Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage...

69
Hinze Dam Stage 3 Project Terms of Reference for an Environmental Impact Statement Under Part (4) of the Queensland State Development and Public Works Organisation Act 1971 The Coordinator-General, Department of Infrastructure April 2007

Transcript of Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage...

Page 1: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Hinze Dam Stage 3 Project

Terms of Referencefor anEnvironmental Impact Statement

Under Part (4) of the Queensland State Development and Public Works Organisation Act 1971

The Coordinator-General, Department of Infrastructure

April 2007

Page 2: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

iHinze Dam Stage 3

Draft Terms of Reference for an EIS

PREAMBLE

Project Proponent

The proponent for the Hinze Dam Stage 3 Project is the Gold Coast City Council (GCCC).The Council has appointed the Hinze Dam Stage 3 Alliance, a consortium involving Thiess Pty Ltd, Sinclair Knight Merz Pty Ltd and URS Australia Pty Ltd, to assist with delivery of the project.

Project Summary

The Project to which this Terms of Reference applies involves the augmentation of Hinze Dam to the Stage 3 height.

Based on the adopted design option, the Hinze Dam Stage 3 Project (HDS3) proposes the raising of the Hinze Dam embankment from 93.5 metres to 108.5 metres, raising the Full Supply Level by 12.3 metres to 94.5 metres and providing a total capacity of in excess of 300,000 million litres. The upgrade will provide an additional 79,000 million litres of flood storage capacity and increase the dam’s yield by at least an additional 16 million litres a day. The project will also provide greater flood mitigation for properties downstream of the Dam and will make the structure compliant with current dam safety design guidelines and standards.

The project scope of works for the dam raising will also include upgrades to the embankment, spillway and intake towers; establishment of site offices, storage, stockpile and lay down areas; establishment and operation of quarry activities to provide construction materials; establishment of construction roads; clearing of vegetation in inundation areas and for establishment of quarries; and upgrading and relocating or replacing of ancillary services and structures including parks, car parks, recreational facilities, roads and bridges, including sections of the Nerang-Murwillumbah Road and Gold Coast-Springbrook Road.

Hinze Dam is located approximately 15 km southwest of Nerang on the Nerang River and supplies the majority of the water needs for Gold Coast City, a rapidly growing urban centre with a healthy economy. In addition to being a major water source for the region, the Hinze Dam catchment provides significant and appreciable benefits to the community through flood mitigation, environmental protection, tourism and recreation. The Hinze Dam was initially completed in 1976, and upgraded to stage 2 in 1989. The Dam impoundment, Advancetown Lake, has a storage capacity of 161,070 million litres, surface area of 9.77 km2 and a catchment area of 212 km2.

GCCC has prepared an Initial Advice Statement (IAS), which provides further detail relating to the Project. The IAS can be viewed at www.infrastructure.qld.gov.au.

Administrative Details for these Terms of Reference On 20 October 2006 the Hinze Dam Stage 3 Project was declared a significant project by the Coordinator-General (CG) pursuant to Section 26 of the State Development and Public Works Organisation Act 1971 (the ‘SDPWOA’) for which an Environmental Impact Statement (EIS) is required. GCCC is now required to prepare an EIS about the project to address the Terms of Reference (ToR) when they are finalised.

On 22 December 2006, the GCCC referred the project to the Commonwealth Minister for the Environment and Heritage (now the Minister for the Environment and Water Resources) for a

Page 3: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

iiHinze Dam Stage 3

Draft Terms of Reference for an EIS

decision as to whether the project constitutes a controlled action under the EnvironmentProtection and Biodiversity Conservation Act 1999 (Commonwealth) (‘the EPBC Act’). The Commonwealth Department of the Environment and Water Resources determined on 17 January 2007 that the project is a controlled action and therefore the Project will require approval under Part 9 of the EPBC Act before it can proceed.

As assessment is also required under the EPBC Act, the EIS will be required to address both State and Commonwealth requirements. The EIS will be undertaken in accordance with requirements of the bilateral agreement between the Australian Government and the Queensland Government which accredits Queensland’s assessment process for significant projects under the SDPWO Act.

State and Local Government representatives will be invited to participate in the EIS process as Advisory Agencies for the EIS and in the first instance were invited to examine the IAS and provide comment on the draft ToR. The IAS and draft ToR were also advertised in national and state newspapers and public comment was invited from 26 February to 28 March 2007. The CG had regard to the comments received from the Advisory Agencies and the public in finalising the ToR for the EIS. The ToR were then provided to GCCC to prepare the EIS.

When GCCC has prepared the EIS to the satisfaction of the CG, it will be made available for public comment (including to the Advisory Agencies) and submissions on the document will be invited. The submissions will be provided to GCCC to consider and respond to the issues raised in the submissions. The CG may request that the proponent prepare a supplementary report to the EIS to address any issues raised in submissions.

When the CG has sufficient information to evaluate the EIS, the CG will prepare a report evaluating the EIS and make recommendations or conditions about the project. The CG’s report will be made publicly available on the Department of Infrastructure’s website and will be provided to relevant government decision makers.

The ToR provides information in two broad categories:

Part A – Information and advice on the preparation of the EIS. Part B – Specific requirements – Content of the EIS.

The Department of Infrastructure’s Project Manager contact details are:

Sonya Booth Project Manager – Hinze Dam Stage 3 Project SEQ Water Grid, Department of Infrastructure PO Box 15009 BRISBANE CITY EAST QLD 4002

Tel: (07) 3237 7473 Fax: (07) 3237 7530 Email: [email protected]

The Coordinator-General, Department of Infrastructure, publicly invited comments on the draft ToR for the EIS from 26 February 2007 to 28 March 2007 and submissions received were considered and incorporated herein into the finalised ToR.

Page 4: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

iii Hinze Dam Stage 3

Draft Terms of Reference for an EIS

CONTENTSAdministrative Details for these Terms of Reference i

Part A – Information and advice on preparation of the EIS 1

Purpose of the Terms of Reference 1

EIS Guidelines 1

EIS Objectives 2

ToR Glossary 4

Part B – Specific Requirements - Content of the EIS 6

Executive Summary 6

Glossary of Terms 6

EIS format 7

1. Introduction 7

1.1 Project Proponent 7

1.2 Project Description 7

1.3 Project Objectives and Scope 7

1.4 Need for the Project 8

1.5 Relationship to other Projects 8

1.6 Alternatives 8

1.7 Cost and Benefits of the Project 9

1.8 The Environmental Impact Assessment Process 9

1.8.1 Methodology of the EIS 9

1.9 Public Consultation Process 9

1.9.1 Objectives of Community Consultation 10

1.9.2 Stakeholders for the Project 10

1.10 The General Community 11

1.11 Planning Context 11

1.12 Project Approvals: legislation and policy requirements 12

2. Description of the Project 13

2.1 Location and General Description 13

2.2 Proposed Works 14

2.2.1 Barrier/Embankment Structures 14

2.2.2 Site Details including Increased Inundation Area 15

2.2.3 Pre-Construction Activities 15

2.2.4 Construction Activities and Infrastructure 15

2.2.5 Auxiliary Infrastructure Requirements 16

2.3 Proposed Water Storage Operation 17

2.4 Rehabilitation and Decommissioning of Construction Works 17

Page 5: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

iv Hinze Dam Stage 3

Draft Terms of Reference for an EIS

3. Environmental Values and Management of Impacts 18

3.1 Land 19

3.1.1 Description of Environmental Values 19

3.1.1.1 Topography and Geomorphology 19

3.1.1.2 Geology and soils 19

3.1.1.3 Land use 20

3.1.1.5 Infrastructure 20

3.1.1.6 Sensitive Environmental Areas 20

3.1.1.7 Landscape and Visual Amenity 20

3.1.1.8 Land Contamination 21

3.1.2 Potential Impacts and Mitigation Measures 21

3.1.2.1 Land Resources and Infrastructure 21

3.1.2.2 Land Use and Tenure 22

3.1.2.3 Land Disturbance – Rehabilitation and Decommissioning of Construction Works 22

3.1.2.4 Soil Erosion 22

3.1.2.5 Acid Sulphate Soils 23

3.1.2.6 Contaminated Land 23

3.1.2.7 Landscape and Visual Amenity 23

3.2 Climate 24

3.3 Water Resources 24

3.3.1 Description of Environmental Values 24

3.3.1.1 Surface Water and Waterways 24

3.3.1.2 Groundwater 25

3.3.2 Potential Impacts and Mitigation Measures 25

3.3.2.1 Waterways and Water Quality 25

3.3.2.2 Hydrology and Flooding 26

3.3.2.3 Groundwater 27

3.4 Potential Impacts on Matters of National Environmental Significance 27

3.5 Terrestrial Flora 29

3.6 Terrestrial Fauna 32

3.7 Aquatic Biology 34

3.8 Cultural Heritage 36

3.8.2.1 Cultural Heritage Management Plan 36

3.9 Air Environment 37

3.10 Greenhouse Gas Impacts 37

3.11 Climate Change Adaptation 38

3.12 Noise and Vibration 38

3.13 Hazard, Risk and Safety 39

3.14 Emergency Management Plan 41

3.15 Waste Management 41

3.16 Transport and Roads 42

Page 6: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

vHinze Dam Stage 3

Draft Terms of Reference for an EIS

3.16.1 Transport Methods and Routes 42

3.16.2 Road Relocations: Potential Impacts and Mitigation Measures 43

4. Socio-Economic Environment 43

4.1 Social values 43

4.2 Economy 44

4.3 Employment and training 45

5. Environmental Management Plan 46

6. Conclusions and Recommendations 47

7. References 47

8. Recommended Appendices 47

8.1 Final Terms of Reference for the EIS 47

8.2 Statutory Permits and Development Approvals 47

8.3 Potential Impacts on Matters of National Environmental Significance 47

8.4 Consultation Report 48

8.5 Project Study Team Qualifications and Experience 48

8.6 Research Reports and Specialist Studies 48

8.7 List of Proponent Commitments 48

Page 7: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

1 Hinze Dam Stage 3 Terms of Reference for an EIS

Part A – Information and advice on preparation of the EIS

Purpose of the Terms of Reference These Terms of Reference (ToR) are for the preparation of an EIS for the HDS3 project, and relate to the assessment of the impacts on the environment of the proposals as initially described in the project’s IAS. It is important to note that these ToR apply to the proponent’s requirement to prepare an EIS on the HDS3 project and do not seek to address the impacts of the existing Hinze Dam structure.

The ToR essentially outline the issues that should be considered in preparing the Environmental Impact Statement (EIS). Furthermore, the ToR provides a framework for the EIS, including information on the purpose and role of the EIS, and the factors considered to be most significant for the proposal. It indicates the types of necessary studies and the data that should be provided.

All potentially significant impacts of the proposed development on the environment are to be investigated, and intentions for the mitigation of any adverse impacts are to be detailed in the EIS. Any prudent and feasible project alternatives should be briefly discussed and treated in sufficient detail and reasons for selection of the preferred option should be clearly identified.

The nature and level of investigations should be relative to the likely extent and gravity of impacts. The guidelines should, however, not be interpreted as excluding from consideration any matters which are currently unforeseen, which may arise during ongoing scientific studies or which may arise from any changes in the nature of the proposal during the preparation of the draft EIS, the community consultation process and associated documentation.

The EIS must address as a minimum the requirements as set out in the ToR. The proponent may be required to prepare a Supplementary Report on the EIS subsequent to the EIS’s release should it be determined by the Coordinator-General that further information on the project is required.

EIS Guidelines The objective of the EIS is to identify potential environmental impacts and to ensure that impacts are avoided where possible. Where unavoidable, impacts must be examined fully and addressed so that the development is based on sound environmental protection and management criteria.

An EIS should provide:

The project’s specific objectives and justification for the proposal.

A description of the relevant aspects of the existing social, economic, natural and built environment.

A description of the development proposal and means of achieving the development objectives, including timelines.

Strategic, economic and environmental implications of the proposal including its:

Page 8: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

2 Hinze Dam Stage 3 Terms of Reference for an EIS

- effectiveness as a flood mitigation measure;

- effect on short, medium and long term water production and consumption; and

- impacts on regional supply security.

Impact on other water infrastructure and downstream water entitlement holders due to increased storage and supply.

Analysis of a ‘no project’ option.

A framework against which State and Federal Government decision–makers can consider the environmental components impacted by the proposal and set conditions for approval to ensure environmentally sound development.

Definition and analysis of all significant environmental, social and economic impacts and measures proposed to avoid and/or mitigate adverse effects and offset any residual adverse effects.

Recommendations on the need for and consents required for the construction environmental management plan and operational environmental management plan to mitigate adverse effects and provide structure on best practice procedures to be followed, particularly during construction by all involved with the project. A draft environmental management plan is to be included in the EIS.

The project’s compatibility with the National Water Initiative, Government Ecologically Sustainable Development (ESD) policy, Queensland Natural Resources (Water) Policy, National Strategy on Conservation of Australia’s Biological Diversity; with water reform under the National Competition Policy; the Water Resource (Gold Coast) Plan 2006; and any other relevant policies.

The term ‘environment’ refers to:

a) ecosystems and their constituent parts, including people and communities;

b) all natural and physical resources;

c) the qualities and characteristics of locations, places and areas, regardless of size, that stimulate biological diversity and integrity, intrinsic or attributed scientific value or interest, amenity, harmony and sense of community;

d) the social, economic, aesthetic and cultural conditions which influence, or are affected by, the entities and attributes mentioned in paragraphs (a) to (c); and

e) the local, regional, Queensland and Australian populations and labour markets.

EIS Objectives Having described the methodology of the EIS, a succinct statement should be made of the objectives of the EIS. The structure of the EIS can then be outlined as an explanation of how the EIS will meet its objectives. The reader should be able to distinguish the EIS as the key environmental document providing advice to decision-makers considering approvals for the project.

Page 9: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

3 Hinze Dam Stage 3 Terms of Reference for an EIS

While the ToR provide guidance on the scope of the EIS studies, they should not be seen as exhaustive or limiting. It is important for proponents and their consultants to recognise that there cannot be perfect knowledge in advance of undertaking an EIS of what the EIS studies may find.

If it transpires during the preparation of the EIS that previously unforeseen matters not addressed in the ToR are found to be relevant to the assessment of impacts of the proposal, those matters should be included in the EIS.

In addition, it is essential that the main text of the EIS should address all relevant matters concerning environmental values, impacts on those values and proposed mitigation measures. No relevant matter should be raised for the first time in an appendix or the draft Environmental Management Plan (EMP).

When considering whether an impact is or is not significant, the proponent should take account of the likelihood, intensity and risk of the impact and the context in which it would occur.

The EIS is a public document. Its purpose is not only to provide information to regulatory agencies, but also to inform the public of the scope, impacts and mitigation measures of the proposal. As such the main text should be written in plain English avoiding jargon as much as possible. Additional technical detail may be provided in appendices. The main text should not assume that a reader would have a prior knowledge of the project site. It should not be necessary for the reader to have visited the site to understand the issues involved in the proposal.

The EIS objectives should be to provide public information on the need for and likely effects of the project, to set out acceptable standards and levels of impacts (both beneficial and adverse) on environmental values, and demonstrate how environmental impacts can be managed through the protection and enhancement of the environmental values. Discussion of options and alternatives and their likely relative environmental management outcomes is a key aspect of the EIS.

The role of the EIS in providing the project’s draft EMP should also be indicated, with particular reference to the EMP’s role in providing management measures that can be carried over into conditions that would attach to any approvals, environmental authorities and permits for the project.

In summary, the key objectives of the EIS are as follows:

For interested persons and bodies: a basis for understanding the Project, prudent and feasible alternatives, affected environmental values, impacts that may occur and measures to be taken to mitigate all adverse impacts.

For groups or persons with rights or interests in the land: an outline of the effects of the Project on that land including access arrangements.

For government agencies: a framework for decision-makers to assess the environmental aspects of the Project with respect to legislative and policy provisions and based on that information to make an informed decision on whether the Project should proceed or not and if so, on what conditions, if any.

Page 10: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

4 Hinze Dam Stage 3 Terms of Reference for an EIS

For the Federal Minister for the Environment and Water Resources: information to determine the extent of potential impacts of the Project on matters of national environmental significance, in particular the controlling provisions under the EPBC Act:

Sections 18 and 18A (Listed threatened species and communities)

For the proponent: a mechanism by which the potential environmental impacts of the Project are identified and understood. Information to support the development of management measures including an Environmental Management Plan, to mitigate the adverse effects of residual environmental impacts of the development.

ToR Glossary The following abbreviations have been used in this document:

AHD Australian Height Datum ACH Act Aboriginal Cultural Heritage Act 2003ANCOLD Australian National Committee on Large Dams ANZECC Australia and New Zealand Environment and Conservation Council AS Australian Standards ASS Acid Sulphate Soils BPA Biodiversity Planning Assessment CAMBA China-Australia Migratory Bird Agreement CHMP Cultural Heritage Management Plan CO Carbon Monoxide CG The Coordinator-General of the Department of Infrastructure

of the State of QueenslandCLR Contaminated Land Register DEW Department of the Environment and Water Resources (Commonwealth) DI Department of Infrastructure (formerly the Office of the Coordinator-

General)DLGPSR Department of Local Government and Planning, Sport and Recreation DNRW Department of Natural Resources and Water DPI&F Department of Primary Industries and Fisheries EIS Environmental Impact Statement EMP Environmental Management Plan EMR Environmental Management Register EPP Air Environmental Protection (Air) Policy 1997 EPP Noise Environmental Protection (Noise) Policy 1997 EPP Waste Environmental Protection (Waste Management) Policy 2000 EPP Water Environmental Protection (Water) Policy 1997 EPR Waste Environmental Protection (Waste Management) Regulation 2000EP Act Environment Protection Act 1994EPA Environment Protection Agency EPBC Act Environment Protection and Biodiversity Conservation Act 1999

(Commonwealth)ERA Environmentally Relevant Activity ESD Environmentally Sustainable Development FSL Full Supply Level GCCC Gold Coast City Council HAT Highest Astronomical Tide HDS3 Hinze Dam Stage 3 Project

Page 11: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

5 Hinze Dam Stage 3 Terms of Reference for an EIS

IAS Initial Advice Statement as described in Part 4 of the State Development and Public Works Organisation Act 1971

IDAS Integrated Development Assessment System ILUA Indigenous Land Use Agreement IPA Integrated Planning Act 1997 (Qld) JAMBA Japan-Australia Migratory Bird Agreement LNCS Local Nature Conservation Strategy MR Department of Main Roads NEPM National Environment Protection Measure NES National Environmental Significance as defined by the

Environment Protection & Biodiversity Conservation Act 1999 (Commonwealth)

NTRB Native Title Representative Bodies PHA Preliminary Hazard Assessment PRW Purified Recycled Water PSI Preliminary Site Investigation QH Queensland Herbarium QH Act Queensland Heritage Act 1992QHC Queensland Heritage Council RE Regional Ecosystem REDD Regional Ecosystem Description Database SEQ South East Queensland SDPWO Act State Development and Public Works Organisation Act 1971SEQRWSS South East Queensland Regional Water Supply Strategy ToR Terms of Reference as described in Part 4 of the State Development

and Public Works Organisation Act 1971 VMA Vegetation Management Act 1999 WRP Water Resource Plan

Page 12: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

6 Hinze Dam Stage 3 Terms of Reference for an EIS

Part B – Specific Requirements - Content of the EIS

The EIS will be used to inform the public, decision-makers and relevant stakeholders of the potential impacts of the project, and the management of those impacts. The EIS should be written in a clear, plain English, in a style easily understood by the general reader. Text within the report should be referenced and where appropriate, supported by coloured maps, plans, diagrams and other descriptive details.

The report should be supported by appendices, which include detailed results of technical studies and results of community consultation (including detailed submissions where appropriate, summaries of submissions, comments and inputs provided, details of individuals and organisations consulted).

An overview of the methodology used to undertake the various assessments should be provided in each section.

It is strongly recommended that the EIS follow the heading structure of these Terms of Reference to facilitate cross-referencing.

Executive Summary The Executive Summary should be written as a stand-alone document, able to be reproduced on request for interested parties who may not wish to read or purchase the EIS as a whole. The structure of the executive summary should follow that of the EIS, though focus strongly on the key issues allowing the reader to obtain a clear understanding of the HDS3 Project, its environmental and socio-economic implications and management objectives. The summary should include:

The title of the Project;

Name and contact details of the Proponent, and a list of previous projects undertaken by the Proponent, their environmental record and commitment to effective environmental management;

A concise statement of the aims and objectives of the Project;

The legal framework, decision-making authorities and advisory agencies;

An outline of the background to and need for the Project, including the consequences of not proceeding with the Project;

An outline of the alternative options considered and reasons for the selection of the proposed development option;

A brief description of the Project (pre-construction, construction and operational activities) and the existing environment, utilising visual aids where appropriate and including timelines; and

An outline of the principal environmental impacts predicted and the proposed environmental management strategies (including water quality and waste minimisation and management) and commitments to minimise the significance of these impacts.

Glossary of Terms A glossary of technical terms, acronyms and references should be provided in the EIS.

Page 13: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

7 Hinze Dam Stage 3 Terms of Reference for an EIS

EIS format The EIS should be produced on A4 size paper capable of being photocopied, with maps and diagrams on A4 or A3 size. The EIS document should not contain watermarks across the body of the text. The EIS should also be provided on CDROM/DVD.

Two separate CDROM/DVD copies should be provided:

1. CDROM/DVD copies resolution equivalent to the printed document for distribution to stakeholders; and

2. CDROM/DVD copies for placement on the internet:

Copies should be in Adobe® PDF format for placement on the internet. All compression must be down-sampled to 72 dpi. PDF documents should be no larger than 2MB in file size. The executive summary should be supplied in HTML 3.2 format with *.jpg graphics files. Text size and graphics files included in the PDF document should be of sufficient resolution to facilitate reading and enable legible printing, but should be such as to keep within the 500 KB file size.

The final nature and number of EIS copies required to be submitted and made available, should be discussed and agreed with the CG Project Manager in the early stages of the EIS process.

1. Introduction

The Introduction to the EIS should detail the key drivers and reason/s for the EIS, the audience who will be reviewing the document, the approval process and legislative context, and structure of the document.

1.1 Project Proponent This section should describe the experience of the Project Proponent (and associated project entities), including the nature and extent of business activities, experience and qualifications, and environmental record including the Proponent’s environmental policy. The proponent’s and project alliance’s previous history with water infrastructure projects should be included.

This section should also provide contact details (postal; email and telephone) for key Project staff from GCCC and the Alliance, detailing their primary function and areas of expertise.

1.2 Project Description This section should provide a brief description of the project, including a summary of any major infrastructure requirements associated with the project.

1.3 Project Objectives and Scope This section should provide a statement of the objectives which have led to the formulation of the project and brief outline of the events which have influenced the formulation of the project. This should include a brief discussion of feasible alternatives, including demand management, proposed time frames for implementation and expected project life, anticipated

Page 14: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

8 Hinze Dam Stage 3 Terms of Reference for an EIS

establishment costs and relevant actions already undertaken in relation to the Project. The additional capacity and supply the project will deliver should be listed here.

1.4 Need for the Project This section should briefly discuss justification and need for the project with respect to regional, State and national contexts. This section will relate to the flood mitigation requirements and the local and state government identified requirements for additional water resources including within the Gold Coast Water Future and the South East Queensland Regional Water Supply Strategy (SEQRWSS). Particular reference should be made to environmental, economic and social costs and benefits.

1.5 Relationship to other Projects This section should also describe how the project relates to any other water infrastructure projects including any strategies outlined in the SEQRWSS. The project’s relationship with other measures listed within the Water Amendment Regulation (No.6) 2006, for example but not limited to, water harvesting into Hinze Dam and the transfer of 20 ML/day via Logan, is to be briefly discussed.

As announced by the Premier of Queensland on 28 January 2007, in the best interest for our region and its residents, purified recycled water (PRW) will be a permanent and ongoing part of South East Queensland’s potable water supplies. Therefore the project’s relationship with potential PRW initiatives relating to the Hinze Dam should also be indicated.

1.6 Alternatives This section should describe all feasible alternatives that have been investigated, as well as the option of taking no action i.e. of not upgrading the dam. Sufficient detail should be provided to establish an understanding of the reasons for preferring certain options and rejecting others. Indication of the following should be provided:

the consequences of not proceeding with the project;

identification of feasible alternatives, including:

– Alternative structure augmentation sizes and capacities. Impacts associated with shortlisted design options and alternative sources (i.e. onsite and offsite) of construction materials, including impacts both of extraction and transporting, should be discussed;

– Provision of flood mitigation for the lower Nerang River; – Demand management strategies; and – Alternative water supply scenarios as identified in the GCCC Water Future report.

Identify the methodology adopted to discern between feasible options. The alternative options should be discussed in sufficient detail to enable an understanding of the reasons for preferring certain options and courses of action and rejecting others.

Page 15: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

9 Hinze Dam Stage 3 Terms of Reference for an EIS

1.7 Cost and Benefits of the Project This section should summarise:

The economic costs and benefits to industry and the wider community, including directly affected enterprises. Analysis should be conducted at the local, regional, state and national levels.

Regional social impacts including community disruption, related land use changes, employment, skills development and any workforce accommodation issues.

Benefits to the region in terms of regional water security and levels of service

1.8 The Environmental Impact Assessment Process This section will clearly identify which legislative process is relevant and the methodology being adopted to comply with the relevant legislation.

1.8.1 Methodology of the EISThis section should include a description of the impact assessment process steps, timing and decision making process for the relevant stages of the Project. This should also include a description of how the consultation process will be integrated with other elements of the impact assessment, including timing and opportunities for public input and participation.

The information in this section is required to ensure:

that relevant legislation is addressed;

readers are informed of the process to be followed; and

that stakeholders are aware of any opportunities for input and participation.

1.9 Public Consultation Process This section should outline the public consultation process that has taken place during the EIS’s preparation, including details on how public submissions on the draft EIS will be invited, considered and addressed in the decision making process and anticipated timelines for the process. The results of such consultation should also be listed.

The public consultation program should provide opportunities to encourage and facilitate active community involvement and education through public meetings, interest group meetings, production of regular summary information and updates, and other consultation mechanisms.

The public consultation process should identify broad issues of concern to the local community and interest groups at all stages from project planning, through construction, commissioning, operations and final decommissioning. This section should also detail how outcomes of the consultation process have been incorporated into the project design and/or management.

Page 16: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

10 Hinze Dam Stage 3 Terms of Reference for an EIS

1.9.1 Objectives of Community ConsultationThe objectives for community consultation for the EIS are to:

Enhance community awareness and understanding of the project, with the provision of adequate and appropriate information;

Identify key stakeholders (including representatives of stakeholder groups), their needs and values;

Facilitate involvement by the community into the project’s development;

Provide information on the EIS process;

Seek input in terms of key issues and concerns and suggestions to mitigate these concerns;

Seek feedback on the preferred concept;

Provide information on the outcomes of project studies; and

Demonstrate how issues of concern to the community will be sourced, identified and considered during the EIS process.

1.9.2 Stakeholders for the ProjectTo facilitate the assessment process, the Proponent is strongly encouraged to regularly consult with Advisory Agencies and other appropriate stakeholders throughout the EIS process.

It is the responsibility of the Proponent, in consultation with Advisory Agencies, to identify legislation, policies and methodologies relevant to the EIS process, and to determine appropriate parts of the community which should be consulted during the EIS preparation stage. It is recommended that an open community consultation process be carried out in addition to the legislated environmental impact assessment process. Copies of the EIS will be provided to all advisory agencies, elected representatives and on request to relevant individuals and peak groups with an interest in the Project.

Advisory Agencies Advisory agencies include government departments, authorities, agencies and key service providers. These organisations will need to be consulted to obtain their view and identify any statutory requirements they consider relevant to the study. Advisory agencies will include, but not be limited to:

Commonwealth Department of the Environment and Water Resources

Environmental Protection Agency

Queensland Water Commission

Department of Natural Resources and Water

Department of Primary Industries and Fisheries

Department of Main Roads

Department of Transport

Queensland Police Service

Department of Public Works

Page 17: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

11 Hinze Dam Stage 3 Terms of Reference for an EIS

Department of Emergency Services

Department of State Development and Trade

Department of Local Government, Planning, Sport and Recreation

Department of Employment and Industrial Relations

Queensland Health

Advisory agencies were asked to provide input to the draft ToR and have been provided with copies of the final ToR for the EIS which incorporated agency feedback. A copy of the finalised ToR should also be included as an appendix to the draft EIS.

Advisory agencies will also be invited to consider the draft EIS and provide submissions on the document.

Other Stakeholder, Community and Special Interest Groups Relevant stakeholder, community and special interest groups should be identified and consulted. Such groups include:

Local authorities;

Relevant local progress associations and other resident organisations;

Indigenous and Native Title Claimant organisations;

Relevant community groups such as ratepayers association, business owners, environmental and heritage groups;

Service providers; and

Recreational and commercial fishers.

1.10 The General Community The general community who are not represented by established interest groups are also key stakeholders for the project. The consultation process on the EIS should also include appropriate mechanisms targeted at ensuring adequate involvement of the general community both in the study area and in the broader Queensland region as appropriate.

1.11 Planning Context This section should discuss the project and provide an assessment of the project’s consistency with relevant planning policy for the area and region. This information is required to demonstrate how the proposal conforms to State, regional and local policies for the area. This section should include an assessment of the project’s consistency with the following:

the GCCC local planning scheme. It should be indicated that much of the project area is already subject to a Community Infrastructure Designation (CID) and pending final decision on the matter by Council, should it be the case that an application will be made by GCCC to seek the CID being extended to cover the additional impoundment area, no Gold Coast City Council Planning Scheme approvals will be required within this area.

planning controls, by-laws and policies relating to the study area and adjacent lands, including Water Resource Planning and Entitlements;

Page 18: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

12 Hinze Dam Stage 3 Terms of Reference for an EIS

regional strategies or plans that relate to existing land uses or long term policy framework for the area or proposal (these include those that are in preparation) particularly in relation to the SEQ Regional Plan and the SEQ Regional Infrastructure Plan and Program; the Regional Water Supply Strategy; the State Coastal Management Plan 2001 and the SEQ Regional Coastal Management Plan 2006 (if applicable), and with legislation, standards, codes or guidelines available to monitor and control operations on site. It should refer to all relevant State and regional planning policies; and

its relationship to other significant developments (existing or proposed) in the study area, surrounding locality and South East Queensland region.

1.12 Project Approvals: legislation and policy requirements This section should identify and explain the federal, state and local legislation and policies controlling the approvals process. Triggers for the application of each of these should be indicated and relevant approval requirements should be identified. This information is required to assess how the legislation applies to the proposal, which agencies have jurisdiction, and whether the proposed impact assessment process is appropriate.

At the State level, the project will be subject to a number of approvals under various legislation. As the HDS3 project was declared by the Coordinator-General (CG) in October 2006 to be a significant project pursuant to Section 26 of the State Development and Public Works Organisation Act 1971 (the ‘SDPWOA’), the project’s approvals process will be facilitated by the CG through the EIS process.

The ToR should note that the relevant legislation includes, but is not limited to:

State Development and Public Works Organisation Act 1971;

Integrated Planning Act 1997;

Integrated Planning Regulation 1998;

Vegetation Management Act 1999;

Environmental Protection Act 1994;

Water Act 2000;

Water Amendment Regulation (No.6) 2006;

Fisheries Act 1994;

Nature Conservation Act 1992;

Aboriginal Cultural Heritage Act 2003;

Queensland Heritage Act 1992;

Transport Infrastructure Act 1994;

Transport Planning and Coordination Act 1995; and

Land Act 1994.

The draft EIS should describe the approval process resulting from the gazettal of this project as a significant project pursuant to the SDPWOA and outline the linkage with the IDAS process under the IPA. The draft EIS should indicate the level of approvals anticipated by the

Page 19: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

13 Hinze Dam Stage 3 Terms of Reference for an EIS

proponent under the IPA and intentions to seek an amendment to the existing Community Infrastructure Designation to extend its boundary to include the additional impoundment area.

This outline should describe the public notification processes and appeal rights that will be available in the anticipated approval process.

The EIS should note that the project has been listed as an emergency water supply measure for the SEQ region within the Water Amendment Regulation (No. 6) 2006 (the ‘water emergency’ regulation). The Regulation instructs that the project must be delivered by the end of 2010.

A description of all Environmentally Relevant Activities (ERAs) necessary for the Project should also be given.

The project’s relationship with the Water Resource (Gold Coast) Plan 2006 should also be indicated in this section.

As the project is a controlled action under the Commonwealth EPBC Act, any requirements of the Commonwealth Environment Protection and Biodiversity Conservation Act 1999should also be indicated in this section.

A list provided of the approvals required for the project and the expected program for approval of applications should be provided.

The project’s compatibility with the National Water Initiative, the South East Queensland Regional Plan 2005-2026, Government Ecologically Sustainable Development policy, Queensland Natural Resources (Water) Policy, National Strategy on Conservation of Australia’s Biological Diversity; with water reform under the National Competition Policy; and any other relevant policy, should be described.

2. Description of the Project

The purpose of this section is to provide a description of the Project through its construction, operation and maintenance stages.

2.1 Location and General Description The project should be described in the local, regional and national contexts. The following should be addressed:

Project area description: The overall project area should be described, including upstream and downstream natural and anthropogenic environments of the Hinze Dam and Nerang River catchments.

Current structure and facilities: The current structures and facilities at and around Hinze Dam and upstream locations should be described.

Construction footprint: The area to be affected by the construction and operation of the dam should be described in detail including details of the area to be directly affected such as the areas to be inundated, quarries, construction sites, road upgrades, areas to be

Page 20: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

14 Hinze Dam Stage 3 Terms of Reference for an EIS

cleared, land requirements for ancillary facilities, road relocation and realignment, infrastructure and recreational facilities.

Maps at suitable scales should be provided showing the precise location of the project area, the location and boundaries of the project footprint, and location and boundaries of land tenures. The features described above should be overlain on a rectified air photo enlargement to illustrate components of the Project in relation to the natural and built features of the area.

A schedule of the overall Project duration and expected timing of works is to be provided.

2.2 Proposed Works A description of the proposed works for the Project should be provided.

The following information should be detailed and be supported by detailed plans where appropriate.

2.2.1 Barrier/Embankment StructuresThe following should be provided through text and design plans:

general arrangement of proposed works;

maximum (final) embankment crest heights;

length and width of embankment crest;

details and dimensions of the proposed downstream chute, plunge pool, dissipaters and other structures within the chute;

offtake and outlet works for downstream discharge;

details of the (existing) hydro-electric facility in relation to the upgraded spillway;

basic spillway dimensions and capacity, including spillway crest length and spillway discharge capacity;

any changes to the shape or discharge properties of the spillway crest;

surface area of storage area at full supply level;

details of any changes or upgrades to flow control or energy dissipation devices downstream of the spillway;

estimated headwater and tailwater levels at different flows including tailwaters in the absence of spilling flows;

frequency of spill (include comparison with current frequencies);

capacity and maximum depth;

average depth;

estimated water yields (with appropriate allowances for environmental requirements);

the dam’s dead storage level;

details of any provision for fish passage in the design;

details on the effectiveness of the proposed fish transfer mechanism/s, drawing on examples used on other dams or similar proposals and including a cost-benefit analysis;

Page 21: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

15 Hinze Dam Stage 3 Terms of Reference for an EIS

details and dimensions of any additional existing water impoundment or control structures that may be augmented as part of the overall Project;

a comparison of differences between the existing and upgraded structures; and

details of any temporary waterway barrier works to be installed downstream during the construction phase.

2.2.2 Site Details including Increased Inundation AreaFor clarity, the existing structure and impoundment’s footprint should be provided and related to the proposed increases in size and scope and changes in downstream flow regime.

The following details should be provided:

impacts on the stream bed downstream of the barrier (e.g. presence of any deep pools, riffles etc);

impacts on the stream bed upstream of the barrier (e.g. presence of natural features likely to be impacted);

inundation area for a range of water levels;

areas inundated (and depth) and the frequency of inundation, including plan with tenure details and current land use;

length of stream (and tributaries) inundated (taking account of varying supply levels); and

the extent of the buffer zone around the inundation area.

2.2.3 Pre-Construction ActivitiesA description of the pre-construction activities should be set out in this section, including:

Upgrading or relocation of roads (e.g. Gold Coast to Springbrook Road), railways and other infrastructure;

Clearing, including clearing and establishment of quarry areas; and

Location and site establishment requirements for construction facilities.

2.2.4 Construction Activities and InfrastructureFull details on the proposed on-going operation and management of the dam during construction of the project should be described.

The following details on construction of the Project should be provided: general construction requirements including source and extraction of construction materials, and access routes to these materials;

details of the method of construction of the dam wall augmentation and volumes of material required;

details of how the integrity of the existing dam wall will be ensured during construction activities;

details of the method for handling flood events during construction;

any staging of construction activities;

construction, realignment and/or upgrading of roads;

Page 22: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

16 Hinze Dam Stage 3 Terms of Reference for an EIS

size and source of construction workforce and construction camp requirements and location (if proposed);

works needed within the impoundment including tree clearing (by manual methods and by inundation) and tree clearing strategies to maximise fish habitat maintenance (but minimise adverse water quality issues), blasting, excavation, dredging and transport infrastructure works;

works downstream including erosion protection;

type, source, quantity and method of transport of construction materials;

general construction standards and site management including environmental and safety management;

timetable for construction;

details of any potential disruption to flows in the waterway during construction and any diversion works required;

the hours of operation;

emergency aid/medical facilities to be provided on site;

the construction methods and containment/disposal of construction spoil;

Any works proposed for downstream to protect water quality - e.g. sediment traps;

solid and liquid waste handling (including effluent disposal and any licensing required); and

the number and type of vehicles, machinery and equipment used for excavation, construction and operation.

2.2.5 Auxiliary Infrastructure RequirementsThis section should provide descriptions of requirements for constructing new infrastructure and upgrading or relocating of existing auxiliary infrastructure relating to the project. The matters to be considered include a fishway or fish transfer devices/methods, pipelines (e.g. requirements for any new pipelines, or augmentation to existing water transfer infrastructure), roads, bridges, tracks and pathways, power lines and recreational facilities.

How the project’s auxiliary infrastructure requirements have been determined in consideration of linkages with projects indicated within section 1.5 of this ToR should also be indicated.

Consideration of measures to be taken to prevent the transfer of aquatic flora and fauna between catchments through associated pipeline infrastructure and the economic and efficiency impacts of these measures should also be included in the EIS.

Page 23: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

17 Hinze Dam Stage 3 Terms of Reference for an EIS

2.3 Proposed Water Storage Operation

Full details on the proposed on-going management of the augmented dam, inundation area and buffer zone should be provided including:

Consideration of how the operation of the water storage will comply with the WaterResources (Gold Coast) Plan 2006 and the subsequent Resource Operations Plan;

arrangements for operation of the works, e.g. flow releases (environmental, irrigation etc, operation of gates (if relevant)), the anticipated pattern of inundation, operation of outlet works including details of operation and administration, including proposals for remote operation, and any proposed changes to existing staffing arrangements, etc;

consideration should be given to how existing seasonal flows will be managed, drawing on baseline or predictive studies, in the operation stage of the Project;

water treatment arrangements for provision for urban supply requirements and environmental flow requirements. This should include a description of how water will be sourced (water offtake operation), treatment facilities, associated infrastructure, and treatment methods. This should also describe the integration of operations within the catchment;

details of any proposed changes to the operational workforce numbers and personnel type;

details of the maximum drawdown level and likely extraction regime, e.g. when water will be sourced and expected demands versus yield, including likely release timings;

proposed access points associated with the increased storage;

infrastructure for recreational purposes;

proposed operation of the fishway and/or other fish transfer mechanisms.

This section should provide details on the timing of the construction of the Project including planning, impact assessment, construction, monitoring, EMP, etc, anticipated establishment and ongoing costs and the Project life. Costs should include monitoring and environmental mitigation/management costs.

The location and design of any existing or new water distribution infrastructure (e.g. pump stations, canals, pipelines etc.) should be described. The capacity of the existing water infrastructure to accept additional loadings resulting from new or increased allocations of water should also be described. As above, consideration of ways in which the inter-basin transfer of aquatic flora and fauna can be prevented through associated pipeline infrastructure and associated costs of this technology.

2.4 Rehabilitation and Decommissioning of Construction Works

Section 3.1.2.3 requires that the EIS should describe the options, strategies and methods for progressive and final rehabilitation of all environmental values disturbed by the Project.

Page 24: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

18 Hinze Dam Stage 3 Terms of Reference for an EIS

3. Environmental Values and Management of Impacts

This section should provide information on the physical, biological social and economic environment in the vicinity of Hinze Dam (such as land, water, nature conservation, cultural heritage, social and economic, air, noise, waste, transport and traffic, and hazards and risk).

The EIS should assess the impacts of pre-construction, construction and operation, decommissioning of redundant infrastructure, and rehabilitation of disturbed lands.

Aspects of the environment should be described to the extent necessary for the assessment of potential impacts of the Project. Baseline information from relevant studies should be used and referenced where appropriate. Any relevant studies undertaken and commitments given in relation to previous studies should be identified and assessed for their relationships to the Project. The impacts associated with potential ongoing maintenance, access and servicing resulting from the development and any other facilities required for the Project should also be assessed.

The functions of this section are to:

To describe the existing environmental values of the area which may be affected by the Project. Environmental values are defined in section 9 of the Environmental Protection Act1994, Environmental Protection Policies and other documents such as the ANZECC 2000 guidelines. Environmental values may also be derived following recognised procedures, such as described in the ANZECC 2000 guidelines and Queensland Water Quality Guidelines 2006. Environmental values should be described by reference to background information and studies, which should be included as appendices to the EIS.

Describe potential adverse and beneficial impacts of the proposal on the identified environmental values.

Any likely harm on the environmental values should be described.

Present environmental protection objectives and the standards and measurable indicators to be achieved.

Examine viable strategies for managing impacts.

Demonstrate whether there is sufficient baseline data to determine impacts on or changes to the existing environmental components and against which the success of mitigation measures can be evaluated.

Environmental protection objectives may be derived from legislative and planning requirements which apply to the Project including Commonwealth strategies, State planning policies, local authority strategic plans, environmental protection policies under the Environmental Protection Act 1994, and any catchment management plans prepared by local water boards or land care groups.

Special attention should be given to those mitigation strategies designed to protect the values of any sensitive areas and any identified ecosystems of high conservation value within the area of possible proposal impact.

Page 25: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

19 Hinze Dam Stage 3 Terms of Reference for an EIS

It is strongly recommended that the EIS follow the heading structure shown below. The mitigation measures, monitoring programs, etc., identified in this section of the EIS should be used to develop the Environmental Management Plan for the project (see Section 5).

3.1 Land

3.1.1 Description of Environmental ValuesThis section describes the existing environment values of the land area that may be affected by the Project, including additional area to be inundated, quarries and any construction areas. It should also define and describe the objectives and practical measures for protecting or enhancing land-based environmental values, describe how nominated quantitative standards and indicators may be achieved, and how the achievement of the objectives will be monitored, audited and managed.

3.1.1.1 Topography and Geomorphology

Description of Environmental Values

Maps should be provided locating the Project in both State, regional and local contexts. The topography of the proposal site should be detailed with contours at suitable increments, shown with respect to Australian Height Datum (AHD) and in relation to the FSL and buffer zone for the project. Significant features of the locality should be included on the maps. Such features would include any locations subsequently referred to in the EIS (e.g. sensitive locations, significant environmental features) that are not included on other maps for this section. Commentary on the maps should be provided highlighting the significant topographical features.

3.1.1.2 Geology and soils

Description of Environmental Values

The EIS should provide a description and maps of the geology of the Project area and briefly discuss the current dam wall foundations and any geological limitation in raising the wall. The availability and suitability of locations in the vicinity of the impoundment for quarry material is also to be identified. Particular reference to the physical and chemical properties of surface and sub-surface materials and geological structures within the proposed areas of any ground disturbance should be listed.

Soils in the project area involved in construction works should be mapped at a suitable scale and described according to the Australian Soil and Land Survey Field Handbook (Gunn et al 1988 and McDonald et al, 1990) using the Australian Soil Classification (Isbell, 1996). An appraisal of the field texture, colour, mottles, drainage, permeability and water holding capacity characteristics, soil structure, erosion hazard rating and pH should be undertaken.

Information should also be provided on soil stability and suitability to construction of all facilities and infrastructure. The availability and suitability of rock, clay, sand and gravel for use as construction materials should also be briefly discussed.

Page 26: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

20 Hinze Dam Stage 3 Terms of Reference for an EIS

3.1.1.3 Land use

Description of Environmental Values

The EIS should provide a description of current land uses in the proposal area, with particular mention of land with special purposes. Maps at suitable scales showing existing land uses and tenures, reserves, roads and road reserves, and the proposed inundation areas should be provided for the entire area that could be affected by the Project. Also indicate locations of gas and water pipelines, power lines and any other easements.

The maps should identify locations of local, regional and state conservation values as identified by the EPA’s Biodiversity Planning Assessment (BPA) and the Gold Coast City Council’s Local Nature Conservation Strategy (the Council’s LNCS), existing dwellings and recreational areas, and the zoning of all affected lands according to any existing town or strategic plan.

3.1.1.4 Native Title

Description of Environmental Values

Areas covered by native title determinations or applications for native title determination, including traditional and contemporary uses of land and water by Aboriginal people, should be described. A description of Native Title Representative Bodies (NTRB) boundaries should be provided. The EIS should identify whether there are any necessary notifications required to the Representative Bodies or if there is evidence that Native Title is not an issue for the areas involved.

3.1.1.5 Infrastructure

Description of Environmental Values

All existing infrastructure at the existing dam wall and any to be affected by the project both upstream and downstream of the impoundment should be identified and locations indicated on a suitably scaled map. This section may be cross-referenced to section 2.2 Proposed Works.

3.1.1.6 Sensitive Environmental Areas

Description of Environmental Values The EIS should identify all sensitive environmental areas that are proximal to the proposal or could be directly affected by the proposal. In particular, the EIS should indicate if the land affected by the proposal is, or is likely, to become part of the protected area estate, or is subject to any treaty. Consideration should be given to national parks, conservation parks, declared fish habitat areas, wilderness areas, aquatic reserves, heritage/historic areas or items, national estates, world heritage listings and sites covered by international treaties or agreements (e.g. Ramsar, JAMBA, CAMBA), areas of cultural significance, both indigenous and non-indigenous, and scientific reserves.

3.1.1.7 Landscape and Visual Amenity

Description of Environmental Values This section should describe existing landscape character and features, panoramas and views for the Project area, in particular from the existing dam wall and recreational areas. Information in the form of maps, sections, elevations and photographs is to be used, particularly where addressing the following issues:

Page 27: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

21 Hinze Dam Stage 3 Terms of Reference for an EIS

major views, view sheds, existing viewing outlooks, ridgelines and other features contributing to the amenity of the area, including assessment from private residences in the affected area along the route;

focal points, landmarks (built form or topography), gateways associated with project site and immediate surrounding areas, waterways, and other features contributing to the visual quality of the area and the project site; and

character of the local and surrounding areas including character of built form (scale, form, materials and colours) and vegetation (natural and cultural vegetation) directional signage and land use.

3.1.1.8 Land Contamination

Description of Environmental Values A search of the EPA’s Environmental Management Register (EMR) and Contaminated Land Register (CLR) should be undertaken to determine the requirements for management under the Environmental Protection Act 1994. The history of the site should be investigated including analysis of historical aerial photographs and determination of past and current land uses. The EIS is to include an assessment of land that has been used, or is being used, for a Notifiable Activity as listed in Schedule 2 of the Environmental Protection Act 1994, or is potentially contaminated or is on the Environmental Management Register (EMR) and Contaminated Land Register (CLR) and is within the impoundment areas and adjacent zones, including the location of ancillary services and structures.

A Preliminary Site Investigation (PSI) of the site consistent with the EPA’s “Draft Guidelines for the Assessment and Management of Contaminated Land in Queensland” (Queensland EPA, 1998) should be undertaken to determine background contamination levels. The results of the PSI should be summarised in the EIS and provided in detail in an appendix.

Should the PSI identify the possibility of contamination, a detailed site investigation is to be undertaken and a remediation plan developed in accordance with the Draft Guidelines for the Assessment and Management of Contaminated Land in Queensland (EPA, 1998). It will be necessary that no affected land will be on the EMR or CLR prior to inundation. Any results of site investigations, remediation and validation must be certified by a Third Party Reviewer prior to being published in the EIS.

3.1.2 Potential Impacts and Mitigation MeasuresThis section defines and describes the objectives and practical measures for protecting or enhancing the land-based environmental values identified through the studies outlined in the previous section. The potential for the construction and operation of the Project to change any existing and potential uses of the project’s impoundment area and adjacent areas, and the measures to minimise these impacts should be described.

3.1.2.1 Land Resources and Infrastructure

Potential Impacts and Mitigation Measures

Identify the Project in the context of major topographic features and any measures taken to avoid or minimise impact to such (if required).

The objectives to be used for the Project in re-contouring and landscaping, especially any quarries and recreational areas should be described. Consideration should be given to the use of threatened plant species during any landscaping and revegetation.

Page 28: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

22 Hinze Dam Stage 3 Terms of Reference for an EIS

3.1.2.2 Land Use and Tenure

Potential Impacts and Mitigation Measures

The potential for the construction and operation of the Project to change existing and potential land uses of the proposal project areas should be detailed.

The full extent of land that is required for the project’s buffer zone should be documented. The process of acquisition and/or resumption (if applicable) of land should be outlined. The method, by which ownership, control or owners’/custodians’ consent is to be acquired, should be presented.

The potential implications of the proposal for future developments in the impact area including constraints on surrounding land uses should be described.

Indicate the range of measures to be taken to minimise the described impacts on surrounding land uses that will arise as a result of the project.

Include the extent of the project’s impacts on, and implications for, the Numinbah State Forest.

3.1.2.3 Land Disturbance – Rehabilitation and Decommissioning of Construction Works

The EIS should describe:

The means of decommissioning the Project, in terms of the removal of plant, equipment, structures and buildings, including interim transport sites created to transport source materials, concrete footings and foundations, hardstand areas, storage tanks (including any potential for reuse of these facilities), and material source extraction site(s), including any required removal of processing plant and infrastructure.

A preferred rehabilitation strategy for all environmental values disturbed by the Project, developed with a view to minimising the amount of land disturbed at any one time, should be included in the project’s construction EMP. Section 3.5.2 contains further requirements to be included in the rehabilitation strategy.

The final topography of the Project site and material extraction site(s) should be described in relation to the identified local, regional and state conservation/biodiversity values of the site and should be shown on plans at a suitable scale.

Options and methods for the disposal of wastes from the demolition of plant and buildings, in sufficient detail for their feasibility and suitability to be established, should be described.

3.1.2.4 Soil Erosion

Potential Impacts and Mitigation Measures For all permanent and temporary landforms in the project area, erosion management techniques should be described. For each soil type identified, erosion potential (wind and water) and erosion management techniques should be outlined. Methods proposed to prevent or control erosion should be specified and should be developed to prevent soil loss in order to maintain land condition, and to prevent significant degradation of local waterways and in particular, Lake Advancetown, by suspended solids. Soil erosion factors should be addressed via reference and in accordance with measures detailed in Soil Erosion and Sediment Control Engineering Guidelines for Queensland Construction Sites (1996) or similar publications.

Methods proposed to prevent or control erosion should be specified and should be developed with regard to (a) preventing soil loss in order to maintain land

Page 29: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

23 Hinze Dam Stage 3 Terms of Reference for an EIS

capability/suitability, and (b) preventing significant degradation of the water quality within Hinze Dam by suspended solids.

A detailed erosion and sediment control plan should be included in the construction and operational Environmental Management Plan.

3.1.2.5 Acid Sulphate Soils

Potential Impacts and Mitigation Measures The potential for acid generation by disturbance of acid sulphate soils during earthworks and construction should be indicated and measures for management of soils and mitigation of impacts should be:

Proposed for all site earthworks and construction activities.

Where required, management measures should be outlined in an Acid Sulphate Soils Management Plan prepared in accordance with QASSIT Guidelines and the requirements of SPP 2/02 in consultation with officers of NRW and EPA.

3.1.2.6 Contaminated Land

Potential Impacts and Mitigation Measures The EIS should describe the possible contamination of land from aspects of the proposals including waste, reject product, acid generation from exposed sulphidic material and spills at chemical and fuel storage areas.

The means of preventing land contamination (within the meaning of the Queensland Environmental Protection Act 1994) should be addressed. Methods proposed for preventing, recording, containing and remediating any contaminated land should be outlined.

Intentions should be stated concerning the classification (in terms of the Queensland Contaminated Land Register) of land contamination on the land, processing plant site and product storage areas after proposal completion.

If the results of the preliminary site investigation indicate potential or actual contamination, a detailed site investigation progressively managed in accordance with the stages outlined in Appendix 5 of the Draft Guidelines for the Assessment and Management of Contaminated Land in Queensland should be undertaken.

3.1.2.7 Landscape and Visual Amenity

Potential Impacts and Mitigation Measures

Describe the potential impacts of the project landscape character of the site and the surrounding area. Particular mention should be made of any changes to the broad-scale topography and vegetation character of the area.

This section should analyse and briefly discuss the visual impact of the proposal on particular panoramas and outlooks. It should be written in terms of the extent and significance of the changed skyline as viewed from places of residence, work, and recreation, from road, cycle and walkways, from the air and other known vantage points.

Detail should be provided of all management options and measures to be implemented and how these will avoid or mitigate the identified impacts.

Page 30: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

24 Hinze Dam Stage 3 Terms of Reference for an EIS

3.2 Climate This section should describe the rainfall patterns (including magnitude and seasonal variability of rainfall) within the region of the proposal. The vulnerability of the area to natural hazards such as floods should also be addressed with particular reference to water management at the proposal site. Reference must be made to any studies undertaken in relation to flooding vulnerability and discussed in more detail in the subsequent section 3.3.2.2. The relative frequency, magnitude and risk of these events should be considered.

3.3 Water Resources

3.3.1 Description of Environmental Values

3.3.1.1 Surface Water and Waterways A description should be given of the surface watercourses and their quality and quantity within the Nerang River catchment. Details provided should include a description of existing and projected surface drainage patterns, flows in major streams (including downstream of the spillway) and wetlands.

Also provide details of the likelihood of flooding, history of flooding including extent, levels and frequency, and a description of present and potential water uses downstream of the areas affected by the proposal. Flood studies should include a range of annual exceedance probabilities for affected waterways, where data permits.

An assessment is required of existing water quality in the impoundment and waterways and wetlands likely to be affected by the proposal. The basis for this assessment should be a monitoring program, with sampling stations located upstream and downstream of the proposal. Complementary stream-flow data should also be obtained from historical records (if available) to aid in interpretation.

The water quality should be described, including records of blue-green algal blooms, seasonal or other variations or variations with flow where applicable. A relevant range of physical, chemical and biological parameters should be measured to gauge the environmental harm on any affected creek or wetland system.

A description of the environmental values of the surface waterways of the affected area (upstream, within and downstream of the dam) should be provided in terms of:

values identified in the Environmental Protection (Water) Policy 1997 and ANZECC 2000;

sustainability, including both quality and quantity;

physical integrity, fluvial processes and morphology of watercourses, including riparian zone vegetation and form;

any Water Resource Plans (including reference to Environmental Flow Objectives outlined in the Water Resource (Gold Coast) Plan 2006), land and water management plans relevant to the affected catchment;

passage opportunities for fish upstream and downstream of the impoundment;

fish habitat;

recreational and commercial fisheries;

any estuarine/marine features in the region that may be affected by the change in the flow regime. For example, sediment supply to the coast, extent and significance of estuarine areas, etc.;

Page 31: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

25 Hinze Dam Stage 3 Terms of Reference for an EIS

environmental values and Water Quality Objectives for the Nerang River upstream and downstream of the dam; and

any values that may be affected by the influx of recycled water.

3.3.1.2 Groundwater

Description of Environmental Values The EIS should review the quality, quantity and significance of groundwater in the proposal area. The possible significance of the Project to groundwater depletion or recharge should be identified.

The review should include a survey of existing groundwater supply facilities (bores, wells, or excavations) within the groundwater area impacted by the Project.

3.3.2 Potential Impacts and Mitigation MeasuresThis section is to assess potential impacts on water resource environmental values identified in the previous section. It will also define and describe the objectives and practical measures for protecting or enhancing water resource environmental values, to describe how nominated quantitative standards and indicators may be achieved, and how the achievement of the objectives will be monitored, audited and managed.

Key water management strategy objectives include:

maintenance of quantity and quality of surface waters to protect existing authorised downstream users and the environment, including compliance with the Water Resource (Gold Coast) Plan 2006 (including maintenance of in-stream biota and the littoral zone); and

minimisation of impacts on flooding levels and frequencies both upstream and downstream of the project.

3.3.2.1 Waterways and Water Quality

Potential Impacts and Mitigation Measures The potential impact of the Project on the water quality of the dam and local/downstream waterways including estuarine waters should be indicated.

Water quality characteristics listed should be those appropriate to the downstream and upstream water uses that may be affected. The Australian and New Zealand Environment an Conservation Council (ANZECC, 2000) National Water Quality Management Strategy, Australian Water Quality Guidelines for Fresh and Marine Waters and the Environmental Protection (Water) Policy 1997 should be used as a reference for evaluating the effects of various levels of contamination.

The potential impacts on water quality within the dam for potable supply as a result of construction activities needs to be addressed and mitigation measures proposed.

The use of a monitoring program to assess the effectiveness of management strategies for protecting water quality during the construction, operation and, if applicable, decommissioning of any temporary structures should be indicated.

The potential environmental harm to the flow and the quality of surface waters, in particular the biota and fisheries of the current impoundment during the construction phase of the Project should be discussed, with particular reference to their suitability for the current and potential downstream uses, including the requirements of any affected riparian area, wetland,

Page 32: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

26 Hinze Dam Stage 3 Terms of Reference for an EIS

estuary, littoral zone, and any marine and in-stream biological uses. The impacts of surface water flow on existing infrastructure should be considered. Refer to the Environmental Protection (Water) Policy 1997 and Water Act 2000.

The environmental flow regime downstream of the dam wall should be reviewed in detail to outline the project’s impacts on reduced flooding and the possible reduction of water quality in the Nerang River. This should occur in the context of the Water Resource Plan (Gold Coast) 2006. proposed methods for ongoing monitoring downstream of the raised dam wall to ensure that environmental flow objectives are appropriate and are maintaining or improving aquatic ecosystem health in the Nerang River should be indicated.

The impacts of storm events on the capacity of waste containment systems (e.g. site bunding/stormwater management) should be addressed with regard to contamination of waterways and with regard to the design of waste containment systems proposed to be utilised by the project.

3.3.2.2 Hydrology and Flooding

Description of Environmental Values Description of the historical and current flow regime including seasonal flow patterns, flood peaks, flow volumes and flow duration at the site and downstream of the site.

Details of current or proposed flow management schemes for the waterways.

Potential Impacts and Mitigation Measures The hydrological impacts of the proposal should be assessed, particularly with regard to scouring and erosion.

Flooding extent, exceedances probabilities and areas inundated both upstream and downstream of the project after the dam is modified at various event frequencies should be indicated. Changes to flooding levels and frequencies should be assessed. When flooding levels will be affected, modelling of headwaters upstream of the dam and incremental effects of the dam on downstream flooding should be provided and illustrated with maps. Flooding studies should be undertaken over an appropriate range of rainfall events.

Describe potential changes in flow patterns at the site and downstream of the site including changes in frequency, volumes and duration and changes in flows reaching estuarine waters. These should be compared with current and pre-regulation flows in the system at a meaningful scale.

Comparisons of flood levels or inundation maps between the existing and upgraded structure for similar sized rainfall events should also be indicated.

Assessment of impacts on the flow and the quality of surface waters and effects on ecosystems should include an assessment of the likely effects on mangrove and other estuarine habitats as a result of changes in flooding regimes. It should also include changes in fish passage opportunities across barriers downstream of the proposed works.

Evaluate the impacts of potential water for fishway operational requirements, on the yield of the proposed storage and its viability, and the cost of construction, monitoring, operation and maintenance of a fishway.

Page 33: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

27 Hinze Dam Stage 3 Terms of Reference for an EIS

3.3.2.3 Groundwater

Potential Impacts and Mitigation Measures The EIS should include an assessment of the potential environmental harm caused by the Project to local groundwater resources, particularly with reference to vegetation clearing, sedimentation and salinity. An assessment of the potential to contaminate groundwater resources and measures to prevent, mitigate and remediate such contamination should be identified.

3.4 Potential Impacts on Matters of National Environmental Significance As discussed, this project is a controlled action under the Commonwealth’s Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act). In this regard, the Commonwealth has accredited the State’s EIS process for the purposes of the Commonwealth’s assessment under Part 8 of the EPBC Act.

When a State EIS process has been accredited, it is necessary for the terms of reference to address potential impacts on the matters of National Environmental Significance (NES) that have been identified in the ‘controlling provisions’ when the project was declared a controlled action. In this case the NES matters are as follows:

Sections 18 and 18A (Listed threatened species and communities).

Care must be taken to identify only the potential impacts from the project itself are described, to the extent that the raising of the dam wall, consequent increased potential impoundment, and altered downstream flooding regime have the potential to affect matters of NES.

The matters of NES to be specifically addressed under the requirements of the EPBC Act are the project’s impacts and mitigation measures relating to, but not limited to, the following species:

BirdsLathamus discolor Swift ParrotRostratula australis Australian Painted Snipe Xanthomyza phrygia Regent Honeyeater

FrogsMixophyes fleayi Fleay's FrogMixophyes iteratus Southern Barred Frog, Giant Barred Frog

MammalsDasyurus maculatus maculatus (SE mainland population)Spot-tailed Quoll, Spotted-tail Quoll, Tiger Quoll (south-eastern mainland population) Petrogale penicillata Brush-tailed Rock-wallaby

Page 34: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

28 Hinze Dam Stage 3 Terms of Reference for an EIS

ReptilesCoeranoscincus reticulatus Three-toed Snake-tooth Skink

PlantsArthraxon hispidus Hairy-joint GrassDiploglottis campbellii Small-leaved Tamarind Endiandra floydii Floyd's WalnutEndiandra hayesii Rusty Rose Walnut, Velvet LaurelFloydia praealta Ball Nut, Possum Nut, Big Nut, BeefwoodHicksbeachia pinnatifolia Monkey Nut, Bopple Nut, Red Bopple, Red Bopple Nut, Red Nut, Beef Nut, Red Apple Nut, Red Boppel Nut, Ivory Silky Oak Macadamia integrifolia Macadamia Nut, Queensland Nut, Smooth-shelled Macadamia, Bush Nut, Nut Oak Owenia cepiodora Onionwood, Bog Onion, Onion CedarPlectranthus nitidus Syzygium hodgkinsoniae Smooth-bark Rose Apple, Red Lilly Pilly Westringia rupicola

A stand-alone report addressing the matters of NES should be provided as an appendix to the EIS (see Appendix 8.3) that exclusively and fully addresses the issues relevant to the controlling provisions. This stand alone section should include the following:

A Description of the Affected Environment Relevant to the Matters Protected It is important that the current status of the matters protected under the EPBC Act be described in sufficient detail, to inform the analysis of the Project’s impact on these matters.

For listed threatened species, the description of the environment should include:

the species’ current distribution;

relevant information about the ecology of the species (habitat, feeding and breeding behaviour etc);

information about any populations of the species or habitat for the species in the area affected by the proposed action;

current pressures on the species, especially those in the area to be affected by the proposal; and

relevant controls or planning regimes already in place.

Page 35: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

29 Hinze Dam Stage 3 Terms of Reference for an EIS

Assessment of Relevant Impacts and Mitigation Measures In this section, the impacts and potential impacts on the matters protected should be described, and the possible mitigation measures for each impact need to be analysed. If alternative ways of taking the action have been identified, the relative impacts of these alternatives should also be considered.

When effective mitigation measures are not available, the discussion should be broadened to include compensatory measures to offset unavoidable impacts.

The identification of impacts to the matters protected should address all relevant impacts, and provide sufficient justification for all conclusions reached on specific impacts.

In some cases impacts may be relevant to more than one matter protected. For example when the species is listed as both a migratory and threatened species under the EPBC Act. In such cases the impacts may be addressed together, clearly stating the relevance of the impact to the different matters protected.

Potential Significant Impacts on Matters of National Environmental Significance (NES) The following potential impacts may need to be addressed in the EIS. The impacts are provided as a guide for specific matters of NES. Not all of these headings will apply to all proposals.

Impact on a listed threatened species Potential impacts vary depending on whether the species is extinct in the wild, endangered or vulnerable but are generally as follows:

lead to long term decrease in the size of a population;

reduce the area of occupancy of the species;

fragment an existing population into two or more populations;

adversely affect habitat critical to the survival of the species;

disrupt the breeding cycle of a population;

modify, destroy, remove, isolate or decrease the availability or quality of habitat to the extent that the species is likely to decline;

result in invasive species that are harmful to the species becoming established;

introduce disease that may cause the species to decline;

interfere with the recovery of the species or ecological community; or

consistent with any recovery plan.

3.5 Terrestrial Flora This section should detail the existing terrestrial flora and vegetation values of the Project area in terms of:

integrity of ecological processes, including habitats of rare and threatened species;

biological diversity, including habitats of rare and threatened species;

integrity of landscapes and places including wilderness and similar natural places;

threatened terrestrial ecosystems;

Page 36: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

30 Hinze Dam Stage 3 Terms of Reference for an EIS

the existence of important local and regional weed species should also be identified. The EIS should identify any actions of the Project which would require an authority or be assessable development for the purposes of the Nature Conservation Act 1992 and Vegetation Management Act 1999.

The flora communities should be described, in particular those that are rare or threatened, in environmentally sensitive localities, including riparian zones, littoral zones, rainforest remnants, old growth indigenous forests and wilderness areas. The description should include species lists.

Reference should be made to both State and Commonwealth legislation and policies on threatened species and ecological communities, Ramsar wetlands and World Heritage areas.

All surveys undertaken should be in accordance with best practice advice from the EPA and should include consideration of seasonality, potential for occurrence of significant species, rarity of species and the sensitivity of the species to disturbance.

This section should also identify all likely direct environmental harm on flora and vegetation communities.

3.5.1 Description of Environmental ValuesThe terrestrial vegetation communities within the Project area should be described at an appropriate scale (i.e. 1:10,000) with mapping produced from aerial photographs and ground-truthing, showing the following:

Location and extent of vegetation types using the EPA’s regional ecosystem type descriptions in accordance with the Regional Ecosystem Description Database (REDD) available at the EPA website.

Location of species listed as Protected Plants under the Nature Conservation (Wildlife) Regulation 1994 and subsequent amendments.

Sensitive or important vegetation types should be highlighted and their value as habitat for fauna and conservation of specific rare floral and faunal assemblages or community types identified.

Details of any riparian and rainforest vegetation, and their value for fauna habitat (including aquatic communities), and conservation of specific rare floral and faunal assemblages or community types, from both a local and regional perspective, should be provided. This should include extent and width of riparian vegetation. Any special landscape values of any natural vegetation communities should be described.

Conduct targeted surveys for legislatively or otherwise significant flora species listed under State and Commonwealth legislation within areas to be permanently and periodically inundated. Flora surveys should be undertaken within each defined vegetation community to be affected by the project and methodology should be discussed with the EPA, the following should be used as a guide:

site data should be recorded in a form compatible with the Queensland Herbarium CORVEG database. Vegetation mapping and data should be submitted to the Queensland Herbarium to assist the updating of the CORVEG database;

information should be recorded for community structure, assemblage and diversity;

a complete list of plant species present at each site should be recorded;

the relative abundance of plant species present should be recorded;

Page 37: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

31 Hinze Dam Stage 3 Terms of Reference for an EIS

any plant species of conservation, cultural, commercial or recreational significance should be identified; and

specimens of species listed as protected plants under the Nature Conservation (Wildlife) Regulation 1994, other than common species, are to be submitted to the Queensland Herbarium for identification and entry into the HERBRECS database.

Methodologies used for flora surveys should be specified in an appendix to the EIS. Any existing information should be revised and comments provided on whether the areas are degraded, cleared or affected in ways that would affect their environmental value.

The occurrence of pest plants (weeds), particularly declared plants under the Land Protection (Land and Stock Route Management) Act 2002 should be shown on a map at an appropriate scale.

3.5.2 Potential Impacts and Mitigation MeasuresThis section should identify all foreseen direct effects on terrestrial flora and the potential level of environmental impact identified. Action plans for protecting rare or threatened species and vegetation types identified as having high conservation value should be described, and any obligations imposed by State or Commonwealth biodiversity protection legislation or policy should be indicated.

With regard to the Project area this section should include:

Identify necessary permits/authorities required by the Project including clearing permits under the Vegetation Management Act 1999.

Development of mitigation plans to address anticipated impacts arising from land clearing and temporary inundation should be outlined. This can include identification of suitable areas for offsets (in consultation with GCCC and NRW if required by relevant legislation and policy) to compensate vegetation loss. A description of offsets or principles of selection, securing and retaining of offsets should be indicated.

Plans to support and allow for the maintenance or enhancement of habitat and corridor functions in the area should also be outlined.

Where required, outline rehabilitation strategies for any compensatory habitat areas and provisions for protecting such areas. As indicated in section 3.1.2.3, a rehabilitation management strategy is to be included in the construction EMP.

Within the strategy, describe the methods to ensure rapid rehabilitation of disturbed areas following construction including the species chosen for revegetation which should be consistent with the surrounding associations. Include details of any post construction monitoring programs and what benchmarks will be used for review of monitoring.

Identify the ability of identified stands of vegetation to withstand any increased pressure resulting from the Project. In relation to periodic inundation events the EIS should briefly discuss the likelihood of long-term impacts, such as dieback occurring.

The future use (such as erosion control or habitat) or method of disposal of cleared vegetation should be detailed.

Inclusion of a weed management plan in the EMP is advised. The weed management plan should be developed in consultation with local government environmental officers, to cover construction, rehabilitation and operation periods.

Page 38: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

32 Hinze Dam Stage 3 Terms of Reference for an EIS

Describe methods of minimising the potential for the introduction and/or spread of weeds, including:

– Identification of the origin of construction materials, machinery and equipment. – The need for vehicle and machinery washdown and any other hygiene protocols. – Staff/operator education programs.

3.6 Terrestrial Fauna The terrestrial and riparian fauna occurring in the areas affected by the Project should be described, noting the broad distribution patterns in relation to vegetation, topography and substrate. Wildlife corridors and habitat along the proposed route should be identified and mapped.

Detail should be provided on the existing nature conservation values of the Project area in terms of:

integrity of ecological processes, including habitats of rare and threatened species; and

biological diversity, including habitats of rare and threatened species.

The EIS should identify any actions of the Project that require an authority under the NatureConservation Act 1992. The description should indicate and map any areas of state or regional significance identified in an approved Biodiversity Planning Assessment (BPA) produced by the EPA and any areas of local significance identified in the GCCC’s LNCS.

Reference to policies on threatened species and ecological communities including any species protected under bilateral agreements between Australia and Japan (JAMBA) and between Australia and China (CAMBA) should also be included.

As with terrestrial flora, all surveys undertaken should be in accordance with best practice advice from the EPA and should include consideration of seasonality, potential for occurrence of significant species, rarity of species and the sensitivity of the species to disturbance.

This section should also discuss all likely direct environmental harm on fauna communities in terrestrial environments in sensitive areas in the project area.

3.6.1 Description of Environmental ValuesThe terrestrial, and riparian fauna occurring in the areas affected by the proposal should be described, noting the broad distribution patterns in relation to vegetation, topography and substrate. The description of the fauna present or likely to be present in the inundation area should include:

species diversity (i.e. a species list) and abundance of animals, including amphibians, birds, reptiles, mammals and bats;

any species that are poorly known but suspected of being rare or threatened;

habitat requirements and sensitivity to changes; including movement corridors and barriers to movement;

the existence of feral or exotic animals;

existence of any rare, threatened or otherwise noteworthy species/communities in the study area, including identification of range, habitat, breeding, recruitment, feeding and

Page 39: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

33 Hinze Dam Stage 3 Terms of Reference for an EIS

movement requirements, and current level of protection (e.g. any requirements of protected area management plans);

use of the area by avian and terrestrial fauna;

identify Glossy Black Cockatoo feeding tree locations, and provide measures to retain these trees where possible;

habitat for priority or endangered, vulnerable or rare taxa as identified by the EPA’s Biodiversity Planning Assessments;

essential habitat for endangered, vulnerable or rare fauna as identified in the Department of Natural Resources and Water’s regional ecosystem maps.

Surveys should be conducted at the appropriate time of day and year when the species are known to be present on the site, so that identification and location of these species is optimal.

The EIS should indicate how well any affected populations are represented and protected elsewhere in the subregion where the Project occurs.

Site data should be recorded in a format compatible with EPA WildNet databases.

3.6.2 Potential Impacts and Mitigation MeasuresThis section should identify all foreseen direct effects on terrestrial fauna including any obligations imposed by the State. Strategies for protecting rare or threatened species should be described, and any obligations imposed by State or Commonwealth endangered species legislation or policy should be outlined.

Impacts during construction and operation of the Project should be assessed. Short term and long term durations should be considered. Measures to mitigate the impact on habitat or the inhibition of normal movement, propagation or feeding patterns, and change to food chains should be described. Any provision for buffer zones and movement corridors should be indicated.

Identify any impact the proposal may have on terrestrial fauna, relevant wildlife habitat and other fauna conservation values.

Identify suitable areas for compensatory habitat (in consultation with Gold Coast City Council, EPA and NRW) that will maintain/enhance wildlife habitat and bioregional and local corridor functions in the area.

Development of mitigation strategies to provide information on the following should be investigated:

– Construction activities that will minimise fauna, including reptiles, becoming trapped or harmed,

– use of cleared vegetation for ground-level habitat; – provision of fauna spotter during clearing activities; – detail of measures proposed to minimise wildlife capture and mortality during

construction; and if accidental injuries should occur the methodologies to assess and handle injuries;

– fauna management actions for quarry sites; and – removal/retention of identified nesting trees/locations and provision of nest hollows.

Page 40: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

34 Hinze Dam Stage 3 Terms of Reference for an EIS

Details of the proposed fauna management and mitigation strategies discussed above should be included in the EMP.

The method of minimising the introduction/ongoing management of feral animals, and other exotic fauna should be described.

3.7 Aquatic Biology

3.7.1 Description of Environmental Values This section should outline aquatic values affected by the proposal, noting the patterns and distribution in the dam impoundment, waterways and downstream associated freshwater andestuarine environments. The description of the aquatic fauna and flora present or likely to be present in the area should include:

fish species, mammals, reptiles, amphibians, crustaceans and aquatic invertebrates occurring in the waterways within the affected area, and downstream estuarine environment;

any rare or threatened marine species in downstream environments;

a description of fish habitat at representative sites upstream of the proposed impoundment, within the impounded area and downstream as far as the effect of the dam/weir will extend. This should include features such as distribution of pool and riffle formations: presence of snags; presence of overhanging vegetation; presence of aquatic macrophytes; sediment type; river profile (bank width and depth); presence of sand and gravel bars; and water quality.

a description of fish and crustacean species (recreational, commercial and other) at representative sites upstream of the proposed impoundment, within the impounded area and downstream as far as the effect of the dam/weir will extend. This should include distribution, diversity, some population descriptors (eg. size classes / length frequency) and relative abundance. Historical information (eg. former distribution, diversities etc.should be included where available. Comparison between the main Nerang River and a control (tributary) fish community may be valid.

discussion of fish habitat requirements and usage at the site and up and downstream of the site, including life cycle, seasonal or flow related variations in those requirements

fish movement requirements through the site (upstream and downstream) need to be determined. Flow, seasonal and temperature related movement should be identified.

a description of recreational and commercial fisheries at the site and up and downstream of the site including impoundment, riverine, estuarine and near coastal fisheries

aquatic invertebrates occurring in the waterways within the Project area;

identification of the sensitivity of fish habitats to disturbance, including potential disturbances and changes resulting from the proposed works, e.g. changes in water quality (including in regard to changes in water level and flow regimes);

aquatic plants;

aquatic and benthic substrate;

habitat downstream of the project or potentially impacted due to changes in flooding regimes on associated lacustrine and marine environments; and

identification of any critical migration/breeding requirements for native aquatic species.

Page 41: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

35 Hinze Dam Stage 3 Terms of Reference for an EIS

Discuss the requirement or otherwise for a fishway to be constructed as part of the project and the process for determining with DPI&F if a Waterway Barrier Works Approval is required.

Discussions with DPI&F on the appropriate methodology for aquatic studies to determine the requirement for a fish way should occur prior to aquatic surveys being completed.

3.7.2 Potential Impacts and Mitigation MeasuresDetail strategies for protecting the Moreton Bay Marine Park and Ramsar Wetland as a result of changes in downstream flooding regimes.

Any rare or threatened species should be described, and any obligations imposed by State or Commonwealth legislation or policy or international treaty obligations (i.e. JAMBA, CAMBA) should be outlined. Emphasis should be given to potential environmental harm to downstream benthic and intertidal communities, seagrass beds and mangroves.

Determine the potential impacts of the proposal on fish habitat at the site and up and downstream of the site as far as the effect of the dam will extend, including impacts on features such as: riparian vegetation; aquatic flora; distribution of pool and riffle environments; water quality; estuarine and near coastal fish habitat (including mangrove, and seagrass communities etc); instream and bank (freshwater and estuarine) profiles; floodplain habitat (such as wetlands, waterbodies) etc.

Determine the potential for the introduction of or facilitation of exotic, non-indigenous and noxious plants or exotic or non-indigenous or noxious aquatic fauna (including fish and crustaceans) through the construction and operation of the proposed structure.

Determine the potential impacts of the proposal on aquatic faunal communities (including fish) at the site and up and downstream of the site as far as the effect of the dam will extend (including estuarine and near coastal aquatic communities). These should include: downstream passage opportunities across the dam and passage opportunities along the Nerang River to the base of the dam.

Indicate effects of changes to flow regime downstream, including the effect of changes in water quality, salinity, habitat structure and flora.

Determine effects of increased level in the impoundment and projected variations in the level of the impoundment on aquatic fauna, particularly in creeks flowing into the impoundment.

Discussion of the sensitivity of fish habitat at the site and up and downstream of the site to disturbance, including potential disturbances and changes resulting from the proposed works (e.g. in water quality, flow regimes, water levels, proposed land use).

Determine the potential impacts on commercial and recreational fisheries, addressing issues such as access, changes to stocks (species, population numbers and structure, recruitment to fishery), and any potential for fish kills and mitigation strategies. Consultation with relevant local groups such as the Hinze Dam Fish Management Advisory Committee should be undertaken.

Page 42: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

36 Hinze Dam Stage 3 Terms of Reference for an EIS

3.8 Cultural Heritage

3.8.1 Description of Environmental Values This section should describe the existing cultural heritage values that may be affected by the Project activities. Acknowledgement that a Cultural Heritage Management Plan (CHMP) will be developed by the project should be indicated.

A cultural heritage study will be required and will describe indigenous and non-indigenous cultural heritage sites and places, and their values. The study must be conducted by an appropriately qualified cultural heritage practitioner and must include the following:

liaison with the Aboriginal party/ies for the area concerning:

– places of significance to that community (including archaeological sites, natural sites, story sites etc;

– appropriate community involvement in field surveys; any requirements by the Aboriginal party/ies relating to confidentiality of site data must be highlighted. Non-indigenous communities may also have relevant information;

a a comprehensive cultural heritage survey or study of the area involving the Aboriginal party/ies for the area;

significant assessment by the Aboriginal party/ies of any cultural heritage sites/places located;

the impact of the proposed development on cultural heritage values;

a report of work done which includes background research, relevant environmental data and methodology, as well as results of field surveys, significance assessment and recommendations; and

the involvement of the Aboriginal party/ies is required under the Aboriginal Cultural Heritage Act 2003 when undertaking the cultural heritage survey/study in order to meet the cultural heritage duty of care

3.8.2 Potential Impacts and Mitigation MeasuresThis section defines and describes the objectives and practical measures for protecting or enhancing cultural heritage environmental values, describes how nominated quantitative standards and indicators may be achieved for cultural heritage management, and how the achievement of the objectives will be monitored, audited and managed.

3.8.2.1 Cultural Heritage Management Plan (Part 7, Aboriginal Cultural Heritage Act 2003)

It is a requirement of the project that a Cultural Heritage Management Plan (CHMP) be developed and approved under Part 7 of the Aboriginal Cultural Heritage Act 2003 which sets out the way in which harm to Aboriginal cultural heritage will be avoided or to the extent it cannot be avoided will be minimised.

The environmental harm to cultural heritage values in the vicinity of the project should be managed under a CHMP developed specifically for the project. The CHMP will provide a process for the management of cultural heritage places both identified and sub-surface at the project sites. It is usual practice for the CHMP to be based on information contained in archaeological reports. The CHMP should address and include the following:

a process for including the Aboriginal party for the area in the assessment, protection and management of their cultural heritage;

Page 43: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

37 Hinze Dam Stage 3 Terms of Reference for an EIS

processes for mitigation, management and protection of identified cultural heritage places and material in the Project area, including associated infrastructure developments;

cultural awareness training or programs for project staff;

a conflict resolution process; and

any other matters agreed with the Aboriginal party for the area. The development of the CHMP must be negotiated directly with the Aboriginal party for the area. The Department of Natural Resources and Water can provide further advice on this process and gazetted CHMP guidelines.

The EIS should note that cultural heritage artefacts removed from the area are the property of the Aboriginal party for the area.

3.9 Air Environment

3.9.1 Description of Environmental ValuesThis section should describe the existing air environment, which may be affected by the proposal in the context of environmental values as defined by the Environmental Protection Act 1994 and Environmental Protection (Air) Policy. It should also describe air quality goals contained in the National Environment Protection Measure (NEPM) Ambient Air Quality 1998.

Ambient air quality conditions in terms of particulate matter should be described for any sensitive sites (residences) in proximity to the dam and associated infrastructure development areas, including any baseline monitoring results.

3.9.2 Potential Impacts and Mitigation MeasuresThe following air quality issues should be considered:

Impacts of dust generation from construction activities, especially from blasting activities associated with quarries and in close proximity to residences;

Identification of climatic patterns that could affect dust generation and movement;

Predicted changes to existing air quality at sensitive receptors and dust generation during construction;

List potential are quality impacts from vehicle emissions and any other sources; and

Propose any amelioration or mitigation measures for each identified impact relating to dust generation, vehicle and equipment emissions and gaseous emissions.

3.10 Greenhouse Gas Impacts This section of the EIS should:

provide an inventory of projected annual emissions during construction for each relevant greenhouse gas, with total emissions expressed in ‘CO2 equivalent’ terms;

briefly describe method(s) by which estimates were made.

The Australian Greenhouse Office Factors and Methods Workbook (available via the internet) can be used as a reference source for emission estimates and supplemented by other sources where practicable and appropriate.

Page 44: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

38 Hinze Dam Stage 3 Terms of Reference for an EIS

An assessment of the type and volume of greenhouse gases emitted by the Project during construction and operation and the measures taken to reduce emissions in line with national and state abatement policies and guidelines should be provided.

3.11 Climate Change Adaptation Climate change, through alterations to weather patterns and rising sea level, has the potential to impact in the future on developments designed now. Most developments involve the transfer to, or use by, a proponent of a community resource in one form or another, such as the granting of a non-renewable resource or the approval to discharge pollutants to air, water or land.

Therefore, it is important that the project design be adaptive to climate change so that community resources are not depreciated by projects that would be abandoned or require costly modification before their potential to provide a full return to the community is realised.

Consequently, the EIS should provide an assessment of the project’s vulnerabilities to climate change and describe possible adaptation strategies for the activity including:

a risk assessment of how changing patterns of rainfall and hydrology, temperature and extreme weather may affect the viability and environmental management of the project;

the impacts of storm events and climate change on the capacity of waste containment systems (e.g. site bunding/stormwater management) should be addressed with regard to contamination of waterways and with regard to the design of waste containment systems proposed to be utilised by the project;

preferred and alternative adaptation strategies to be implemented; and

commitments to undertaking, where practicable, a cooperative approach with government, other industry and other sectors to address adaptation to climate change.

It is recognised that predictions of climate change and its effects have inherent uncertainties, and that a balance must be found between the costs of preparing for climate change and the uncertainty of outcomes. However, proponents should use their best efforts to incorporate adaptation to climate change in their EIS and project design.

3.12 Noise and Vibration

3.12.1 Description of Environmental ValuesThis section describes the existing environment values that may be affected by noise and vibration from the proposal.

The identification of potential noise sources from the conduct of the project are to be identified. Project activities, especially in regards to quarry operation could adversely impact on noise and vibration at proximal sensitive receptors and baseline monitoring should be undertaken at a selection of sensitive sites potentially affected by the proposal. Noise sensitive places are defined in the Environmental Protection (Noise) Policy 1997. The locations of sensitive sites should be identified on a map at a suitable scale. The results of any baseline monitoring of noise and vibration in the proposed vicinity of the proposal should be described.

Comment should be provided on any current activities near the proposal area that may cause a background level of ground vibration (for example: major roads, quarrying activities, etc.).

Page 45: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

39 Hinze Dam Stage 3 Terms of Reference for an EIS

3.12.2 Potential Impacts and Mitigation Measures The potential environmental harm of noise at all potentially sensitive places, in particular any places of work or residence, should be quantified and compared with objectives, standards to be achieved and measurable indicators. This should also include environmental harm on terrestrial animals.

Proposals to minimise or eliminate these effects should be provided, including details of any screening, lining, enclosing or mounding of construction sites, or timing schedules for construction that would minimise environmental harm and environmental nuisance from noise and vibration.

Community consultation procedures to be employed to notify residents of blasting events should be detailed.

Assessment should be made of the potential emission of low-frequency noise (noise with components below 200Hz) from major construction equipment. If necessary, measures should be described for reducing the intensity of these components.

A discussion should be supplied on blasting which might cause ground vibration or fly rock on, or adjacent to, the site. The magnitude, duration and frequency of any vibration should be indicated.

Measures to prevent or minimise environmental nuisance and harm should be identified.

Assessment should be made of the potential impacts (including compliance with relevant legislation) of blasting required, including potential buffers to minimise or eliminate these effects. Blasting noise and vibration limits are provided in section 61 of the Environmental Protection Regulation 1998. Reference should also be made to the EPA Guideline: Noise and Vibration from Blasting.

3.13 Hazard, Risk and Safety

3.13.1 Hazard AnalysisThis section of the EIS should describe the potential hazards and risks that may be associated with the Project. A preliminary hazard analysis should be conducted for the Project.

The preliminary hazard analysis should incorporate possible hazards, accidents, and abnormal events that may arise for the Project, both during construction and in operation, including:

Vulnerability of the Project area to flooding, bushfire, and landslip.

Seismic stability of the Project area.

Identification of all hazardous substance to be used, stored, processed or produced and the rate of usage.

Accidental release of hazardous goods or other materials.

Security of equipment and materials stored at the project site and identification of ramifications for e.g. public safety should security be breached.

Explosions and fires associated with incidents arising from the Project activities.

Work injuries.

Page 46: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

40 Hinze Dam Stage 3 Terms of Reference for an EIS

The effects of predictable climatic extremes (droughts, floods) upon the structural integrity of the containing wall, causing Dam wall overfilling and failure.

An outline of the public liability of the Council and/or State for private infrastructure and visitors on public land.

Indication of cumulative risk levels to surrounding land uses.

Any potential incremental hazards that may arise from the project that accounts for the augmentation of an existing structure.

Possible frequency of potential hazards, accidents, spillages and abnormal events occurring during all stages of the Project should be indicated.

3.13.2 Risk AssessmentA preliminary risk assessment for all components of the Project (including, but not limited to, dam wall, quarries, clearing, downstream flooding) shall be undertaken as part of the EIS process in accordance with appropriate parts of ANCOLD and Queensland Dam Safety Regulator guidelines and AS/NZS Risk Management Standard 4360:1999. While it is anticipated that risk assessment will mainly be undertaken as part of the dam design process, where risk criteria/processes are not defined in recognised guidelines, a preliminary risk assessment may need to be included in the EIS.

Discussion of project delivery risk should be indicated, including failure to deliver the required outcome or for the project to deliver future supply requirements.

The EIS should deal comprehensively with on-site risks. External risks to the Project should also be considered. External risks from natural hazards could be determined on the basis of AS/NZS Risk Management Standard 4360:1999. The EIS should indicate that the project will comply with relevant risk assessment and management guidelines.

The study should assess risks during the construction, decommissioning of temporary construction works and operational phases associated with the Project. These risks should be assessed in quantitative terms where possible.

Analysis of the consequences of each of the events identified in Section 3.13.1 Hazard Analysis on safety and environmental damage in the Project area should be conducted, including:

Injuries, illness and death to workers and to the public.

Direct harm to the environment as a result of project hazards.

The analysis should examine the likelihood of these consequences being experienced, both individually and collectively. Quantitative levels of risks and risk contours should be presented from the above analysis.

Details should be provided on the safeguards that would be employed or installed to reduce the likelihood and severity of hazards, consequences and risks to persons, fauna and environmentally sensitive sites within and adjacent to the Project area. The information should include the reduced level of risk that would be experienced with these safeguards in place.

A comparison of assessed and mitigated risks with acceptable risk criteria for land uses adjacent to the Project area should be presented.

Page 47: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

41 Hinze Dam Stage 3 Terms of Reference for an EIS

3.14 Emergency Management Plan An outline of the proposed emergency management procedures is to be provided for the range of situations identified in the above risk assessment as providing measurable risks. An Emergency Management Plan is to be developed in consultation with the relevant emergency services and included in the Environmental Management Plan.

The following should be presented in the Plan:

contingency plans to deal with hydrocarbon (e.g. diesel, lubricating oils) oil spills during construction;

contingency plans to account for natural disasters such as storms, floods and fires during the construction, operation and maintenance phases;

plans for involvement of the relevant State agencies (such as the Queensland Ambulance Service) in relation to emergency medical response and transport;

plan to ensure access for emergency services vehicle/s to and into the site; and

first aid matters.

3.15 Waste Management Having regard for best practice waste management strategies, the Environmental Protection (Waste Management) Policy 2000 (EPP Waste) and the Environmental Protection (Waste Management) Regulation 2000 (EPR Waste), the proposals for waste avoidance, reuse, recycling, treatment and disposal should be described.

This section should discuss waste management strategies, including reduction, reuse, recycling, storage, transport and disposal of waste, including measures to minimise attraction of vermin, insects and pests.

This section should assess the potential impact of all wastes to be generated during construction and operation and provide details of each waste in terms of:

operational handling and fate of all wastes including storage;

on-site treatment methods proposed for the wastes;

methods of disposal (including the need to transport wastes off-site for disposal) proposed to be used for any trade wastes, liquid wastes and solid wastes;

the potential level of impact on environmental values;

measures to ensure stability of the waste storage areas and impoundments;

methods to prevent, seepage and contamination of groundwater from stockpiles and/or storage areas and impoundments; and

market demand for recyclable waste (where appropriate).

The EIS should address waste minimisation techniques and processes proposed and the market demand for recyclable waste (where appropriate).

Page 48: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

42 Hinze Dam Stage 3 Terms of Reference for an EIS

3.16 Transport and Roads

3.16.1 Transport Methods and RoutesThe EIS should describe the existing road network and intersections of the surrounding region specifying current traffic volumes, including, but not limited to, the Gold Coast-Springbrook, Nerang-Murwillumbah and Nerang-Beaudesert road networks.

The EIS should also describe and assess the stability and durability of existing bridges/culverts and embankments.

The EIS should discuss transport methods and routes for delivering construction and operational equipment and materials, other necessary goods and consumables and workforce transportation. Information should include:

The likely impacts and mitigation strategies of increased traffic on local and regional road networks (with appropriate directional distributions), with reference to:

– Traffic volume. – Vehicle size and types, including heavy vehicle access. – Usage rates. – Road safety issues, including safe access to construction sites and the potential

impacts of dust (e.g. consideration of the need for turning lanes, improved sight lines, waiting areas, off-road parking locations).

– Reduced efficiency of traffic flows or intersections along key routes, especially during construction.

– Additional wear/reduced life of pavements requiring additional or accelerated rehabilitation and maintenance if any.

– The proposed traffic management arrangements and plans, especially within rural residential areas and steps to be taken to prevent public access to construction access ways not provided on public roads.

– Site depot location and access. – Construction traffic on local road networks, daily movement patterns and emergency

access, especially in rural residential areas. – Methods to be adopted to avoid obstruction to other road users during construction.

The impacts of construction with regard to seasonal considerations such as potential for road impacts during wet weather.

Findings of studies and assessments should be incorporated into a road management strategy including Transport and Traffic Management Plans.

The EIS should detail any proposals to provide centralised staff transport to site and include the provision that relevant authorities such as the Queensland Police Service will be advised in advance and included in consultation on staff transit methods and procedures.

Reference should be made to any relationship between Project road works and works proposed in the current Road Implementation Program(s) of MR. Road infrastructure impacts should be described and assessed according to MR’s Guidelines for Assessment of Road Impacts of Development (2006). Reference should be made to other MR planning documents.

Page 49: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

43 Hinze Dam Stage 3 Terms of Reference for an EIS

The EIS should describe the existing public transport network, including school bus services, and discuss the likely impacts and mitigation strategies of increased traffic on the safe provision of school bus services in the project area.

An analysis of impacts on traffic, road networks and road users and suggested mitigation strategies if construction activities and quarrying needs to be undertaken offsite should be indicated.

3.16.2 Road Relocations: Potential Impacts and Mitigation MeasuresAssessment of impacts for the entire area impacted by the Project should identify the following:

The likely impacts and mitigation strategies of new roads or road realignments that are required as a result of the Project, including impacts on all stakeholders along the routes.

Within this section the following should be identified:

– Road realignment requirements, clearly indicated on maps with existing infrastructure and planned realignments indicated;

– Associated land requirements; – An assessment of the potential to isolate communities (such as Springbrook); – An assessment of the potential to disrupt community access to any health, education or

government services, and any relevant facilities such as shops, churches, clubs as a result of the realignments.

4. Socio-Economic Environment

4.1 Social values This section describes the existing social values that may be affected by the proposal.

Description of Environmental Values The social amenity and use of the proposal area for recreational, fishing, sporting, educational or residential purposes should be described. Consideration should be given to:

community infrastructure and services, access and mobility;

population and demographics of the affected community;

local community values, vitality and lifestyles;

recreational, cultural, leisure and sporting facilities and activities in relation to the affected area;

local businesses in relation to the affected area, including the kiosk and Cedar Lake Country Resort;

sports clubs, groups and community facilities in the area;

current property values; and

number of properties and owners directly affected by the project.

Page 50: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

44 Hinze Dam Stage 3 Terms of Reference for an EIS

Potential Impacts and Mitigation Measures The social impact assessment of the project should consider the information gathered in the community consultation program and the analysis of the existing socio-economic environment, and describe the project’s impact, both beneficial and adverse, on the local community. The impacts of the project on local residents, community services and recreational activities are to be analysed and briefly discussed. The nature and extent of the community consultation program are to be described and a summary of the results incorporated in the EIS.

The EIS should address the following matters:

Community

An assessment of impacts on local residents, current land uses and existing lifestyles and enterprises.

An assessment of the inundation of existing community and recreational facilities during construction and discussion on the relocation/re-establishment of recreational and sporting facilities and any community requirements identified during the community consultation process.

Workforce

The EIS should address impacts of both construction and operational workforces and associated contractors on housing demand, community services and community cohesion. The capability of the existing housing stock, including rental accommodation, to meet any additional demands created by the project is to be identified.

Flood Mitigation

An assessment of downstream flooding on residential, commercial and community facilities, and anticipated reduction in flooding potential and associated reduction in flood damage costs.

For the construction and operational phases of the development, describe the effects of the proposal on local residents, including flooding, land acquisition and road relocation issues and property valuation and marketability, community services and recreational activities.

For identified impacts to social values, suggest mitigation and enhancement strategies and facilitate initial negotiations towards acceptance of these strategies. Practical monitoring regimes should also be recommended.

Social, economic and cultural values are not as easily separated as physical and ecological values. Therefore it may be necessary for some material in this section to be cross-referenced within sections 3.8: Cultural Heritage, 4.2: Economy, and 3.13: Hazard, Risk and Safety.

4.2 Economy This section describes the existing economic environment that may be affected by the project.

The economic analysis component of the EIS should consider:

the significance of this Project on the local and regional economic context;

Page 51: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

45 Hinze Dam Stage 3 Terms of Reference for an EIS

the anticipated increased supply and reliability of water within the Gold Coast region and flow on effects;

the cost to all levels of government of any additional infrastructure provision;

an outline of the economic flows of the project expenditure on the regional and state economies;

any negative economic impact on affected local individuals or businesses from the construction of the project;

any negative economic impact on the project viability due to the cost of the long-term provision of fish passage. Where fish passage is a requirement, it will be for the life of the structure of the dam (as opposed to the commercial life of the dam); and

the use by the project of locally sourced goods and services as described in the Department of State Development Local Industry Policy.

4.3 Employment and training This section should provide details on the employment requirements and skills base of the required workforce for both the construction and operations phases of the project. The report should also describe the deployment strategies proposed for the workforce over the construction period.

Information should be provided on the accommodation requirements for the workforce, (if any), and if applicable, of their family members.

In particular, with regards to anticipated workforce impacts, the following should be addressed:

estimates should be provided of: a) construction workforce - i.e. the number of workers to be employed on-site during the

construction activities, including the number of sub-contractors and an outline of the recruitment schedule and policies for the recruitment of workers

b) operational phase workforce - i.e. the number of any additional workers to be employed on-site during operational activities.

If camp sites are to be used to accommodate the workforce, provide details on the number, location (shown on a map), proximity to the construction site and typical facilities for these sites. Information should include data relating to facilities for:

– Food preparation and storage; – ablution facilities; – vector and vermin control; – fire safety; – indoor air quality; and – dust and noise control in relation to proximity of camp site to the construction area.

If applicable, outline local government approvals required for establishment and operation of such camps.

On the matter of workforce training, the EIS should describe the project’s relation and use of strategies responding to Government Policy relating to:

Page 52: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

46 Hinze Dam Stage 3 Terms of Reference for an EIS

The level of training provided for construction contracts on Queensland Government building and construction contracts - The State Government Building and Construction Contracts Structured Training Policy (the 10% Policy).

Indigenous employment opportunities - Indigenous Employment Policy for Queensland Government Building and Civil Construction Projects (the 20% Policy).

5. Environmental Management Plan

An Environmental Management Plan (EMP) should be provided detailing the measures to be adopted to address identified impacts during the construction, operation and maintenance phases of the Project. The EMP should detail:

Environmental element – the environmental aspect requiring management consideration.

Potential impacts – potential impacts identified in the EIS.

Performance objective – the target or strategy to be achieved through management.

Management actions – the actions to be undertaken to achieve the performance objective, including any necessary approvals, applications and consultation.

Performance indicators – criteria against which the implementation of the actions and the level of achievement of the performance objectives will be measured.

Monitoring – process of measuring actual performances.

Responsibility – assign responsibility for carrying out each action to a relevant person/organisation.

Reporting – the process and responsibility for reporting monitoring results.

Corrective action – the action to be implemented in the case of non-compliance and the person/organisation responsible for action.

An EMP should commit to manage, enhance or protect identified environmental values. The commitments should contain the following components for performance criteria and implementation strategies:

Environmental protection objectives for enhancing or protecting each relevant value.

Indicators to be measured to demonstrate the extent to which the environmental protection objective is achieved.

Environmental protection standards (a numerical target or value for the indicator), which defines the achievement of the objective.

An action program to ensure the environmental protection commitments are achieved and implemented. This will include strategies in relation to: a. Continuous improvement; b. Environmental auditing; c. Monitoring; d. Reporting; e. Staff training; and

Page 53: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

47 Hinze Dam Stage 3 Terms of Reference for an EIS

f. A decommissioning program for land proposed to be disturbed under each relevant aspect of the proposal.

6. Conclusions and Recommendations

The EIS should make conclusions and recommendations with respect to the Project, based on the studies presented, the Environmental Management Plans and conformity of the proposal with ESD policy. This should include reference to proponent commitments for the management and operation of the project.

7. References

References should be presented in a consistent and recognised format.

8. Recommended Appendices

Items that should be located in the Appendices should include, but not be limited to, the following:

8.1 Final Terms of Reference for the EIS A copy of the final ToR should be included in the EIS. Where it is intended to bind appendices in a separate volume from the main body of the EIS, the ToR at least should be bound with the main body of the EIS for ease of cross-referencing. A summary, cross-referencing specific items of the ToR to the relevant section of the EIS, should also be provided in the EIS.

8.2 Statutory Permits and Development Approvals A list of all the approvals required by all phases of the project should be presented along with their corresponding regulating legislation and the approving authority.

8.3 Potential Impacts on Matters of National Environmental Significance The EIS should provide a stand-alone report that exclusively and fully addresses the issues relevant to the matters of national environmental significance (NES) that were identified in the ‘controlling provisions’ when the project was declared a controlled action under Part 3, Division 1 of the Environment Protection and Biodiversity Conservation Act 1999(Commonwealth).

The report should provide a:

description of proposed action (as it would impact on NES matters);

description of the Affected Environment Relevant to the Controlling Provisions (i.e. describe the features of the environment that are NES matters protected under the EPBC Act); and

assessment of Impacts on NES Matters and Mitigation Measures.

Page 54: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

48 Hinze Dam Stage 3 Terms of Reference for an EIS

8.4 Consultation Report A list of advisory agencies should be provided in a summary Consultation Report, which should also list the Commonwealth, State and Local government agencies consulted, and the individuals and groups of stakeholders consulted. A summary of the issues raised by these groups, and the means by which the issues have been addressed, should be provided in the text of the EIS.

The EIS should summarise the results of the community consultation program, providing a summary of the groups and individuals consulted, the issues raised, and the means by which the issues were addressed. The methodology used in the community consultation program, including criteria for identifying stakeholders and the communication methods used should also be indicated.

Information about identifying affected parties (as defined by the EPBC Act) and interested and/or affected persons (as defined by the EP Act) should be included.

8.5 Project Study Team Qualifications and Experience The qualifications and experience of the study team and specialist sub-consultants should be provided.

8.6 Research Reports and Specialist Studies Any projects for researching alternative environmental management strategies or for obtaining any further necessary information should be outlined in an appendix.

All reports generated on specialist studies undertaken as part of the EIS are to be included as appendices. These may include:

– geology; – soil survey and land suitability studies; – contaminated land register findings; – surface water hydrology and quality; – groundwater; – flora and fauna studies; – economic studies; and – hazard and risk studies.

8.7 List of Proponent Commitments Each section of the EIS is to conclude with a set of commitments made by the Proponent relevant to the section’s impacts and mitigation measures.

Additionally, a list of all commitments made by the Proponent in the EIS (in addition to the performance criteria stipulated in the EMP) should be provided along with a reference to the relevant section in the EIS, as an Appendix.

Page 55: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n

1 In

trod

uctio

n D

etai

l the

key

driv

ers

and

reas

on/s

for t

he E

IS, t

he a

udie

nce

who

will

be

revi

ewin

g th

e do

cum

ent,

the

appr

oval

pro

cess

and

legi

slat

ive

cont

ext,

and

stru

ctur

e of

the

docu

men

t. Se

ctio

n 1

1.1

Proj

ect P

ropo

nent

Des

crip

tion

of p

ropo

nent

’s e

xper

ienc

e, q

ualif

icat

ions

and

con

tact

det

ails

S

ectio

n 1.

4

1.2

Proj

ect D

escr

iptio

nB

rief d

escr

iptio

n of

the

proj

ect,

incl

udin

g a

sum

mar

y of

any

maj

or in

frast

ruct

ure

requ

irem

ents

ass

ocia

ted

with

the

proj

ect.

S

ectio

n 1.

2, 3

1.3

Proj

ect o

bjec

tives

and

sco

pe1.

S

tate

the

obje

ctiv

es w

hich

led

to th

e fo

rmul

atio

n of

the

proj

ect a

nd b

rief o

utlin

e of

the

even

ts w

hich

hav

e in

fluen

ced

the

form

ulat

ion

of

the

proj

ect.

2.

fe

asib

le a

ltern

ativ

es;

3.

prop

osed

tim

e fra

mes

for i

mpl

emen

tatio

n an

d ex

pect

ed p

roje

ct li

fe,

4.

antic

ipat

ed e

stab

lishm

ent c

osts

.

1.

Sec

tion

1.3

2.

Sec

tion

2.3

3.

Sec

tion

3.4

4.

Sec

tion

16.3

1.4

Nee

d fo

r the

pro

ject

1.

Dis

cuss

just

ifica

tion

and

need

for t

he p

roje

ct w

ith re

spec

t to

regi

onal

, Sta

te a

nd n

atio

nal c

onte

xts.

2.

Th

is s

ectio

n w

ill re

late

to th

e flo

od m

itiga

tion

requ

irem

ents

and

the

loca

l and

sta

te g

over

nmen

t ide

ntifi

ed re

quire

men

ts fo

r add

ition

al

wat

er re

sour

ces

incl

udin

g w

ithin

the

Gol

d C

oast

Wat

er F

utur

e an

d th

e S

outh

Eas

t Que

ensl

and

Reg

iona

l Wat

er S

uppl

y S

trate

gy

(SE

QR

WS

S).

3.

P

artic

ular

refe

renc

e sh

ould

be

mad

e to

env

ironm

enta

l, ec

onom

ic a

nd s

ocia

l cos

ts a

nd b

enef

its.

1.

Sec

tion

2.1

2.

Sec

tion

1.1,

1.4

, 7.1

3.

S

ectio

n 2.

4, 1

6.2,

16.

3

1.1

Rel

atio

nshi

p to

oth

er p

roje

cts

Des

crib

e ho

w th

e pr

ojec

t rel

ates

to o

ther

wat

er in

frast

ruct

ure

proj

ects

incl

udin

g an

y st

rate

gies

out

lined

in S

EQ

RW

SS

.S

ectio

n 2.

2

1.6

Alte

rnat

ives

Des

crib

e al

l fea

sibl

e al

tern

ativ

es th

at h

ave

been

inve

stig

ated

, inc

lude

: 1.

th

e co

nseq

uenc

es o

f not

pro

ceed

ing

with

the

proj

ect

2.

iden

tific

atio

n of

feas

ible

alte

rnat

ives

3.

D

iscu

ssio

n of

the

met

hodo

logy

ado

pted

to d

isce

rn b

etw

een

feas

ible

opt

ions

. Th

e al

tern

ativ

e op

tions

sho

uld

be d

iscu

ssed

in s

uffic

ient

de

tail

to e

nabl

e an

und

erst

andi

ng o

f the

reas

ons

for p

refe

rring

cer

tain

opt

ions

and

cou

rses

of a

ctio

n an

d re

ject

ing

othe

rs.

1.

Sec

tion

2.3

2.

Sec

tion

2.3

3.

Sec

tion

2.3

1.7

Cos

ts a

nd B

enef

its o

f the

Pro

ject

This

sec

tion

shou

ld s

umm

aris

e:

1.

The

econ

omic

cos

ts a

nd b

enef

its to

indu

stry

and

the

wid

er c

omm

unity

, inc

ludi

ng d

irect

ly a

ffect

ed e

nter

pris

es. A

naly

sis

shou

ld b

e co

nduc

ted

at th

e lo

cal,

regi

onal

, sta

te a

nd n

atio

nal l

evel

s.

2.

Reg

iona

l soc

ial i

mpa

cts

incl

udin

g co

mm

unity

dis

rupt

ion,

rela

ted

land

use

cha

nges

, em

ploy

men

t, sk

ills d

evel

opm

ent a

nd a

ny w

orkf

orce

acco

mm

odat

ion

issu

es.

1.

Sec

tion

2.4,

16.

3 2.

S

ectio

n 2.

4, 6

.6 1

6.2

1.8

The

Envi

ronm

enta

l Im

pact

Ass

essm

ent P

roce

ss1.

Th

is s

ectio

n w

ill c

lear

ly id

entif

y w

hich

legi

slat

ive

proc

ess

is re

leva

nt a

nd th

e m

etho

dolo

gy b

eing

ado

pted

to c

ompl

y w

ith th

e re

leva

nt

legi

slat

ion.

2.

D

escr

ibe

the

impa

ct a

sses

smen

t pro

cess

ste

ps, t

imin

g an

d de

cisi

on m

akin

g pr

oces

s fo

r the

rele

vant

sta

ges

of th

e P

roje

ct.

3.

Incl

ude

a de

scrip

tion

of h

ow th

e co

nsul

tatio

n pr

oces

s w

ill b

e in

tegr

ated

with

oth

er e

lem

ents

of t

he im

pact

ass

essm

ent,

incl

udin

g tim

ing

0.

Sec

tion

1.5,

1.8

, 1.9

0.

S

ectio

n 1.

5, 1

.9

0.

Sec

tion

1.7

0.

Sec

tion

1.5

0.

Sec

tion

1.10

Page 56: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n an

d op

portu

nitie

s fo

r pub

lic in

put a

nd p

artic

ipat

ion.

4.

D

escr

ibe

the

obje

ctiv

es o

f the

EIS

. 1.

D

etai

l how

pub

lic s

ubm

issi

ons

on th

e E

IS w

ill b

e in

vite

d, c

onsi

dere

d an

d ad

dres

sed

and

antic

ipat

ed ti

mel

ines

. 1.

9 Pu

blic

Con

sulta

tion

Proc

ess

1.

This

sec

tion

shou

ld o

utlin

e th

e pu

blic

con

sulta

tion

proc

ess

that

has

take

n pl

ace

durin

g th

e E

IS’s

pre

para

tion

and

the

resu

lts o

f suc

h co

nsul

tatio

n. It

sho

uld

outli

ne a

ny fu

rther

opp

ortu

nitie

s fo

r pub

lic in

put o

n th

e dr

aft E

IS re

port.

Th

e ob

ject

ives

for c

omm

unity

con

sulta

tion

for t

he E

IS a

re to

: 2.

E

nhan

ce c

omm

unity

aw

aren

ess

and

unde

rsta

ndin

g of

the

proj

ect,

with

the

prov

isio

n of

ade

quat

e an

d ap

prop

riate

info

rmat

ion;

3.

Id

entif

y ke

y st

akeh

olde

rs (i

nclu

ding

repr

esen

tativ

es o

f sta

keho

lder

gro

ups)

, the

ir ne

eds

and

valu

es;

4.

Faci

litat

e in

volv

emen

t by

the

com

mun

ity in

to th

e pr

ojec

t’s d

evel

opm

ent;

5.

Pro

vide

info

rmat

ion

on th

e E

IS p

roce

ss;

6.

See

k in

put i

n te

rms

of k

ey is

sues

and

con

cern

s an

d su

gges

tions

to m

itiga

te th

ese

conc

erns

; 7.

S

eek

feed

back

on

the

pref

erre

d co

ncep

t; 8.

P

rovi

de in

form

atio

n on

the

outc

omes

of p

roje

ct s

tudi

es; a

nd

9.

Dem

onst

rate

how

issu

es o

f con

cern

to th

e co

mm

unity

will

be

sour

ced,

iden

tifie

d an

d co

nsid

ered

dur

ing

the

EIS

pro

cess

. 10

. A

dvis

ory

agen

cies

- A

dvis

ory

agen

cies

incl

ude

gove

rnm

ent d

epar

tmen

ts, a

utho

ritie

s, a

genc

ies

and

key

serv

ice

prov

ider

s.

11.

Oth

er S

take

hold

er, C

omm

unity

and

Spe

cial

Inte

rest

Gro

ups

1.

Sec

tion

1.7

and

App

endi

x D

2.

S

ectio

n 1.

7 an

d A

ppen

dix

D

3.

Sec

tion

1.7

and

App

endi

x D

4.

S

ectio

n 1.

7 an

d A

ppen

dix

D

5.

Sec

tion

1.7

and

App

endi

x D

6.

S

ectio

n 1.

7 an

d A

ppen

dix

D

7.

Sec

tion

1.7

and

App

endi

x D

8.

S

ectio

n 1.

7 an

d A

ppen

dix

D

9.

Sec

tion

1.7

and

App

endi

x D

10

. Se

ctio

n 1.

7 an

d Ap

pend

ix D

11

. Se

ctio

n 1.

7 an

d Ap

pend

ix D

1.10

Th

e G

ener

al C

omm

unity

The

cons

ulta

tion

proc

ess

on th

e E

IS s

houl

d al

so in

clud

e ap

prop

riate

mec

hani

sms

targ

eted

at e

nsur

ing

adeq

uate

invo

lvem

ent o

f the

gen

eral

co

mm

unity

bot

h in

the

stud

y ar

ea a

nd in

the

broa

der Q

ueen

slan

d re

gion

as

appr

opria

te.

Sec

tion

1.7

and

App

endi

x D

1.11

Pl

anni

ng C

onte

xtD

iscu

ss th

e pr

ojec

t and

pro

vide

an

asse

ssm

ent o

f the

pro

ject

’s c

onsi

sten

cy w

ith re

leva

nt p

lann

ing

polic

y fo

r the

are

a an

d re

gion

. Ass

ess

the

proj

ect’s

con

sist

ency

with

the

follo

win

g:

1.

the

GC

CC

loca

l pla

nnin

g sc

hem

e. It

sho

uld

be d

iscu

ssed

that

muc

h of

the

proj

ect a

rea

is a

lread

y su

bjec

t to

a C

omm

unity

In

frast

ruct

ure

Des

igna

tion

and

this

will

be e

xten

ded

to c

over

the

addi

tiona

l im

poun

dmen

t are

a an

d as

suc

h no

Gol

d C

oast

City

Cou

ncil

Pla

nnin

g S

chem

e ap

prov

als

will

be

requ

ired

with

in th

is a

rea.

2.

pl

anni

ng c

ontro

ls, b

y-la

ws

and

polic

ies

rela

ting

to th

e st

udy

area

and

adj

acen

t lan

ds, i

nclu

ding

Wat

er R

esou

rce

Pla

nnin

g an

dE

ntitl

emen

ts.

3.

regi

onal

stra

tegi

es o

r pla

ns th

at re

late

to e

xist

ing

land

use

s or

long

term

pol

icy

fram

ewor

k fo

r the

are

a or

pro

posa

l (th

ese

incl

ude

thos

e th

at a

re in

pre

para

tion)

par

ticul

arly

in re

latio

n to

the

SE

Q R

egio

nal P

lan

and

the

SE

Q R

egio

nal I

nfra

stru

ctur

e P

lan

and

Pro

gram

; the

R

egio

nal W

ater

Sup

ply

Stra

tegy

; the

Sta

te C

oast

al M

anag

emen

t Pla

n 20

01 a

nd th

e S

EQ

Reg

iona

l Coa

stal

Man

agem

ent P

lan

2006

(if

appl

icab

le),

and

with

legi

slat

ion,

sta

ndar

ds, c

odes

or g

uide

lines

ava

ilabl

e to

mon

itor a

nd c

ontro

l ope

ratio

ns o

n si

te. I

t sho

uld

refe

r to

all

rele

vant

Sta

te a

nd re

gion

al p

lann

ing

polic

ies;

and

4.

its

rela

tions

hip

to o

ther

sig

nific

ant d

evel

opm

ents

(exi

stin

g or

pro

pose

d) in

the

stud

y ar

ea,

]sur

roun

ding

loca

lity

and

Sou

th E

ast

Que

ensl

and

regi

on.

1.

Sec

tion

1.8

2.

Sec

tion

1.8

3.

Sec

tion

1.8

4.

Sec

tion

2.2

1.12

Pr

ojec

t App

rova

l: le

gisl

atio

n an

d po

licy

requ

irem

ents

1.

Iden

tify

and

expl

ain

the

fede

ral,

stat

e an

d lo

cal l

egis

latio

n an

d po

licie

s co

ntro

lling

the

appr

oval

s pr

oces

s.

1.

Trig

gers

for t

he a

pplic

atio

n of

eac

h of

thes

e sh

ould

be

disc

usse

d an

d re

leva

nt a

ppro

val r

equi

rem

ents

sho

uld

be id

entif

ied.

Thi

s in

form

atio

n is

requ

ired

to a

sses

s ho

w th

e le

gisl

atio

n ap

plie

s to

the

prop

osal

, whi

ch a

genc

ies

have

juris

dict

ion,

and

whe

ther

the

prop

osed

impa

ct a

sses

smen

t pro

cess

is a

ppro

pria

te.

1.

Sec

tion

1.8,

1.9

2.

S

ectio

n 1.

8, 1

.9

3.

Sec

tion

18, 1

.9 a

nd A

ppen

dix

B

4.

Sec

tion

1.9

5.

Sec

tions

1.1

0

Page 57: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n 2.

Th

e To

R s

houl

d no

te th

at th

e re

leva

nt le

gisl

atio

n.

3.

Des

crib

e th

e ap

prov

al p

roce

ss re

sulti

ng fr

om th

e ga

zetta

l of t

his

proj

ect a

s a

sign

ifica

nt p

roje

ct p

ursu

ant t

o th

e S

DP

WO

A a

nd o

utlin

e th

e lin

kage

with

the

IDA

S p

roce

ss u

nder

the

IPA

. Ind

icat

e th

e le

vel o

f app

rova

ls a

ntic

ipat

ed b

y th

e pr

opon

ent u

nder

the

IPA

and

inte

ntio

ns to

see

k an

am

endm

ent t

o th

e ex

istin

g C

omm

unity

Infra

stru

ctur

e D

esig

natio

n to

ext

end

its b

ound

ary

to in

clud

e th

e ad

ditio

nal

impo

undm

ent a

rea.

4.

D

escr

ibe

the

publ

ic n

otifi

catio

n pr

oces

ses

and

appe

al ri

ghts

that

will

be

avai

labl

e in

the

antic

ipat

ed a

ppro

val p

roce

ss.

5.

The

ToR

sho

uld

note

that

the

proj

ect h

as b

een

liste

d as

an

emer

genc

y w

ater

sup

ply

mea

sure

for t

he S

EQ

regi

on w

ithin

the

Wat

er

Am

endm

ent R

egul

atio

n (N

o. 6

) 200

6 (th

e ‘w

ater

em

erge

ncy’

regu

latio

n). T

he R

egul

atio

n in

stru

cts

that

the

proj

ect m

ust b

e de

liver

ed b

y th

e en

d of

201

0.

6.

A d

escr

iptio

n of

all

Env

ironm

enta

lly R

elev

ant A

ctiv

ities

(ER

As)

nec

essa

ry fo

r the

Pro

ject

sho

uld

also

be

give

n.

7.

As

the

proj

ect i

s a

cont

rolle

d ac

tion

unde

r the

Com

mon

wea

lth E

PB

C A

ct, a

ny re

quire

men

ts o

f the

Com

mon

wea

lth E

nviro

nmen

t P

rote

ctio

n an

d B

iodi

vers

ity C

onse

rvat

ion

Act

199

9 sh

ould

als

o be

indi

cate

d in

this

sec

tion.

8.

P

rovi

de a

list

of t

he a

ppro

vals

requ

ired

for t

he p

roje

ct a

nd th

e ex

pect

ed p

rogr

am fo

r app

rova

l of a

pplic

atio

ns.

9.

Des

crib

e th

e pr

ojec

t’s c

ompa

tibilit

y w

ith th

e N

atio

nal W

ater

Initi

ativ

e, G

over

nmen

t Eco

logi

cally

Sus

tain

able

Dev

elop

men

t pol

icy,

Q

ueen

slan

d N

atur

al R

esou

rces

(Wat

er) P

olic

y, N

atio

nal S

trate

gy o

n C

onse

rvat

ion

of A

ustra

lia’s

Bio

logi

cal D

iver

sity

; with

wat

er re

form

unde

r the

Nat

iona

l Com

petit

ion

Pol

icy;

and

any

oth

er re

leva

nt p

olic

y.

6.

Sec

tion

1.8

7.

Sec

tion

1.9

8.

Sec

tion

1.9

9.

Sec

tion

1.9

and

App

endi

x B

10

. S

ectio

n 1.

8, 1

.9

2 Pr

ojec

t Des

crip

tion

2.1

Loca

tion

and

gene

ral d

escr

iptio

n 1.

P

roje

ct a

rea

desc

riptio

n 2.

C

urre

nt s

truct

ure

and

faci

litie

s 3.

C

onst

ruct

ion

foot

prin

t: 4.

P

rovi

de m

aps

at s

uita

ble

scal

es s

how

ing

the

prec

ise

loca

tion

of th

e pr

ojec

t are

a, th

e lo

catio

n an

d bo

unda

ries

of th

e pr

ojec

t foo

tprin

t, an

d lo

catio

n an

d bo

unda

ries

of la

nd te

nure

s.

5.

Pro

vide

the

over

all P

roje

ct d

urat

ion

and

expe

cted

tim

ing

of w

orks

.

1.

Sec

tion

3.1

2.

Sec

tion

3.1

3.

Sec

tion

3.1

4.

Sec

tion

3.1

5.

Sec

tion

3.4

2.2

Prop

osed

Wor

ks

A d

escr

iptio

n of

the

prop

osed

wor

ks fo

r the

Pro

ject

sho

uld

be p

rovi

ded

incl

udin

g

1.

barri

er/e

mba

nkm

ent s

truct

ures

2.

si

te d

etai

ls in

clud

ing

incr

ease

d in

unda

tion

area

3.

pr

e-co

nstru

ctio

n ac

tiviti

es

4.

cons

truct

ion

activ

ities

and

infra

stru

ctur

e 5.

au

xilia

ry in

frast

ruct

ure

requ

irem

ents

1.

Sec

tion

3.2

2.

Sec

tion

3.2

3.

Sec

tion

3.3

4.

Sec

tion

3.4

5.

Sec

tion

3.5

2.3

Prop

osed

Wat

er S

tora

ge O

pera

tion

1.

Pro

vide

full

deta

ils o

n th

e pr

opos

ed o

n-go

ing

man

agem

ent o

f the

aug

men

ted

dam

, inu

ndat

ion

area

and

buf

fer z

one.

2.

P

rovi

de d

etai

ls o

n th

e tim

ing

of th

e co

nstru

ctio

n of

the

Pro

ject

incl

udin

g pl

anni

ng, i

mpa

ct a

sses

smen

t, co

nstru

ctio

n, m

onito

ring,

EM

P,

etc,

ant

icip

ated

est

ablis

hmen

t and

ong

oing

cos

ts a

nd th

e P

roje

ct li

fe.

3.

Cos

ts s

houl

d in

clud

e m

onito

ring

and

envi

ronm

enta

l miti

gatio

n/m

anag

emen

t cos

ts.

4.

The

loca

tion

and

desi

gn o

f any

exi

stin

g or

new

wat

er d

istri

butio

n in

frast

ruct

ure

(e.g

. pum

p st

atio

ns, c

anal

s, p

ipel

ines

etc

.) sh

ould

be

desc

ribed

.

Sec

tion

3.4,

3.5

, 3.6

, 16.

3

2.4

Reh

abili

tatio

n an

d de

com

mis

sion

ing

of c

onst

ruct

ion

wor

ksD

escr

ibe

the

optio

ns, s

trate

gies

and

met

hods

for p

rogr

essi

ve a

nd fi

nal r

ehab

ilitat

ion

of a

ll en

viro

nmen

tal v

alue

s di

stur

bed

by th

e P

roje

ct.

Sec

tion

3.8

Page 58: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n

3 En

viro

nmen

tal V

alue

s an

d M

anag

emen

t of I

mpa

ct

3.1

Land

La

nd -

Des

crip

tion

of E

nviro

nmen

tal V

alue

sTo

pogr

aphy

and

Geo

mor

phol

ogy

1.

M

aps

shou

ld b

e pr

ovid

ed lo

catin

g th

e P

roje

ct in

bot

h re

gion

al a

nd lo

cal c

onte

xts.

2.

Th

e to

pogr

aphy

of t

he p

ropo

sal s

ite s

houl

d be

det

aile

d w

ith c

onto

urs

at s

uita

ble

incr

emen

ts, s

how

n w

ith re

spec

t to

Aus

tralia

n H

eigh

t D

atum

(AH

D) a

nd in

rela

tion

to th

e FS

L an

d bu

ffer z

one

for t

he p

roje

ct.

Sig

nific

ant f

eatu

res

of th

e lo

calit

y sh

ould

be

incl

uded

on

the

map

s. S

uch

feat

ures

wou

ld in

clud

e an

y lo

catio

ns s

ubse

quen

tly re

ferre

d to

in th

e E

IS (e

.g. s

ensi

tive

loca

tions

, sig

nific

ant e

nviro

nmen

tal

feat

ures

) tha

t are

not

incl

uded

on

othe

r map

s fo

r thi

s se

ctio

n.

1.

Sec

tion

3.1

2.

Sec

tion

4.1,

4.2

Geo

logy

and

Soi

ls

1.

Pro

vide

a d

escr

iptio

n an

d m

aps

of th

e ge

olog

y of

the

Pro

ject

are

a 2.

D

iscu

ss th

e cu

rrent

dam

wal

l fou

ndat

ions

and

any

geo

logi

cal l

imita

tion

in ra

isin

g th

e w

all.

3.

D

iscu

ss th

e av

aila

bilit

y an

d su

itabi

lity

of lo

catio

ns in

the

vici

nity

of t

he im

poun

dmen

t for

qua

rry

mat

eria

l.

1.

Sec

tion

4.3

2.

Sec

tion

4.3

3.

Sec

tion

3.4

Land

use

1.

P

rovi

de a

des

crip

tion

of c

urre

nt la

nd u

ses

in th

e pr

opos

al a

rea,

with

par

ticul

ar m

entio

n of

land

with

spe

cial

pur

pose

s.

2.

Map

s at

sui

tabl

e sc

ales

sho

win

g ex

istin

g la

nd u

ses

and

tenu

res,

rese

rves

, roa

ds a

nd ro

ad re

serv

es, a

nd th

e pr

opos

ed in

unda

tion

area

s sh

ould

be

prov

ided

for t

he e

ntire

are

a th

at c

ould

be

affe

cted

by

the

Pro

ject

.

3.

Indi

cate

loca

tions

of g

as a

nd w

ater

pip

elin

es, p

ower

line

s an

d an

y ot

her e

asem

ents

. The

map

s sh

ould

iden

tify

loca

tions

of c

onse

rvat

ion

valu

e, e

xist

ing

dwel

lings

and

recr

eatio

nal a

reas

, and

the

zoni

ng o

f all

affe

cted

land

s ac

cord

ing

to a

ny e

xist

ing

tow

n or

stra

tegi

c pl

an.

4.

Des

crib

e ar

eas

cove

red

by n

ativ

e tit

le d

eter

min

atio

ns o

r app

licat

ions

for n

ativ

e tit

le d

eter

min

atio

n, in

clud

ing

tradi

tiona

l and

co

ntem

pora

ry u

ses

of la

nd a

nd w

ater

by

Abo

rigin

al p

eopl

e.

1.

Sec

tion

6.2

2.

Sec

tion

6.1

3.

Sec

tion

6.4

4.

Sec

tion

6.3

Infr

astr

uctu

re

All

exis

ting

infra

stru

ctur

e at

the

exis

ting

dam

wal

l and

any

to b

e af

fect

ed b

y th

e pr

ojec

t bot

h up

stre

am a

nd d

owns

tream

of t

he im

poun

dmen

t sh

ould

be

iden

tifie

d an

d lo

catio

ns in

dica

ted

on a

sui

tabl

y sc

aled

map

.

Sec

tion

6.4

Sens

itive

Env

ironm

enta

l Are

as

1.

Iden

tify

all s

ensi

tive

envi

ronm

enta

l are

as th

at a

re p

roxi

mal

to th

e pr

opos

al o

r cou

ld b

e af

fect

ed, d

irect

ly a

nd in

dire

ctly

, by

the

prop

osal

.

2.

Indi

cate

if th

e la

nd a

ffect

ed b

y th

e pr

opos

al is

, or i

s lik

ely,

to b

ecom

e pa

rt of

the

prot

ecte

d ar

ea e

stat

e, o

r is

subj

ect t

o an

y tre

aty.

3.

C

onsi

dera

tion

shou

ld b

e gi

ven

to n

atio

nal p

arks

, con

serv

atio

n pa

rks,

dec

lare

d fis

h ha

bita

t are

as, w

ilder

ness

are

as, a

quat

ic re

serv

es,

herit

age/

hist

oric

are

as o

r ite

ms,

nat

iona

l est

ates

, wor

ld h

erita

ge li

stin

gs a

nd s

ites

cove

red

by in

tern

atio

nal t

reat

ies

or a

gree

men

ts (e

.g.

Ram

sar,

JAM

BA

, CA

MB

A),

area

s of

cul

tura

l sig

nific

ance

, bot

h in

dige

nous

and

non

-indi

geno

us, a

nd s

cien

tific

rese

rves

.

1.

Sec

tion

6.5

2.

Sec

tion

6.5

3.

Sec

tion

6.5

Land

scap

e an

d Vi

sual

Am

enity

Th

is s

ectio

n sh

ould

des

crib

e ex

istin

g la

ndsc

ape

char

acte

r and

feat

ures

, pan

oram

as a

nd v

iew

s fo

r the

Pro

ject

are

a, in

par

ticul

ar fr

om th

e ex

istin

g da

m w

all a

nd re

crea

tiona

l are

as.

Info

rmat

ion

in th

e fo

rm o

f map

s, s

ectio

ns, e

leva

tions

and

pho

togr

aphs

is to

be

used

, par

ticul

arly

w

here

add

ress

ing

the

follo

win

g is

sues

: 1.

m

ajor

vie

ws,

vie

w s

heds

, exi

stin

g vi

ewin

g ou

tlook

s, ri

dgel

ines

and

oth

er fe

atur

es c

ontri

butin

g to

the

amen

ity o

f the

are

a, in

clud

ing

asse

ssm

ent f

rom

priv

ate

resi

denc

es in

the

affe

cted

are

a al

ong

the

rout

e;

2.

foca

l poi

nts,

land

mar

ks (b

uilt

form

or t

opog

raph

y), g

atew

ays

asso

ciat

ed w

ith p

roje

ct s

ite a

nd im

med

iate

sur

roun

ding

are

as, w

ater

way

s,

and

othe

r fea

ture

s co

ntrib

utin

g to

the

visu

al q

ualit

y of

the

area

and

the

proj

ect s

ite; a

nd

3.

char

acte

r of t

he lo

cal a

nd s

urro

undi

ng a

reas

incl

udin

g ch

arac

ter o

f bui

lt fo

rm (s

cale

, for

m, m

ater

ials

and

col

ours

) and

veg

etat

ion

4.

Sec

tion

18.2

5.

S

ectio

n 18

.2

6.

Sec

tion

18.2

Page 59: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n (n

atur

al a

nd c

ultu

ral v

eget

atio

n) d

irect

iona

l sig

nage

and

land

use

. La

nd C

onta

min

atio

n 1.

A

sea

rch

of th

e E

PA

’s E

nviro

nmen

tal M

anag

emen

t Reg

iste

r (E

MR

) and

Con

tam

inat

ed L

and

Reg

iste

r (C

LR) s

houl

d be

und

erta

ken

to

dete

rmin

e th

e re

quire

men

ts fo

r man

agem

ent u

nder

the

Env

ironm

enta

l Pro

tect

ion

Act

199

4.2.

Th

e hi

stor

y of

the

site

sho

uld

be in

vest

igat

ed in

clud

ing

anal

ysis

of h

isto

rical

aer

ial p

hoto

grap

hs a

nd d

eter

min

atio

n of

pas

t and

cur

rent

la

nd u

ses.

3.

A

Pre

limin

ary

Site

Inve

stig

atio

n (P

SI)

of th

e si

te c

onsi

sten

t with

the

EP

A’s

“Dra

ft G

uide

lines

for t

he A

sses

smen

t and

Man

agem

ent o

f C

onta

min

ated

Lan

d in

Que

ensl

and”

(Que

ensl

and

EP

A, 1

998)

sho

uld

be u

nder

take

n to

det

erm

ine

back

grou

nd c

onta

min

atio

n le

vels

.

1.

Sec

tion

5.1

2.

Sec

tion

5.1

3.

Sec

tion

5.2

4.

Sec

tion

5.2

Land

- Po

tent

ial I

mpa

cts

and

Miti

gatio

n M

easu

res

Land

Res

ourc

es a

nd In

fras

truc

ture

1.

D

iscu

ss th

e P

roje

ct in

the

cont

ext o

f maj

or to

pogr

aphi

c fe

atur

es a

nd a

ny m

easu

res

take

n to

avo

id o

r min

imis

e im

pact

to s

uch

(ifre

quire

d).

2.

The

obje

ctiv

es to

be

used

for t

he P

roje

ct in

re-c

onto

urin

g an

d la

ndsc

apin

g, e

spec

ially

any

qua

rries

and

recr

eatio

nal a

reas

sho

uld

be

desc

ribed

.

1.

Sec

tion

4.5

2.

Sec

tion

4.5

Land

Use

and

Ten

ure

1.

Det

ail t

he p

oten

tial f

or th

e co

nstru

ctio

n an

d op

erat

ion

of th

e P

roje

ct to

cha

nge

exis

ting

and

pote

ntia

l lan

d us

es o

f the

pro

posa

l pro

ject

ar

eas.

2.

The

pote

ntia

l im

plic

atio

ns o

f the

pro

posa

l for

futu

re d

evel

opm

ents

in th

e im

pact

are

a in

clud

ing

cons

train

ts o

n su

rroun

ding

land

use

s sh

ould

be

desc

ribed

. 3.

In

dica

te th

e ra

nge

of m

easu

res

to b

e ta

ken

to m

inim

ise

the

desc

ribed

impa

cts

on s

urro

undi

ng la

nd u

ses

that

will

aris

e as

a re

sult

of th

e pr

ojec

t. 4.

In

clud

e th

e ex

tent

of t

he p

roje

ct’s

impa

cts

on, a

nd im

plic

atio

ns fo

r, th

e N

umin

bah

Sta

te F

ores

t.

1.

Sec

tion

6.6

2.

Sec

tion

6.6

3.

Sec

tion

6.6

4.

Sec

tion

6.6

Land

Dis

turb

ance

– re

habi

litat

ion

and

deco

mm

issi

onin

g of

con

stru

ctio

n w

orks

Th

e E

IS s

houl

d de

scrib

e:

1.

The

proc

ess

for d

ecom

mis

sion

ing

and

reha

bilit

atio

n of

the

mat

eria

l sou

rce

extra

ctio

n si

te(s

), in

clud

ing

any

requ

ired

rem

oval

of

proc

essi

ng p

lant

and

infra

stru

ctur

e.

2.

A p

refe

rred

reha

bilit

atio

n st

rate

gy, d

evel

oped

with

a v

iew

to m

inim

isin

g th

e am

ount

of l

and

dist

urbe

d at

any

one

tim

e.

3.

The

final

topo

grap

hy o

f the

Pro

ject

site

and

mat

eria

l ext

ract

ion

site

(s),

to b

e sh

own

on p

lans

at a

sui

tabl

e sc

ale.

4.

Th

e m

eans

of d

ecom

mis

sion

ing

the

Pro

ject

, in

term

s of

the

rem

oval

of p

lant

, equ

ipm

ent,

stru

ctur

es a

nd b

uild

ings

. 5.

O

ptio

ns a

nd m

etho

ds fo

r the

dis

posa

l of w

aste

s fro

m th

e de

mol

ition

of p

lant

and

bui

ldin

gs, i

n su

ffici

ent d

etai

l for

thei

r fea

sibi

lity

and

suita

bilit

y to

be

esta

blis

hed,

sho

uld

be d

escr

ibed

.

1.

Sec

tion

3.7

2.

Sec

tion

3.7

3.

Sec

tion

3.8

4.

Sec

tion

3.8

5.

Sec

tion

15.5

Soil

Eros

ion

1.

For a

ll pe

rman

ent a

nd te

mpo

rary

land

form

s in

the

proj

ect a

rea,

ero

sion

man

agem

ent t

echn

ique

s sh

ould

be

desc

ribed

. 2.

Fo

r eac

h so

il ty

pe id

entif

ied,

ero

sion

pot

entia

l (w

ind

and

wat

er) a

nd e

rosi

on m

anag

emen

t tec

hniq

ues

shou

ld b

e ou

tline

d.

3.

Met

hods

pro

pose

d to

pre

vent

or c

ontro

l ero

sion

sho

uld

be s

peci

fied

and

shou

ld b

e de

velo

ped

to p

reve

nt s

oil l

oss

in o

rder

to m

aint

ain

land

con

ditio

n, a

nd to

pre

vent

sig

nific

ant d

egra

datio

n of

loca

l wat

erw

ays

and

in p

artic

ular

, Lak

e A

dvan

ceto

wn,

by

susp

ende

d so

lids.

4.

A d

etai

led

eros

ion

and

sedi

men

t con

trol p

lan

shou

ld b

e in

clud

ed in

the

cons

truct

ion

Env

ironm

enta

l Man

agem

ent P

lan.

1.

Sec

tion

4.6,

App

endi

x F.

4 2.

S

ectio

n 4.

4 3.

S

ectio

n 4.

6, A

ppen

dix

F.4

4.

Appe

ndix

F.4

Aci

d Su

lpha

te S

oils

1.

S

ectio

n 4.

4

Page 60: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n 1.

D

iscu

ss th

e po

tent

ial f

or a

cid

gene

ratio

n by

dis

turb

ance

of a

cid

sulp

hate

soi

ls d

urin

g ea

rthw

orks

and

con

stru

ctio

n

Con

tam

inat

ed L

and

1.

Th

e E

IS s

houl

d de

scrib

e th

e po

ssib

le c

onta

min

atio

n of

land

from

asp

ects

of t

he p

ropo

sals

incl

udin

g w

aste

, rej

ect p

rodu

ct, a

cid

gene

ratio

n fro

m e

xpos

ed s

ulph

idic

mat

eria

l and

spi

lls a

t che

mic

al a

nd fu

el s

tora

ge a

reas

. 2.

Th

e m

eans

of p

reve

ntin

g la

nd c

onta

min

atio

n (w

ithin

the

mea

ning

of t

he Q

ueen

slan

d E

nviro

nmen

tal P

rote

ctio

n A

ct 1

994)

sho

uld

bead

dres

sed.

3.

M

etho

ds p

ropo

sed

for p

reve

ntin

g, re

cord

ing,

con

tain

ing

and

rem

edia

ting

any

cont

amin

ated

land

sho

uld

be o

utlin

ed.

4.

Inte

ntio

ns s

houl

d be

sta

ted

conc

erni

ng th

e cl

assi

ficat

ion

(in te

rms

of th

e Q

ueen

slan

d C

onta

min

ated

Lan

d R

egis

ter)

of la

nd

cont

amin

atio

n on

the

land

, pro

cess

ing

plan

t site

and

pro

duct

sto

rage

are

as a

fter p

ropo

sal c

ompl

etio

n.

1.

Sec

tion

5.3,

15.

5 2.

S

ectio

n 5,

15.

5 3.

S

ectio

n 15

.5

4.

Sec

tion

5.2

Land

scap

e an

d Vi

sual

Am

enity

1.

D

escr

ibe

the

pote

ntia

l im

pact

s of

the

proj

ect l

ands

cape

cha

ract

er o

f the

site

and

the

surro

undi

ng a

rea.

2.

A

naly

se a

nd d

iscu

ss th

e vi

sual

impa

ct o

f the

pro

posa

l on

parti

cula

r pan

oram

as a

nd o

utlo

oks,

in te

rms

of th

e ex

tent

and

sig

nific

ance

of

the

chan

ged

skyl

ine

as v

iew

ed fr

om p

lace

s of

resi

denc

e, w

ork,

and

recr

eatio

n, fr

om ro

ad, c

ycle

and

wal

kway

s, fr

om th

e ai

r and

oth

erkn

own

vant

age

poin

ts.

3.

D

etai

l sho

uld

be p

rovi

ded

of a

ll m

anag

emen

t opt

ions

and

mea

sure

s to

be

impl

emen

ted

and

how

thes

e w

ill a

void

or m

itiga

te th

e id

entif

ied

impa

cts.

1.

Sec

tion

18.3

2.

S

ectio

n 18

.3

3.

Sec

tion

18.4

3.2

Clim

ate

1.

Des

crib

e th

e ra

infa

ll pa

ttern

s, a

ir te

mpe

ratu

res,

hum

idity

, win

d an

d an

y ot

her s

peci

al fa

ctor

s th

at m

ay a

ffect

air

qual

ity w

ithin

the

regi

on

of th

e pr

opos

al.

2.

Ext

rem

es o

f clim

ate

shou

ld a

lso

be d

iscu

ssed

with

par

ticul

ar re

fere

nce

to w

ater

man

agem

ent a

t the

site

.

1.

Sec

tion

7.1

2.

Sec

tion

7.1

3.3

Wat

er R

esou

rces

W

ater

Res

ourc

es -

Des

crip

tion

of E

nviro

nmen

tal V

alue

s Su

rfac

e W

ater

and

Wat

erw

ays

1.

D

escr

ibe

the

surfa

ce w

ater

cour

ses

and

thei

r qua

lity

and

quan

tity

with

in th

e H

inze

Dam

cat

chm

ent.

2.

D

escr

ibe

exis

ting

surfa

ce d

rain

age

patte

rns,

flow

s in

maj

or s

tream

s an

d w

etla

nds.

3.

D

etai

l the

like

lihoo

d of

floo

ding

, his

tory

of f

lood

ing

incl

udin

g ex

tent

, lev

els

and

frequ

ency

4.

D

escr

ibe

pres

ent a

nd p

oten

tial w

ater

use

s do

wns

tream

of t

he a

reas

affe

cted

by

the

prop

osal

. 5.

Fl

ood

stud

ies

shou

ld in

clud

e a

rang

e of

ann

ual e

xcee

danc

e pr

obab

ilitie

s fo

r affe

cted

wat

erw

ays,

whe

re d

ata

perm

its.

6.

An

asse

ssm

ent i

s re

quire

d of

exi

stin

g w

ater

qua

lity

in th

e im

poun

dmen

t and

wat

erw

ays

and

wet

land

s lik

ely

to b

e af

fect

ed b

y th

e pr

opos

al.

The

basi

s fo

r thi

s as

sess

men

t sho

uld

be a

mon

itorin

g pr

ogra

m, w

ith s

ampl

ing

stat

ions

loca

ted

upst

ream

and

dow

nstre

am o

f th

e pr

opos

al.

Com

plem

enta

ry s

tream

-flow

dat

a sh

ould

als

o be

obt

aine

d fro

m h

isto

rical

reco

rds

(if a

vaila

ble)

to a

id in

inte

rpre

tatio

n.7.

Th

e w

ater

qua

lity

shou

ld b

e de

scrib

ed, i

nclu

ding

reco

rds

of b

lue-

gree

n al

gal b

loom

s, s

easo

nal o

r oth

er v

aria

tions

or v

aria

tions

with

flow

w

here

app

licab

le.

8.

A

rele

vant

rang

e of

phy

sica

l, ch

emic

al a

nd b

iolo

gica

l par

amet

ers

shou

ld b

e m

easu

red

to g

auge

the

envi

ronm

enta

l har

m o

n an

y af

fect

ed c

reek

or w

etla

nd s

yste

m.

9.

A d

escr

iptio

n of

the

envi

ronm

enta

l val

ues

of th

e su

rface

wat

erw

ays

of th

e af

fect

ed a

rea

shou

ld b

e pr

ovid

ed.

1.

Sec

tion

7.1

2.

Sec

tion

7.1

3.

Sec

tion

7.1

4.

Sec

tion

7.1

5.

Sec

tion

7.1

6.

Sec

tion

7.2

7.

Sec

tion

7.2

8.

Sec

tion

7.2

9.

Sec

tion

7.2

Gro

undw

ater

1.

Th

e E

IS s

houl

d re

view

the

qual

ity, q

uant

ity a

nd s

igni

fican

ce o

f gro

undw

ater

in th

e pr

opos

al a

rea.

2.

Th

e re

view

sho

uld

incl

ude

a su

rvey

of e

xist

ing

grou

ndw

ater

sup

ply

faci

litie

s (b

ores

, wel

ls, o

r exc

avat

ions

) with

in th

e gr

ound

wat

er a

rea

1.

Sec

tion

8.2

2.

Sec

tion

8.2

Page 61: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n im

pact

ed b

y th

e P

roje

ct.

Wat

er R

esou

rces

- Po

tent

ial I

mpa

cts

and

Miti

gatio

n M

easu

res

Wat

erw

ays

and

Wat

er Q

ualit

y 1.

Th

e po

tent

ial i

mpa

ct o

f the

Pro

ject

on

loca

l wat

erw

ays

shou

ld b

e di

scus

sed.

2.

W

ater

qua

lity

char

acte

ristic

s di

scus

sed

shou

ld b

e th

ose

appr

opria

te to

the

dow

nstre

am a

nd u

pstre

am w

ater

use

s th

at m

ay b

e af

fect

ed.

The

Aus

tralia

n an

d N

ew Z

eala

nd E

nviro

nmen

t and

Con

serv

atio

n C

ounc

il (A

NZE

CC

, 200

0) N

atio

nal W

ater

Qua

lity

Man

agem

ent

Stra

tegy

, Aus

tralia

n W

ater

Qua

lity

Gui

delin

es fo

r Fre

sh a

nd M

arin

e W

ater

s an

d th

e E

nviro

nmen

tal P

rote

ctio

n (W

ater

) Pol

icy

1997

sh

ould

be

used

as

a re

fere

nce

for e

valu

atin

g th

e ef

fect

s of

var

ious

leve

ls o

f con

tam

inat

ion.

3.

Th

e po

tent

ial i

mpa

cts

on w

ater

qua

lity

with

in th

e da

m fo

r pot

able

sup

ply

as a

resu

lt of

con

stru

ctio

n ac

tiviti

es n

eeds

to b

e ad

dres

sed

and

miti

gatio

n m

easu

res

prop

osed

.

4.

The

use

of a

mon

itorin

g pr

ogra

m to

ass

ess

the

effe

ctiv

enes

s of

man

agem

ent s

trate

gies

for p

rote

ctin

g w

ater

qua

lity

durin

g th

eco

nstru

ctio

n, o

pera

tion

and,

if a

pplic

able

, dec

omm

issi

onin

g of

any

tem

pora

ry s

truct

ures

sho

uld

be d

iscu

ssed

.

1.

Sec

tion

7.2

2.

Sec

tion

7.2

3.

Sec

tion

7.2

4.

Sec

tion

7.2,

App

endi

x F.

19

Hyd

rolo

gy a

nd F

lood

ing

1.

The

pote

ntia

l env

ironm

enta

l har

m to

the

flow

and

the

qual

ity o

f sur

face

wat

ers.

2.

Th

e im

pact

s of

sur

face

wat

er fl

ow o

n ex

istin

g in

frast

ruct

ure

shou

ld b

e co

nsid

ered

. 3.

Th

e en

viro

nmen

tal f

low

regi

me

dow

nstre

am o

f the

dam

wal

l sho

uld

be re

view

ed in

det

ail t

o di

scus

s th

e pr

ojec

t’s im

pact

s on

redu

ced

flood

ing

and

the

poss

ible

redu

ctio

n of

wat

er q

ualit

y in

the

Ner

ang

Riv

er.

4.

Pro

pose

d m

etho

ds fo

r ong

oing

mon

itorin

g do

wns

tream

of t

he ra

ised

dam

wal

l. 5.

Th

e hy

drol

ogic

al im

pact

s of

the

prop

osal

sho

uld

be a

sses

sed.

6.

W

hen

flood

ing

leve

ls w

ill b

e af

fect

ed, m

odel

ling

of a

fflux

sho

uld

be p

rovi

ded

and

illus

trate

d w

ith m

aps.

7.

A

sses

smen

t of i

mpa

cts

on th

e flo

w a

nd th

e qu

ality

of s

urfa

ce w

ater

s an

d ef

fect

s on

eco

syst

ems.

1.

Sec

tion

7.1

2.

Sec

tion

7.1

3.

Sec

tion

7.1

4.

Sec

tion

7.2,

App

endi

x F.

19

5.

Sec

tion

7.1

6.

Sec

tion

7.1

7.

Sec

tion

7.2

Gro

undw

ater

1.

Th

e E

IS s

houl

d in

clud

e an

ass

essm

ent o

f the

pot

entia

l env

ironm

enta

l har

m c

ause

d by

the

Pro

ject

to lo

cal g

roun

dwat

er re

sour

ces,

parti

cula

rly w

ith re

fere

nce

to v

eget

atio

n cl

earin

g, s

edim

enta

tion

and

salin

ity.

2.

A

n as

sess

men

t of t

he p

oten

tial t

o co

ntam

inat

e gr

ound

wat

er re

sour

ces

and

mea

sure

s to

pre

vent

, miti

gate

and

rem

edia

te s

uch

cont

amin

atio

n sh

ould

be

disc

usse

d.

1.

Sec

tion

8.3

2.

Sec

tion

8.5

3.4

Pote

ntia

l Im

pact

s on

Mat

ters

of N

atio

nal E

nviro

nmen

tal S

igni

fican

ce

A

sta

nd-a

lone

repo

rt ad

dres

sing

the

mat

ters

of N

ES

mus

t be

prov

ided

as

an a

ppen

dix

to th

e E

IS th

at e

xclu

sive

ly a

nd fu

lly a

ddre

sses

the

issu

es re

leva

nt to

the

cont

rolli

ng p

rovi

sion

s. T

his

stan

d al

one

sect

ion

shou

ld in

clud

e th

e fo

llow

ing:

Ap

pend

ix C

Des

crip

tion

of th

e A

ffect

ed E

nviro

nmen

t Rel

evan

t to

the

Mat

ters

Pro

tect

ed

For l

iste

d th

reat

ened

spe

cies

, the

des

crip

tion

of th

e en

viro

nmen

t sho

uld

incl

ude:

1.

th

e sp

ecie

s’ c

urre

nt d

istri

butio

n;

2.

rele

vant

info

rmat

ion

abou

t the

eco

logy

of t

he s

peci

es (h

abita

t, fe

edin

g an

d br

eedi

ng b

ehav

iour

etc

);

3.

info

rmat

ion

abou

t any

pop

ulat

ions

of t

he s

peci

es o

r hab

itat f

or th

e sp

ecie

s in

the

area

affe

cted

by

the

prop

osed

act

ion;

4.

cu

rrent

pre

ssur

es o

n th

e sp

ecie

s, e

spec

ially

thos

e in

the

area

to b

e af

fect

ed b

y th

e pr

opos

al; a

nd

5.

rele

vant

con

trols

or p

lann

ing

regi

mes

alre

ady

in p

lace

.

Sec

tion

9, A

ppen

dix

C

Ass

essm

ent o

f Rel

evan

t Im

pact

s an

d M

itiga

tion

Mea

sure

s1.

In

this

sec

tion,

the

impa

cts

and

pote

ntia

l im

pact

s on

the

mat

ters

pro

tect

ed s

houl

d be

des

crib

ed, a

nd th

e po

ssib

le m

itiga

tion

mea

sure

s fo

r eac

h im

pact

nee

d to

be

anal

ysed

.

Sec

tion

9, A

ppen

dix

C

Page 62: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n 2.

W

hen

effe

ctiv

e m

itiga

tion

mea

sure

s ar

e no

t ava

ilabl

e, th

e di

scus

sion

sho

uld

be b

road

ened

to in

clud

e co

mpe

nsat

ory

mea

sure

s to

offs

et

unav

oida

ble

impa

cts.

3.

Th

e di

scus

sion

of i

mpa

cts

to th

e re

leva

nt m

atte

rs p

rote

cted

sho

uld

addr

ess

all r

elev

ant i

mpa

cts,

and

pro

vide

suf

ficie

nt ju

stifi

catio

n fo

r al

l con

clus

ions

reac

hed

on s

peci

fic im

pact

s.

Pote

ntia

l Sig

nific

ant I

mpa

cts

on M

atte

rs o

f Nat

iona

l Env

ironm

enta

l Sig

nific

ance

(NES

) P

oten

tial i

mpa

cts

may

nee

d to

be

addr

esse

d in

the

EIS

. S

ectio

n 9,

App

endi

x C

3.5

Terr

estr

ial F

lora

Th

is s

ectio

n sh

ould

det

ail t

he e

xist

ing

natu

re te

rrest

rial f

lora

and

veg

etat

ion

valu

es o

f the

Pro

ject

are

a.

1.

Sec

tion

9.4

Des

crip

tion

of E

nviro

nmen

tal V

alue

s 1.

Th

e te

rrest

rial v

eget

atio

n co

mm

uniti

es w

ithin

the

Pro

ject

are

a sh

ould

be

desc

ribed

at a

n ap

prop

riate

sca

le (i

.e. 1

:10,

000)

with

map

ping

pr

oduc

ed fr

om a

eria

l pho

togr

aphs

and

gro

und-

truth

ing,

sho

win

g th

e fo

llow

ing:

2.

Lo

catio

n an

d ex

tent

of v

eget

atio

n ty

pes

usin

g th

e E

PA

’s re

gion

al e

cosy

stem

type

des

crip

tions

in a

ccor

danc

e w

ith th

e R

egio

nal

Eco

syst

em D

escr

iptio

n D

atab

ase

[RE

DD

] ava

ilabl

e at

the

EP

A’s

web

site

. 3.

Lo

catio

n of

spe

cies

list

ed a

s P

rote

cted

Pla

nts

unde

r the

Nat

ure

Con

serv

atio

n (W

ildlif

e) R

egul

atio

n 19

94 a

nd s

ubse

quen

t am

endm

ents

. 4.

S

ensi

tive

or im

porta

nt v

eget

atio

n ty

pes

shou

ld b

e hi

ghlig

hted

and

thei

r val

ue a

s ha

bita

t for

faun

a an

d co

nser

vatio

n of

spe

cific

rare

flor

al

and

faun

al a

ssem

blag

es o

r com

mun

ity ty

pes

disc

usse

d.

5.

Det

ails

of a

ny ri

paria

n an

d ra

info

rest

veg

etat

ion,

and

thei

r val

ue fo

r fau

na h

abita

t and

con

serv

atio

n of

spe

cific

rare

flor

al a

nd fa

unal

as

sem

blag

es o

r com

mun

ity ty

pes,

from

bot

h a

loca

l and

regi

onal

per

spec

tive,

sho

uld

be p

rovi

ded.

Any

spe

cial

land

scap

e va

lues

of

any

natu

ral v

eget

atio

n co

mm

uniti

es s

houl

d be

des

crib

ed.

6.

Con

duct

targ

eted

sur

veys

for l

egis

lativ

ely

or o

ther

wis

e si

gnifi

cant

flor

a sp

ecie

s lis

ted

unde

r Sta

te a

nd C

omm

onw

ealth

legi

slat

ion

with

in

area

s to

be

perm

anen

tly a

nd p

erio

dica

lly in

unda

ted.

Flo

ra s

urve

ys s

houl

d be

und

erta

ken

with

in e

ach

defin

ed v

eget

atio

n co

mm

unity

to

be a

ffect

ed b

y th

e pr

ojec

t. 7.

S

how

the

occu

rrenc

e of

pes

t pla

nts

(wee

ds),

parti

cula

rly d

ecla

red

plan

ts u

nder

the

Land

Pro

tect

ion

(Lan

d an

d S

tock

Rou

te

Man

agem

ent)

Act

200

2 on

a m

ap a

t an

appr

opria

te s

cale

.

1.

Sec

tion

9.4,

App

endi

x F9

.1

2.

Sec

tion

9.4,

App

endi

x F9

.1

3.

Sec

tion

9.4,

App

endi

x F9

.1

4.

Sec

tion

9.4,

App

endi

x F9

.1

5.

Sec

tion

9.4,

App

endi

x F9

.1

6.

Sec

tion

9.3,

App

endi

x F9

.1

7.

Sec

tion

9.4,

App

endi

x F9

.1

Pote

ntia

l Im

pact

s an

d M

itiga

tion

Mea

sure

s Th

is s

ectio

n sh

ould

iden

tify

all f

ores

een

dire

ct e

ffect

s on

terre

stria

l flo

ra a

nd th

e po

tent

ial l

evel

of e

nviro

nmen

tal i

mpa

ct id

entif

ied.

Act

ion

plan

s fo

r pro

tect

ing

rare

or t

hrea

tene

d sp

ecie

s an

d ve

geta

tion

type

s id

entif

ied

as h

avin

g hi

gh c

onse

rvat

ion

valu

e sh

ould

be

desc

ribed

, and

an

y ob

ligat

ions

impo

sed

by S

tate

or C

omm

onw

ealth

bio

dive

rsity

pro

tect

ion

legi

slat

ion

or p

olic

y sh

ould

be

indi

cate

d.

With

rega

rd to

the

Pro

ject

are

a th

is s

ectio

n sh

ould

incl

ude:

1.

Id

entif

y ne

cess

ary

perm

its/a

utho

ritie

s re

quire

d by

the

Pro

ject

2.

D

evel

opm

ent o

f miti

gatio

n pl

ans

to a

ddre

ss a

ntic

ipat

ed im

pact

s ar

isin

g fro

m la

nd c

lear

ing

and

tem

pora

ry in

unda

tion

shou

ld b

e ou

tline

d.

3.

Pla

ns to

sup

port

and

allo

w fo

r the

mai

nten

ance

or e

nhan

cem

ent o

f hab

itat a

nd c

orrid

or fu

nctio

ns in

the

area

sho

uld

also

be

outli

ned.

4.

W

here

requ

ired,

out

line

reha

bilit

atio

n st

rate

gies

for a

ny c

ompe

nsat

ory

habi

tat a

reas

and

pro

visi

ons

for p

rote

ctin

g su

ch a

reas

.5.

W

ithin

the

stra

tegy

, des

crib

e th

e m

etho

ds to

ens

ure

rapi

d re

habi

litat

ion

of d

istu

rbed

are

as fo

llow

ing

cons

truct

ion

incl

udin

g th

e sp

ecie

s ch

osen

for r

eveg

etat

ion

whi

ch s

houl

d be

con

sist

ent w

ith th

e su

rroun

ding

ass

ocia

tions

. 6.

Id

entif

y th

e ab

ility

of i

dent

ified

sta

nds

of v

eget

atio

n to

with

stan

d an

y in

crea

sed

pres

sure

resu

lting

from

the

Pro

ject

. 7.

Th

e fu

ture

use

(suc

h as

ero

sion

con

trol o

r hab

itat)

or m

etho

d of

dis

posa

l of c

lear

ed v

eget

atio

n sh

ould

be

deta

iled.

8.

In

clus

ion

of a

wee

d m

anag

emen

t pla

n in

the

EM

P is

adv

ised

.

1.

Appe

ndix

B

2.

Sec

tion

9.6

and

App

endi

x C

3.

S

ectio

n 9.

6 4.

S

ectio

n 9.

6 5.

S

ectio

n 9.

6 6.

S

ectio

n 9.

6 7.

S

ectio

n 9.

6 8.

S

ectio

n 9.

6

3.6

Terr

estr

ial F

auna

1.

D

escr

ibe

the

terre

stria

l and

ripa

rian

faun

a oc

curri

ng in

the

area

s af

fect

ed b

y th

e P

roje

ct, n

otin

g th

e br

oad

dist

ribut

ion

patte

rns

in

1.

Sec

tion

9.4

2.

Sec

tion

9.4

Page 63: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n re

latio

n to

veg

etat

ion,

topo

grap

hy a

nd s

ubst

rate

. Ide

ntify

and

map

wild

life

corri

dors

and

hab

itat a

long

the

prop

osed

rout

e.

Pro

vide

det

ail o

n th

e ex

istin

g na

ture

con

serv

atio

n va

lues

of t

he P

roje

ct a

rea

in te

rms

of:

2.

inte

grity

of e

colo

gica

l pro

cess

es, i

nclu

ding

hab

itats

of r

are

and

thre

aten

ed s

peci

es; a

nd

3.

biol

ogic

al d

iver

sity

, inc

ludi

ng h

abita

ts o

f rar

e an

d th

reat

ened

spe

cies

. 4.

Th

e E

IS s

houl

d id

entif

y an

y ac

tions

of t

he P

roje

ct th

at re

quire

an

auth

ority

und

er th

e E

nviro

nmen

t Pro

tect

ion

and

Bio

dive

rsity

C

onse

rvat

ion

Act

199

9 an

d N

atur

e C

onse

rvat

ion

Act

199

2. T

he d

escr

iptio

n sh

ould

indi

cate

any

are

as o

f sta

te o

r reg

iona

l sig

nific

ance

id

entif

ied

in a

n ap

prov

ed b

iodi

vers

ity p

lann

ing

asse

ssm

ent (

BP

A) p

rodu

ced

by th

e E

PA

. 5.

W

hile

refe

renc

e sh

ould

be

mad

e to

bot

h S

tate

and

Com

mon

wea

lth le

gisl

atio

n, re

fere

nce

to p

olic

ies

on th

reat

ened

spe

cies

and

ec

olog

ical

com

mun

ities

incl

udin

g an

y sp

ecie

s pr

otec

ted

unde

r bila

tera

l agr

eem

ents

bet

wee

n A

ustra

lia a

nd J

apan

(JA

MB

A) a

nd

betw

een

Aust

ralia

and

Chi

na (C

AMBA

) sho

uld

also

be

incl

uded

. 6.

A

ll su

rvey

s un

derta

ken

shou

ld b

e in

acc

orda

nce

with

bes

t pra

ctic

e ad

vice

from

the

EP

A a

nd s

houl

d in

clud

e co

nsid

erat

ion

of

seas

onal

ity, p

oten

tial f

or o

ccur

renc

e of

sig

nific

ant s

peci

es, r

arity

of s

peci

es a

nd th

e se

nsiti

vity

of t

he s

peci

es to

dis

turb

ance

.7.

D

iscu

ss a

ll lik

ely

dire

ct a

nd in

dire

ct e

nviro

nmen

tal h

arm

on

faun

a co

mm

uniti

es in

terre

stria

l env

ironm

ents

in s

ensi

tive

area

s.

3.

Sec

tion

9.4

4.

Sect

ion

9.4,

App

endi

x C

5.

S

ectio

n 9.

4 6.

S

ectio

n 9.

4 7.

S

ectio

n 9.

4

Des

crip

tion

of E

nviro

nmen

tal V

alue

s Th

e te

rrest

rial a

nd ri

paria

n fa

una

occu

rring

in th

e ar

eas

affe

cted

by

the

prop

osal

sho

uld

be d

escr

ibed

, not

ing

the

broa

d di

strib

utio

n pa

ttern

s in

rela

tion

to v

eget

atio

n, to

pogr

aphy

and

sub

stra

te.

The

desc

riptio

n of

the

faun

a pr

esen

t or l

ikel

y to

be

pres

ent i

n th

e ar

ea s

houl

d in

clud

e:

1.

spec

ies

dive

rsity

(i.e

. a s

peci

es li

st) a

nd a

bund

ance

of a

nim

als,

incl

udin

g am

phib

ians

, bird

s, re

ptile

s, m

amm

als

and

bats

; 2.

ha

bita

t req

uire

men

ts a

nd s

ensi

tivity

to c

hang

es; i

nclu

ding

mov

emen

t cor

ridor

s an

d ba

rrier

s to

mov

emen

t; 3.

th

e ex

iste

nce

of fe

ral o

r exo

tic a

nim

als;

4.

ex

iste

nce

of a

ny ra

re, t

hrea

tene

d or

oth

erw

ise

note

wor

thy

spec

ies/

com

mun

ities

in th

e st

udy

area

, inc

ludi

ng d

iscu

ssio

n of

rang

e,ha

bita

t, br

eedi

ng, r

ecru

itmen

t, fe

edin

g an

d m

ovem

ent r

equi

rem

ents

, and

cur

rent

leve

l of p

rote

ctio

n (e

.g. a

ny re

quire

men

ts o

f pro

tect

ed

area

man

agem

ent p

lans

); 5.

us

e of

the

area

by

avia

n an

d te

rres

trial

faun

a;

6.

iden

tify

Glo

ssy

Bla

ck C

ocka

too

feed

ing

tree

loca

tions

, and

pro

vide

mea

sure

s to

reta

in th

ese

trees

whe

re p

ossi

ble;

7.

Th

e E

IS s

houl

d co

ntai

n re

sults

from

sur

veys

for s

peci

es li

sted

as

thre

aten

ed u

nder

the

EP

BC

Act

with

atte

ntio

n to

spe

cies

indi

cate

d in

se

ctio

n xx

like

ly to

occ

ur w

ithin

are

as to

be

perm

anen

tly a

nd p

erio

dica

lly in

unda

ted.

Sur

veys

sho

uld

be c

ondu

cted

at t

he a

ppro

pria

tetim

e of

day

and

yea

r whe

n th

e sp

ecie

s ar

e kn

own

to b

e pr

esen

t on

the

site

, so

that

iden

tific

atio

n an

d lo

catio

n of

thes

e sp

ecie

s is

op

timal

. 8.

Th

e E

IS s

houl

d in

dica

te h

ow w

ell a

ny a

ffect

ed p

opul

atio

ns a

re re

pres

ente

d an

d pr

otec

ted

else

whe

re in

the

subr

egio

n w

here

the

Pro

ject

occ

urs.

1.

Sect

ion

9.4,

App

endi

x 9.

2 2.

S

ectio

n 9.

4 3.

S

ectio

n 9.

4 4.

Se

ctio

n 9.

4, A

ppen

dix

C

5.

Sec

tion

9.4

6.

Sec

tion

9.4

7.

Sec

tion

9.4

8.

Sec

tion

9.4

Pote

ntia

l Im

pact

s an

d M

itiga

tion

Mea

sure

s Th

is s

ectio

n sh

ould

dis

cuss

all

fore

seen

dire

ct a

nd in

dire

ct e

ffect

s on

terre

stria

l fau

na.

1.

Stra

tegi

es fo

r pro

tect

ing

rare

or t

hrea

tene

d sp

ecie

s sh

ould

be

desc

ribed

, and

any

obl

igat

ions

impo

sed

by S

tate

or C

omm

onw

ealth

enda

nger

ed s

peci

es le

gisl

atio

n or

pol

icy

shou

ld b

e di

scus

sed.

2.

Im

pact

s du

ring

cons

truct

ion

and

oper

atio

n of

the

Pro

ject

sho

uld

be a

sses

sed.

Sho

rt te

rm a

nd lo

ng te

rm d

urat

ions

sho

uld

be

cons

ider

ed. M

easu

res

to m

itiga

te th

e im

pact

on

habi

tat o

r the

inhi

bitio

n of

nor

mal

mov

emen

t, pr

opag

atio

n or

feed

ing

patte

rns,

and

chan

ge to

food

cha

ins

shou

ld b

e de

scrib

ed. A

ny p

rovi

sion

for b

uffe

r zon

es a

nd m

ovem

ent c

orrid

ors

shou

ld b

e di

scus

sed.

3.

Id

entif

y an

y im

pact

the

prop

osal

may

hav

e on

terre

stria

l fau

na, r

elev

ant w

ildlif

e ha

bita

t and

oth

er fa

una

cons

erva

tion

valu

es.

4.

Iden

tify

suita

ble

area

s fo

r com

pens

ator

y ha

bita

t (in

con

sulta

tion

with

Cou

ncil

and

NR

W) t

hat w

ill m

aint

ain/

enha

nce

wild

life

habi

tat a

nd

corri

dor f

unct

ions

in th

e ar

ea.

Dev

elop

men

t of m

itiga

tion

stra

tegi

es to

pro

vide

info

rmat

ion

on th

e fo

llow

ing

shou

ld b

e in

vest

igat

ed:

1.

Sect

ion

9.6,

App

endi

x C

2.

Se

ctio

n 9.

6, A

ppen

dix

C

3.

Sec

tion

9.6

4.

Sec

tion

9.6

5.

Sec

tion

9.6,

Sec

tion

19

6.

Sec

tion

9.6,

Sec

tion

19

7.

Sec

tion

9.6,

Sec

tion

19

8.

Sec

tion

9.6,

Sec

tion

19

9.

Sec

tion

9.6,

Sec

tion

19

10.

Sec

tion

9.6,

Sec

tion

19

Page 64: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n 5.

C

onst

ruct

ion

activ

ities

that

will

min

imis

e fa

una,

incl

udin

g re

ptile

s, b

ecom

ing

trapp

ed o

r har

med

,

6.

use

of c

lear

ed v

eget

atio

n fo

r gro

und-

leve

l hab

itat;

7.

pr

ovis

ion

of fa

una

spot

ter d

urin

g cl

earin

g ac

tiviti

es;

8.

deta

il of

mea

sure

s pr

opos

ed to

min

imis

e w

ildlif

e ca

ptur

e an

d m

orta

lity

durin

g co

nstru

ctio

n; a

nd if

acc

iden

tal i

njur

ies

shou

ld o

ccur

the

met

hodo

logi

es to

ass

ess

and

hand

le in

jurie

s;

9.

faun

a m

anag

emen

t act

ions

for q

uarr

y si

tes;

and

10

. re

mov

al/re

tent

ion

of id

entif

ied

nest

ing

trees

/loca

tions

and

pro

visi

on o

f nes

t hol

low

s.

11.

Det

ails

of t

he p

ropo

sed

faun

a m

anag

emen

t and

miti

gatio

n st

rate

gies

dis

cuss

ed a

bove

sho

uld

be in

clud

ed in

the

EM

P.

12.

The

met

hod

of m

inim

isin

g th

e in

trodu

ctio

n/on

goin

g m

anag

emen

t of f

eral

ani

mal

s, a

nd o

ther

exo

tic fa

una

shou

ld b

e de

scrib

ed.

11.

Sec

tion

9.6,

Sec

tion

19

12.

Sec

tion

9.6,

Sec

tion

19

3.7

Aqu

atic

Bio

logy

A

quat

ic B

iolo

gy -

Des

crip

tion

of E

nviro

nmen

tal V

alue

s

1.

This

sec

tion

shou

ld d

iscu

ss a

quat

ic v

alue

s af

fect

ed b

y th

e pr

opos

al, n

otin

g th

e pa

ttern

s an

d di

strib

utio

n in

the

dam

impo

undm

ent,

wat

erw

ays

and

dow

nstre

am a

ssoc

iate

d fre

shw

ater

and

est

uarin

e en

viro

nmen

ts.

Th

e de

scrip

tion

of th

e aq

uatic

faun

a an

d flo

ra s

houl

d in

clud

e:

2.

fish

spec

ies,

mam

mal

s, re

ptile

s, a

mph

ibia

ns, c

rust

acea

ns a

nd a

quat

ic in

verte

brat

es o

ccur

ring

in th

e w

ater

way

s w

ithin

the

affe

cted

area

, and

dow

nstre

am e

stua

rine

envi

ronm

ent;

3.

an

y ra

re o

r thr

eate

ned

mar

ine

spec

ies

in d

owns

tream

env

ironm

ents

; 4.

co

mm

erci

al fi

sh s

peci

es w

hich

are

pre

sent

with

in th

e w

ater

way

s;

5.

othe

r fis

h sp

ecie

s an

d aq

uatic

inve

rtebr

ates

occ

urrin

g in

the

wat

erw

ays

with

in th

e P

roje

ct a

rea;

6.

di

scus

sion

of t

he s

ensi

tivity

of f

ish

habi

tats

to d

istu

rban

ce, i

nclu

ding

pot

entia

l dis

turb

ance

s an

d ch

ange

s re

sulti

ng fr

om th

e pr

opos

ed

wor

ks, e

.g. c

hang

es in

wat

er q

ualit

y (in

clud

ing

in re

gard

to c

hang

es in

wat

er le

vel a

nd fl

ow re

gim

es);

7.

aqua

tic p

lant

s;

8.

aqua

tic a

nd b

enth

ic s

ubst

rate

; 9.

ha

bita

t dow

nstre

am o

f the

pro

ject

or p

oten

tially

impa

cted

due

to c

hang

es in

floo

ding

regi

mes

on

asso

ciat

ed la

cust

rine

and

mar

ine

envi

ronm

ents

; and

10

. di

scus

sion

s of

any

crit

ical

mig

ratio

n/br

eedi

ng re

quire

men

ts fo

r nat

ive

aqua

tic s

peci

es.

11.

Dis

cuss

the

requ

irem

ent o

r oth

erw

ise

for a

fish

way

to b

e co

nstru

cted

as

part

of th

e pr

ojec

t and

the

proc

ess

for d

eter

min

ing

with

DP

I&F

if a

Wat

erw

ay B

arrie

r Wor

ks A

ppro

val i

s re

quire

d.

1.

Sec

tion

10.3

2.

S

ectio

n 10

.3

3.

Sec

tion

10.3

4.

S

ectio

n 10

.3

5.

Sec

tion

10.3

6.

S

ectio

n 10

.3

7.

Sec

tion

10.3

8.

S

ectio

n 10

.3

9.

Sec

tion

10.3

10

. Se

ctio

n 10

.5

11.

Sect

ion

10.2

Aqu

atic

Bio

logy

- Po

tent

ial I

mpa

cts

and

Miti

gatio

n M

easu

res

Pote

ntia

l Im

pact

s an

d M

itiga

tion

Mea

sure

s 1.

D

escr

ibe

any

rare

or t

hrea

tene

d sp

ecie

s, a

nd a

ny o

blig

atio

ns im

pose

d by

Sta

te o

r Com

mon

wea

lth le

gisl

atio

n or

pol

icy

or in

tern

atio

nal

treat

y ob

ligat

ions

(i.e

. JA

MB

A, C

AM

BA

). E

mph

asis

sho

uld

be g

iven

to p

oten

tial e

nviro

nmen

tal h

arm

to d

owns

tream

ben

thic

and

in

terti

dal c

omm

uniti

es, s

eagr

ass

beds

and

man

grov

es.

2.

Dis

cuss

exi

stin

g an

d po

tent

ial c

hang

es in

fish

pop

ulat

ions

as

a re

sult

of th

e pr

ojec

t.

3.

Dis

cuss

effe

cts

of c

hang

es to

flow

regi

me

dow

nstre

am, i

nclu

ding

the

effe

ct o

f cha

nges

in w

ater

qua

lity,

sal

inity

, hab

itat s

truct

ure

and

flora

.4.

D

eter

min

e ef

fect

s of

incr

ease

d le

vel i

n th

e im

poun

dmen

t and

pro

ject

ed v

aria

tions

in th

e le

vel o

f the

impo

undm

ent o

n aq

uatic

faun

a,

parti

cula

rly in

cre

eks

flow

ing

into

the

impo

undm

ent.

5.

D

eter

min

e th

e po

tent

ial i

mpa

cts

on c

omm

erci

al a

nd re

crea

tiona

l fis

herie

s, a

ddre

ssin

g is

sues

suc

h as

acc

ess,

cha

nges

to s

tock

s

1.

Sec

tion

10.2

2.

S

ectio

n 10

.4

3.

Sec

tion

10.4

4.

S

ectio

n 10

.4

5.

Sec

tion

10.4

Page 65: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n (s

peci

es, p

opul

atio

n nu

mbe

rs a

nd s

truct

ure,

recr

uitm

ent t

o fis

hery

), an

d an

y po

tent

ial f

or fi

sh k

ills a

nd m

itiga

tion

stra

tegi

es.

3.8

Cul

tura

l Her

itage

C

ultu

ral H

erita

ge -

Des

crip

tion

of E

nviro

nmen

tal V

alue

s1.

D

escr

ibe

the

exis

ting

cultu

ral h

erita

ge v

alue

s th

at m

ay b

e af

fect

ed b

y th

e P

roje

ct a

ctiv

ities

. 2.

A

cultu

ral h

erita

ge s

tudy

if re

quire

d, w

ill d

escr

ibe

indi

geno

us a

nd n

on-in

dige

nous

cul

tura

l her

itage

site

s an

d pl

aces

, and

thei

r val

ues.

2.

S

ectio

n 17

.1, 1

7.2

3.

Sec

tion

17.1

C

ultu

ral H

erita

ge -

Pote

ntia

l Im

pact

s an

d M

itiga

tion

Mea

sure

s1.

Th

e en

viro

nmen

tal h

arm

to c

ultu

ral h

erita

ge v

alue

s in

the

vici

nity

of t

he p

roje

ct s

houl

d be

man

aged

und

er a

cul

tura

l her

itage

man

agem

ent p

lan

(CH

MP

) dev

elop

ed s

peci

fical

ly fo

r the

pro

ject

.

1.

Sec

tion

17.1

3.

9 A

ir En

viro

nmen

t A

ir En

viro

nmen

t - D

escr

iptio

n of

Env

ironm

enta

l Val

ues

1.

This

sec

tion

shou

ld d

escr

ibe

the

exis

ting

air e

nviro

nmen

t, w

hich

may

be

affe

cted

by

the

prop

osal

in th

e co

ntex

t of e

nviro

nmen

tal

valu

es a

s de

fined

by

the

Env

ironm

enta

l Pro

tect

ion

Act

199

4 an

d E

nviro

nmen

tal P

rote

ctio

n (A

ir) P

olic

y. I

t sho

uld

also

dis

cuss

air

qual

ity g

oals

con

tain

ed in

the

Nat

iona

l Env

ironm

ent P

rote

ctio

n M

easu

re (N

EP

M) A

mbi

ent A

ir Q

ualit

y 19

98.

2.

Am

bien

t air

qual

ity c

ondi

tions

in te

rms

of p

artic

ulat

e m

atte

r sho

uld

be d

escr

ibed

for a

ny s

ensi

tive

site

s (re

side

nces

) in

prox

imity

to th

e da

m a

nd a

ssoc

iate

d in

frast

ruct

ure

deve

lopm

ent a

reas

, inc

ludi

ng a

ny b

asel

ine

mon

itorin

g re

sults

.

1.

Sec

tion

11.4

2.

S

ectio

n 11

.4

Air

Envi

ronm

ent -

Pot

entia

l Im

pact

s an

d M

itiga

tion

Mea

sure

s Th

e fo

llow

ing

air q

ualit

y is

sues

sho

uld

be c

onsi

dere

d:

1.

Impa

cts

of d

ust g

ener

atio

n fro

m c

onst

ruct

ion

activ

ities

, esp

ecia

lly fr

om b

last

ing

activ

ities

ass

ocia

ted

with

qua

rries

and

in c

lose

pr

oxim

ity to

resi

denc

es;

2.

Pre

dict

ed c

hang

es to

exi

stin

g ai

r qua

lity

at s

ensi

tive

rece

ptor

s an

d du

st g

ener

atio

n du

ring

cons

truct

ion;

3.

D

iscu

ss p

oten

tial a

re q

ualit

y im

pact

s fro

m v

ehic

le e

mis

sion

s an

d an

y ot

her s

ourc

es; a

nd

4.

Prop

ose

any

amel

iora

tion

or m

itiga

tion

mea

sure

s fo

r eac

h id

entif

ied

impa

ct re

latin

g to

dus

t gen

erat

ion,

veh

icle

and

equ

ipm

ent

emis

sion

s an

d ga

seou

s em

issi

ons

1.

Sec

tion

11.5

2.

S

ectio

n 11

.6

3.

Sec

tion

11.6

4.

S

ectio

n 11

.5, 1

9

3.10

G

reen

hous

e G

as Im

pact

s Th

is s

ectio

n of

the

EIS

sho

uld:

1.

P

rovi

de a

n in

vent

ory

of p

roje

cted

ann

ual e

mis

sion

s du

ring

cons

truct

ion

for e

ach

rele

vant

gre

enho

use

gas,

with

tota

l em

issi

ons

expr

esse

d in

‘CO

2 eq

uiva

lent

’ ter

ms;

2.

B

riefly

des

crib

e m

etho

d(s)

by

whi

ch e

stim

ates

wer

e m

ade.

3.

P

rovi

de a

n as

sess

men

t of t

he ty

pe a

nd v

olum

e of

gre

enho

use

gase

s em

itted

by

the

Pro

ject

dur

ing

cons

truct

ion

and

oper

atio

n an

d th

e m

easu

res

take

n to

redu

ce e

mis

sion

s in

line

with

nat

iona

l and

sta

te a

bate

men

t pol

icie

s an

d gu

idel

ines

.

1.

Sec

tion

11.7

2.

S

ectio

n 11

.7

3.

Sec

tion

11.7

3.11

C

limat

e C

hang

e A

dapt

atio

n Th

e E

IS s

houl

d pr

ovid

e an

ass

essm

ent o

f the

Pro

ject

’s v

ulne

rabi

litie

s to

clim

ate

chan

ge a

nd d

escr

ibe

poss

ible

ada

ptat

ion

stra

tegi

es fo

r the

ac

tivity

.

1.

Sec

tion

7.3

3.12

N

oise

and

Vib

ratio

n N

oise

and

Vib

ratio

n - D

escr

iptio

n of

Env

ironm

enta

l Val

ues

1.

The

iden

tific

atio

n of

pot

entia

l noi

se s

ourc

es fr

om th

e co

nduc

t of t

he p

roje

ct a

re to

be

iden

tifie

d.

2.

Pro

ject

act

iviti

es, e

spec

ially

in re

gard

s to

qua

rry

oper

atio

n co

uld

adve

rsel

y im

pact

on

nois

e an

d vi

brat

ion

at p

roxi

mal

sen

sitiv

e1.

S

ectio

n 12

.2

2.

Sec

tion

12.3

Page 66: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n re

cept

ors

and

base

line

mon

itorin

g sh

ould

be

unde

rtake

n at

a s

elec

tion

of s

ensi

tive

site

s po

tent

ially

affe

cted

by

the

prop

osal

. 3.

Th

e lo

catio

ns o

f sen

sitiv

e si

tes

shou

ld b

e id

entif

ied

on a

map

at a

sui

tabl

e sc

ale.

The

resu

lts o

f any

bas

elin

e m

onito

ring

of n

oise

and

vi

brat

ion

in th

e pr

opos

ed v

icin

ity o

f the

pro

posa

l sho

uld

be d

escr

ibed

. 4.

C

omm

ent s

houl

d be

pro

vide

d on

any

cur

rent

act

iviti

es n

ear t

he p

ropo

sal a

rea

that

may

cau

se a

bac

kgro

und

leve

l of g

roun

d vi

brat

ion

(for e

xam

ple:

maj

or ro

ads,

qua

rryi

ng a

ctiv

ities

, etc

.).

3.

Sec

tion

12.3

4.

S

ectio

n 12

.2

Noi

se a

nd V

ibra

tion

- Pot

entia

l Im

pact

s an

d M

itiga

tion

Mea

sure

s1.

Th

e po

tent

ial e

nviro

nmen

tal h

arm

of n

oise

at a

ll po

tent

ially

sen

sitiv

e pl

aces

, in

parti

cula

r any

pla

ces

of w

ork

or re

side

nce,

sho

uld

be

quan

tifie

d an

d co

mpa

red

with

obj

ectiv

es, s

tand

ards

to b

e ac

hiev

ed a

nd m

easu

rabl

e in

dica

tors

. 2.

P

ropo

sals

to m

inim

ise

or e

limin

ate

thes

e ef

fect

s sh

ould

be

prov

ided

, inc

ludi

ng d

etai

ls o

f any

scr

eeni

ng, l

inin

g, e

nclo

sing

or m

ound

ing

of c

onst

ruct

ion

site

s, o

r tim

ing

sche

dule

s fo

r con

stru

ctio

n th

at w

ould

min

imis

e en

viro

nmen

tal h

arm

and

env

ironm

enta

l nui

sanc

e fro

mno

ise

and

vibr

atio

n.

3.

Com

mun

ity c

onsu

ltatio

n pr

oced

ures

to b

e em

ploy

ed to

not

ify re

side

nts

of b

last

ing

even

ts s

houl

d be

det

aile

d.

4.

Ass

essm

ent s

houl

d be

mad

e of

the

pote

ntia

l em

issi

on o

f low

-freq

uenc

y no

ise

(noi

se w

ith c

ompo

nent

s be

low

200

Hz)

from

maj

or

cons

truct

ion

equi

pmen

t. If

nece

ssar

y, m

easu

res

shou

ld b

e de

scrib

ed fo

r red

ucin

g th

e in

tens

ity o

f the

se c

ompo

nent

s.

5.

A d

iscu

ssio

n sh

ould

be

supp

lied

on b

last

ing

whi

ch m

ight

cau

se g

roun

d vi

brat

ion

or fl

y ro

ck o

n, o

r adj

acen

t to,

the

site

. Th

e m

agni

tude

, du

ratio

n an

d fre

quen

cy o

f any

vib

ratio

n sh

ould

be

indi

cate

d.

6.

Mea

sure

s to

pre

vent

or m

inim

ise

envi

ronm

enta

l nui

sanc

e an

d ha

rm s

houl

d be

iden

tifie

d.

7.

Ass

essm

ent s

houl

d be

mad

e of

the

pote

ntia

l im

pact

s (in

clud

ing

com

plia

nce

with

rele

vant

legi

slat

ion)

of b

last

ing

requ

ired,

incl

udin

gpo

tent

ial b

uffe

rs to

min

imis

e or

elim

inat

e th

ese

effe

cts.

Bla

stin

g no

ise

and

vibr

atio

n lim

its a

re p

rovi

ded

in s

ectio

n 61

of t

heE

nviro

nmen

tal P

rote

ctio

n R

egul

atio

n 19

98.

Ref

eren

ce s

houl

d al

so b

e m

ade

to th

e E

PA

Gui

delin

e: N

oise

and

Vib

ratio

n fro

m B

last

ing.

1.

Sec

tion

12.6

, 12.

7 2.

S

ectio

n 12

.10

3.

Sec

tion

12.1

0 4.

S

ectio

n 12

.2

5.

Sec

tion

12.7

6.

S

ectio

n 12

.10

7.

Sec

tion

12.7

3.13

H

azar

d, R

isk

Safe

ty

Haz

ard

Ana

lysi

s Th

is s

ectio

n of

the

EIS

sho

uld

desc

ribe

the

pote

ntia

l haz

ards

and

risk

s th

at m

ay b

e as

soci

ated

with

the

Pro

ject

. A

pre

limin

ary

haza

rd

anal

ysis

sho

uld

be c

ondu

cted

for t

he P

roje

ct.

The

prel

imin

ary

haza

rd a

naly

sis

shou

ld in

corp

orat

e po

ssib

le h

azar

ds, a

ccid

ents

, and

abno

rmal

eve

nts

that

may

aris

e fo

r the

Pro

ject

, bot

h du

ring

cons

truct

ion

and

in o

pera

tion.

1.

Sec

tion

14.2

, 14.

3

Ris

k A

sses

smen

t 1.

A

pre

limin

ary

risk

asse

ssm

ent f

or a

ll co

mpo

nent

s of

the

Pro

ject

(inc

ludi

ng, b

ut n

ot li

mite

d to

, dam

wal

l, qu

arrie

s, c

lear

ing,

dow

nstre

am

flood

ing)

sha

ll be

und

erta

ken

as p

art o

f the

EIS

pro

cess

in a

ccor

danc

e w

ith a

ppro

pria

te p

arts

of A

NC

OLD

and

Que

ensl

and

Dam

Saf

ety

Reg

ulat

or g

uide

lines

and

AS

/NZS

Ris

k M

anag

emen

t Sta

ndar

d 43

60:1

999.

2.

Th

e E

IS s

houl

d de

al c

ompr

ehen

sive

ly w

ith o

n-si

te ri

sks.

Ext

erna

l ris

ks to

the

Pro

ject

sho

uld

also

be

cons

ider

ed. E

xter

nal r

isks

from

na

tura

l haz

ards

cou

ld b

e de

term

ined

on

the

basi

s of

AS

/NZS

Ris

k M

anag

emen

t Sta

ndar

d 43

60:1

999.

The

EIS

sho

uld

indi

cate

that

the

proj

ect w

ill c

ompl

y w

ith re

leva

nt ri

sk a

sses

smen

t and

man

agem

ent g

uide

lines

. 3.

Th

e st

udy

shou

ld a

sses

s ris

ks d

urin

g th

e co

nstru

ctio

n, d

ecom

mis

sion

ing

of te

mpo

rary

con

stru

ctio

n w

orks

and

ope

ratio

nal p

hase

sas

soci

ated

with

the

Pro

ject

. The

se ri

sks

shou

ld b

e as

sess

ed in

qua

ntita

tive

term

s w

here

pos

sibl

e.

4.

The

anal

ysis

sho

uld

exam

ine

the

likel

ihoo

d of

thes

e co

nseq

uenc

es b

eing

exp

erie

nced

, bot

h in

divi

dual

ly a

nd c

olle

ctiv

ely.

Qua

ntita

tive

leve

ls o

f ris

ks a

nd ri

sk c

onto

urs

shou

ld b

e pr

esen

ted

from

the

abov

e an

alys

is.

5.

Det

ails

sho

uld

be p

rovi

ded

on th

e sa

fegu

ards

that

wou

ld b

e em

ploy

ed o

r ins

talle

d to

redu

ce th

e lik

elih

ood

and

seve

rity

of h

azar

ds,

cons

eque

nces

and

risk

s to

per

sons

, fau

na a

nd e

nviro

nmen

tally

sen

sitiv

e si

tes

with

in a

nd a

djac

ent t

o th

e P

roje

ct a

rea.

The

info

rmat

ion

shou

ld in

clud

e th

e re

duce

d le

vel o

f ris

k th

at w

ould

be

expe

rienc

ed w

ith th

ese

safe

guar

ds in

pla

ce.

6.

A c

ompa

rison

of a

sses

sed

and

miti

gate

d ris

ks w

ith a

ccep

tabl

e ris

k cr

iteria

for l

and

uses

adj

acen

t to

the

Pro

ject

are

a sh

ould

be

pres

ente

d.

1.

Sec

tion

14.5

, 14.

6 2.

S

ectio

n ??

3.

S

ectio

n 14

.3

4.

Sec

tion

14.6

5.

S

ectio

n 14

.7

6.

Sec

tion

??

Page 67: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n

3.14

Em

erge

ncy

Man

agem

ent P

lan

An

outli

ne o

f the

pro

pose

d em

erge

ncy

man

agem

ent p

roce

dure

s is

to b

e pr

ovid

ed fo

r the

rang

e of

situ

atio

ns id

entif

ied

in th

e ab

ove

risk

asse

ssm

ent a

s pr

ovid

ing

mea

sura

ble

risks

. An

Em

erge

ncy

Man

agem

ent P

lan

is to

be

deve

lope

d in

con

sulta

tion

with

the

rele

vant

em

erge

ncy

serv

ices

and

incl

uded

in th

e E

nviro

nmen

tal M

anag

emen

t Pla

n.

1.

Sec

tion

19.2

3.15

W

aste

Man

agem

ent

1.

Hav

ing

rega

rd fo

r bes

t pra

ctic

e w

aste

man

agem

ent s

trate

gies

, the

Env

ironm

enta

l Pro

tect

ion

(Was

te M

anag

emen

t) P

olic

y 20

00 (E

PP

Was

te) a

nd th

e E

nviro

nmen

tal P

rote

ctio

n (W

aste

Man

agem

ent)

Reg

ulat

ion

2000

(EP

R W

aste

), th

e P

roje

ct’s

for w

aste

avo

idan

ce,

reus

e, re

cycl

ing,

trea

tmen

t and

dis

posa

l sho

uld

be d

escr

ibed

.

1.

Sec

tion

15

3.16

Tr

ansp

ort a

nd R

oads

Tr

ansp

ort M

etho

ds a

nd R

oute

s Th

e E

IS s

houl

d de

scrib

e th

e ex

istin

g ro

ad n

etw

ork

and

inte

rsec

tions

of t

he s

urro

undi

ng re

gion

spe

cify

ing

curre

nt tr

affic

vol

umes

, inc

ludi

ng,

but n

ot li

mite

d to

, the

Gol

d C

oast

-Spr

ingb

rook

, Ner

ang-

Mur

will

umba

h an

d N

eran

g-B

eaud

eser

t roa

d ne

twor

ks.

The

EIS

sho

uld

also

de

scrib

e an

d as

sess

the

stab

ility

and

dur

abili

ty o

f exi

stin

g br

idge

s/cu

lver

ts a

nd e

mba

nkm

ents

. Th

e E

IS s

houl

d di

scus

s tra

nspo

rt m

etho

ds

and

rout

es fo

r del

iver

ing

cons

truct

ion

and

oper

atio

nal e

quip

men

t and

mat

eria

ls, o

ther

nec

essa

ry g

oods

and

con

sum

able

s an

d w

orkf

orce

tra

nspo

rtatio

n. In

form

atio

n sh

ould

incl

ude:

2.

Th

e lik

ely

impa

cts

and

miti

gatio

n st

rate

gies

of i

ncre

ased

traf

fic o

n lo

cal a

nd re

gion

al ro

ad n

etw

orks

(with

app

ropr

iate

dire

ctio

nal

dist

ribut

ions

) 3.

Fi

ndin

gs o

f stu

dies

and

ass

essm

ents

sho

uld

be in

corp

orat

ed in

to a

road

man

agem

ent s

trate

gy in

clud

ing

Tran

spor

t and

Tra

ffic

Man

agem

ent P

lans

.

4.

The

EIS

sho

uld

deta

il an

y pr

opos

als

to p

rovi

de c

entra

lised

sta

ff tra

nspo

rt to

site

and

incl

ude

the

prov

isio

n th

at re

leva

nt a

utho

ritie

s su

ch

as th

e Q

ueen

slan

d P

olic

e S

ervi

ce w

ill b

e ad

vise

d in

adv

ance

and

incl

uded

in c

onsu

ltatio

n on

sta

ff tra

nsit

met

hods

and

pro

cedu

res.

5.

Ref

eren

ce s

houl

d be

mad

e to

any

rela

tions

hip

betw

een

Pro

ject

road

wor

ks a

nd w

orks

pro

pose

d in

the

curre

nt R

oad

Impl

emen

tatio

nP

rogr

am(s

) of M

R. R

oad

infra

stru

ctur

e im

pact

s sh

ould

be

desc

ribed

and

ass

esse

d ac

cord

ing

to M

R’s

Gui

delin

es fo

r Ass

essm

ent o

f R

oad

Impa

cts

of D

evel

opm

ent (

2006

). R

efer

ence

sho

uld

be m

ade

to o

ther

MR

pla

nnin

g do

cum

ents

. 6.

Th

e E

IS s

houl

d de

scrib

e th

e ex

istin

g pu

blic

tran

spor

t net

wor

k, in

clud

ing

scho

ol b

us s

ervi

ces,

and

dis

cuss

the

likel

y im

pact

s an

d m

itiga

tion

stra

tegi

es o

f inc

reas

ed tr

affic

on

the

safe

pro

visi

on o

f sch

ool b

us s

ervi

ces

in th

e pr

ojec

t are

a.

7.

An

anal

ysis

of i

mpa

cts

on tr

affic

, roa

d ne

twor

ks a

nd ro

ad u

sers

and

sug

gest

ed m

itiga

tion

stra

tegi

es if

con

stru

ctio

n ac

tiviti

es a

nd

quar

ryin

g ne

eds

to b

e un

derta

ken

offs

ite s

houl

d be

indi

cate

d.

1.

Sec

tion

13.6

2.

S

ectio

n 13

.6

3.

Sec

tion

13

4.

Sec

tion

13

5.

Sec

tion

13.4

6.

S

ectio

n 13

.6

Roa

d R

eloc

atio

ns: P

oten

tial I

mpa

cts

and

Miti

gatio

n M

easu

res

Ass

essm

ent o

f im

pact

s fo

r the

ent

ire a

rea

impa

cted

by

the

Pro

ject

sho

uld

disc

uss

the

follo

win

g:

1.

The

likel

y im

pact

s an

d m

itiga

tion

stra

tegi

es o

f new

road

s or

road

real

ignm

ents

that

are

requ

ired

as a

resu

lt of

the

Pro

ject

, inc

ludi

ng

impa

cts

on a

ll st

akeh

olde

rs a

long

the

rout

es. I

nclu

ding

with

in th

is d

iscu

ssio

n sh

ould

be:

2.

R

oad

real

ignm

ent r

equi

rem

ents

, cle

arly

indi

cate

d on

map

s w

ith e

xist

ing

infra

stru

ctur

e an

d pl

anne

d re

alig

nmen

ts in

dica

ted;

3.

A

ssoc

iate

d la

nd re

quire

men

ts to

be

disc

usse

d in

det

ail i

n S

ectio

n 3.

1.2.

2 –

Land

Use

and

Ten

ure;

4.

A

n as

sess

men

t of t

he p

oten

tial t

o is

olat

e co

mm

uniti

es (s

uch

as S

prin

gbro

ok) t

o be

pro

vide

d;

5.

An

asse

ssm

ent o

f the

pot

entia

l to

disr

upt c

omm

unity

acc

ess

to a

ny h

ealth

, edu

catio

n or

gov

ernm

ent s

ervi

ces,

and

any

rele

vant

faci

litie

s su

ch a

s sh

ops,

chu

rche

s, c

lubs

as

a re

sult

of th

e re

alig

nmen

ts;

6.

How

eac

h of

thes

e is

sues

will

be

man

aged

and

dis

rupt

ion

min

imis

ed s

houl

d be

dis

cuss

ed.

1.

Sec

tion

13.6

2.

S

ectio

n 13

.6

3.

Sec

tion

13.6

4.

S

ectio

n 13

.4

5.

Sec

tion

13.4

6.

S

ectio

n 13

.6

4 So

cio-

econ

omic

Env

ironm

ent

Page 68: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n

4.1

Soci

al V

alue

s So

cial

Val

ues

- Des

crip

tion

of E

nviro

nmen

tal V

alue

sTh

is s

ectio

n de

scrib

es th

e ex

istin

g so

cial

val

ues

that

may

be

affe

cted

by

the

prop

osal

. Th

e so

cial

am

enity

and

use

of t

he p

ropo

sal a

rea

for r

ecre

atio

nal,

fishi

ng, s

porti

ng, e

duca

tiona

l or r

esid

entia

l pur

pose

s sh

ould

be

desc

ribed

. 1.

S

ectio

n 16

.1

Soci

al V

alue

s - P

oten

tial I

mpa

cts

and

Miti

gatio

n M

easu

res

The

soci

al im

pact

ass

essm

ent o

f the

pro

ject

sho

uld

cons

ider

the

info

rmat

ion

gath

ered

in th

e co

mm

unity

con

sulta

tion

prog

ram

and

the

anal

ysis

of t

he e

xist

ing

soci

o-ec

onom

ic e

nviro

nmen

t, an

d de

scrib

e th

e pr

ojec

t’s im

pact

, bot

h be

nefic

ial a

nd a

dver

se, o

n th

e lo

cal

com

mun

ity.

The

impa

cts

of th

e pr

ojec

t on

loca

l res

iden

ts, c

omm

unity

ser

vice

s an

d re

crea

tiona

l act

iviti

es a

re to

be

anal

ysed

and

brie

fly

disc

usse

d. T

he n

atur

e an

d ex

tent

of t

he c

omm

unity

con

sulta

tion

prog

ram

are

to b

e de

scrib

ed a

nd a

sum

mar

y of

the

resu

lts in

corp

orat

ed in

th

e E

IS.

The

EIS

sho

uld

addr

ess

the

follo

win

g m

atte

rs:

1.

Com

mun

ity

2.

Wor

kfor

ce

3.

Floo

d M

itiga

tion

For i

dent

ified

impa

cts

to s

ocia

l val

ues,

sug

gest

miti

gatio

n an

d en

hanc

emen

t stra

tegi

es a

nd fa

cilit

ate

initi

al n

egot

iatio

ns to

war

ds a

ccep

tanc

e of

thes

e st

rate

gies

. P

ract

ical

mon

itorin

g re

gim

es s

houl

d al

so b

e re

com

men

ded.

1.

Sec

tion

16.2

4.2

Econ

omy

This

sec

tion

desc

ribes

the

exis

ting

econ

omic

env

ironm

ent t

hat m

ay b

e af

fect

ed b

y th

e pr

ojec

t. T

he e

cono

mic

ana

lysi

s co

mpo

nent

of t

he

EIS

sho

uld

cons

ider

: 1.

th

e si

gnifi

canc

e of

this

Pro

ject

on

the

loca

l and

regi

onal

eco

nom

ic c

onte

xt;

2.

the

antic

ipat

ed in

crea

sed

supp

ly a

nd re

liabi

lity

of w

ater

with

in th

e G

old

Coa

st re

gion

and

flow

on

effe

cts;

3.

th

e co

st to

all

leve

ls o

f gov

ernm

ent o

f any

add

ition

al in

frast

ruct

ure

prov

isio

n;

4.

an o

utlin

e of

the

econ

omic

flow

s of

the

proj

ect e

xpen

ditu

re o

n th

e re

gion

al a

nd s

tate

eco

nom

ies;

5.

an

y ne

gativ

e ec

onom

ic im

pact

on

affe

cted

loca

l ind

ivid

uals

or b

usin

esse

s fro

m th

e co

nstru

ctio

n of

the

proj

ect;

6.

any

nega

tive

econ

omic

impa

ct o

n th

e pr

ojec

t via

bilit

y du

e to

the

cost

of t

he lo

ng-te

rm p

rovi

sion

of f

ish

pass

age.

Whe

re fi

sh p

assa

ge is

a

requ

irem

ent,

it w

ill b

e fo

r the

life

of t

he s

truct

ure

of th

e da

m (a

s op

pose

d to

the

com

mer

cial

life

of t

he d

am).

1.

Sec

tion

16.3

2.

S

ectio

n 16

.3

3.

Sec

tion

16.3

4.

S

ectio

n 16

.3

5.

Sec

tion

16.3

6.

S

ectio

n 16

.3

4.3

Empl

oym

ent a

nd tr

aini

ng

This

sec

tion

shou

ld p

rovi

de d

etai

ls o

n th

e em

ploy

men

t req

uire

men

ts a

nd s

kills

bas

e of

the

requ

ired

wor

kfor

ce fo

r bot

h th

e co

nstru

ctio

n an

d op

erat

ions

pha

ses

of th

e pr

ojec

t. Th

e re

port

shou

ld a

lso

desc

ribe

the

depl

oym

ent s

trate

gies

pro

pose

d fo

r the

wor

kfor

ce o

ver t

heco

nstru

ctio

n pe

riod.

1.

In

form

atio

n sh

ould

be

prov

ided

on

the

acco

mm

odat

ion

requ

irem

ents

for t

he w

orkf

orce

, (if

any)

, and

if a

pplic

able

, of t

heir

fam

ily

mem

bers

.2.

In

par

ticul

ar, w

ith re

gard

s to

ant

icip

ated

wor

kfor

ce im

pact

s, th

e fo

llow

ing

shou

ld b

e ad

dres

sed:

3.

es

timat

es s

houl

d be

pro

vide

d of

:

a)

cons

truct

ion

wor

kfor

ce -

i.e. t

he n

umbe

r of w

orke

rs to

be

empl

oyed

on-

site

dur

ing

the

cons

truct

ion

activ

ities

, inc

ludi

ng th

enu

mbe

r of s

ub-c

ontra

ctor

s an

d an

out

line

of th

e re

crui

tmen

t sch

edul

e an

d po

licie

s fo

r the

recr

uitm

ent o

f wor

kers

b)

oper

atio

nal p

hase

wor

kfor

ce -

i.e. t

he n

umbe

r of a

ny a

dditi

onal

wor

kers

to b

e em

ploy

ed o

n-si

te d

urin

g op

erat

iona

l ac

tiviti

es.

4.

On

the

mat

ter o

f wor

kfor

ce tr

aini

ng, t

he E

IS s

houl

d de

scrib

e th

e pr

ojec

t’s re

latio

n an

d us

e of

stra

tegi

es re

spon

ding

to G

over

nmen

t

1.

Sec

tion

16.4

2.

S

ectio

n 16

.4

3.

Sec

tion

16.4

4.

S

ectio

n 16

.4

Page 69: Hinze Dam Stage 3 Project Terms of Reference for an ...eisdocs.dsdip.qld.gov.au/Hinze Dam Stage 3/EIS/Appendices/a-tor.pdf · ii Hinze Dam Stage 3 Draft Terms of Reference for an

Term

s of

Ref

eren

ce S

ectio

n R

elev

ant E

IS S

ectio

n P

olic

y re

latin

g to

:

The

leve

l of t

rain

ing

prov

ided

for c

onst

ruct

ion

cont

ract

s on

Que

ensl

and

Gov

ernm

ent b

uild

ing

and

cons

truct

ion

cont

ract

s

Indi

geno

us e

mpl

oym

ent o

ppor

tuni

ties

5 En

viro

nmen

tal M

anag

emen

t Pla

n A

n E

nviro

nmen

tal M

anag

emen

t Pla

n (E

MP

) sho

uld

be p

rovi

ded

deta

iling

the

mea

sure

s to

be

adop

ted

to a

ddre

ss id

entif

ied

impa

cts

durin

gth

e co

nstru

ctio

n, o

pera

tion

and

mai

nten

ance

pha

ses

of th

e P

roje

ct.

1.

Sec

tion

19