beam- Tank 30101C