Honduras Forest Development Public Corporation (COHDRFOR ...
Transcript of Honduras Forest Development Public Corporation (COHDRFOR ...
![Page 1: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/1.jpg)
• Honduras Forest Development Public Corporation (COHDRFOR): In charge of forest
conservation and protection in the country.
6. Outline of the Project, Analysis of Alternatives
(1) Background and Objectives
In October 1998, Hurricane Mitch attacked the whole country of Honduras. The country was
seriously devastated by the Hurricane and the casualties were reported as over 13,000 in the
country. In Tegucigalpa, more than thousand people were dead or missing.
Various countries and international agencies provided assistances in recovering the land and
the people from the damages after the disaster. The government of Japan was one of them. Among
the activities taken by the government of Japan, JICA study team was dispatched from 2000 to
2002 for “the Study on Flood Control and Landslide Prevention in Tegucigalpa Metropolitan
Area of the Republic of Honduras”. The Final Report was prepared in May 2002.
Upon the results of the JICA study, the government of Honduras requested the government of
Japan to provide grant aid corporation for the Landslide Prevention in the Tegucigalpa
Metropolitan Area (El Berrinche, El Reparto, and El Bambu), of which areas are considered
necessary to take urgent countermeasures.
The JICA Preliminary Study Mission was dispatched, from November 20 to December 11 in
Tegucigalpa, to confirm the adequacy of request as well as to see the actual site conditions.
(2) Outline of the Proposed Project
The proposed project aims at providing countermeasures against landslide in the following three
(3) objective areas:
① El Berrinche
② El Reparto
③ El Bambu
The proposed plan in respective area was prepared by JICA study in 2002. Then the tentative
review of the previous plans was carried out by the Preliminary Study Team in late 2008. The
updated proposed plan are basically not remarkably different from the previous plans and it
is not yet detailed final plans, which will be prepared during the basic design stage.
Accordingly the environmental considerations and IEE study at the time of this preliminary
study are carried out based on the plans proposed by the JICA study in 2002, although some
probable modification of plans are taken into consideration for the evaluation.
The general outlines of the proposed plans are presented as follows:
① El Berrinche
The work items with quantities, which are modified by the preliminary study team, are listed
as follows:
・Excavation (Removal of upper surface block) (184,000 m3)
・Revetment/Retaining wall on the lower end existing embankment slope(300 m)
・Channel works(Open channel、Culvert channel)(520m, 1,200m)
・Water gathering basin (3 units)
・Catchment well work, Water gathering boring, Drainage boring, Horizontal boring (8
units, 4,000m, 600m, 250m)
16
![Page 2: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/2.jpg)
・Protection of river bank (Lower end of slope) by gabion(700m)
General Reference for Proposed Plans at El Berrinche
Data source: JICA Study in 2002
Note:The shaft works shown in the plan will be cancelled.
② El Reparto
The work items with quantities, which are modified by the preliminary study team, are listed
as follows:
・ Excavation (Removal of upper surface block) (40,000 m3)
・ Slope surface land reforming and protection work (15,000 m2)
・ Channel works(Open channel、Culvert channel)(1,770m, 150m, 630m)
・ Water gathering basin work (4 unit)
・ Catchment well work, Water gathering boring, Drainage boring, Horizontal boring (2 units,
1,000m, 300m)
・ Channel works(Lower end structure)(300m)
・ Road embankment at the lower bottom slope (1,200m)
17
![Page 3: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/3.jpg)
Data source: JICA Study in 2002
General Reference for Proposed Plans at El Reparto
Data source: JICA Study in 2002
③ El Bambu
The work items with quantities, which are modified by the preliminary study team, are listed
as follows:
・ Channel works(Open channel、Culvert channel)(210m)
・ Ground sill (Gabion Works)(700m3)
・ Water gathering basin work, Debris barrier with function of water gathering (4 unit,
4 unit)
・ Horizontal boring (1,250m)
18
![Page 4: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/4.jpg)
General Reference for Proposed Plans at El Bambu
Data source: JICA Study in 2002
(3) Alternatives
The alternative study is carried out to evaluate the appropriateness of the proposed project,
by assuming that the proposed project is substituted by the other plans. The following two
alternative plans are considered and evaluated:
Alternative A:Resettlement from the dangerous zones (Without structural measures)
The resettlements from the dangerous zones which need to include the wide affected areas
become large in scale. There are more than 20 dangerous areas designated by the city.
It may not be realistic and reasonable to take this option due to the following points:
• It is necessary to prepare huge amount of budget.
• It is quite difficult to find and prepare the resettlement areas for such
large population.
• It is difficult to convince the inhabitants of the necessity of resettlement,
as most houses have been located there for many years without any disaster.
• The damage caused by land sliding generally may not make human death, as
the movement is more or less slow.
Alternative B:Continuous monitoring with Establishment of forecasting, warning, and
evacuation system
This option may be accepted by the inhabitants and no definite opposition will be made.
It is also technically possible for AMDC and SOPTRAVI to establish the necessary system,
as far as the budget is secured and the education to the inhabitants are made properly.
19
![Page 5: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/5.jpg)
However, this option may be also not recommendable. It is not sure when the next movement
to a dangerous level will happen. It is probable that the system will be not effective
for several decades or longer. In this case, it seems very difficult to keep the
monitoring system as well as the system for forecasting, warning, and evacuation for
many years from the viewpoints of budget and intention by people. This kind of option
will be possible for the areas with habitual (or annual) flooding.
As the result, it is concluded that the proposed plans with structural measures are most desirable
to accomplish the objectives of the project.
7. Adverse Environmental and Social Impacts
The study on adverse environmental and social impacts are carried out by review of previous
reports, site reconnaissance, interview survey, consultation to relevant agencies, information
& data collected from various offices/agencies, etc.
The scoping results with reasons of respective evaluation are summarized in the following table:
Table of Scoping
Items Evaluati
on Reasons
Social impacts
1 Resettlement
B It is difficult to confirm at present the accurate
numbers of houses which need to be relocated by the
proposed project, as the detailed plan/design with
alignment/locations may be finalized during the basic
design stage, which is expected to be realized after 2
years from now. However, as far as the observation based
on the tentative plans proposed by the JICA study in
2001, it may be probable that 0 ~10 houses will be
necessary to be relocated at respective site. It is,
however, in any cases, not considerable that people will
show opposition for the resettlement as they are rather
happy to move to a resettlement site prepared by the
government from the current dangerous sites.
2 Economic activity D No particular productive land-uses and no negative
economic activities
3 Traffic/Public
facilities
D There are daily used alleys (roads) by local residences.
Traffic by local residences will be possible during and
after the construction. In addition, there are bypass
roads if necessary.
4 Division of
Communities
D The project sites are not legally accepted by the
government as residential area as they are specified as
dangerous land slide zone ‘Category A’, although there
are some illegally located houses. In addition, no
structures to divert the community may be constructed.
5 Archaeological/Cultu
ral Heritage
D No archaeological/cultural heritage sites in the
proposed project sites. Although there are historically
valuable building/structural site on the right bank of
the Choluteca River in front of the Berrinche project
site, no direct impacts may be predicted.
6 Vested Right D No vested right to be used currently.
20
![Page 6: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/6.jpg)
7 Health and Hygiene
D Rather improved. In addition, the construction scale is
not so large as to may cause such impacts on health and
hygiene.
8 Waste Disposal
B Disposal from the surplus soils from the excavation is
necessary. There are available disposal sites.
Appropriate control measures of disposal are necessary.
9 Disaster/Accident
C The project is not large in scale and the construction
is not a type with dangerous works. It is, however,
probable that disaster/accident may happen, if the
safety control during construction is not sufficient.
Natural impacts
10 Topography &
Geology
D Topography and geology of the sites may be neither
special one, nor valuable one.
11 Soil erosion D Soil erosion and runoff from the sites may be much
reduced after the completion of project
12 Ground water
D The groundwater level will be lowered after the project
completion and it may be positive impacts on the slope
stability.
13 River & Lake
D No adverse impacts on rivers are predicted. The
river/stream conditions in or along the project sites
may be rather stabilized/improved after the project
completion.
14 Coast D The project sites are located in the inland area.
15 Fauna & Flora D No faunas and floras to be protected exist. The
respective site is currently covered with weeds.
16 Climate D The project scale and type may not cause any impacts on
local climate changes.
17 Landscape
C Although the current landscape of the sites itself is
not valuable and much improved by the project, it is
probable that bare lands will appear just after the
construction works.
Pollution
18 Air pollution
D The project scale and type may not cause any impacts on
air pollution. Although some dust may occur during
construction, it is within a partial area and may not
reach to the housing area.
19 Water pollution
C The water body of the river section located downstream
side of the respective project site is currently used
neither for human uses nor activities. It is, however,
probable to give some impacts on aquatic eco-system in
the river, if much amount of soils runs off to the river
during construction due to insufficient control.
20 Soil
contamination
D There is no construction works which may cause soil
contamination.
21 Noise/Vibration
B Noise may happen to some extent by drilling works, earth
works, etc. The noise may not be so remarkably large as
to cause serious nuisance for the local inhabitants.
22 Ground Subsidence
D The project is implemented for the stability of ground,
so that the ground subsidence may not happen by the
construction.
23 Odor D There is no construction works which may cause odor.
21
![Page 7: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/7.jpg)
Assessment Classification:
A: Significant impact anticipated.
B: Slight impact anticipated
C: Unknown (subject to further verification)
D: Almost no impact anticipated and not subject for IEE and EIA.
As seen in the table, there is no item evaluated as A (Significant impacts). The following
Three (3) items become B (Slight impacts):
• Resettlement
• Waste disposal (Disposal of excavated soils)
• Noise/Vibration (during construction)
8. Mitigation and Monitoring for Key Impacts
(1) Mitigation and Monitoring
(A) Items with predicted impact level B
The mitigation measures and necessary monitoring for the three (3) items with predicted impact
level B, shown in the previous “ 7. Adverse Environmental and Social Impacts”, are studied.
The study results are summarized as follows:
① Resettlement
Mitigation measures
Resettlement is the most important item for the impact study of the project implementation.
There are different circumstances in individual cases and the mitigation measures are also
individually different. At the preliminary study stage, some representative measures are
presented as follows:
• Plan and design of structural measures needs consideration to reduce the number
of resettlement houses as much as possible.
• For the resettlement activities, offices & agencies concerned are required to be
cooperated with each other to take special cares for the people to be resettled
who are not landowners.
• Exchange of information and opinions between the implementation agency and the
people is carried out, by public consultation, and their expectations /opinions
are taken into consideration for the resettlement plan.
• Preparation of relocation sites should be done at early stage for earlier
preliminary activities by resettlement people. The resettlement site is selected
in consideration of safety and conveniences for daily living.
• For the planning of resettlement, it is required to get and consider the opinions
and desires from the people to be resettled.
• Compensation prices should be reasonable based on the current market prices and
the conditions of compensation need to be appropriate for the resettlement people.
• Compulsory resettlement should not be considered.
• Past experiences and activities should be sufficiently utilized.
• Cares for social impacts including education opportunities are required.
• Establishment of a special office and committee by the cooperation of relevant
agencies for coordination of activities.
Required Monitoring/study/Survey
• The project implementation will be realized after 2 or 3 years. It is necessary
to control the sites for preventing new houses to be built. For this purpose, the
regular inspection, notice by signboards, establishment of bylaw to restrict to
22
![Page 8: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/8.jpg)
use, etc.
• The inventory survey of houses and lands shall be carried out in detail to get
accurate and specific data.
• Monitoring and guidance of living conditions for the resettled people, after the
project.
② Waste Disposal
It is roughly estimated that the amount of approximately 180 thousands m3 in Berrinche and
approximately 40 thousands m3 in Reparto will be excavated. Some part of the excavated materials
will be used for the embankment and the volume of balance needs to disposal.
Mitigation measures
• The volume of surplus soil is reduced as much as possible, by using the material
for embankment at the respective site.
• It may be probable that the surplus soil is used for the other construction sites
nearby the respective site, as they are natural soils.
• When the road is narrow, traffic control as well as selection of vehicles may be
required for transportation for surplus soils disposal for avoiding congestion.
• The appropriate planning for disposal, for transportation, disposal, method, and
maintenance of the disposal site.
• The schedule of transportation of disposal materials is adjusted to minimize the
possible nuisance by the inhabitants and informed them beforehand.
Required Monitoring/study/Survey
• The volume of surplus soils is to be estimated accurately after planning on the
use for embankment.
• The detailed survey on disposal site is to be carried out. (Note:For Berrinche,
there is a wide space sufficient for the disposal in high water channel of the
Choluteca River, where the distance from Berriche site is more or less 1 km. For
Reparto, the volume may be large in comparison with Berrince. It may be possible
to find separate disposal sites. Or the transportation to the same site as for
Berriche is also possible, although the distance is a few km away.)
• The disposal plan including the design of embankment is carried out in consideration
of the future maintenance and safety.
• The monitoring of disposal site is to be carried out.
③ Noise/Vibration
Mitigation measures
Noise/vibration during the construction may be caused mostly by drilling, earth works, and
transportation. Although the noise level may not be seriously high, the mitigation measures
are necessary:
• Information and notice of construction schedule to the inhabitants.
• Construction time at respective site should be flexible and adjusted in
consideration of day (holiday) and working hours which are desirable for the
inhabitants. Avoid the work at night and on holidays as much as possible.
• Try to get understanding for the importance and necessity of the project works.
• If any claim comes from the inhabitants, the countermeasures are to be taken as
much as possible.
• Try to use the construction method and equipment/machines with low noise.
• Walls to mitigate noises are constructed if any hospitals, schools, etc. located
along a road where the increase of noise is remarkable.
• Speed limit control regulation is applied in a partial section, if necessary.
23
![Page 9: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/9.jpg)
Required Monitoring/study/Survey
• Impact level is predicted by a survey at some existing projects with similar
conditions and the evaluated based on the noise standards.
• During the construction period, periodical monitoring of noise and the other
impacts items is to be carried out.
• The survey on facilities & buildings (such as hospitals, schools, etc.) which may
be sensible against noise along the transportation routes required for the
construction and the surroundings
(B) Items with predicted impact level C
The mitigation measures and necessary monitoring for the three (3) items with predicted impact
level C, shown in the previous “ 7. Adverse Environmental and Social Impacts”, are studied.
The study results are summarized as follows:
① Accidents during Construction
The construction scale is not large and it is expected that no serious accidents may happen
as far as the general safety control is properly carried out. In other words, it is probable
that unexpected accidents may happen, if the proper safety control is failed. Accordingly,
the following measures are required to be carried out:
・ To get information on accident cases of the similar works or projects in the past and
take the information into account for the safety control.
・ To investigate the possibility and requirement for the inhabitants to enter to the
project sites during the construction. Then the countermeasures are taken for
preventing the inhabitants entering into the construction area, if necessary. The
bypass construction may be one of the considerable measures.
・ To establish the safety control management system, with the periodical check.
・ To review the construction plans from the safety viewpoints. The construction plans
will be prepared during the design stage. It is necessary to propose the revision or
improvement, if any remarkable undesirable points are identified.
② Landscape
The project sites are mostly composed of bare lands and areas covered with weeds at present.
In addition, a part of the area has solid wastes dumping site and the lands have irregular
forms in general. Accordingly, the sites are not valuable from the landscape viewpoints. It
is rather remarkable that the landscape may be much improved by the project implementation.
It is, however, considered necessary to take countermeasures against the following points:
・ Bare lands remains widely for a certain period just after the construction.
・ Solid waste dumping may be carried out even after the construction.
Accordingly, it is recommended to take the following measures:
・ The city has an idea to construct public parks (with sport grounds) after the slope
stability works are completed. It is desirable to exchange opinions with the city
officers in charge about the planning and recommend implementing the project earlier.
・ To plant grasses in bare areas at the last stage of the construction as a temporary
works until the park construction is realized.
・ The inhabitants will dump the solid waste somewhere in the project area, even if the
construction works are completed as there is no proper garbage collection system at
present. It may be necessary to control the dumping activities and at the same time
to proposed the city to improve the garbage collection system.
24
![Page 10: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/10.jpg)
③ Water Contamination during Construction
The water body of the river section located downstream side of the respective project site
is currently used neither for human uses nor activities. It is, however, probable to give some
impacts on aquatic eco-system in the river, if much amount of soils runs off to the river during
construction due to insufficient control. It is recommended to take the following measures:
・ To investigate more in detail the river uses for human activities.
・ To investigate more in detail the conditions of ecosystem in and along the river,
including the further downstream sections (e.g.2-3km).
・ To take measures for prevention and constraint against soil runoff, if any possibility
of impacts on the river uses or ecosystem are identified.
・ To take proper control for preventing spills of oil and grease from the construction
machineries.
(2) Overall Evaluation and Conclusion of the Environmental Study
The results of overall evaluation of the environmental study are concluded as summarized as
follows:
• The project may create positive environmental improvement in the respective project
area.
• The serious negative impacts may not happen by the proposed project. Only slight
adverse impacts are predicted for resettlement, disposal of excavated soils, and
noise during construction.
• Such slight impacts will be mitigated by proper cares and management, without
difficulty.
• The resettlement may be an only issue, which need special attention, as there are
some indefinite matters such as follows:
・ The structural plans will be updated and become a final one during the design
stage.
・ The detailed alignment and locations of proposed structures are difficult
to confirm at the site at present, as the detailed plans/maps are not
available yet.
・ The site conditions with houses will be changed after 2 or 3 years, when
the construction works will commence.
• The resettlement is expected to be carried out without serious difficulties as the
inhabitants show cooperative attitude for the resettlement and also some of them
are rather happy to move out of the dangerous site, according to the interview
survey.
• The resettlement is a sensible matter and also a matter of special concerns by
relevant agencies. Accordingly, careful follow-up may be required not only during
the project implementation stage, but also during preparation stage as well as post
construction stage. For example, the activities to avoid new houses built before
the project commencement and the monitoring to support the resettled people are
necessary.
• The alternative plans of the currently proposed structural plans are studied. But
it is concluded that these optional plans are not feasible.
9. Necessity of Another Environmental and Social Considerations Study at this stage
It is considered that another Environmental and Social Considerations Study is not required
at this stage due to the following reasons:
• JICA study in 2001 and 2002 already carried out the IEE and EIA studies, although
the currently proposed project for landslide countermeasures at three areas was
a part of the overall project by the JICA study.
25
![Page 11: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/11.jpg)
• The plans proposed by the JICA study are basically not changed yet, although the
preliminary study team (in late 2007) recommended some modifications. The detailed
review and finalization of the proposed plans will be prepared at the design stage,
when the results of additional monitoring on ground movement will be available.
• The site conditions, especially concerning number houses required to be resettled,
will be changed until the final definite plan/design is prepared possibly after
two years from now.
10. Consultation to the Relevant Offices on Environmental Study
The consultation was carried out to the relevant government offices: UGA/SOPTRAVI, DECA/SERNA,
and GMDAM/AMDC as summarized as follows:
① Category of the Proposed Project
Although there is the official table to decide category for the environmental license for
SERNA, the proposed project is not applicable for any items in the table. On this point, the
relevant agencies answered to the inquiries by the Preliminary study team as follows:
From UGA of SOPTRAVI
・SOPTRAVI(UGA) generally decides the category by themselves based on the table. But, it
is necessary to consult to DECA, if any difficulty is found to decide the Category. In
case of the proposed project, it is difficult to decide by the table.
・If the SOPTRAVI has to decide without consultation to SERNA, it may be “Category 2”
as the project may not cause serious adverse impacts and it may be mitigated even if
some impacts are predicted.
From DECA of SERNA (Note: GMDAM of AMDC has the similar opinion)
・SERNA(DECA) also can not decide the category of the proposed project only by the table.
・It is difficult to decide the category without understanding the details of the project
by reading the documents and site visits.
・If the DECA has to suggest the category without knowing the details, it may be Category
3, although it is difficult to say Category 3-I or 3-II.
② Predicted Impacts
The scoping is requested to UGA/SOPTRAVI and GMDAM/AMDC. The GMDAM/AMDC replied that it is
not possible within such short period of study and without the study on the necessary documents.
While, the UGA/SOPTRAVI, of which staff accompanied the Social and Environmental Specialist
of the Preliminary Study Team for the site visits, commented that it is also difficult to study
in a limited short period. But, the UGA/SOPTRAVI staff showed their personnel opinions as
follows:
・No serious impacts are predicted
・The project may create environmentally positive impacts
・Slight impacts are predicted for “Noise, vibration, and dust at construction site”,
but it may be easily mitigated by construction management.
・Slight impacts are also predicted for “Resettlement”, but this issue is also possible
to be mitigated without difficulty from their experiences of the SOPTRAVI projects.
Even when the agreement is not made at the beginning stage, it could be settled without
taking too much time by preparation of the resettlement site and the negotiation. It
is also necessary to take into consideration that the objective sites are all located
in the designated dangerous areas, where the inhabitants generally are happy to move
out from such place.
26
![Page 12: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/12.jpg)
11. Social Acceptability (Involuntary Resettlement and Land Acquisition)
The resettlement is the most significant item of environmental consideration for the proposed
project. The reference information obtained during the preliminary study is summarized below:
Land Conditions:
• All the areas of project sites are private lands, as far as checked by the cadastral
maps of AMDC. But, it is actually abandoned to use and the land taxes are exempted
by the bylaw.
• Although there were villages before 1998 disaster, all the inhabitants, except some
of them, are relocated mostly to the resettlement sites prepared by the government.
• The sites can not be used for residential purposes, as the government designated
the areas as dangerous zone, where house building is not allowed.
• There are houses located in and around the objective project area. Although it is
difficult to estimate at present the reliable number of houses to be relocated,
it is roughly counted by the site visit. The number of houses to be relocated will
be less than 5 or 6 units only, as far as assuming that no new settlement will happen
in the future.
Houses beside the fence in Berrince
Acceptability of Resettlement
It is concluded as the results of the Preliminary Study that the resettlement issue need careful
considerations and mitigation measures, but it may not cause serious impacts, due to the
following reasons:
• The relevant agencies such as AMDC and SOPTRAVI have good experiences of
resettlement for their many projects.
• The relevant agencies have positive intention to take special cares for the
resettlement issues of the JICA project.
27
![Page 13: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/13.jpg)
• The AMDC already has a resettlement site owned by the AMDC.
• The SOPTRAVI informed that they would control the site for avoiding the new
settlers.
• The budget may not be large, even if the compensation is done by payment, as the
property value is generally very low.
• The Mayor announced the basic program to support the poor people with priority.
• The UGA/SOPTRAVI will carry out the monitoring to support the resettles, after the
project.
• It may be possible to prepare the final plan and design in consideration of reducing
the resettlement numbers.
• The interview survey was carried out during the Preliminary study at 15 houses in
total. It was found that no answers to oppose the resettlement for the project were
obtained.
• The inhabitants generally have intention to move to the other safe places, if
possible, although they can not do because of financial problems.
• Some of them feel fears to stay in the house every time when heavy rain happens.
• Most inhabitants living in the objective area are poor and they do not show strong
or expensive desires.
12. Important Notice on Basic Design Research
There are the following reference points for the basic design:
• It is desirable to make alignment and locations of structures and works in
respective site in consideration of reducing the number of houses to be relocated.
• It is suggested to try to get relevant information from the inhabitants as much
as possible. They have various information, such as past movement, changes of land
uses, etc. useful for the effective plan and design.
• It is suggested to visit directly the departments/units of SOPTRAVI, AMDC, SERNA,
etc. to collect information and data. It may be possible to find or get additional
or unexpected information.
• It is suggested that the information given by an agency/office sometimes need
confirmation, as their information is not always consistent/correct.
• It is suggested to visit local consultants as well to collect supplementary
information and data, as the government agency has more or less poor system of data
base management.
• It is necessary to assist in the relevant agencies to carry out the inventory survey
of the houses and lands which need to use or relocate by the project implementation.
• The guidance and assistance will be necessary for the preparation of the
resettlement plan in reference to the results of interview survey of the
inhabitants.
• The guidance and assistance will be necessary to the relevant agencies to prepare
the appropriate and acceptable relocation site.
• The guidance and assistance will be necessary to the relevant agencies to prepare
the follow-up monitoring for supporting the re-settlers to be carried out after
the project implementation.
• The guidance and assistance will be necessary to the relevant agencies to prepare
the plan for effective uses of the project area, possibly for parks, sports, etc.,
after the completion of the project.
• It is necessary to hold the stakeholder meetings at the basic design stage, when
the necessity of resettlement as well as the objective houses of resettlement will
becomes definite.
• It is necessary to propose the implementing agency to carry out the official
procedures for obtaining earlier the environmental license of the project, after
28
![Page 14: Honduras Forest Development Public Corporation (COHDRFOR ...](https://reader036.fdocuments.us/reader036/viewer/2022081506/62a35d6faf83c308d87149ee/html5/thumbnails/14.jpg)
the basic plan and design of the project becomes definite. It is desirable to assist
in the implementing agency for the EIA.
13. Other Relevant Information
Some reference information is given as follows:
• There are various environmental laws and bylaws related to the environmental control
and management. But, some of them are too old and not sufficiently updated. In addition,
some of them are practically not effective, as they do not properly reflect the actual
conditions. Further, it seems difficult for the offices in charge to execute effective
control due to lack of compulsory right and shortage of budge, vehicles, and personnel.
The management by respective office is carried out occasionally without sufficient
knowledge of relevant laws and regulations.
• Control of solid waste seems to be one of big environmental issues for the City. There
are two aspects of the reasons. One is that the relevant offices can not (or do not)
control based on the laws/regulations. Another one is that the current system for
collection, treatment, and disposal of wastes is poor. There are waste dumping site
in the respective proposes project area. The inhabitants do not have another way of
disposal as the municipality does not have capacity to collect the solid waste.
• In the cadastral document, there are prices of all the registered land and houses.
These prices are not updated since 2000 and there are remarkable differences between
the actual market prices and the official government prices.
• Honduras is a country to have positive intention for environmental conservation and
protection. As an example, the country ratified or agreed various international
environmental conventions such as listed as follows:
List of representative International Convention
Convention of Biological Diversity
Climate Change Convention
CITES (Convention on International Trade in Endangered Species of Wild Fauna and
Flora.)
United Nations Convention to Combat Desertification in Those Countries Experiencing
Serious Drought and/or Desertification, Particularly in Africa
Convention on Wetlands of International Importance Especially as Waterfowl Habitat
Basel Convention on the Control of Trans-boundary Movements of Hazardous Waste and
their Disposal
Kyoto Protocol to the United Nations Framework Convention on Climate Change
Convention for the Protection of the World Cultural and Natural Heritage
Vienna Convention for the Protection of the Ozone Layer
Montreal Protocol on Substances that Deplete the Ozone Layer
Stockholm Convention on Persistent Organic Pollutants (POPs)
There are many other conventions, especially for Central or Latin America and Caribbean
region.
29