H&L Remediation 2011

35
μg/L In Situ Chemical Reduction of Hexavalent Chromium in Soils and Groundwater Using Ferrous Sulfide (FeS) Nanotechnology Richard H. Christensen, PhD, LPG Indianapolis, IN Steven R. Irvin Jim V. Rouse (MWH)

Transcript of H&L Remediation 2011

Page 1: H&L Remediation 2011

µg/L

In Situ Chemical Reduction of Hexavalent Chromium in Soils and Groundwater Using Ferrous Sulfide (FeS)

NanotechnologyRichard H. Christensen, PhD, LPG Indianapolis, INSteven R. IrvinJim V. Rouse (MWH)

Page 2: H&L Remediation 2011

Site Location -- Muncie, IN

Source Areas

© AcuityES 2011

Page 3: H&L Remediation 2011

Chrome Platingat its best!

© AcuityES 2011

Page 4: H&L Remediation 2011

Site OverviewSite Conditions

First investigation – 2005

AcuityES - 2008

Status:Equipment DeconnedBuilding Demolished

FOLLOWING SLIDES- GEOLOGY- HYDROGEOLOGY- REMEDIAL APPROACH- RESULTS

A’

A

© AcuityES 2011

Page 5: H&L Remediation 2011

Geology

FORMER BASEMENT

SOURCE AREA

© AcuityES 2011

Page 6: H&L Remediation 2011

Hydrogeology

Unconfined Aquifer

Sands & fine gravels

Static Water at 15’ bgl

Saturated thickness5’ in SE to

> 25’ in NW

© AcuityES 2011

Page 7: H&L Remediation 2011

Soil Impacts

Two Adjacent Source Areas5,400 cubic yards of impactPerched water sand stringers

Max Cr+6 concentration:7,900,000 µg/Kg

3,600,000 µg/Kg Cr+6 at 12’ bgl

© AcuityES 2011

Page 8: H&L Remediation 2011

Groundwater Impacts

Groundwater CoCsCr+6, Sb, As, and Ni

On-SiteCr+6

800,000 µg/L

9,700,000 µg/L

66,000 sq ft PlumeOffsite Cr+6 at 58,800 µg/L

© AcuityES 2011

Page 9: H&L Remediation 2011

Selected ISCR for Remediation Enhanced what was already occurring at Site

© AcuityES 2011

Page 10: H&L Remediation 2011

Chemical Reductant – FeSBENCH TESTED

•Ferrous Sulfide

•CaSx

•Sodium Thiosulfate

•Sodium Metabisulfite

•Zero Valent Iron

•Organosulfates

SELECTED –FeS

Liquid suspension of 7% FeSFeS - With additional 2% free Sulfide

to simulate CaSx

Nanoscale: 98% crystals <5 microns

Cation (Iron) & Anion (sulfide) Reaction

4 H2O + Cr042-+ 3 Fe2- + 4 OH-

3 Fe(OH)3+ Cr(OH)3 (1)

17 H2O + 8 Cr042- + 3 HS-

3 S + 8 Cr(OH)3 + 12 OH- (2)

© AcuityES 2011

Page 11: H&L Remediation 2011

In-Situ Soil Blending

Dual Axis Blender – 15’ PlungeTotal Area – 130’ x 110’

GPS Grid Network – 10’ x 10’Deep to 15’ & Shallow to 5’

Computerized Dosing

© AcuityES 2011

Page 12: H&L Remediation 2011

In-Situ Soil Blending

Dual Axis Blender

FeS - 5% admix (15 gals/yd3)

© AcuityES 2011

Page 13: H&L Remediation 2011

In-Situ Soil Blending

Thorough Mixing to 15’ BGL

Note: Cement barrier for uncompaction

© AcuityES 2011

Page 14: H&L Remediation 2011

In-Situ Soil BlendingCompleted in 2 weeksTotal FeS = 78,300 gallonsSubsequent stabilization with aglime required

© AcuityES 2011

Page 15: H&L Remediation 2011

Confirmation Sampling

© AcuityES 2011

Page 16: H&L Remediation 2011

Groundwater Injections – FeS

THE NUMBERS

155 Inject Pts

15 ft ROI

3% by volume

25 gals / LF

6 wks complete

© AcuityES 2011

Page 17: H&L Remediation 2011

Groundwater Injections

DifficultInjections

Boulder Fields

6’ caliche

Lodgement till

© AcuityES 2011

Page 18: H&L Remediation 2011

GroundwaterInjections

FeS Injection Totes35,385 gallons injected

Rotosonic DrillingTop Down Injection – 5ft intervals

© AcuityES 2011

Page 19: H&L Remediation 2011

Groundwater Injections

CommunitySensitivityRequired

ResidentialHours

© AcuityES 2011

Page 20: H&L Remediation 2011

Preferential Flow Paths15 – 20’ bglSand Unit

© AcuityES 2011

Page 21: H&L Remediation 2011

Preferential Flow Paths20 - 25’ bglSand Unit

© AcuityES 2011

Page 22: H&L Remediation 2011

Pre-Treatment Cr+6

© AcuityES 2011

Page 23: H&L Remediation 2011

1st Q Post-Treatment Cr+6

© AcuityES 2011

Page 24: H&L Remediation 2011

2nd Q Post-Treatment Cr+6

© AcuityES 2011

Page 25: H&L Remediation 2011

3rd Q Post-Treatment Cr+6

© AcuityES 2011

Page 26: H&L Remediation 2011

On-Site Monitoring Wells - Cr+6

© AcuityES 2011

Page 27: H&L Remediation 2011

Off-Site Monitoring Wells - Cr+6

© AcuityES 2011

Page 28: H&L Remediation 2011

Summary of Cr+6 Reduction

© AcuityES 2011

Page 29: H&L Remediation 2011

Pre-Treatment Antimony

© AcuityES 2011

Page 30: H&L Remediation 2011

1st Q Post-Treatment Antimony

© AcuityES 2011

Page 31: H&L Remediation 2011

2nd Q Post-Treatment Antimony

© AcuityES 2011

Page 32: H&L Remediation 2011

3rd Q Post-Treatment Antimony

© AcuityES 2011

Page 33: H&L Remediation 2011

Other Constituents of ConcernNickel – off-Site up to 4,100 µg/L

on-Site up to 50,000 µg/LSame footprint as AntimonyComplete 100% Reduction by 1st Quarter

Arsenic – Overall reduction in pervasiveness.Occurrence generally coincides with Cr+6

© AcuityES 2011

Page 34: H&L Remediation 2011

Lessons Learned 1. Forced to use Rotosonic over direct push

- Budget for the unexpected

2. Chemical injection instead of GW recirculation- Can’t wear blinders when considering delivery

method options for chemicals

3. Agency onboard for the technology- Relationship, communication, education

© AcuityES 2011

Page 35: H&L Remediation 2011

QUESTIONS?

Thank you!!

© AcuityES 2011