© The ERIGrid Consortium EU H2020 Programme GA No. 654113 Holistic system integration and validation procedure developed in ERIGrid Cyndi Moyo Center for Energy – Electric Energy Systems AIT Austrian Institute of Technology, Vienna, Austria Workshop “Holistic System Validation, Methods and Tools, Free Access to Best Smart Grid Laboratories” October 5, 2017, Amsterdam, The Netherlands

Transcript of Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing &...

Page 1: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Holistic system integration and validation procedure developed in ERIGrid

Cyndi MoyoCenter for Energy – Electric Energy SystemsAIT Austrian Institute of Technology, Vienna, Austria

Workshop “Holistic System Validation, Methods and Tools, Free Access to Best Smart Grid Laboratories”

October 5, 2017, Amsterdam, The Netherlands

Page 2: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Coordinated Voltage Control (CVC)

05.10.2017Cyndi Moyo, AIT Energy 2

Validate this!

Page 3: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Holistic Testing & Validation

05.10.2017Cyndi Moyo, AIT Energy 3

"Holistic testing is the process and methodology for the evaluation of a concretefunction, system or component (object under investigation) within its relevantoperational context (system under test), corresponding to the purpose of investigation”

Holistic Validation Procedure(an interactive process)

Page 4: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Holistic Test vs. Component Test

Component Test Example: inverter MPPT test, anti-

islanding

No interactions with the system

Usually open loop test (predefined voltage, frequency; setpoints are applied to the hardware under test)

Holistic/System Test Combining several tests

(testing process)

Using simulations

Testing a system rather than just component

05.10.2017Cyndi Moyo, AIT Energy 5

DC AC

PV simulator AC gid simulatorHardware inverter

under test

RTDS Simulated Network

PV inverterPV simulator

Central Controller(optimization)

PHIL

Page 5: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

HOLISTIC TEST DESCRIPTIONThe basics

05.10.2017Cyndi Moyo, AIT Energy 6

Page 6: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Holistic test description

05.10.2017Cyndi Moyo, AIT Energy 7

THRE

E le

vels

ofsp

ecifi

catio

n

Map/split

Test Case (TC)

Use CasesTest Objective(s)

ExperimentSpecification

Map/split

ExperimentSpecification

ExperimentSpecification (ES)

Test specificationTest specificationTest Specification (TS)

Generic

Specific

Lab

Page 7: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Holistic testing procedure –different mapping steps

05.10.2017Cyndi Moyo, AIT Energy 8

5

6

4

3

2

1

RI 1 RI 2 RI n

ExperimentSpecification

Exp. Spec.

ExperimentSpecification

Exchange of data and results

Holistic Test Case

Sub-test specification

Sub-test

spec. 2

Sub-test specification n

Division into individual (sub-)tests

1

3

5

6

7

Experiment in RI n

Exp. in RI 1

Exp.in RI 2

Use Case(s)Use Case(s)

holistic test

evaluation

test refinement

rese

arch

infr

astr

uctu

re (R

I) ca

pabi

lity

prof

iles Scenario & Generic

System ConfigurationUse Cases

2

4

Test ObjectiveMapping from SC, UC,

TO to holistic test case

Mapping of holistic test case to (sub-) test specifications, i.e. specific (sub-) test

system(s)

Mapping of (sub-)tests to RI and specify

experiments

Mapping between tests resp. experiments

Mapping (preliminary) results to test adjustments

Mapping of results of experiments to

represent holistic result

x – mapping step

532x Process steps

Page 8: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Validate this!WHY TO TEST?WHAT TO TEST?WHAT TO TEST FOR?HOW TO TEST?

Key Questions to be answered for test specification:

05.10.2017Cyndi Moyo, AIT Energy 9

Page 9: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Validate this!WHY TO TEST?WHAT TO TEST?WHAT TO TEST FOR?HOW TO TEST?

Key Questions to be answered for test specification:

05.10.2017Cyndi Moyo, AIT Energy 10

Page 10: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Test System & Domain

05.10.2017Cyndi Moyo, AIT Energy 11

System under Test (SuT): is a system configuration that includes all relevant properties, interactions and behaviors (closed loop I/O and electrical coupling), that are required for evaluating an OuI as specified by the test criteria.

Object under Investigation (OuI): the component(s) (1..n) that are subject to the test objective(s).

Remark: OuI is a subset of the SuT.

Domain under Investigation (DuI): Identifies the domains of test parameters and connectivity relevant to the test objectives.

OuI

Page 11: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

SuT

measurements

Test System Functions

05.10.2017Cyndi Moyo, AIT Energy 12

Functions under Test (FuT): the functions relevant to the operation of the system under test, as referenced by use cases. Function(s) under Investigation (FuI): the referenced specification of a function realized (operation-alized) by the object under investigation.

Remark: the FuI are a subset of the FuT.

OuI

DER P,Q control

optimization in the controller

state estimation

OLTC tap controlmeasurementsmeasurements

Use Cases define FunctionsOf Systems (IEC 62559 approach)

Page 12: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

WHY TO TEST?WHAT TO TEST?WHAT TO TEST FOR?HOW TO TEST?

Key Questions to be answered for test specification:

05.10.2017Cyndi Moyo, AIT Energy 13

Page 13: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Purpose of Investigation (PoI)

Verification

Validation

Characterization

05.10.2017Cyndi Moyo, AIT Energy 14

Scoring / Performance

Modeling /Understanding

Test objectives/PoI: Characterization and validation of the DMS controller1. Convergence of the optimization

(validation)2. Performance of the optimization

under realistic conditions (characterization)

3. Accuracy of the state estimation (characterization)

Page 14: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Designing Test CriteriaDetailing Sequence

Test objective PoI Test Crit.

Test criteria: How to break down the PoIs?

– Target metrics (criteria): list of metrics to quantify each PoI

– Variability attributes:controllable or uncontrollable parameters to “disturb” SuT

– Quality attributes (thresholds): test result level or quality of the TM required to pass or conclude the testing.

05.10.2017Cyndi Moyo, AIT Energy 15

Target metrics: 1. 1.1 convergence (when/how

often?), 1.2. How fast?, 1.3. solution quality

2. 2.1 Voltage deviation 2.2 number of tap changes, 2.3 network losses

3. Voltage, P, Q estimation errorsVariability attributes: Load patterns (realistic, annual variation; applies to criteria 1-3); Communication attributes (packet loss, delays)Quality attributes (thresholds):

“1.2: convergence within 2 sec” (validation)“3.* estimation quality characterized with confidence 95%” …

Page 15: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

WHY TO TEST?WHAT TO TEST?WHAT TO TEST FOR?HOW TO TEST?

Key Questions to be answered for test specification:

05.10.2017Cyndi Moyo, AIT Energy 16

Page 16: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Test Specification & Design Given:

Purpose of Investigation (PoI) & Test Criteria

System & Domain categories and relations

To Specify:

Precise system (specific system configuration)

Which variables to manipulate & which to measure

How to quantify the test metrics (based on test data)

Sampling of the input spaces (design of experiments methodology)

Combination and interpretation of the outputs

The test design / procedure.

Mapping to actual lab setup (experiement setup)

05.10.2017Cyndi Moyo, AIT Energy 17

Research Infrastructure (RI)

Experiment Specification

Test CaseSuT, FuT, PoI, TC

Test SpecificationTest Design, I/O

1

6

7

Experiment in RI

test evaluation

test refinement

TO

rese

arch

infr

astr

uctu

re (R

I) ca

pabi

lity

prof

iles

SC UC

2

4 map

3

5

Test SpecificationTest Design, I/O

Page 17: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Scoping & specification of

test system.

Separate specification

of lab implementation

Detailing test setup &Mapping to the Lab

05.10.2017Cyndi Moyo, AIT Energy 18

Page 18: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

FIRST APPLICATION EXPERIENCE

05.10.2017Cyndi Moyo, AIT Energy 19

Can I just say, that it's very nice to get these questions sorted out now, rather than when you're sitting down and have to implement something. You would then usually go "Oh shit, how does this work again?“ – ERIGrid participant

Page 19: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

ERIGrid Transnational Access: Preparation & Documentation

External Lab users apply description procedure

E.g. DiNODR – distribution network oriented application of demand response – currently ongoing in SYSLAB

“The preparation work helped us a lot. Except minor changes in the plan and configurations due to a number of device, communication and control unavailabilities, we are following our test and experiment specifications. The template is also useful for our user team to exchange ideas in an organized and effective way. “ - Alparslan Zehir (DiNODR)

05.10.2017 Cyndi Moyo, AIT Energy 20

Page 20: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Collaboration with other Projects

ELECTRA IRP – Web-of-Cells (WoC) concept

– Large set of use cases (distributed control)

– Concurrent development and lab implementation

– Specification of test cases andexperiments

SmartNet – TSO/DSO interaction

– Different interaction schemes

– Proof-of-concept lab validationand field testing

– Specification of test cases andexperiments

05.10.2017Cyndi Moyo, AIT Energy 21

Page 21: Holistic system integration and validation procedure ......Oct 05, 2017  · Holistic Testing & Validation Cyndi Moyo, AIT Energy 05.10.2017 3 " Holistic testing is the process and

© The ERIGrid ConsortiumEU H2020 Programme GA No. 654113

Summary and future work

A clear vision for “holistic validation”

Initial results

– 3-level – test description template & guidelines

– Multi-Domain System Configuration description (CIM compatible)

– Several successful applications & encouraging feedback

Future work

– Further exemplify, simplify & detail description method

– Develop & apply full holistic validation procedure

05.10.2017Cyndi Moyo, AIT Energy 22