A Few Things to Think About
• A 2015 research study found that in the U.S., the number of adults who identify themselves as Christians fell by almost 10% in the past seven years.– 78.4% (2007) to 70.6% (2014)
• In the age group from 18 to 29, 36% have noreligious affiliation.
Source: http://www.pewforum.org/2015/05/12/americas-changing-religious-landscape/
How About Greek Orthodox Christians?
• Statistics compiled by the Greek Orthodox Archdiocese of America from 1996 to 2014 show:– The number of Baptisms dropped by over 19%
• 7,155 (1996) to 5,816 (2014)– The number of Weddings dropped by over 38%
• 3,855 (1996) to 2,400 (2014)– Sadly, the number of Funerals increased by 31%
• 3,313 (1996) to 4,362 (2014)
• The good news is that there were 33% more Baptisms than Funerals.
How Can We Even Consider an Expansion?
Our Parish Is Unique!
From 1976 until 2014, Greek Orthodox weddings in the Americas dropped by 50%.But during that same timeframe, the Saint Haralambos Parish grew from 60 Stewards to over 650.
With the help of our Stewards, our Parish purchased land, built a Community Center
and a church, and we paid for all of it.
Our Greek Schools have grown to the point where we now have over 240 students!
Dozens more, including children, teens, and adults, are involved in our many ministries.
Where Do We Go From Here?
• To ensure the future of our faith, our heritage, and our community, we must connect closely with our Parishioners and their children.
• This can best be done by continuing to support and grow the ministries of our church.
How Can We Support Our Ministries? Financial Support Clergy & Volunteers
Facilities – Unfortunately, the accommodations available to our ministries are lacking.– Not enough classrooms– Not enough meeting areas– No athletic facilities– Outdated kitchen– No auditorium– Small dining hall
Upgrading Our FacilitiesThe Expansion Project includes two major components:
1. A renovation of the existing classrooms and Community Center.
2. The construction of a new gymnasium / multipurpose center.
Proposed Site Plan
New Gymnasium / Multipurpose
Room
New Building with youth center, classrooms,
meeting rooms, offices
and storage
New Kitchen
ExpandedParking Lot
with 200 spaces
Renovated Community Center
with classrooms, offices, bookstore and
chapel
Renovated Lobby
Renovated Existing Space
Three AdditionalClassrooms
Updated Bathrooms
School Directors’
Office
Four Pre-school Rooms with private
restrooms
Expanded Lobby
Chapel
Bookstore
Existing Church Offices(no changes)
Existing Entrancefrom Parking Lot
Expanded Lobby & Book Store
Chapel
Four Pre-School Rooms• Classrooms will meet all DCFS
standards• Private restroom attached to each
classroom• Natural lighting• Technology friendly• Access to enclosed playground
Seven Classrooms• Three classrooms in the renovated
building• Four classrooms in the new building• Classrooms will meet all DCFS
standards• Technology friendly• Natural lighting
New Building – 1st Floor
Internal Storage (for tables, chairs, etc.)
Retractable Stage
External Storage (for Food Festival and
other outdoor items)
Gymnasium /Multipurpose Room
Two AdditionalClassrooms
Storage / OfficesFor Philoptochos
andPTAs
Kitchen AreaEntrance from
Parking Lot
Library / Meeting Room
Retractable Bleachers
MultiPurpose Gymnasium / Auditorium / Reception Hall
Kitchen
Refrigerator and Freezer Units
Serving Window / Concession Area
Lockable Storage Dishwashing Area Prep and Cooking Area
New Building – 2nd Floor
Two Additional Classrooms
Three StoryElevator
Youth Center
New Building – Basement
Three StoryElevator
Open Storage(to be configured)
Does It Meet Our Needs?Problem Solution
1. Outdated Classrooms All of the classrooms will be completely redone. Preschool rooms will meet all DCFS standards and will have private bathrooms.
2. Shortage of Classrooms We will have 11 classrooms available to the schools.
3. Shortage of Meeting Areas The Youth Center will be available for all youth ministries, and we will have several additional meeting rooms and access to the multipurpose room for large groups.
Does It Meet Our Needs?Problem Solution
4. Outdated / Small Kitchen The kitchen will be completely redone and will be over twice its current size.
5. Shortage of Storage Space The entire basement in the new building will be designated for storage. We will also have several storage rooms throughout.
6. Shortage of Parking Spaces We will add over 50 new parking spaces and have 200 spaces in total.
7. No Gymnasium / Multipurpose Room
We will finally have our own multipurpose room to be used as a gymnasium, auditorium and banquet facility.
How Much Will It Cost?• $6 million, based on initial contractor bids and
potential cost-saving ideas.• To put that in perspective:
– Our existing Community Center cost about $780,000 in 1983
• Adjusted for inflation, the same building would cost about $1.9 million today.
– Our church and offices originally cost $1.6 million in 1987
• Adjusted for inflation, the same structures would cost about $3.3 million today.
– Roughly $5.2 million (87% of our expansion cost) was raised by a community less than half our current size.
When Will It Be Done?• There are two ideal start dates – July (right
after the Food Fest) and February.• The start date will depend heavily on
fundraising. We need at least 40% on hand to break ground.
• Construction will take about 1 year• All attempts will be made to minimize the
disruption to the schools and the Parish, while balancing the related costs.
How Will We Pay For It?By working together and
all doing our part, just like our community has done throughout its history!
We need Leaders, Visionaries and
Benefactors.
We have about $1 million raised already, but no major donor has come
forward yet.
Leaders Commitments ranging from $5,000 to $50,000 Donors will be identified on the recognition
wall. Three randomly selected Leaders will represent
this group during the Groundbreaking and Opening Ceremonies.
If the average Steward commits
$10,000 over 3 years ($278 per
month), the entire cost of the project
will be covered!
Visionaries Commitments from $100,000 to $250,000 Sponsoring various areas of the project,
including each classroom, the youth center, the library, the playground, and the chapel. Visionaries will be identified in their
sponsored area as well as on the recognition wall. They will also take part in the
Groundbreaking and Opening Ceremonies.
Benefactors• We are depending on a few Benefactors who are
inspired by their Faith to lead the way for our Parish. Benefactors will receive prominent recognition within
the school, inside the multipurpose gymnasium, or on the outside of the multipurpose building. They will also be identified on the
recognition wall. Benefactors will be invited to
serve an important role in the Groundbreaking and Opening Ceremonies.
What Can You Do?• Pledge!
– Make your 3-year commitment. Forms are available tonight!
– Contact Rubine, DeeDee or the church office with any questions.
– Donation materials will also go out in the mail soon.
• Spread the word! – Tell others what you heard tonight and share the
excitement.
Your Donation Is Tax Deductible
Please consult a tax professional to compute your exact savings!
Tax BracketAnnual
DonationPotential Tax
SavingsPotential Net Cost
of Annual DonationPotential 3 Year Cost of Donation
25% $3,333 $833 $2,500 $7,50028% $3,333 $933 $2,400 $7,20033% $3,333 $1,100 $2,233 $6,70035% $3,333 $1,167 $2,167 $6,500
39.60% $3,333 $1,320 $2,013 $6,040
$10,000 Commitment over 3 Years
Tax BracketAnnual
DonationPotential Tax
SavingsPotential Net Cost
of Annual DonationPotential 3 Year Cost of Donation
25% $1,667 $417 $1,250 $3,75028% $1,667 $467 $1,200 $3,60033% $1,667 $550 $1,117 $3,35035% $1,667 $583 $1,083 $3,250
39.60% $1,667 $660 $1,007 $3,020
$5,000 Commitment over 3 Years
Impact to Annual Expenses
• Known Offsets - $20,000 per year– Parking lot rental– Culver rental fees
• Potential Offsets– Hosting larger fundraisers on site– Gymnasium / banquet hall rental opportunities– More Greek school revenue– More efficient environmental controls– More Stewards and/or Higher Stewardship!
• Plan on an annual increase of $50 per Steward
Expense Paid in 2014
50% Increase Due to
Expansion
Annual Impact Per
Steward1
Utilities 24,026$ 12,013$ 18$ Insurance 30,321$ 15,160$ 23$ Repairs & Maintenance 32,064$ 16,032$ 25$ Janitorial Wages & Supplies 41,418$ 20,709$ 32$ TOTAL 127,829$ 63,915$ 98$ 1 Based on 650 Stewards
Summary of The Project
INITIAL COMMITMENT
$5,000 Pledge
$10,000 Pledge
Annual Payment 1,667$ 3,333$ Annual Tax Savings1 (550)$ (1,100)$ Annual Cost 1,117$ 2,233$ Total Cost for 3 years 3,350$ 6,700$ 1 Based on 33% tax rate, itemized deductions and no limitations.
IMPACT TO ANNUAL
STEWARDSHIP220%
Mortgage30%
Mortgage40%
Mortgage
Mortgage3 119$ 178$ 238$ Additional Expenses 50$ 50$ 50$ TOTAL INCREASE 169$ 228$ 288$ 2 Based on 650 Stewards.3 Mortgage amounts calculated with a 5% rate over 30 years.
• Project Cost of $6 Million• 1 Year to Complete, starting July or February• Must have 40% on deposit to break ground• Mortgage Options of 20%, 30% or 40%• In the 1980’s our Parish, which was half the current size, took on
projects that were comparable to a $5.2 Million project today.
Discussion