Hinkley Point C our approach to Health and Safety · • Occupational Health team on site •...

28
Hinkley Point C our approach to Health and Safety Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED 1 Iain Graham Head of Health & Safety

Transcript of Hinkley Point C our approach to Health and Safety · • Occupational Health team on site •...

Page 1: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Hinkley Point C – our approach to

Health and Safety

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED1

Iain Graham Head of Health & Safety

Page 2: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Where are we…?

2

Hinkley Point

EDF Energy’s Nuclear New Build Projects © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 3: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

3 Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 4: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

4

What we want to build

• Areva/EDF evolutionary design

• Pressurised water reactor

(like Sizewell B)

• 2 x 1630 MW (electrical)

• Each can supply around 2.5m homes

• Uses 17% less uranium and produces less waste

• Under construction in France

• c. 900 operating staff

• 60 year operating life

Cross section of single UK

EPR (illustrative layout)

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 5: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Title of Presentation © 1 January 2014 EDF Energy plc. All rights

Reserved5

Model of nuclear

reactor

EDF Energy’s Nuclear New Build Projects © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED21

Page 6: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Hinkley Point C – Enabling Construction

Europe’s 2nd biggest hotel development

On-site accommodation for

c.500 workers

Combwich Wharf Bridgwater highway

schemes

Off-site accommodation for

c.1,000 workers

2 freight management,

4 park and ride facilities

• An additional £20 million investment into local road

infrastructure. The majority already completed.

• Temporary Jetty on-site – able to deliver 80% of the

aggregates required for construction

6 Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 7: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

7

The Journey So Far….Hinkley Point C will be the first nuclear power station to be built in the UK in a generation.

2006 2009

JAN 2006Government policy proposes

nuclear as a significant part of our

future energy mix.

OCT 2008Early engagement begins with

local residents.

2012

NOV 2009Formal consultation begins with

local communities over 2 years.

2013 2014 2016

DEC 2012UK EPR reactor approved under

GDA.

MAR 2013Secretary of State approves

construction of HPC.

OCT 2014European Commission

approves agreement between

EDF Group and UK

Government.

OCT 2015EDF and CGN agree joint

investment in HPC.

SEP 2016Final approval granted

by UK Govt.

MAR 2017First Nuclear Safety Concrete used

on-site

2017

SEPT 2017East Office Welfare

Complex Open

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

2018

DEC 2017Cooling Water Pipe

installation Starts

FEB 2018Pre-stressing gallery

for Unit 1

Page 8: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Hinkley Point C Indicative Construction Timeline

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 9: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

9

Milestones Achieved So Far….

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 10: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

March 2017 - The First Nuclear Safety Concrete pour at Hinkley Point C

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 11: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

May 2017 - North West area of site with heavy haul road and material crushing operations in the foreground

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 12: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

June 2017 - Inspection of the rock formation before blinding concrete is applied

Intro to HPC © EDF Energy plc 18 Jan 2018 All rights

reserved NOT PROTECTIVELY MARKED 12

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 13: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

July 2017 - Work continues on the jetty with girders being installed to bridge the crosshead saddles

13

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 14: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

The jetty when complete will allow all aggregate to be delivered by sea

14Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 15: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

October 2017 - Work continues on the HPC on-site accommodation campus

15

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 16: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

November 2017 - Progress of Unit 1 Nuclear Island pre-stressing gallery trench construction

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 17: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

December 2017 – The sixth and final project goal of 2017 was achieved with the start of the installation of the CRF cooling

water pipes.

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 18: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

December 2017 - Two sections of the CRF pipes are welded into couples before they are moved to the platform

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 19: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

January 2018- Enabling team celebrating completion and handover of the foundations for Unit 1 Nuclear Island

Page 20: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Comparison of Safety Performance

CHSEC Presentation Aug 2017| NOT PROTECTIVELY MARKED | ©15 Aug 2017 EDF Energy plc. All rights Reserved.20

Notes

• Rates are calculated in accordance with RIDDOR 1995 definitions (ie injuries resulting in more than 3 days absence from work.

• Rates are rolling twelve month averages.

• HPC trace starts at award of FID. (October 2016)

• Other projects’ AFR rates are shown at same relative time on project schedule.

• For comparison , Tideway AFR-3 for March 2018 = 0.10; HPC AFR-3 for March 2018 = 0.05.

Page 21: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Our Safety Challenges

Intro to HPC © EDF Energy plc 18 Jan 2018 All rights reserved NOT PROTECTIVELY MARKED 21

• Contractors

• Supervision

• Procedural Compliance

• Culture

Page 22: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Our Safety Challenges - Contractors

Intro to HPC © EDF Energy plc 18 Jan 2018 All rights reserved NOT PROTECTIVELY MARKED 22

• Selection and evaluation

• Early Contractor Involvement

• Clearly setting expectations

• Collaborative Working

• Developing Common Standards

Page 23: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Our Safety Challenges - Supervision

Intro to HPC © EDF Energy plc 18 Jan 2018 All rights reserved NOT PROTECTIVELY MARKED 23

• Formal training through Institute of Learning and Management

• Dedicated supervisor community

• Coaching in the field

• Supervisor forums

Page 24: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Our Safety Challenges - Procedural Compliance

Intro to HPC © EDF Energy plc 18 Jan 2018 All rights reserved NOT PROTECTIVELY MARKED 24

• Focus on quality

• Developed ‘right first time’ metrics

• Focused training sessions and authorisations

Page 25: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Our Safety Challenges - Culture

Intro to HPC © EDF Energy plc 18 Jan 2018 All rights reserved NOT PROTECTIVELY MARKED 25

• Behavioural Safety training

• Leaders lanyard programme

• Recognition

• Engagement

Page 26: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Health & Well-being

Intro to HPC © EDF Energy plc 18 Jan 2018 All rights reserved NOT PROTECTIVELY MARKED 26

• Occupational Health team on site

• Pre-employment questionnaires and safety critical medicals

• Health risk management – support to contractors

• Proactive health and well-being initiatives

• Liaison with local healthcare trust

• Itinerant workers with unhealthy lifestyles…

• Focus on Mental Health

Page 27: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Intro to HPC © EDF Energy plc 18 Jan 2018 All rights reserved

NOT PROTECTIVELY MARKED 27

Introduction to HPC © February 2018 EDF Energy plc. All rights Reserved NOT PROTECTIVELY MARKED

Page 28: Hinkley Point C our approach to Health and Safety · • Occupational Health team on site • Pre-employment questionnaires and safety critical medicals • Health risk management

Thank you

Intro to HPC © EDF Energy plc 18 Jan 2018 All rights reserved NOT PROTECTIVELY MARKED