Honoraria for Design Build Projects

Methodology Assessment Matrix

Page 2: Honoraria for Design Build Projects Methodology Assessment Matrix

Honoraria

Principles for the selection of a Design Builder– Development of the Honoraria Matrix

– How to use the Honoraria Matrix

Page 3: Honoraria for Design Build Projects Methodology Assessment Matrix

Joint Industry-Government Design-Build Task Force

• Association of Consulting Engineers of Canada• Canadian Construction Association• Canadian Design-Build Institute• Construction Specifications Canada• Royal Architectural Institute of Canada• Department of Foreign Affairs and International Trade• Department of National Defence• Public Works and Government Services Canada• Defence Construction Canada

Page 4: Honoraria for Design Build Projects Methodology Assessment Matrix

Joint Industry-Government Design-Build Task Force

Principles for the selection of a Design Builder

• Remuneration– 50% of a reasonable fee– Based on complexity of the project and on level of

detail contained in the Request for Proposal

Page 5: Honoraria for Design Build Projects Methodology Assessment Matrix

Guide for Calculation of Remuneration

Remuneration = estimate of construction cost x scope factor x cost factor

Page 6: Honoraria for Design Build Projects Methodology Assessment Matrix

Scope Factor

Combination of:• Level of detail in the RFP documents

– High– Medium– Low

• Complexity of the project– High– Medium– Low

Page 7: Honoraria for Design Build Projects Methodology Assessment Matrix

Scope Factor:

Detail Low

0.004 Min $20,000

0.005 Min $25,000

0.006 Min $30,000

Detail Medium

0.003 Min $15,000

0.004 Min $20,000

0.005 Min $25,000

Detail High

0.002 Min $ 7,500

0.003 Min $15,000

0.004 Min $20,000

Level of Detail in Request for

Proposal Documents

Complexity Low

Complexity Medium

Complexity High

Complexity of Project

Page 8: Honoraria for Design Build Projects Methodology Assessment Matrix

Cost Factor:

Estimated Construction Cost

Cost Factor (1)

Up to $25,000,000 1.0 to 0.9

$25,000,000 to $50,000,000 0.9 to 0.8

$50,000,000 to $100,000,000

0.8 to 0.7

$100,000,000 to $150,000,000

0.7 to 0.6

$150,000,000 to $200,000,000

0.6 to 0.5

$200,000,000 to $250,000,000 0.5 to 0.4

Note 1: Cost Factor is a sliding scale within each estimate category

Page 9: Honoraria for Design Build Projects Methodology Assessment Matrix

Example

• Aquatic Centre with competition pool, wave pool, leisure water play area, weight training, and exercise room - $32,000,000

• RFP included building program, functional relationships and description of intended image and character

• Best Value Selection 50% quality/50% price requiring a comprehensive proposal

Page 10: Honoraria for Design Build Projects Methodology Assessment Matrix

Example - Scope Factor:

Detail Low

0.004 Min $20,000

0.005 Min $25,000

0.006 Min $30,000

Detail Medium

0.003 Min $15,000

0.004 Min $20,000

0.005 Min $25,000

Detail High

0.002 Min $ 7,500

0.003 Min $15,000

0.004 Min $20,000

Level of Detail in Request for

Proposal Documents

Complexity Low

Complexity Medium

Complexity High

Complexity of Project

Page 11: Honoraria for Design Build Projects Methodology Assessment Matrix

Example - Cost Factor:

Estimated Construction Cost

Cost Factor (1)

$25,000,000 to $50,000,000 0.9 to 0.8

Note 1: Cost Factor is a sliding scale within each estimate category

Cost Factor = 0.872

Page 12: Honoraria for Design Build Projects Methodology Assessment Matrix

Example - Remuneration

$32,000,000 x 0.006 x 0.872 = $167,000

Page 13: Honoraria for Design Build Projects Methodology Assessment Matrix

Remuneration

Guide for the Calculation of Remuneration for Design-Build

Proposals@

www.cdbi.org

Page 14: Honoraria for Design Build Projects Methodology Assessment Matrix

Methodology Assessment Matrix

Design• For what project complexity is the delivery

method best suited• To what extent must user requirements be

defined prior to tender• What level of design quality is

characteristically achieved with the delivery method

Page 15: Honoraria for Design Build Projects Methodology Assessment Matrix

Methodology Assessment Matrix

Design• How complex is the design review

process for the owner• To what extent can the delivery

method accommodate scope/design changes during construction phase

Page 16: Honoraria for Design Build Projects Methodology Assessment Matrix

Methodology Assessment Matrix

Design• To what extent does the delivery method

inherently minimize changes• To what degree do the owner and user

have direct contact with the designer and are they able to directly influence the design

Page 17: Honoraria for Design Build Projects Methodology Assessment Matrix

Methodology Assessment Matrix

Schedule• To what extent can the delivery

method achieve accelerated delivery, or ensure delivery to specific schedule

• Ability to accommodate early construction start

Page 18: Honoraria for Design Build Projects Methodology Assessment Matrix

Methodology Assessment Matrix

Cost• Potential to obtain an early cost commitment• To what extent does the method

accommodate adjustments to scope change during construction to achieve final costs within budget

• To what ability can the delivery method reduce claims/costs for changes and delays

Page 19: Honoraria for Design Build Projects Methodology Assessment Matrix

Methodology Assessment Matrix

Cost

• Ability to meet cash flow

• To what extent does the method permit the Owner to influence systems, materials and construction methods to minimize life cycle costs

Page 20: Honoraria for Design Build Projects Methodology Assessment Matrix

Methodology Assessment Matrix

Contracting• To what extent is the required design

and construction experience and knowledge available for the method

• Ability to pre-qualify the prime contractor on publicly funded projects

• Ability to pre-qualify the prime contractor on privately funded projects

Page 21: Honoraria for Design Build Projects Methodology Assessment Matrix

Methodology Assessment Matrix

Contracting• Ability to pre-qualify subcontractors• To what extent does the method employ

a simple bid evaluation and selection system

• What level of construction quality can be achieved with the applicable delivery method

Page 22: Honoraria for Design Build Projects Methodology Assessment Matrix

Methodology Assessment Matrix

Risk

• To what extent does the method permit the Owner to transfer the liability for design errors and omissions, delays, construction errors and omissions and non conformance to contract documents

Page 23: Honoraria for Design Build Projects Methodology Assessment Matrix

Methodology Assessment Matrix

General

• To what extent do Owners have the experience and knowledge required to employ the method

• Market readiness