Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for...

97
1 | Page Himachal Pradesh State Roads Transformation Program (Funded by World Bank) Dadhol-Ladrour (Km 0.00 to KM 13.500) Environment and Social Management Plan (Draft) HIMACHAL PRADESH ROAD & OTHER INFRASTRUCTURE DEVELOPMENT CORPORATION LTD. (Government of Himachal Pradesh Undertaking) (An ISO 9001:2008 QMS & ISO 14001:2004 EMS conforming company) November 2019

Transcript of Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for...

Page 1: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

1 | P a g e

Himachal Pradesh State Roads

Transformation Program (Funded by World Bank)

Dadhol-Ladrour (Km 0.00 to KM 13.500)

Environment and Social Management Plan

(Draft)

HIMACHAL PRADESH ROAD & OTHER INFRASTRUCTURE DEVELOPMENT CORPORATION LTD.

(Government of Himachal Pradesh Undertaking) (An ISO 9001:2008 QMS & ISO 14001:2004 EMS conforming company)

November 2019

Page 2: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

1 | P a g e

TABLE OF CONTENTS

LIST OF TABLES................................................................................................................................... 1

LIST OF FIGURES ................................................................................................................................ 1

1. ENVIRONMENTAL MANAGEMENT PLAN ............................................................................... 2

1.1 DESCRIPTION OF THE PROJECT ROAD .............................................................. 2 1.2 SCOPE .......................................................................................................... 3 1.3 OBJECTIVES ................................................................................................... 3 1.4 MEETING THE EMP OBJECTIVES ....................................................................... 3 1.5 CONTEXT FOR THE EMP ................................................................................. 4 1.6 CRITICAL IMPACTS TO BE ADDRESSED .............................................................. 4 1.7 METHODOLOGY FOR EMP PREPARATION ........................................................... 5 1.8 LEGAL REQUIREMENTS .................................................................................... 6 1.9 OTHER LEGISLATIONS/ACTS/RULES APPLICABLE TO ROAD CONSTRUCTION .......... 14 1.10 ENVIRONMENTAL AND SOCIAL FRAMEWORK OF WORLD BANK ............................. 14 1.11 WORLD BANK ESF POLICY, DIRECTIVES AND STANDARDS – EXTENT OF RELEVANCE ............ 19 1.12 COMPARATIVE ANALYSIS OF KEY NATIONAL, STATE AND BANK POLICIES ........................... 29 1.13 COMPARISON OF NATIONAL ENVIRONMENTAL FRAMEWORK AND ESF, 2018 ....................... 30 1.14 INSTITUTIONAL FRAMEWORK ................................................................................... 33

2. ENVIRONMENTAL AND SOCIAL RISKS AND MITIGATION MEASURES .............................. 35

2.1 SUMMARY OF RISK/IMPACTS ......................................................................... 35 2.2 MITIGATION MEASURES ................................................................................. 36

2.2.1 Design Proposals ................................................................................ 36 2.2.2 Site Specific Management Measures ....................................................... 42

3. ENVIRONMENTAL MANAGEMENT ACTION PLAN ............................................................... 48

3.1 PRE-CONSTRUCTION ACTIVITIES ..................................................................... 48 3.2 CONSTRUCTION STAGE ................................................................................. 48

4. ENVIRONMENTAL MONITORING PROGRAMME ................................................................. 71

4.1 GENERAL ..................................................................................................... 71 4.2 PERFORMANCE INDICATORS ............................................................................ 71 4.3 MONITORING PLAN FOR ENVIRONMENTAL CONDITIONS ...................................... 73 4.4 REPORTING SYSTEM ..................................................................................... 76 4.5 INSTITUTIONAL ARRANGEMENTS ..................................................................... 79

Client Logo

CCOONNSSUULLTTAANNCCYY SSEERRVVIICCEESS FFOORR PPRROOJJEECCTT MMAANNAAGGEEMMEENNTT PPHHAASSEE––II IINNCCLLUUDDIINNGG

PPRREEPPAARRAATTIIOONN OOFF DDEETTAAIILLEEDD PPRROOJJEECCTT RREEPPOORRTT FFOORR UUPP--GGRRAADDAATTIIOONN OOFF

Radhanpur–Kamalpur–Khakhal–Roda–Dunawada- Patan, Chanasma–Mehesana-

Kherva, Gozaria–Sama–Churada -Kuvadara section of NH68 and terminating at its

junction with NH-48 near Prantij in the state of Gujarat to two/four lane with paved

shoulder configuration

((PPKKGG NNOO:: NNHH//IIAAHHEE//1133))

Environmental Screening and Preliminary Environmental Assessment

Page 3: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

2 | P a g e

5. CAPACITY BUILDING AND TRAINING ................................................................................. 82

5.1 CAPACITY BUILDING AND TRAINING ................................................................. 82 5.2 TRAINING PROGRAMMES ................................................................................ 82

6. IMPLEMENTATION SCHEDULE ............................................................................................ 87

7. EMERGENCY RESPONSE PLAN .......................................................................................... 89

8. ENVIRONMENTAL BUDGETORY PROVISIONS ................................................................... 92

Page 4: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

1 | P a g e

LIST OF TABLES

TABLE 1-1 CRITICAL ENVIRONMENTAL ISSUES TO BE ADDRESSED ........................................ 4

TABLE 3-1: ENVIRONMENT MANAGEMENT ACTION PLAN .................................................. 49

TABLE 4-1: PERFORMANCE INDICATORS ..................................................................... 71

TABLE 4-2: ENVIRONMENTAL MONITORING PLAN FOR AIR, WATER, NOISE AND SOIL ............... 74

TABLE 4-3: REPORTING SYSTEM ............................................................................. 77

TABLE 4-4: SUMMARY DETAILS OF REPORTING FORMATS ................................................ 77

TABLE 4-4: ROLES AND RESPONSIBILITIES OF THE STAFF IN ESMU OF HPRIDC .................... 79

TABLE 6-1: INDUCTIVE FRAMEWORK OF IMPLEMENTATION SCHEDULE .................................. 87

TABLE 6-2: INDICATIVE IMPLEMENTATION SCHEDULE ..................................................... 88

TABLE 8-1: EMP WORKS TO BE IMPLEMENTED AS PER CIVIL WORKS BOQ ............................ 92

LIST OF FIGURES

FIGURE 1.1: LOCATION MAP OF THE PROJECT ................................................................. 2

Page 5: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

2 | P a g e

1. ENVIRONMENTAL MANAGEMENT PLAN

1.1 DESCRIPTION OF THE PROJECT ROAD

The project road traverses entirely within Bharari tehsil of Bilaspur district and connects to SH-32 at

Ladrour end and to NH-103 at Dadhol. The total length of the Dadhol to Ladrour project road (OSR-09) is

13+500 Km. The road completely falls in district Bilaspur of Himachal Pradesh. The project road

commences from Dadhol and traverses through different settlement like Bhater, Lethwin, Ladyani,

Bharari, Ghandalwin to Ladrour. The Santoshi Mata temple at Ladrour is center of religious importance.

As per 2011 census, the total population of Bharari tehsil is 45,713 with 10,174 households. Ghumarwin

is the adjacent tehsil, which has a population of 89,516 with 19,593 households. Both tehsils are the

primary beneficiaries of project road improvement. The latitude of the project road at Dadhol and Ladrour

are 31.29’.52” N to 31.34’.22” N respectively and Longitude is 76.29’.52” E to76.40’.07” E respectively.

The altitude of project corridor ranges between 737-979 m above mean sea level. The existing width of

carriage way varies from 3.0 m to 7.0 m. The location map/index map of the project road has been

shown in the Figure 1.1.

Figure 1.1: Location Map of the project

Page 6: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

3 | P a g e

1.2 SCOPE

The Environmental Management Plan (EMP) consists of the set of mitigation, monitoring and institutional

measures to be taken during the design, construction and operation phase of the project to eliminate

adverse environmental impacts, to offset them, or to reduce them to acceptable levels. The plan also

includes the actions needed for the implementation of these measures.

The major components of the Environmental Management Plan are:

Mitigation of potentially adverse impacts;

Integration of EMP with Project planning, design, construction and operation;

Environment Enhancement Measures;

Environment and Social Management Action Plan

Institutional Capacity Building and Training;

Implementation Schedule and Environmental Cost Estimates;

Monitoring during project implementation and operations;

1.3 OBJECTIVES

The main objective of Environmental Management Plan is to mitigate the various adverse impacts and

enhance positive impacts of the project. The objectives at various stages of the project planning, design

and implementation stages are as follows.

Design Phase

To minimize impact on roadside trees and vegetation cover.

To keep land acquisition and building demolition at minimum.

To incorporate safety of road users and roadside communities in project design.

To provide mitigation measures to all anticipated environmental degradation.

To develop a design that incorporate environmental safeguards.

Construction Stage

To prevent and reduce the negative environmental impacts of the project by implementing the

mitigation measures to be carried out by the contractor.

To ensure that the provision of the ESMP (Environment & Social Management Plan) are strictly

followed and implemented by strengthening implementation arrangement.

Operation Stage

To monitor deterioration of natural environmental components of air, water, soil and noise, etc.

To improve the safety of road users and the roadside communities.

1.4 MEETING THE EMP OBJECTIVES

The following commitments are important to effectively implement the EMP and achieve the above

objectives.

Page 7: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

4 | P a g e

Commitment to address Environmental, Social, Health & Safety impacts:

To improve conditions in the areas of Environmental, Social, and Health & Safety impacts. Mitigation

measures have been suggested.

Commitment for constant dialogue with the Stake holders:

Community consultations have been carried out right from inception stage of the project. Continuous

dialogue with local inhabitants and stakeholders including public agencies has been undertaken to obtain

their feedback. Consultations would continue throughout the project implementation.

Commitment related to capacity building:

For effective implementation of the proposed measures, sustainable institutional arrangements have been

implemented by the ESMU. To educate and train the PIU personnel, supervision consultant’s/ Contactor’s

staff about WB’s Environment Safeguards Measures, a training schedule has been proposed and provided

in later sections of the report.

Commitment to meet legal requirements:

Applicable legal requirements and procedures are followed including conditions stipulated by statutory

authorities such as State Forest Department and State Pollution Control Board etc.

1.5 CONTEXT FOR THE EMP

This EMP for Dadhol-Bharari-Ladrour Road is based on the findings of EIA (Environment Impact

Assessment) carried out in the project corridor and provides for effective implementation of the

environmental management measures required for addressing the potential environmental impacts. This

Environmental Management Plan assists the project proponent and the contractor to implement the

environmental management measures effectively.

1.6 CRITICAL IMPACTS TO BE ADDRESSED

The critical environmental components that may be impacted are identified in the EIA report. The most

critical issues to be addressed in EMP are described in Table 1-1.

Table 1-1 Critical Environmental Issues to be Addressed

Critical Environmental Issues Locations Management of excess debris generated due to hill excavation

Along the entire road Stretch due to excavation of hill and demolition activities. Excess quantity of debris to be disposed off (56251 m3).

Traffic congestion due to development close to the road including Pedestrian and Traffic Safety

Along settlements areas of road. The major settlement areas along road are Padyalag, Gahar, Gatwar, Ladhyani, Bharari, Mihara and Ladrour are major settlements along roadside. Km 1+300, 3+400, 4+520, 6+470, 6+530, 6+640, 7+830 and 12+00

are locations with sensitive receptors and would require addressing of safety related issues.

Air Quality at sensitive receptors Hospitals, educational institutions, community and religious places (Km 1+300, 3+400, 4+520, 6+470, 6+530, 6+640, 7+830, 12+000 and 12+500)

High Noise Level Exposure At sensitive receptors in settlements along the road length (Km 1+300, 3+400, 4+520, 6+470, 6+530, 6+640, 7+830, 12+000 and 12+500)

Removal of vegetation cover/roadside tree plantation

Along roadside. There exist 3615 trees in RoW.

Presence of invasive species Along the entire road stretch except settlements areas

Page 8: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

5 | P a g e

1.7 METHODOLOGY FOR EMP PREPARATION

The comprehensive environmental management approach for the project involves following key steps and processes.

1. Preliminary Environmental Screening

2. Detailed Environmental Screening

3. Environmental Impact assessment

4. Environmental Management Plan

a) Preliminary Environmental Screening: This step involved an initial desk review of the available information about the project road. The exercise helped in identifying the key/significant potential environmental impacts.

b) Detailed Environmental Screening: The purpose of environmental screening was to get an overview of the nature, scale and magnitude of the issues in order to determine the project feasibility and proper scoping of the detailed EIA.

c) Environmental risks/Impact Assessment: ESIA involved comprehensive study that involves through documentation of existing conditions and identification of impacts with comparison of alternative project design options.

d) Environmental Management Plan: Preparation of EMP involved the identification and development of measures aimed at avoiding, mitigating and offsetting or reducing impacts to levels that are environmentally accepted during implementation and operation of the project road. EMP provides an essential link between the impacts predicted and mitigation measures specified within the EIA and implementation and operation activities.

For developing the EMP; findings from the stake holder/Public consultation process including suggestions from domain experts, project affected people and vulnerable people were considered.

Page 9: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

6 | P a g e

1.8 LEGAL REQUIREMENTS

The Government of India has laid out various policy guidelines, acts and regulations pertaining to

sustenance of environment. The Environment (Protection) Act, 1986 is umbrella legislation for the

protection of environment and under this act, the responsibility to administer the legislation has been

jointly entrusted to the Ministry of Environment, Forests and Climate Change (MoEF&CC), and the Central

Pollution Control Board (CPCB) at Government of India (GoI) level and the State Pollution Control Boards

(SPCB) at the respective state levels which in the present case Himachal Pradesh State Pollution Control

Board (HPSPCB), Government of Himachal Pradesh (GoHP). The lists of all applicable regulations at GoI

and state levels are provided in the Table 1-2 below.

Table 1-2 Summaries of Applicable Regulations of GOI/GoHP

Page 10: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

7 | P a g e

S.No. Act / Rules Key provisions and purpose Applicability to Project Road

1

Environmental protection

Act, 1986 and subsequent

amendments

The Act provides for mandatory public consultation for all listed projects and activities

requiring prior Environmental Clearance (EC) and includes road and highways

requiring further land acquisition. The Public Consultation shall ordinarily have two

components comprising of:- (a) a public hearing at the site or in its close proximity-

district wise, to be carried out in the manner prescribed, for ascertaining concerns of

local affected persons; (b) obtain responses in writing from other concerned persons

having a plausible stake in the environmental aspects of the project or activity.

Yes (applicable for construction & operation

phase)

2

Environmental Impact

Assessment Notification-

2006, 14th Sep-2006, as

amended in 2009 and 2013

To provide environmental clearance to new development activities following

environmental impact assessment

No (The project road is other district road and

it does not fall under the category of state

Highway (7f of the schedule, EIA notification)

and thus is outside the preview of EIA, 2006

Notification).

Therefore, no prior environmental clearances

are required from central or state levels.

3

Notification for use of fly

ash, 2003 and MoEF&CC

notification dated 25th

March 2015

Reuse large quantity of fly ash discharged from thermal power plant to minimize land

use for disposal

No (as there is no thermal plant with in 300km

of project road)

4 The Forest (Conservation)

Act. 1980 To check deforestation by restricting diversion of forest areas into non- forest uses. No.

5

MoEF&CC circular (1998) on

linear Plantation on

roadside, canals and railway

lines modifying the

applicability of provisions of

forest (Conversation) Act, to

Protection / planting roadside strip as avenue/strip plantations as these are declared

protected forest areas.

Yes, permission is needed for cutting 75

affected trees.

Page 11: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

8 | P a g e

S.No. Act / Rules Key provisions and purpose Applicability to Project Road

linear Plantation

6 The Wild Life Protection Act,

1972 To protect wildlife such as National Parks and Sanctuaries

No (No wild life Sanctuary or National park is

within 10 km of project road)

7 Biological Diversity Act, 2002 Disclosure of species survey

No, As per act, there is no presence of any

rare, endangered, threatened species

reported along the corridor.

8 Air (Prevention and Control

of Pollution) Act, 1981 To control air pollution Pollutants

Yes (During construction phase contractor to

obtain CTO and CFO) to regulate air quality at

construction

9

Water (Prevention and

Control of Pollution) Act,

1974

To control water pollution by controlling discharge of pollutants as per the prescribed

standards

Yes (During construction phase contractor to

obtain CTO and CFO) to regulate water quality

at construction

10 Noise Pollution (Regulation

and Control Act) 1990

The standards for noise for day and night have been promulgated by the MoEF&CC

for various land uses.

Yes, (During construction phase contractor to

obtain CTO and CFO) to regulate noise level at

construction

11 The Explosive Act 1984 Safe transportation, storage and use of explosive material No (as explosive are prohibited to be used.)

12

The Mines and Minerals

(Development and

Regulation) Act 1957

For opening new quarry.

Yes (During construction only, if any new

quarries are opened, contractor shall avail the

permission/license from competent agencies)

13

The Ancient Monuments and

Archaeological Sites and

Remains Act 1958

Conservation of cultural and historical remains found in India No

Page 12: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

9 | P a g e

S.No. Act / Rules Key provisions and purpose Applicability to Project Road

14 National Resource Efficiency

Policy, 2019 (Draft)

To create a facilitative and regulatory environment to mainstream resource efficiency

across all sectors by fostering cross-sectoral collaborations, development of policy

instruments, action plans and efficient implementation and monitoring frameworks.

Yes (During construction Phase)

15

Municipal Solid Waste

(Management & Handling)

Rules, 2000 (MSW Rules)

Segregation, Handling & safe disposal of domestic solid waste No

16

Hazardous Wastes

(Management, Handling and

Trans-boundary Movement)

Rules, 2008.

Safe handling, storage, transportation & disposal of hazardous wastes

Yes (Applicable during construction phase, the

contractor shall obtain the requisite licenses

for handling and disposal of hazardous waste

generated during construction phase.)

17 Batteries (Management and

Handling) Rules, 2001 Safe recycling of lead acid batteries

Yes (Applicable during construction phase, the

contractor shall obtain the requisite licenses

for handling and disposal of batteries during

construction phase.)

18

Central Motor Vehicle Act

1988 and Central Motor

Vehicle Rules 1989

To check vehicular air and noise pollution

Yes (contractors responsibility to obtain

Pollution Under Control certificates during

construction stage for all vehicles deployed for

construction activities)

19 National Labour Act, 1970.

An Act to regulate the employment of contract labour in certain establishments and

to provide for its abolition in certain circumstances and for matters connected

therewith

Yes (This shall be contractors responsibility for

compliance)

20 Public Liability and Insurance

Act 1991

To provide through insurance, immediate relief, by you who control or handle

hazardous chemicals.

Protection form hazardous materials and accidents.

Yes (The contractor shall obtain the required

insurance policy prior to commencement of

construction)

Page 13: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

10 | P a g e

S.No. Act / Rules Key provisions and purpose Applicability to Project Road

21 Building and Other

Construction act, 2006

To regulate the employment and conditions of service of building and other

construction workers and to provide for their safety, health and welfare measures and

for other matters connected therewith or incidental thereto.

Yes (This shall be contractors responsibility

for compliance)

22 The Petroleum Rules, 2002 Safe use and storage of petroleum products and will need to be compiled by the

contractors.

Yes (contractors responsibility to obtain PUC

certificates during construction stage for all

vehicles deployed for construction activities)

23 The E-Waste (Management)

Rules, 2016,

This provides for management of E-wastes (but not covering lead acid batteries and

radio-active wastes) aiming to enable the recovery and/or reuse of useful material

from e-waste, thereby reducing the hazardous wastes destined for disposal and to

ensure the environmentally sound management of all types of waste of electrical and

electronic equipment.

Yes (contractor is responsibility during the

construction period)

24 Plastic waste Management

Rules, 2016

This provides for control and management of the plastic waste generated from any

activity. Contractors will ensure compliance to this Rule.

Yes (contractor is responsibility during the

construction period)

25 State Groundwater Acts and

Rules

These provide for regulating extraction of ground water for construction/industrial

and drinking and domestic purposes.

Contractors will need to obtain permission

from Central/State Groundwater Boards prior

to groundwater abstraction through either

new/existing tube well or through any other

means; and will to ensure full compliance to

all applicable rules and any conditions

imposed in the permit by competent

authority.

Page 14: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

11 | P a g e

S.No. Act / Rules Key provisions and purpose Applicability to Project Road

26

Construction & Demolition,

Waste Management Rules,

2016

This rule shall be applicable to construction waste/debris resulting from road

construction including RCC bridge and other protection works

Yes. As, this Project is a

rehabilitation/widening of road with

demolition of old and damaged CD structures,

the project road is likely to generate the

demolition waste. The project is likely to

generate more than 20MT waste per day

and/or 300 MT in a month, a project specific

waste management plan will be required as

per the stipulations under this rule.

The project considers balancing the cut and

filling volumes and reusing the debris/muck

generated in the construction of sub base and

base layers of the road. Excess debris will be

safely disposed in approved sites by the

project authorities and district administration.

27

Right to Fair Compensation

and Transparency in Land

Acquisition, Rehabilitation

and Resettlement Act, 2013

(RFCTLARR)

The act provides for a transparent process and fair compensation in land acquisition

for public purpose and provides for rehabilitation and resettlement of land owners

and those affected by land acquisition. It comprises four schedules that provide the

minimum applicable norms for compensation based on market value, multiplier and

solatium; resettlement and rehabilitation (R&R) entitlements to land owners and

livelihood losers; and facilities at resettlement sites for displaced persons, besides

providing flexibility to states and implementing agencies to provide higher norms for

compensation and R&R.

Applicable to all sub-projects when land is

required to be taken on involuntary basis i.e. if

land is not taken on direct purchase from the

owner

28

The Himachal Pradesh Right

to Fair Compensation and

Transparency in Land

Acquisition, Rehabilitation

and Resettlement (Social

Provides the rules for operationalizing the provisions of the above-mentioned act

Applicable to all sub-projects when land is

required to be taken on involuntary basis i.e. if

land is not taken on direct purchase from the

owner

Page 15: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

12 | P a g e

S.No. Act / Rules Key provisions and purpose Applicability to Project Road

Impact Assessment and

Consent) Rules 2015,

29

Acquisition of Land by

Private Negotiation and

Upkeep of Land

Record/General Guidelines

and Instruction (Standing

Order No

.28)(PBW(B)F(5)40/2017-

PWD/ GoHP, January 2018

For speedier acquisition of land, the process of acquisition by private negotiations

with the interested landowners have proved to be beneficial to both the parties i.e.

landowners as well as acquiring department, Government of Himachal Pradesh in

January 2018 publish the order to execute for infrastructure projects. If it is found

that acquisition of land is imminent for a public purpose, following two options will be

available with the concerned department

i) Acquisition by private negotiation.

ii) Compulsory acquisition under the provisions of the new Land Acquisition Act “Right to Fair Compensation and Transparency in Land Acquisition

Rehabilitation and Resettlement Act, 2013.”

Either of the options would be used for

acquiring land under the project

30

The Himachal Pradesh Road

Infrastructure Protection

Act, 2002 (and Rules 2004)

The Act defines road infrastructure that includes: roads, paths and streets for

transport or communication and also shall include: - (i) acquired road land width; (ii)

all types of road and their structure, such as road pavements, shoulders, retaining

walls, breasts walls, (iii) any structure ancillary to road transport and communication

system; (iv) bridges including approaches, return walls, wing walls, protection works

and allied structures;(v) expressways including interchanges, (vi) road furniture,

such as parapets, railings, etc. No person shall: encroach upon the Government land

under road infrastructure; iii) raise any permanent, temporary or movable

structure on or from road infrastructure;

Applicable to all roads in HP specifically to

address the issue of encroachments

31

The Himachal Pradesh

roadside land control act

1968

Act has provisions for restriction on buildings etc., in a controlled area no person shall

erect or re-erect any building or make or extend any excavation or lay out means of

access to a road in a controlled area.

Applicable to all roads in HP specifically to

address the issue of encroachments

Page 16: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

13 | P a g e

S.No. Act / Rules Key provisions and purpose Applicability to Project Road

32

The Right to Information Act,

2005

The Act provides for setting out the practical regime of right to information for

citizens to secure access to information under the control of public authorities, in

order to promote transparency and accountability in the working of every public

authority, the constitution of a Central Information Commission and State Information

Commissions and for matters connected therewith or incidental thereto.

Applicable to the project as a whole.

33 The Rights of Persons with

Disabilities Act, 2016

The Act ensures that persons with disabilities enjoy the right to equality and non-

discrimination in all aspects of life. Every entity has to comply with the accessibility

standards relating to physical environment, transport and information and

communication technology as per the standards prescribed in the RPD Act. These

include barrier free built environment having elevators/ramps for the benefit of

wheelchairs. In respect to Access to Transport”- mentioned that-the appropriate

Government shall take suitable measures to provide,—(a) facilities for persons with

disabilities at bus stops, railway stations and airports conforming to the accessibility

standards relating to parking spaces, toilets, ticketing counters and ticketing

machines;(b) access to all modes of transport that conform the design standards,

including retrofitting old modes of transport, wherever technically feasible

Applicable to the project road infrastructure in

terms of making it more accessible for those

who are physically challenged

Page 17: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

14 | P a g e

1.9 OTHER LEGISLATIONS/ACTS/RULES APPLICABLE TO ROAD CONSTRUCTION PROJECTS

Environmental, Health and Safety issues and engagement of labour during any project construction

generally involve equity, safety and public health issues. The road construction agencies required to

comply with the applicable laws of the land, which include inter alia, the following:

Workmen's Compensation Act 1923, the Act provides for compensation in case of injury by

accident arising out of and during employment;

Payment of Gratuity Act, 1972, gratuity is payable to an employee under the Act on

satisfaction of certain conditions on separation if an employee has completed 5 years;

Employees Provident Fund and Miscellaneous Provision Act 1952, the Act provides for

monthly contributions by the employer plus workers;

Maternity Benefit Act, 1951, the Act provides for leave and some other benefits to women

employees in case of confinement or miscarriage, etc;

Minimum Wages Act, 1948, the employer is supposed to pay not less than the

Minimum Wages fixed by appropriate Government;

Payment of Wages Act, 1936, it lays down as to by what date the wages are to be paid,

when it will' be paid and what deductions can be made from the wages of the workers);

Equal Remuneration Act, 1979, the Act provides for payment of equal wages for work

of equal nature to Male and Female workers and not for making discrimination against Female

employees);

Payment of Bonus Act, 1965, the Act provides for payments of annual bonus subject

to a minimum of 83.3% of wages and maximum of 20% of wages;

Child Labour (Prohibition and Regulation) Act ,1986, the Act prohibits employment of

children below 14 years of age in certain occupations and processes and provides for regulation

of employment of children in all other occupations and processes. Employment of child

labour is prohibited in Building and Construction Industry;

Inter-State Migrant Workmen’s (Regulation of Employment and Conditions of

Service) Act, 1979, the inter-state migrant workers, in an establishment to which this Act

becomes applicable, are required to be provided certain facilities such as housing,

medical aid, traveling expenses from home to the establishment and back, etc.;

1.10 ENVIRONMENTAL AND SOCIAL FRAMEWORK OF WORLD BANK

The Environmental and Social Framework (ESF) has become applicable to all investment Project

financing operations by the World Bank since, Oct 2018. The ESF protects people and

the environment from potential adverse impacts that could arise from Bank-financed projects, and

promotes sustainable development.

The Environmental and Social Standards (ESS) 1 to 10 of ESF, 2018, which gets triggered due to the

Dadhol – Ladrour project road, are presented in the Table 1-3.

Page 18: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

15 | P a g e

Table 1-3: Environmental and Social Standards (1 to 10) under ESF 2018, World Bank

ESS Description Objective Requirement

Applicability to Project

Road under HPSRTP

ESS-1

Assessment and

Management of Environmental and Social Risks and Impacts

Identify, assess, evaluate, and manage environment and social risks and impacts in a

manner consistent with the ESF. Adopt differentiated measures so that adverse impacts do not fall disproportionately on the disadvantaged or vulnerable, and they are not disadvantaged in sharing development benefits and opportunities

The types of E&S risks and impacts that should be considered in the

environmental and social assessment. The use and strengthening of the Borrower’s environmental and social framework for the assessment, development and implementation of World Bank financed projects where appropriate.

Yes

ESS-2 Labour-and-Working-Conditions

Promote safety and health at work. Promote the fair treatment, non-discrimination, and equal opportunity of project workers. Protect project workers, with emphasis on vulnerable workers. Prevent the use of all forms of forced labour and child labour. Support the principles of freedom of association and

collective bargaining of project workers in a manner consistent with national law. Provide project workers with accessible means to raise workplace concerns.

Requirements for the Borrower to prepare and adopt labor management procedures. Provisions on the treatment of direct, contracted, community, and primary supply workers, and government civil servants. Requirements on terms and conditions of work, non-discrimination and equal opportunity and workers organizations. Provisions on

child labour and forced labour. Requirements on occupational health and safety, in keeping with the World Bank Group’s Environmental, Health, and Safety Guidelines (EHSG).

Yes

ESS-3

Resource-Efficiency-and-Pollution-Prevention-and-Management

Promote the sustainable use of resources, including energy, water, and raw materials. Avoid or minimize adverse impacts on human health and

the environment caused by pollution from project activities. Avoid or minimize project-related emissions of short and long-lived climate pollutants. Avoid or minimize generation of hazardous and non-hazardous waste. Minimize and manage the risks and impacts associated with pesticide use. Requires

technically and financially feasible measures to improve efficient consumption of energy, water, and raw materials, and introduces specific requirements for water efficiency where a project has high water demand.

Requires an estimate of gross greenhouse gas emissions resulting from project (unless minor), where technically and financially feasible. Requirements on management of wastes, chemical and hazardous materials, and contains provisions to address historical pollution. ESS3 refers to national law and Good

International Industry Practice, in the first instance the World Bank Groups’ EHSGs.

Yes

Page 19: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

16 | P a g e

ESS Description Objective Requirement

Applicability

to Project Road under

HPSRTP

ESS-4 Community-Health-and-Safety

Anticipate or avoid adverse impacts on the health and safety of project-affected communities during project life cycle from routine and non-

routine circumstances. Promote quality, safety, and climate change considerations in infrastructure design and construction, including dams. Avoid or minimize community exposure to project-related traffic and road safety risks, diseases and hazardous materials. Have in place effective measures to address emergency events. Ensure that

safeguarding of personnel and property is carried out in a manner that avoids or minimizes risks to the project-affected communities.

Requirements on infrastructure, considering safety and climate change, and applying the concept of universal access, where technically and

financially feasible. Requirements on traffic and road safety, including road safety assessments and monitoring. Addresses risks arising from impacts on provisioning and regulating ecosystem service. Measures to avoid or minimize the risk of water-related, communicable, and non-communicable diseases. Requirements to

assess risks associated with security personnel, and review and report unlawful and abusive acts to relevant authorities.

Yes

ESS-5

Land-Acquisition-Restrictions-on-Land-Use-and-Involuntary-Resettlement

Avoid or minimize involuntary resettlement by exploring project design alternatives. Avoid forced eviction. Mitigate

unavoidable adverse impacts from land acquisition or restrictions on land use by providing compensation at replacement cost and assisting displaced persons in their efforts to improve, or at least restore, livelihoods and living standards to pre-displacement levels or to levels prevailing prior to the beginning of project

implementation, whichever is higher. Improve living conditions of poor or vulnerable persons who are physically displaced, through provision of adequate housing, access to services and facilities, and security of tenure. Conceive and execute resettlement activities as sustainable development

programs.

Applies to permanent or temporary physical and economic displacement resulting from different types of

land acquisition and restrictions on access. Does not apply to voluntary market transactions, except where these affects third parties. Provides criteria for “voluntary” land donations, sale of community land, and parties obtaining income from illegal rentals. Prohibits forced eviction (removal against the will of affected people, without legal and other protection

including all applicable procedures and principles in ESS5). Requires that acquisition of land and assets happens only after payment of compensation and resettlement has occurred. Requires community engagement and consultation, disclosure of information and a grievance mechanism.

Yes

Page 20: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

17 | P a g e

ESS Description Objective Requirement

Applicability

to Project Road under

HPSRTP

ESS-6 Biodiversity-Conservation

Protect and conserve biodiversity and habitats.

Apply the mitigation hierarchy and the precautionary approach in the design and implementation of projects that could have an impact on biodiversity. To promote the sustainable management of living natural resources.

Requirements for projects affecting areas that are legally protected, designated for protection or regionally/internationally

recognized to be of high biodiversity value. Requirements on sustainable management of living natural resources, including primary production and harvesting, distinguishing between small-scale and commercial activities. Requirements relating to primary suppliers, where a project is purchasing natural resource commodities,

including food, timber and fibre.

No

ESS-7 Indigenous-Peoples

Ensure that the development process fosters full respect for affected parties’ human rights, dignity, aspirations, identity, culture, and natural resource-based livelihoods. Promote sustainable development benefits and opportunities in a manner that is accessible, culturally appropriate and inclusive. Improve project design and promote local

support by establishing and maintaining an ongoing relationship based on meaningful consultation with affected parties. Obtain the Free, Prior, and Informed Consent (FPIC) of affected parties in three circumstances. Recognize, respect and preserve the culture, knowledge, and practices of Indigenous Peoples, and to

provide them with an opportunity to adapt to changing conditions in a manner and in a timeframe acceptable to them.

Applies when the IP/SSAHUTLC are present or have a collective attachment to the land, whether they are affected positively or negatively and regardless of economic, political or social vulnerability. The option to use different terminologies for groups that

meet the criteria set out in the Standard. The use of national screening processes, providing these meet World Bank criteria and requirements. Coverage of forest dwellers, hunter gatherers, and pastoralists and other nomadic groups. Requirements for meaningful consultation tailored to affected parties and a grievance mechanism. Requirements for a

process of free, prior and informed consent in three circumstances.

No

Page 21: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

18 | P a g e

ESS Description Objective Requirement

Applicability

to Project Road under

HPSRTP

ESS-8 Cultural-Heritage

Protect cultural heritage from the adverse impacts of project activities and support its preservation. Address cultural heritage as an integral aspect of sustainable development. Promote meaningful consultation with stakeholders regarding cultural heritage. Promote the equitable sharing

of benefits from the use of cultural heritage.

Requires a chance finds procedure to be established. Recognition of the need to ensure peoples’ continued access to culturally important

sites, as well as the need for confidentiality when revealing information about cultural heritage assets that would compromise or jeopardize their safety or integrity. Requirement for fair and equitable sharing of benefits from commercial use of cultural resources. Provisions of archaeological sites and material, built heritage, natural features with cultural

significance, and moveable cultural heritage.

No

ESS-9 Financial-Intermediaries

Sets out how Financial Intermediaries (FI) will assess and manage environmental and social risks and impacts associated with the subprojects it finances. Promote good environmental and social management practices in the subprojects

the FI finance. Promote good environmental and sound human resources management within the FI.

Financial Intermediaries (FIs) to have an Environmental and Social Management System (ESMS) - a system for identifying, assessing, managing, and monitoring the environmental and social risks and impacts of FI subprojects on an ongoing basis. FI to develop a categorization system for all subprojects; with special provisions for

subprojects categorized as high or substantial risk. FI borrowers to conduct stakeholder engagement in a manner proportionate to the risks and impacts of the FI subprojects.

No

ESS-10

Stakeholder-Engagement-and-Information-

Disclosure

Establish a systematic

approach to stakeholder engagement that helps Borrowers identify stakeholders and maintain a constructive relationship with them. Assess stakeholder interest and support for the project and enable stakeholders’ views to be considered in project design. Promote and provide means

for effective and inclusive engagement with project-affected parties throughout the project life cycle. Ensure that appropriate project information is disclosed to stakeholders in a timely, understandable, accessible and appropriate manner.

Requires stakeholder

engagement throughout the project life cycle, and preparation and implementation of a Stakeholder Engagement Plan (SEP). Requires early identification of stakeholders, both project-affected parties and other interested parties, and clarification on how effective engagement takes place. Stakeholder engagement

to be conducted in a manner proportionate to the nature, scale, risks and impacts of the project, and appropriate to stakeholders’ interests. Specifies what is required for information disclosure and to achieve meaningful consultation.

Yes

Page 22: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

19 | P a g e

ESS Description Objective Requirement

Applicability

to Project Road under

HPSRTP

Good Practice

Note on Road

Safety

Road Safety

To identify, evaluate and monitor the potential traffic and road safety risks to workers, affected communities and road users throughout the project life cycle and, where appropriate, will develop measures and plans to address

them. The Borrower will incorporate technically and financially feasible road safety measures into the project design to prevent and mitigate potential road safety risks to road users and affected communities”.

Requirements on traffic and road safety, including road

safety assessments and monitoring. .

Yes

1.11 World Bank ESF Policy, Directives and Standards – Extent of Relevance

Section below discusses the relevance of ESF Policy, each of the ten standards (ESS1 to 10) and associated Directive; their requirements. Additionally, it also discusses the relevance and requirements relating to other guidance notes of World Bank.

Page 23: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

20 | P a g e

Table 1.4 – Relevance of World Bank E&S Policy, ESS, Directive and guidance notes to the sub-project

World Bank ESS Policy,

Standards, Directive Objectives Requirements

Relevance & Extent of Relevance to

the sub-project/project

World Bank Environment and

Social Policy for Investment

Project Financing

It sets out the mandatory

requirements of the Bank in

relation to the projects it supports

through Investment Project

Financing.

The types of E&S risk and impacts that should be

considered in the environmental and social

assessment. The use and strengthening of the

Borrower’s environmental and social framework for

the assessment, development and implementation of

World Bank financed projects where appropriate.

Applicable to this project

ESS-1

Assessment and Management

of Environmental and Social

Risks and Impacts

Identify, assess, evaluate, and

manage environment and social

risks and impacts in a manner

consistent with the ESF. Adopt

differentiated measures so that

adverse impacts do not fall

disproportionately on the

disadvantaged or vulnerable, and

they are not disadvantaged in

sharing development benefits and

opportunities

The types of E&S risk and impacts that should be

considered in the environmental and social

assessment. The use and strengthening of the

Borrower’s environmental and social framework for

the assessment, development and implementation of

World Bank financed projects where appropriate.

E&S risks and Impacts have been

identified based on surveys and

consultations with primary stakeholders

including communities and implementing

agency

ESS-2

Labor-and-Working-

Conditions

Promote safety and health at work.

Promote the fair treatment, non-

discrimination, and equal

opportunity of project workers.

Protect project workers, with

particular emphasis on vulnerable

workers. Prevent the use of all

forms of forced labor and child

labor. Support the principles of

freedom of association and

collective bargaining of project

workers in a manner consistent with

Requirements for the Borrower to prepare and adopt

labor management procedures. Provisions on the

treatment of direct, contracted, community, and

primary supply workers, and government civil

servants. Requirements on terms and conditions of

work, non-discrimination and equal opportunity and

workers organizations. Provisions on child labor and

forced labor. Requirements on occupational health

and safety, in keeping with the World Bank Group’s

Environmental, Health, and Safety Guidelines

(EHSG).

Project will following types of workers:

i) Direct workers will include the project

managers and supervisors, who are

employees of HPRIDC, deployed for

HPSRTP; ii) All the work force deployed

by the Contractors and the Project

Management Consultant (for all

packages) under the HPSRTP will be

deemed to be contracted workers. The

Contractor(s) might further engage

multiple subcontractors; iii) Influx of

Page 24: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

21 | P a g e

Table 1.4 – Relevance of World Bank E&S Policy, ESS, Directive and guidance notes to the sub-project

World Bank ESS Policy,

Standards, Directive Objectives Requirements

Relevance & Extent of Relevance to

the sub-project/project

national law. Provide project

workers with accessible means to

raise workplace concerns.

migrant labor from other states for

construction works has been a norm in

the state and is likely to continue in this

project; iv) Community workers may be

employed by the contractor in relation to

this Project from local sources

particularly for supporting bio-

engineering solutions towards slope

stabilization workers.

ESS-3

Resource-Efficiency-and-

Pollution-Prevention-and-

Management

Promote the sustainable use of

resources, including energy, water,

and raw materials. Avoid or

minimize adverse impacts on

human health and the environment

caused by pollution from project

activities. Avoid or minimize

project-related emissions of short

and long-lived climate pollutants.

Avoid or minimize generation of

hazardous and non-hazardous

waste. Minimize and manage the

risks and impacts associated with

pesticide use. Requires technically

and financially feasible measures to

improve efficient consumption of

energy, water, and raw materials,

and introduces specific

requirements for water efficiency

where a project has high water

Requires an estimate of gross greenhouse gas

emissions resulting from project (unless minor),

where technically and financially feasible.

Requirements on management of wastes, chemical

and hazardous materials, and contains provisions to

address historical pollution. ESS-3 refers to national

law and Good International Industry Practice, in the

first instance the World Bank Groups’ EHSGs.

With respect to Resource Efficiency, the

project preparation and the ESA process

will identify feasible measures for

efficient (a) energy use; (b) water usage

and management to minimize water

usage during construction, conservation

measures to offset total construction

water demand and maintain balance for

demand of water resources; and (c) raw

materials use by exploring use of local

materials, recycled aggregates, use of

innovative technology so as to minimize

project’s foot prints on finite natural

resources.

With respect to Pollution Management,

based on past road project experiences,

the project will develop, as part of the

ESA process, prevention and

management measures to offset risks

Page 25: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

22 | P a g e

Table 1.4 – Relevance of World Bank E&S Policy, ESS, Directive and guidance notes to the sub-project

World Bank ESS Policy,

Standards, Directive Objectives Requirements

Relevance & Extent of Relevance to

the sub-project/project

demand. and impacts of pollution from potential

sources such as dust and emission from

operation of hot-mix and batching

plants, crushers, construction and

haulage

vehicles, material and spoil stockpile;

effluents and wastewater from labor

camps, construction camp; spillage or

leakage during handling of chemical

admixtures, hazardous materials like

bitumen, high strength diesel, used oil,

battery wastes etc.; and disposal of non-

hazardous wastes (municipal wastes)

generated during project implementation

period.

ESS-4

Community-Health-and-

Safety

Anticipate or avoid adverse impacts

on the health and safety of project-

affected communities during project

life-cycle from routine and non-

routine circumstances. Promote

quality, safety, and climate change

considerations in infrastructure

design and construction, including

dams. Avoid or minimize community

exposure to project-related traffic

and road safety risks, diseases and

Requirements on infrastructure, taking into account

safety and climate change, and applying the concept

of universal access, where technically and financially

feasible. Requirements on traffic and road safety,

including road safety assessments and monitoring.

Addresses risks arising from impacts on provisioning

and regulating ecosystem service. Measures to avoid

or minimize the risk of water-related, communicable,

and non-communicable diseases. Requirements to

assess risks associated with security personnel, and

In the project corridor there is likely to

be i) hill cutting, land slides, road

excavation, use of vibratory equipment,

construction debris handling and disposal

etc. during construction; ii) high

likelihood of direct exposure to increased

construction related traffic and

equipment especially at road sections

traversing settlement area with limited

carriageway/roadway width, and

sensitive receptors such as schools,

Page 26: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

23 | P a g e

Table 1.4 – Relevance of World Bank E&S Policy, ESS, Directive and guidance notes to the sub-project

World Bank ESS Policy,

Standards, Directive Objectives Requirements

Relevance & Extent of Relevance to

the sub-project/project

hazardous materials. Have in place

effective measures to address

emergency events. Ensure that

safeguarding of personnel and

property is carried out in a manner

that avoids or minimizes risks to the

project-affected communities.

review and report unlawful and abusive acts to

relevant authorities.

religious place, health centre/hospitals;

iii) high dust levels from earthworks/hill

cutting, high noise and emission level

from traffic congestion and idling of

vehicles;

and iv) influx of migrant workers could

potentially cause local discomfort or

potential conflicts with local people.

ESS-5

Land-Acquisition-Restrictions-

on-Land-Use-and-

Involuntary-Resettlement

Avoid or minimize involuntary

resettlement by exploring project

design alternatives. Avoid forced

eviction. Mitigate unavoidable

adverse impacts from land

acquisition or restrictions on land

use by providing compensation at

replacement cost and assisting

displaced persons in their efforts to

improve, or at least restore,

livelihoods and living standards to

pre-displacement levels or to levels

prevailing prior to the beginning of

project implementation, whichever

is higher. Improve living conditions

of poor or vulnerable persons who

are physically displaced, through

provision of adequate housing,

access to services and facilities, and

security of tenure. Conceive and

execute resettlement activities as

Applies to permanent or temporary physical and

economic displacement resulting from different types

of land acquisition and restrictions on access. Does

not apply to voluntary market transactions, except

where these affect third parties. Provides criteria for

“voluntary” land donations, sale of community land,

and parties obtaining income from illegal rentals.

Prohibits forced eviction (removal against the will of

affected people, without legal and other protection

including all applicable procedures and principles in

ESS5). Requires that acquisition of land and assets

happens only after payment of compensation and

resettlement has occurred. Requires community

engagement and consultation, disclosure of

information and a grievance mechanism.

Land will be required for widening,

upgradation works in identified corridors

and possibly for rehabilitation corridor

works, curve/geometric improvements,

blind spots, etc. Hence impacts on land,

private and community owned assets

including structures, trees and crops

within existing and proposed ROW is

likely. Physical and economic

displacement too is very likely.

Page 27: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

24 | P a g e

Table 1.4 – Relevance of World Bank E&S Policy, ESS, Directive and guidance notes to the sub-project

World Bank ESS Policy,

Standards, Directive Objectives Requirements

Relevance & Extent of Relevance to

the sub-project/project

sustainable development programs.

ESS-6

Biodiversity-Conservation

Protect and conserve biodiversity

and habitats. Apply the mitigation

hierarchy and the precautionary

approach in the design and

implementation of projects that

could have an impact on

biodiversity. To promote the

sustainable management of living

natural resources.

Requirements for projects affecting areas that are

legally protected designated for protection or

regionally/internationally recognized to be of high

biodiversity value. Requirements on sustainable

management of living natural resources, including

primary production and harvesting, distinguishing

between small-scale and commercial activities.

Requirements relating to primary suppliers, where a

project is purchasing natural resource commodities,

including food, timber and fiber.

Site clearance activities for road

construction will involve removal of road

side vegetation and felling of trees. The

biodiversity studies has indicated that

entire corridor along the project road is

rich in biodiversity, interspersed with

invasive species. Other than the

clearance of road side vegetation, road

construction will also require felling of

trees.

ESS-7

Indigenous-Peoples

Ensure that the development

process fosters full respect for

affected parties’ human rights,

dignity, aspirations, identity,

culture, and natural resource-based

livelihoods. Promote sustainable

development benefits and

opportunities in a manner that is

accessible, culturally appropriate

and inclusive. Improve project

design and promote local support by

establishing and maintaining an

ongoing relationship based on

meaningful consultation with

affected parties. Obtain the Free,

Prior, and Informed Consent (FPIC)

Applies when the Indigenous Peoples are present or

have a collective attachment to the land, whether

they are affected positively or negatively and

regardless of economic, political or social

vulnerability. The option to use different

terminologies for groups that meet the criteria set out

in the Standard. The use of national screening

processes, providing these meet World Bank criteria

and requirements. Coverage of forest dwellers,

hunter gatherers, and pastoralists and other nomadic

groups. Requirements for meaningful consultation

tailored to affected parties and a grievance

mechanism. Requirements for a process of free, prior

and informed consent in three circumstances.

Not relevant to this sub-project road.

Though it has 3 tribal households might

be impacted across the 13.5 km corridor

these households do not meet the

characteristics outlined in this Standard.

Hence no differential provisions will be

required to address the impacts on these

households.

Page 28: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

25 | P a g e

Table 1.4 – Relevance of World Bank E&S Policy, ESS, Directive and guidance notes to the sub-project

World Bank ESS Policy,

Standards, Directive Objectives Requirements

Relevance & Extent of Relevance to

the sub-project/project

of affected parties in three

circumstances. Recognize, respect

and preserve the culture,

knowledge, and practices of

Indigenous Peoples, and to provide

them with an opportunity to adapt

to changing conditions in a manner

and in a timeframe acceptable to

them.

ESS-8

Cultural-Heritage

Protect cultural heritage from the

adverse impacts of project activities

and support its preservation.

Address cultural heritage as an

integral aspect of sustainable

development. Promote meaningful

consultation with stakeholders

regarding cultural heritage. Promote

the equitable sharing of benefits

from the use of cultural heritage.

Requires a chance finds procedure to be established.

Recognition of the need to ensure peoples’ continued

access to culturally important sites, as well as the

need for confidentiality when revealing information

about cultural heritage assets that would compromise

or jeopardize their safety or integrity. Requirement

for fair and equitable sharing of benefits from

commercial use of cultural resources. Provisions of

archaeological sites and material, built heritage,

natural features with cultural significance, and

moveable cultural heritage.

The alignment of the project road does

not have any ancient monuments and/or

archaeological site(s), protected but it

has 1 religious structures/shrines of local

importance that is partially impacted by

the proposed road improvement

activities

Page 29: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

26 | P a g e

Table 1.4 – Relevance of World Bank E&S Policy, ESS, Directive and guidance notes to the sub-project

World Bank ESS Policy,

Standards, Directive Objectives Requirements

Relevance & Extent of Relevance to

the sub-project/project

ESS-9

Financial-Intermediaries

Sets out how Financial

Intermediaries (FI) will assess and

manage environmental and social

risks and impacts associated with

the subprojects it finances. Promote

good environmental and social

management practices in the

subprojects the FI finance. Promote

good environmental and sound

human resources management

within the FI.

Financial Intermediaries (FIs) to have an

Environmental and Social Management System

(ESMS) - a system for identifying, assessing,

managing, and monitoring the environmental and

social risks and impacts of FI subprojects on an

ongoing basis. FI to develop a categorization system

for all subprojects; with special provisions for

subprojects categorized as high or substantial risk. FI

borrowers to conduct stakeholder engagement in a

manner proportionate to the risks and impacts of the

FI subprojects.

Not relevant as there is no financial

intermediary involved.

ESS-10

Stakeholder-Engagement-

and-Information-Disclosure

Establish a systematic approach to

stakeholder engagement that helps

Borrowers identify stakeholders and

maintain a constructive relationship

with them. Assess stakeholder

interest and support for the project

and enable stakeholders’ views to

be taken into account in project

design. Promote and provide

means for effective and inclusive

engagement with project-affected

parties throughout the project life-

cycle. Ensure that appropriate

project information is disclosed to

stakeholders in a timely,

understandable, accessible and

appropriate manner.

Requires stakeholder engagement throughout the

project life cycle, and preparation and implementation

of a Stakeholder Engagement Plan (SEP). Requires

early identification of stakeholders, both project-

affected parties and other interested parties, and

clarification on how effective engagement takes

place. Stakeholder engagement to be conducted in a

manner proportionate to the nature, scale, risks and

impacts of the project, and appropriate to

stakeholders’ interests. Specifies what is required for

information disclosure and to achieve meaningful

consultation.

Relevant as the project will involve a

wide variety of stakeholders during its

project cycle including Police Department

that are associated with activities under

other components of the project such as

Road Safety

Page 30: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

27 | P a g e

Table 1.4 – Relevance of World Bank E&S Policy, ESS, Directive and guidance notes to the sub-project

World Bank ESS Policy,

Standards, Directive Objectives Requirements

Relevance & Extent of Relevance to

the sub-project/project

Environmental and Social

Directive for Investment

Project Financing

This Directive applies to the Bank

and sets out the mandatory

requirements for the

implementation of the

Environmental and Social Policy for

Investment Project Financing (IPF).

It lays down the following responsibilities of the Bank

to manage ES risks and impacts as below: a)

undertake its own due diligence of the ES risks and

impacts related to the Project; b) support the

Borrower to engage in meaningful consultation with

stakeholders, in particular affected communities, and

in providing Project-based grievance mechanisms; c)

assist the Borrower in identifying appropriate

methods and tools to assess and manage the

potential ES risks and impacts of the Project; d)

agree with the Borrower on the conditions under

which the Bank is prepared to provide support to the

Project, as set out in the ESCP; and e) monitor the ES

performance of a Project in accordance with the ESCP

and the ESSs.

Applies to Bank in addressing E&S

aspects of this project

Bank Directive Addressing

Risks and Impacts on

Disadvantaged or Vulnerable

Individuals or Groups

This Directive establishes directions

for Bank staff regarding due

diligence obligations relating to the

identification of, and mitigation of

risks and impacts on, individuals or

groups who, because of their

particular circumstances, may be

It requires the Bank task team to support the

borrower in establishing arrangements for the

undertaking and preparation of the environmental

and social assessment of the project as required by

ESS1. It reviews the terms of reference for the

environmental and social assessment to verify that

(a) identifies (or requires the identification of) groups

Applies to Bank in addressing E&S risks

and impacts on disadvantaged and

vulnerable persons or groups that are

identified in this project corridor

Page 31: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

28 | P a g e

Table 1.4 – Relevance of World Bank E&S Policy, ESS, Directive and guidance notes to the sub-project

World Bank ESS Policy,

Standards, Directive Objectives Requirements

Relevance & Extent of Relevance to

the sub-project/project

disadvantaged or vulnerable

or individuals affected by the project that may be

disadvantaged or vulnerable; and

(b) requires an assessment of project risks and

impacts, and identification of differentiated mitigation

measures, as they pertain to the disadvantaged or

vulnerable individuals or groups that are identified.

World Bank’s Guidance note

on managing the risks of

adverse impacts on

communities from temporary

project induced labor influx,

2016

The document provides guidelines

to address issues and risks arising

from influx of migrant labor leading

to gender-based violence, forced

labor etc.

Requires HPRIC to prepare a labor influx

management and GBV risk mitigation plan

Applicable to all sub-projects, as influx of

migrant labor in construction works is a

norm in Himachal Pradesh

Page 32: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

29 | P a g e

1.12 Comparative Analysis of key national, state and Bank policies

A comparison between RFCTLARR Act, HP Private Negotiations order and guidelines, 2018, and World Bank’s ESF that provides gap-filling measures reflected in the entitlement matrix is presented as Appendix 4. These are summarized below:

The Act, like provisions of ESS, require SIAs for projects involving land acquisition with

elaborate process of consultation at every notification stage. It also expands compensation coverage of the principal act by requiring that the value of structure, trees, plants, or standing crops damaged must also be included and the solatium being 100 percent of all amounts inclusive. The Act similar to World Bank, requires compensation to be paid, prior to project taking possession of any land and provide R&R support including transitional support and moving allowances.

Act in its computation of compensation for structures takes depreciation into account and is not explicit about providing replacement cost of structures, though presumably the provision

of 100% solatium will help arrive at replacement cost of structures or higher. GoHP standing order and guidelines for establishing the compensation amount upto the threshold as would have been determined under the Act, 2013

Cut-off date for determining the compensation and entitlements and assistance to all those who are affected by the project irrespective of the ownership of titles. According to the RFCTLARR Act, the cut-off date for assistance to those depending on affected private lands is three years preceding the acquisition and for the titleholders it is the date of notification under the said Act. To bring this RPF in line with World Bank requirements, RPF mandates that while in the case of land acquisition, the date of issue of public notice of intended acquisition under Section 3(a) under the Act will be treated as the cut-off date for title

holders. In case of non-titleholders such as squatters and encroachers, cut-off date will be the start date of the census survey. In case of all affected non-title holders, suitable compensation (ex-gratia payments) for loss of assets and R&R assistance is proposed in the entitlement matrix. GoHP standing order does not have any provisions for non-titleholders

Also similar to provisions laid down in RFCTLARR Act 2013, World Bank ESS requires

consultation with PAPs during planning and implementation of resettlement action plan,

Tribal Development Plan and public disclosure of drafts.

In GoHP standing order, land compensation under private negotiations, the latest circle rate is considered and multiplied with 1 or 2 times in urban or rural areas respectively and 100% solatium is added to arrive at the final compensation upto the threshold as would have been determined under the Act, 2013. However, there could be gaps in asset valuation and

resettlement assistance. There is also a gap in case of those who loose land, the lump sum payment of INR 5, 00,000 towards livelihood loss is not extended.

1. In the event of any conflict or inconsistency between the provisions of this GOI, GoHP and RPF and the provisions of World Bank’s ESF, the provisions of the ESF shall prevail.

Page 33: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

30 | P a g e

1.13 Comparison of National Environmental Framework and ESF, 2018

2. The National Environmental Policy and Regulatory Framework and ESF, 2018 of World Bank have been compared and gaps if any are summarized in the Table 2-3.

Table 1-5: Comparison of National Environmental Policy and Regulations and ESF, 2018

S.No ESF, 2018 Description Equivalent National Environmental

Policy and Regulations

Gaps

1 ESS-1

Assessment and

Management of

Environmental and Social

Risks and Impacts

Environmental Impact Assessment

Notification-2006, 14th Sep-2006, as

amended in 2009 and 2013

The ESS 1 requires EA for road irrespective of its

type. While, EIA notification is limited to Expressway,

National highway and State Highway.

However, Environmental Impact Assessment

Notification-2006 is not applicable to the project

road.

2 ESS-2 Labor-and-Working-

Conditions

National Labour Act, 1970, The Building and

Other Construction Workers (Regulation Of

Employment And Conditions Of Service) Act,

1996 and Himachal Pradesh Building and

Other Construction Workers (Regulation Of

Employment And Conditions Of Service)

Rules, 2008

None at policy level. Broadly both cover all aspects.

3

ESS-3 and

EHS

Guidelines

of IFC

Resource-Efficiency-and-

Pollution-Prevention-and-

Management

Environmental protection Act, 1986 and

subsequent amendments

Air (Prevention and Control of Pollution) Act,

1981;

Water (Prevention and Control of Pollution)

Act, 1974, for Pollution-Prevention-and-

Management;

The Noise Pollution (Regulation And Control)

Rules, 2000

National Resource Efficiency Policy, 2019

(Draft)

Gap exists for Resource efficiency as the policy is in draft stage and yet to take off.

Gaps exist between National Air quality standards,

Water pollution limits and respective interim targets and guideline values of EHS Guidelines.

Page 34: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

31 | P a g e

S.No ESF, 2018 Description Equivalent National Environmental

Policy and Regulations

Gaps

4 ESS-4 Community-Health-and-

Safety

No Specific regulations for Community Health

but safety regulations at work place are

available

Gaps exist for Community-Health-and-Safety

5 ESS-5

Land-Acquisition-

Restrictions-on-Land-

Use-and-Involuntary-

Resettlement

The Himachal Pradesh Right to Fair

Compensation and Transparency in Land

Acquisition, Rehabilitation and Resettlement

(Social Impact Assessment and Consent)

Rules 2015, Acquisition of Land by Private

Negotiation and Upkeep of Land2017-PWD/

GoHP, January 2018 Record/General

Guidelines and Instruction (Standing Order

No .28)(PBW(B)F(5)40/

None at policy level. Broadly both cover all aspects.

6 ESS-6 Biodiversity-Conservation Biological Diversity Act, 2002 None at policy level. Broadly both cover all aspects.

7 ESS-7 Indigenous-Peoples Not applicable

8 ESS-8 Cultural-Heritage

Ancient Monuments and Archaeological Sites

and Remains Act, 1958 and The Himachal

Pradesh Ancient and Historical Monuments

and Archaeological Sites and Remains Act,

1976

None at policy level. Broadly both cover all aspects.

9 ESS-9 Financial-Intermediaries Not applicable

Page 35: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

32 | P a g e

S.No ESF, 2018 Description Equivalent National Environmental

Policy and Regulations

Gaps

10 ESS-10

Stakeholder-

Engagement-and-

Information-Disclosure

Environmental Impact Assessment

Notification-2006, 14th Sep-2006, as

amended in 2009 and 2013

None at policy level. Broadly both cover all aspects.

However, Environmental Impact Assessment

Notification-2006 is not applicable to the project road

11 EHS Guidelines for Construction

Materials Extraction, April, 2007, IFC

National Resource Efficiency Policy, 2019

(Draft)

Gap exists for Resource efficiency including materials extraction as the policy is in draft stage and yet to take off.

Page 36: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

33 | P a g e

1.14 Institutional Framework

The project implementation involves multiple institutions, namely: HPRIDC of HPPWD, HPDOT and HP

State Police Commission. HPRIDC will be responsible for the overall coordination of the project

implementation. The reform of HPPWD and road infrastructure improvement will be implemented by

HPRIDC. HP State Police Commission will implement the Road Safety component.

Himachal Pradesh Road & Other Infrastructure Development Corporation Limited, a wholly owned

Company of Government of Himachal Pradesh was incorporated on 10.06.1999 under the Companies Act,

1956,

HPRIDC is an apex organization in Himachal Pradesh engaged in fostering the growth of infrastructure

development in the State. Its objectives are to:

a) construct erect build, re-model, execute, repair, develop, improve, administer, manage, control,

maintain, demolish, grade, curve, pave, macadamize, cement, Highways, Expressways, Roads,

Paths, Streets, Bridges, Sideways, Bypasses, Tunnels, Pavements, Reclamation, Improvements,

Road over Bridges, Road under Bridges, Underground Road, or any other structural or

architectural work and also to do other similar construction, leveling or paving work at present

being a part of the activity of the Himachal Pradesh Public Works Department;

b) facilitate and or undertake to construct, erect, build, renovate, develop, improve, manage, control

maintain other infrastructure projects including those related to Power, Telecom Information and

Technology, Transmission of Electricity, Water Supply Projects, etc.;

c) act as a special purpose vehicle for resource mobilization on behalf of the State Government for

all infrastructure projects

HPRIDC headed by the Managing Director (Principal Secretary of HPPWD) and governed by a Board of

Directors chaired by the Chief Secretary of the State is currently the focal unit for the development of the

state core roads network (SCRN) and managing upgrading and major rehabilitation contracts.

HPRIDC has acquired some experience from the implementation of HPSRP – I. It has built capacity and

has procurement, financial management, contract administration and support staff necessary for the

implementation of the proposed project.

HPRIDC will engage Environment and Social Safeguards officers and Project Management Consultant

(PMC), which will be responsible for quality assurance and monitoring

HPRIDC has established a system dealing with external complaints on procurement, fraud/corruption and

construction quality. This system will include maintaining files to monitor status of follow up of each

received comments, suggestions and grievances. The implementation of the system will be monitored by

Chief Vigilance Officer of the PWD (who shall act Vigilance Officer (VGO) for the HPRIDC). The

mechanisms will include provision for follow up investigations of substantial complaints to ensure

independency and reliability of the system. For the complaint mechanism to function efficiently, the

information concerning the alternative conduits for complaint (dedicated email address and physical

mailing box) are being publicized. Complaints, suggestions and grievances handling system have been

included at HPRIDC website: http://admis.hp.nic.in/himachal/hpridc. An Information Officer who has been

designated by HPRIDC as a full-time Assistant Public Information Officer under the RTI Act is responsible

for monthly updates of the system on the website

Page 37: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

34 | P a g e

Responding to Complaints on Construction Quality Complaints received directly from the public relating to

the quality of a specific work, good or service shall be in writing. They will be received and then reviewed

by CE-cum-PD or if applicable, Zonal Chief Engineer of HPPWD concerned and dealt with in the following

way. i) The CE-cum-PD shall record all complaints, whether they are referred from other recipients or

directly, in a register to be maintained in a secure location in his own office. The email and physical

address of the CE-cum-PD is available on web site. ii) The CE-cum-PD shall, within 5 working days of

receipt of complaint, acknowledge receipt in writing to the complainant indicating that the HPRIDC is

considering the issues raised and will discuss them with the concerned officers of the HPRIDC. iii) The CE-

cum-PD shall then consult with the relevant officers of the HPRIDC and, after thorough review of the facts

as well as interviewing of officers concerned as necessary, shall make a judgment as to the validity of the

complaint. iv) Within 20 working days, the CE-cum-PD shall instruct the relevant officer to take remedial

action as necessary. v) The CE-cum-PD shall write to the complainant within 30 working days of the

receipt of such complaint as to the final decision of the competent authority. vi) In the event, that a

complaint is received concerning an externally funded contract, the relevant funding agency shall be

informed at each stage of the complaint handling process.

There is no specific GRM to systematically receive, record and redress complaints from project affected

persons.

Page 38: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

35 | P a g e

2. ENVIRONMENTAL AND SOCIAL RISKS AND MITIGATION MEASURES

2.1 SUMMARY OF RISK/IMPACTS

Identification of Environmental and social Risks/Impacts was carried during EIA process is summarized as follows in table 2-1.

Table 2-1: Environmental and Social Risks/Impacts

Components Environmental and social Risks Risk Type

Construction Phase

Topography &

Geology

Change in existing profile of the land due to earthwork and rock

excavation.

Disturbance on geological setting due to hill side cutting/quarrying

resulting in the accumulation of debris material.

Low risk

Soil Loosening of topsoil & loss of vegetative cover along the road due to

excavation and back filling which will lead to enhanced soil erosion. Low risk

Land Use

Generation of debris waste in the form of excavated

material/construction spoils from construction sites.

Changes in existing land use pattern of the ROW for construction of

the road.

Roadside agricultural land will be affected by unauthorised debris

disposal.

Moderate risk

Drainage Chances of filling of existing drainage courses during earth filling.

Scouring of land in the outfall locations of culverts. Moderate risk

Water Use Impact on the local water sources due to its usage as construction

water. Low risk

Water Quality Water pollution due to sewage from construction camps. Moderate risk

Air Quality

Deterioration of air quality due to fugitive dust emission from

construction activities like excavation, backfilling & concreting,

hauling & dumping of earth materials & construction spoils, and

vehicular movement along unpaved roads.

Deterioration of air quality due to gaseous emissions from

construction activities.

Moderate risk

Noise Level Increase in noise level due to construction activities like operation of

construction equipment and vehicular traffic. Moderate risk

Flora and

Fauna

Loss of flora & loss of habitat of fauna due to felling of trees along

the ROW. Low risk

Construction

Camp

Influx of construction work force and supplier who are likely to

construct temporary sheds in the vicinity.

Likely sanitation and health hazards & other impacts on the

surrounding environment due to inflow of construction labourers.

Health risks due to lack of health and sanitation conditions through

disposal of sewage on open land which may cause mosquito

nuisance, water borne diseases etc. Chances of spread of sexually

transmittable diseases like AIDs.

Moderate risk

Occupational

Health &

Safety

Health & safety related problems to construction workers due to

inadequate health & safety measures. Moderate risk

Road Safety Increase on incidence of road accidents due to disruptions caused in

existing traffic movements. Moderate risk

Page 39: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

36 | P a g e

Components Environmental and social Risks Risk Type

Operational Phase

Land Use &

Encroachment

Change of land use by squatter/ encroachment within ROW and

induced development outside the ROW.

New spaces generated due to shift in alignment could be encroached

by local people or other people.

Moderate risk

Drainage Environment degradation is due to improper maintenance of

drainage. Moderate risk

Air Quality Air pollution due to vehicular emission from road traffic. Low risk

Noise Level Noise pollution due to increased traffic. Low risk

Access

Significant severance problem on pedestrian & animal crossing and

cross traffic due to widening, partially access control & increase in

traffic speed.

Low risk

Road Safety Impacts on human health due to accidents.

Damage of road due to wear and tear. Low risk

Potential Social and Environmental Impacts The social and environmental impacts /risks are given as below.

DESCRIPTION

POTENTIAL SOCIAL AND ENVIRONMENTAL IMPACTS/RISKS

LOW MODERATE SUBSTANTIAL HIGH

Land Use

Water Resources

Floods

Climate

Physiography And Drainage

Slope Stability And Land Slides

Air Quality And Noise Levels

Surface Water Quality

Biodiversity

Ancient And Historical Monuments And Chance Finds

NO RISK

Tourism NO RISK

Industries/Industrial Corridor NO RISK

Common Property Resources

Sensitive Receptors

Vulnerability

Carbon Footprint And Ghg Emissions

2.2 MITIGATION MEASURES

To address above risks, mitigation measures have been proposed and have been included in various

design proposals (as described below) and site-specific enhancement or management plans. These are;

2.2.1 Design Proposals

2.2.1.1 Provision of Protection Measures

Based on the designed alignment and topographic survey results, the location, where the normal fill

slopes cannot be used due to the topographic conditions, retaining walls have been provided. Stone

Masonry will be used for the retaining wall and breast wall construction respectively. The locations of the

proposed protection measures are provided in Table 2-2.

Page 40: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

37 | P a g e

Table 2-2: Locations of the proposed protection measures

S. No Chainage

length (meters) Description from to

1 3+350 3+400 50 Retaining wall both sides

2 4+000 4+050 50 Breast wall on one side

3 4+170 4+250 80 Breast wall on one both side

4 4+250 4+350 100 Breast wall on LHS

5 4+480 4+620 140 Breast wall on RHS

6 4+730 5+100 370 Breast wall on RHS

7 6+550 6+760 210 Retaining wall at School (LHS)

8 8+720 8+830 110 Breast wall on RHS

9 8+930 8+990 60 Breast wall on LHS

10 9+080 9+130 50 Breast wall on LHS

11 9+230 9+260 30 Breast wall on RHS

12 9+630 9+680 50 Breast wall on RHS

13 9+770 9+800 30 Breast wall on LHS

14 9+880 9+910 30 Breast wall on LHS

15 10+010 10+110 100 Breast wall on LHS

16 10+170 10+330 160 Breast wall on LHS

17 10+400 10+500 100 Breast wall on LHS

18 10+620 10+680 60 Breast wall on LHS

19 10+730 10+760 30 Breast wall on LHS

20 10+870 10+910 40 Breast wall on LHS

21 11+310 11+450 140 Breast wall on RHS

22 11+510 11+600 90 Breast wall on RHS

23 12+070 12+100 30 Breast wall on LHS

24 12+100 12+150 50 Breast wall on LHS

25 12+390 12+460 70 Breast wall on LHS

Total Length 2230

2.2.1.2 Provision for Bio Engineering Interventions

Provisions made for the bioengineering interventions covers areas/locations along the RoW at upstream

and downstream of seasonal streams, CD structures, muck/debris disposal sites, areas reclaimed /open

areas in RoW, areas of cleared of invasive vegetation’s among others. Based on the slope angles, slope

stability and suitability of Bio engineering interventions, the following has been considered as given in

table 2-4.

Table 2-4 Provision of Bioengineering Interventions

S.No Item Unit Quantity

1.1 Construction of hedge brush layer RM 1,500.00

1.2 Construction of brush layer RM 900

2 Construction of live palisade RM 900

3 Construction of live Fascine RM 900

4.1 Grass slip plantation on slope <45° @ 100 drills/sqm sqm 3000

4.2 Grass slip plantation on slope 45°-60° @ 100 drills/sqm sqm 600

4.3 Grass slip plantation on >60° slope @ 100 drills/sqm sqm 600

Page 41: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

38 | P a g e

S.No Item Unit Quantity

4.4 Plantation of large sized stature grass slips at slope of <45° @ 20 slips/sqm

sqm 600

5 Bamboo crib wall cum 1,200.00

6 Tree plantation in plains with tree guard nos 1,000.00

7.1 Shrub Plantation in plains with tree guard nos 2,500.00

7.2 Agave plantation in slopes nos 1,500.00

8.1 Group plantation of shrubs sqm 1,200.00

8.2 Hedge Plantation (2 plants/RM) RM 900

8.3 Hedge Plantation (4 plants/RM) RM 900

9 Bamboo plantation with Bamboo tree guard nos 600

10 Construction of Gabion cum Under Civil

Works

11 Construction of barb wire RM Under Civil

Works

12.1 Grass seed sowing<40° sqm 6000

12.2 Grass seed sowing<40° with mulch sqm 5000

12.3 Grass seed sowing on slope 40-45⁰ with mulch and jute netting sqm 3500

13 Hydro seeding sqm 5000

2.2.1.3 Provision of Drainage

Based on topography, two types of surface drains have been proposed for the project and schedule for same is given in table 2-5. These two types are;

V-Shaped Drain: This drain is provided normally in the cut slopes located in hilly and rolling terrain, this

drain is of lined in nature. Predominant lengths in hilly areas are provided with this drain type.

Rectangular Drain: For the locations, such as built up areas and those with pedestrian movements rectangular drains have been proposed. As per the requirement, it is provided on one side or both sides of the project road.

Table 2-5: Drainage Provisions

Sr No Chainage

Length (m) Type of Drain

From To LHS RHS

1 0+00 0+520 520 Rectangular drain Rectangular drain

2 0+520 0+600 80 V-Drain V-Drain

3 0+600 1+150 550 V-Drain V-Drain

4 1+150 1+400 250 Rectangular drain Rectangular drain

5 1+400 1+890 490 V-Drain V-Drain

6 1+890 2+500 610 Rectangular drain Rectangular drain

7 2+500 3+700 1200 V-Drain V-Drain

8 3+700 3+850 150 V-Drain V-Drain

9 3+850 3+890 40 V-Drain V-Drain

10 3+890 3+930 40 V-Drain V-Drain

11 3+930 4+050 120 V-Drain V-Drain

12 4+050 4+170 120 V-Drain V-Drain

13 4+170 4+270 100 V-Drain V-Drain

14 4+270 4+300 30 V-Drain V-Drain

15 4+300 4+370 70 V-Drain V-Drain

16 4+370 4+420 50 V-Drain V-Drain

Page 42: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

39 | P a g e

Sr No Chainage

Length (m) Type of Drain

From To LHS RHS

17 4+420 4+480 60 V-Drain V-Drain

18 4+480 4+600 120 V-Drain V-Drain

19 4+600 4+620 20 V-Drain V-Drain

20 4+620 4+730 110 V-Drain V-Drain

21 4+730 5+100 370 V-Drain V-Drain

22 5+100 5+300 200 V-Drain V-Drain

23 5+300 6+550 1250 Rectangular drain Rectangular drain

24 6+550 6+760 210 Rectangular drain Rectangular drain

25 6+760 7+100 340 Rectangular drain Rectangular drain

26 7+100 7+500 400 V-Drain V-Drain

27 7+500 7+770 270 Rectangular drain Rectangular drain

28 7+770 8+720 950 V-Drain V-Drain

29 8+720 8+830 110 V-Drain V-Drain

30 8+830 8+930 100 V-Drain V-Drain

31 8+930 8+990 60 V-Drain V-Drain

32 8+990 9+080 90 V-Drain V-Drain

33 9+080 9+130 50 V-Drain V-Drain

34 9+130 9+150 20 V-Drain V-Drain

35 9+150 9+230 80 Rectangular drain Rectangular drain

36 9+230 9+260 30 Rectangular drain V-Drain

37 9+260 9+450 190 Rectangular drain Rectangular drain

38 9+450 9+630 180 V-Drain V-Drain

39 9+630 9+680 50 V-Drain V-Drain

40 9+680 9+770 90 V-Drain V-Drain

41 9+770 9+800 30 V-Drain V-Drain

42 9+800 9+880 80 V-Drain V-Drain

43 9+880 9+910 30 V-Drain V-Drain

44 9+910 9+930 20 V-Drain V-Drain

45 9+930 9+990 60 V-Drain V-Drain

46 9+990 10+010 20 V-Drain V-Drain

47 10+010 10+110 100 V-Drain V-Drain

48 10+110 10+170 60 V-Drain V-Drain

49 10+170 10+330 160 V-Drain V-Drain

50 10+330 10+400 70 V-Drain V-Drain

51 10+400 10+500 100 V-Drain V-Drain

52 10+500 10+620 120 V-Drain V-Drain

53 10+620 10+680 60 V-Drain V-Drain

54 10+680 10+730 50 V-Drain V-Drain

55 10+730 10+760 30 V-Drain V-Drain

56 10+760 10+870 110 V-Drain V-Drain

57 10+870 10+910 40 V-Drain Rectangular drain

58 10+910 11+180 270 Rectangular drain Rectangular drain

59 11+180 11+250 70 V-Drain V-Drain

60 11+250 11+310 60 V-Drain V-Drain

61 11+310 11+450 140 V-Drain V-Drain

62 11+450 11+510 60 V-Drain V-Drain

Page 43: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

40 | P a g e

Sr No Chainage

Length (m) Type of Drain

From To LHS RHS

63 11+510 11+600 90 V-Drain V-Drain

64 11+600 11+650 50 V-Drain V-Drain

65 11+650 11+900 250 V-Drain V-Drain

66 11+900 11+950 50 V-Drain V-Drain

67 11+950 12+000 50 V-Drain V-Drain

68 12+000 12+070 70 V-Drain V-Drain

69 12+070 12+150 80 V-Drain V-Drain

70 12+150 12+390 240 V-Drain V-Drain

71 12+390 12+460 70 V-Drain V-Drain

72 12+460 12+700 240 V-Drain V-Drain

73 12+700 13+320 620 Rectangular drain Rectangular drain

Total 13320m

2.2.1.4 Provision of Cross drainage structure

Surface drains are further connected to culverts so that water can be channelized down the valley. Erosion control measures in the form of step apron have been provided at the outlet of the culvert. Schedule of the culvert is provided in table 2-6 below.

Table 2-6: Schedule of Proposed Culverts

S. No

Chainage Improvement

Proposal Structure

Type S.No Chainage

Improvement Proposal

Structure Type

1 0+358 Reconstruction to Box Box 22 4+250 Reconstruction to Box Box

2 0+460 Reconstruction Box 23 4+317 Reconstruction to Box Box

3 0+600 Reconstruction Box 24 4+637 Reconstruction to Box Box

4 0+761 Reconstruction to Box Box 25 4+897 Reconstruction to Box Box

5 0+858 Reconstruction to Box Box 26 5+131 Reconstruction to Box Box

6 0+887 reconstruction MNB 27 5+508 Reconstruction to Box Box

7 0+910 retained MNB 28 5+797 Reconstruction to Box Box

8 1+125 Reconstruction Box 29 7+211 Reconstruction to Box Box

9 1+293 Reconstruction to Box Box 30 7+380 Reconstruction to Box Box

10 1+907 Reconstruction to Box Box 31 7+629 Reconstruction to Box Box

11 2+060 New Construction Box 32 8+420 New Construction Box

12 2+480 New Construction Box 33 8+783 Reconstruction to Box Box

13 2+935 New Construction Box 34 9+046 Reconstruction to Box Box

14 3+127 Reconstruction to Box Box 35 9+630 New Construction Box

15 3+342 Reconstruction to Box Box 36 9+846 Reconstruction to Box Box

16 3+502 Reconstruction to Box Box 37 10+174 New Construction Box

17 3+604 Reconstruction to Box Box 38 10+643 Reconstruction to Box Box

18 3+733 New Construction Box 39 11+178 Reconstruction to Box Box

19 3+843 Reconstruction to Box Box 40 12+167 New Construction Box

20 3+906 Reconstruction to Box Box 41 12+389 New Construction Box

21 4+093 Reconstruction to Box Box 42 12+500 New Construction Box

Page 44: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

41 | P a g e

2.2.1.5 Bus Stops/ Rain Shelters

Based on the locations of the existing bus stops/ rain shelters and the consultations carried out by both Social and Environmental teams; a 6 seater toilet (3 seat for men, 3 seat for women) is provided at (13+100) Ladrour bazar. The maintenance of these toilets will be undertaken by the local market bazar association at Ladrour. Provisions to have bio toilets at bus stops could not be finalized due to required high level of maintenance issues during operational stage despite this issue was requirement from the

local people during the consultations.

2.2.1.6 Improvement of Major/Minor Intersections

To establish better connectivity to the nearby towns, villages/ settlements, the major/minor intersections

along the project road has been designed the details are given in the table 2-8 (Major/minor junctions).

Table 2-8 Lists of Major/Minor Junctions to be Improved

S. No chainage Type of Junction

Cross Road Details

Surface Type

Width of Carriage way

Cross Road Leads to

1 0/000 Y (Major) BT 11.2 Connecting NH-103

2 0+940 Y (Minor) BT 3.4 Ladrour

3 1+620 Y (Minor) BT 3.1 Naswal

4 2+100 Y(Minor) BT 3.2 Village link road

5 6+220 Y(Minor) BT 3.4 Chakrana

6 6+260 Y(Minor) BT 3 Lohat

7 7+670 Y(Minor) BT 3.3 Kuthura

8 10+210 Y(Minor) BT 3 Village link road

9 10+690 Y(Minor) BT 2.4 Village link road

10 12+240 Y(Minor) BT 3.1 Hatwad

11 12+940 Y(Minor) BT 2.4 Village link road

12 13+383 T(Minor) BT 8 Hamirpur/Mandi

2.2.1.7 Safety Measures:

To ensure safe movement of traffic/people along the road, safeguard measures like information/caution boards, object markers, chevrons etc. has been proposed. Quantity of road signage proposed is given in

table 2-9.

Table 2-9 Summary of Road Signs for Project Road

S. No Description Unit Dadhol-Ladrour

A

Informatory Signs

a) Facility information Signs of size 800mm x 600mm Nos. 26

b) Direction / Place Identification signs Nos. 56

c) Advance Direction / Destination / Reassurance / Place Identification signs

Nos. 6

e) Route marker signs Nos. 8

B

Mandatory Signs, Size

a) Circular of size 900mm Nos. 18

b) Octagonal of size 900mm Nos. 12

c) Triangular of size 900mm Nos. 222

c Object Marker (Hazardous) Nos. 164

D Chevron Signs (Hazardous) Nos 142

Page 45: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

42 | P a g e

2.2.2 Site Specific Management Measures

As part of the Environmental Assessment, consultations were held in the project road at various locations. The outcome of the consultations was noted and for the discussed impacts and suggested mitigation/enhancement measures have been proposed on locations, as given in table 2.10.

Table 2-10: Provision of Specific management or Enhancement measures

Chainage Feature Specific Measures Reference drawing

1+130

Km

Govt High

School Gahar

Provision of Noise barrier (RHS);

Masonry boundary wall (of 60m length and 3m height) over the edge of the road & 20 nos tree plantation along the wall. Provision of two pits (having configuration of 2m X 4m X 1.2m) for disposal of solid and

liquid wastes within School.

Drawing no; HP/DAD-LAD/NB-01

(Appendix-15)

Page 46: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

43 | P a g e

Chainage Feature Specific Measures Reference drawing

4+520 Km

Govt Primary School

Provision of Noise barrier (RHS); Masonry boundary wall (of 30m length and 3m height) & 20 nos tree plantation along the wall and access road.

Drawing no;

HP/DAD-LAD/NB-01 (Appendix-15)

Page 47: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

44 | P a g e

Chainage Feature Specific Measures Reference drawing

6+470 Km

Govt Primary School, Bharari

Provision of Noise barrier (RHS); Masonry boundary wall (of 60m length and 3m height) over the edge of the road & 30 nos tree plantation along the wall.

Provision of two pits (having configuration of 2m X 4m X 1.2m) for disposal of solid and liquid wastes within School.

Drawing no; HP/DAD-LAD/NB-01 (Appendix-15)

Page 48: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

45 | P a g e

Chainage Feature Specific Measures Reference Drawing

6+640 Km

Govt Hospital, Bharari

Provision of Noise barrier at Hospital at Bharari (RHS); Masonry wall boundary 40-meter long and 3-meter height.

15 nos trees plantation along the wall and access road.

Drawing no; HP/DAD-LAD/NB-01 (Appendix-15)

Page 49: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

46 | P a g e

Chainage Feature Specific Measures Reference Drawing

12+500 Km

Existing Crematorium

Improvement of access, Construction of water

tank and provision of benches proposed as

enhancement measures for the roadside

crematorium;

Retaining wall with dimensions (L= 15m, a water tank & H=4m and 15 numbers of benches

(3-seater).

Drawing no; HP/DAD-LAD/CR-01 (Appendix-15)

Page 50: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

47 | P a g e

Chainage Reference Drawing Specific Measures

13+100 Drawing no;

HP/DAD-LAD/TOILET-001 (Appendix-15)

Provision of 6 Toilets (3 male & 3 female) at identified

location in Ladrour bazar. The maintenance and water

management during operation stage will be done by Vyapar

Mandal (assurance to do so is given in writing by the

Organisation/Mandal).

Page 51: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

48 | P a g e

3. ENVIRONMENTAL MANAGEMENT ACTION PLAN

Descriptions of the various management measures during various stages (Pre-construction, Construction

& Operation Phase) of the project have been provided in Table 3.1 EMAP (Environment Management

Action Plan).

3.1 PRE-CONSTRUCTION ACTIVITIES

Pre-Construction Activities by Project Implementation Unit (ESMU)

Prior to the Contractor mobilization, the PIU will ensure that an encumbrance free road section is handed

over to enable the start of construction. The RoW clearance involves 1) Removal of trees. 2) Relocation of

private/common property resources impacted.

Pre-Construction Activities by Contractor

The pre-construction stage involves mobilization of the Contractor, the activities undertaken by the

Contractor pertaining to the planning of logistics and site preparation necessary for commencing

construction activities. The activities includes; 1) Modification of Contract documents 2) Procurement of

construction equipment / machinery such as crushers, hot mix plants, batching plants and other

construction equipment and machinery 3) Identification and selection of material sources (quarry and

borrow material, water, sand etc.) and debris disposal locations 4) Planning traffic diversions and detours,

including arrangements for temporary land acquisition for Construction camps.

3.2 CONSTRUCTION STAGE

Construction Stage Activities by the Contractor

Construction stage activities require careful management to avoid environmental impacts. Activities that

trigger the need for environmental measures to be followed include 1) Implementation of site-specific

mitigation/management measures suggested 2) Monitoring the quality of environment along the

construction sites (as air, noise, water and soil).

There are several other environmental issues that have been addressed as part of good engineering

practices, the costs for which have been accounted in the engineering costs. They include improvement of

major & minor junctions, roadside drainage, provision of additional cross drainage structures or raising

the road height in low-lying stretches, provision of bus stops including bio toilets, provision of

landslide/erosion prevention measures etc.

Operation Stage

Monitoring the environmental attributes during the initial years of operation of the road shall be carried

out by the PIU (ESMU) Contractor as laid down in the monitoring plan, under the supervision of the

Engineer.

Page 52: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

49 | P a g e

Table 3-1: Environment Management Action Plan

S. No Project

Stage/Activity Mitigation Management Measures/GIIP Measures

Responsibility

Planning and

Execution

Supervision/

Monitoring

PRE-CONSTRUCTION ACTIVITIES BY ESMU (ENVIRONMENT AND SOCIAL MANAGEMENT UNIT OF HPSRTP/HPRIDC

1

Construction

Package including both Road and Bridge Components

The project road does not require any prior environmental clearances. Only permission for tree felling

will be required from department of forests, GoHP.

ESMU shall apply for the tree permissions well in advance and no site clearance or pre-construction

activities shall be initiated in stretches, which involve tree felling.

Environment & Social

Management Unit (ESMU) for project Road under HPSRTP/HPRIDC

Nodal Environmental Officer under HPSRTP under the guidance of Superintending Engineer of HPSRTP/HPRIDC

2

Land Acquisition (If required) and

clearance of encroachments

The acquisition of land and private properties will be carried out in accordance to project specific

resettlement policy framework. ESMU (Environment and Social Management Unit) must ascertain that

acquisition of land in the post design phase are addressed and integrated into the EMP and relevant

contract documents. In accordance to project specific Resettlement policy framework the encroachers

& squatters present in the Corridor of Impact, are relocated. All R&R activities will be undertaken.

ESMU, Revenue Dept, Collaborating Agencies

ESMU (Environment and Social Management Unit)

3

Relocation of Community Utilities and Common

Property

All community utilities and properties i.e., hand pumps, compound walls for school, govt building &

temple will be build/relocated before construction starts in the project road. Details of the community

properties affected are provided in the table below. There will be an impact to two hand pumps, one

Govt Building, one religious place and two compound walls due to project activities.

ESMU, Revenue Dept, Collaborating Agencies

ESMU (Environment and Social Management Unit)

PRE-CONSTRUCTION ACTIVITIES BY CONTRACTOR OR PROJECT MANAGEMENT CONSULTANTS (PMC)

4 Orientation for Contractor

Contractor is required to be oriented with the requirement of ESMF and ESS requirement of WB. This will include;

Regulatory compliance requirements

Grievance redress mechanism for both social and environmental issues

Health & safety related measures

labour management procedures

Community health & safety aspects at workplace and

Reporting requirements etc. under the project.

Contractor shall designate a dedicated one Environmental Officer and one Health and Safety Officer,

both of whom shall solely be responsible for implementation of all EMP provisions in close co-

ordination/consultation with EHS officer under CMU.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

5 Joint Field Verification

The Environmental Specialist of PMC and the Contractor will carry out joint field verification to ascertain any possibilities of saving trees, environmental and community resources, if these activities are to be taken up by the construction Contractor.

Environmental officer and Project Manager of the Contractor

Environment Specialist and Resident Engineer of Project Management Consultant (PMC)

Page 53: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

50 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

6

Crushers, Hot-mix Plants and Batching Plants Location

All construction plants will be sited sufficiently away from settlements and agricultural operations or any commercial establishments. Such plants will be located at least 100 m away from the nearest dwelling preferably in the downwind direction.

The Contractor shall submit a detailed layout plan for all such sites and approval of Environmental Specialist of PMC shall be necessary prior to the establishment. Protection measures will be considered, if the site selection is in rolling terrain.

Arrangements to control dust pollution through provision of wind Screens, water sprinklers, and dust extraction systems will have to be provided at all such sites.

Specifications for crushers, hot mix plants and batching plants will comply with the requirements of the relevant emission control legislations. Consent for the Establishment and Operation from HPPCB shall be obtained before establishment and operation respectively and a copy should be submitted to the PMC and ESMU. For dust suppression, water sprinkling will be done minimum three times a day.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

7

Other Construction Vehicles, Equipment and Machinery

All vehicles, equipment and machinery to be procured for construction will confirm to the relevant Bureau of India Standard (BIS) norms. The discharge standards promulgated under the Environment Protection Act, 1986 and Motor Vehicles Act, (Amendment) 2019 shall be strictly adhered to.

The Contractor shall maintain a record of PUC for all vehicles and machinery used during the contract period which shall be produced EO, ESMU/ PWD’s verification whenever required.

Contractor will also be required to have a vehicle fitness certificate, which is issued for two years for new vehicles and subsequently renewed after one year.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

IDENTIFICATION AND SELECTION OF MATERIAL SOURCES

8 Borrow Areas

Finalizing soil borrow areas for borrowing earth and all logistic arrangements as well as compliance to environmental requirements, as applicable, will be the sole responsibility of the Contractor.

The Contractor will not start borrowing earth from selected borrow areas until the formal agreement is signed between landowner and Contractor and a copy is submitted to the PMC for approval. If the land belongs to Govt then a prior approval from Govt will also require to be taken.

Locations finalized by the Contractor shall be reported to the Environmental Specialist of PMC and he will submit the report to ESMU.

Planning of haul roads for accessing borrows areas will be undertaken during this stage. The haul roads shall be routed to avoid agricultural areas as far as possible and will use the existing village roads wherever available. Following are the identified borrow areas locations and contractor may or may not use based on its requirement and ease.

Borrow Area Chainage (km) Distance from road Side Land use type

1 10+000 Roadside RHS Govt. Land

2 13+000 Roadside RHS Govt. Land

The environmental Specialist of the PMC will be required to inspect every borrow area location prior to approval. The PMC should include the Request for Inspection form for borrows area approval from the environmental angle. Following are the locations, identified during planning phase to open a borrow

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

Page 54: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

51 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

area. Contractor may or may not use these locations during implementation phase.

9 Quarry

Contractor will finalize the quarry for procurement of construction materials after assessment of the availability of enough materials, quality and other logistic arrangements.

In case the Contractor decides to use quarries other than recommended by DPR consultant, then the Contractor should give substantiation.

Contractor will also work out haul road network and report to Environmental Specialist of PMC and PMC will inspect and in turn report to ESMU before approval.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

10 Arrangement for Construction Water

To meet daily water requirements of water, Contractor shall prepare and implement the approved water management plan in accordance with the Appendix 3.

The Contractor will use ground /surface water as a source of water for the construction and may set up own bore well facility for construction work.

To avoid disruption/disturbance to other water users, the Contractor will extract water from fixed locations and consult with Environmental Specialist of PMC before finalizing the locations.

The Contractor will provide a list of locations and type of sources from where water for construction will be extracted.

The Contractor will need to comply with the requirements of the State Ground Water Department for the extraction and seek their approval for doing so and submit copies of the permission to PMC and ESMU.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

11 Labour Requirements

The Contractor preferably will use unskilled labour drawn from local communities to give the maximum benefit to the local community.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

12

Arrangements for Temporary Land Requirement

The Contractor as per prevalent rules will carry out negotiations with the landowners for obtaining their consent for temporary use of lands for construction camp/ borrow areas/Debris Disposal Area etc.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

13

Orientation of Implementing Agency and Contractors

The ESMU shall organize orientation sessions and regular training sessions during all stages of the Project. This shall include on-site training (general as well as in the specific context of a sub-project). These sessions shall involve of ESMU (involved in the implementation of EMP), staff of PMC and Contractors.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

CONSTRUCTION STAGE

Page 55: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

52 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

14 Clearing and Grubbing

Vegetation will be removed from the construction zone before commencement of construction. All works will be carried out such that the damage or disruption to flora other than those identified for minimum cutting.

Only ground cover/shrubs that impinge directly on the permanent works or necessary temporary works will be removed with prior approval from the Environmental Specialist of PMC.

The Contractor, under any circumstances will not cut or damage trees and forest reserves. Trees identified under the project will be cut only after receiving clearance from the Forest Department and after the receipt of ESMU’s written permission in this regard.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

15

Stripping, Stocking and Preservation of

Topsoil

The topsoil from all areas of cutting and all areas to be permanently covered will be stripped off to a specified depth of 150 mm and stored in stockpiles. A portion of the temporarily acquired area and/or Right of Way will be earmarked for storing topsoil. The locations for stock piling will be pre-identified in consultation and with approval of Environmental Specialist of PMC.

Such stockpiled topsoil will be utilized for –

To prepare surface for bioengineering measures.

Covering all disturbed areas including borrow areas

Dressing of slopes of road embankment

Agricultural fields of farmers acquired temporarily land.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

16

Construction Camp Locations -

Selection, Design and Lay-out

Contractor’s Environmental Officer and Health and Safety Officer in consultation and requisite

approvals from Gram panchayat and/or private land owners shall identify suitable lands, which can be

used as material stack yards and work camp sites for establishing macadam mix plants, hot mix plants

and storage of construction materials by the contractor during construction phase. The contractor will

have to lease private land for setting up campsites at suitable locations along road alignment and shall

mandatorily restore to its previous state after completion of road construction works.

Preferably barren lands or uncultivable lands and those away from human settlements shall be the

given preference, while selecting and establishing work camp sites. Also, these shall be at least 500m

distance away from forest areas and water bodies. The selected land shall not warrant significant

change in landforms or terrain, to make it suitable for establishing work camp sites/store yards. In

case, land had been earlier used for establishing work camp site and meets the above requirements,

same shall be given preference

If private land (s) has been identified, no site clearing operations shall commence without a written

agreement. The agreement with landowner shall clearly state the lease duration, compensation for the

agreed lease period, site restoration plan as desired/required by the landowner and any other

condition mutually agreed upon between contractor and landowner. In case agricultural land have

been chosen with no alternatives, then topsoil (30-45 cm deep) shall be collected and stored in an

access-controlled area and covered with net cloth. Regular sprinkling of water in pressurized fine spray

shall be done to prevent blowing away of soil. The topsoil shall be used during the restoration of site

and/or construction of shoulders

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

Page 56: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

53 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

Requisite consent to establish and consent to operate shall be obtained from HPSPCB. All stipulated

consent conditions by HPSPCB shall be strictly adhered and complied by contractor.

The work camp sites shall be access controlled with fixed entry and exit points.

The dust levels at the work camps sites is to be controlled through regular sprinkling of water through

similar mobile tankers deployed at operational areas for road construction. Bitumen mix plants,

Batch mix plants deployed for road construction shall conform to regulatory norms/requirements. The

site shall be cleared from all remnants of construction and debris and site restored to its previous

state, prior to handing the site to the owner. The work camp sites shall mandatorily have designated

paved areas for storage of used oils/lubes in plastic/HDPE drums, prior to their final disposal in

HPSPCB approved disposal locations

All work force deployed in operational areas shall be provided with PPEs like safety helmets, masks,

gloves, protective gear with reflective jackets and safety shoes. It shall be made mandatory to wear

them at work site. The PPEs shall be provided at no cost to workforce and shall be replaced once in

three months. Any damaged/lost PPEs shall be replaced with no cost to workforce. Visitors/officials to

worksite are to be provided with PPEs (hard hats and safety shoes) and shall be briefed ongoing

operations on that specific time and related safety requirement at work site including safe distances to

keep during the site visit.

Work force shall be subjected only to standard work shifts/hours. Overtime allowances, if

applicable/warranted shall be paid with ceiling limits. Working beyond such ceiling limits shall be

discouraged, even if, so desired workforce or contractor. All workforce deployed shall be governed

by labour management procedures under HPSRTP and Himachal Building and Other Construction

Workers (Regulation of Employment and Conditions of Service) Act, with regards to safety and

welfare measures (including equal wages for men and women) for workers employed at building and

other construction sites.

Provision of one mobile toilet of 2 seater capacity (1 men and 1 women with separate entrances) shall

be stationed at a suitable place within 100 metres from each operational area. The mobile toilet shall

have at least 1000 litres overhead water storage, well always maintained and in usable condition.

Bottom tanks shall be regularly cleaned and overhead tank replenished as per requirement. Work

force shall be oriented to use mobile toilets and avoid using public toilets and/or nearby open

places/parks.

Every operational area shall be provided with one mobile drinking water kiosk having a storage of 300

litres and placed at a suitable place within 100 metres from work site.

The operational work site shall have first aid kits and details of major/nearby hospitals

displayed prominently in local language, in case of emergency and/fatalities to work force and/or

Page 57: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

54 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

public, as a consequence of operations. The supervisory staff shall be provided with wireless

communication system (mobile telephones for better communication at operational area and also with

other operational area within same substation area, in case of emergency or otherwise. For

supervision staff, contractor shall provide rented residential accommodation with water, sanitation and

allied facilities for comfortable stay. The project will provide employment opportunities to both skilled

and unskilled largely to the local people and also urban poor. All work force sourced from local areas

can be expected to return to their places of residence after work shift hours. Pooled transportation

facilities wherever required shall be provided to workforce as a welfare measure.

The ambient air and noise levels within the work camps sites shall be monitored, once in month and

corrective measures if any required shall be taken in order be complaint with National Ambient Air

Quality and Noise Standards.

All work force shall be provided with suitable type of accommodation, if required and local labour or

can return to their normal places of residence. Pooled transportation facilities as may be required,

shall be provided by contractor. If establishing workforce camps become utmost necessary, then same

shall be established at least 500m away from the settlement areas and away from bridge sites and or

any other water body. The camp site shall be restored to its previous state or as agreed upon with the

landowner prior to establishing the workforce camp.

The workforce camps shall be provided with all basic facilities like water supply, cooking gas facility,

sanitation facilities including provision of mobile toilet (of adequate seating capacity for men and

women separately) shall be stationed within the workforce camp. The mobile toilet shall be periodically

replenished with fresh water for ablution purposes and wastewater shall be emptied through suction

tankers and carried to the nearest municipal sewage treatment facilities. Alternatively, septic tank cum

soak pit arrangements of adequate capacity shall be provided. The workforce camps shall have

arrangements for periodic health check-up by a visiting doctor at least once in a month, depending

upon size of the workforce camp, among others.

All work force shall be subjected to an orientation program, which familiarize them with work

requirements, safety practices at work, safe distances to keep from earth moving equipment, first aid

facilities, emergency response, on-site sanitation facilities and practices to be adopted, rights and

privileges of workforce among others. Orientation shall also include concern for safety of public around

operational areas as well. First aid facilities and free emergency care shall be provided to all

workforce, irrespective of their rank/level and no cost shall be recovered from them on this account.

Further, no wages shall be cut for period of absence as a result of injury – The contractor shall

mandatorily have Contractor All Risk (CAR) policy to cover workers of main contractor and as well as

all sub-contractors and third party. Work force shall be subjected only to standard work shifts/hours

without any wage parity. Overtime allowances shall be paid with ceiling limits. Working beyond such

Page 58: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

55 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

ceiling limits shall be discouraged, even if, so desired workforce or contractor.

Road construction related pollution risks include accidental release of fuel, used oil or chemicals and

contamination from poor waste practices that can affect surface and groundwater; contamination from

construction machinery working near springs and seasons streams; discharges and disturbance of soil

and sediment that drain into surface waters.

In addition, camp site, construction sites will generate and average sanitary wastes which need to be

treated through septic tank and soak pit disposal arrangements.

If not treated properly, the liquid waste will potentially cause both surface and ground water

contamination through surface run off and or through leaching through surface to groundwater

aquifers

All toilets and wash areas within the camp site and work force camps shall be provided with septic

tanks and soak pit arrangements, of adequate capacity. No wastewater from the camp/work force site

shall be discharged directly without any treatment in to any surface water channels or drain, which

eventually join surface water bodies.

The camp sites shall have 4 numbers of septic tank (each 5m Length, 2m Breadth and 1.5 m Clear

depth with 0.3 free board) with soak pit arrangement which can serve for work force at peak level as

per CPWD specifications. (See appendix 17)

The camp site shall have compost pits for treating organic waste and separate bins for collecting the

inorganic waste, which shall be disposed at nearest municipal disposal sites. The nearest such sites

are available at Mandi and Ghumarwin.

17

Earth / Rock excavation and Disposal of Muck/Construction Debris

The site clearance and/or excavation activities shall be opened up only in segments of 250m stretch at

a time and no new stretches shall be opened up unless the clearance and/or excavation activities in

previous stretches been satisfactorily completed and clearance given for the opening of next stretch by

CMU/CSC/EO of ESMU. Identified debris disposal locations;

Prior to undertaking any site clearance and/or excavation activities, particularly hill cut operations in

any segmental operational stretch, the contractor shall mandatorily prepare an excavation plan,

detailing the type and numbers of equipment required, estimated volume of material to be cut or

excavated, details of approved disposal sites, arrangements made for transport of excavated material

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

Page 59: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

56 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

to the approved disposal sites, dust suppression measures at excavation site and along transportation

routes, method of stacking and/or handling the excavated material at the disposal site including

rehabilitation plan of the disposal site, health and safety measures and emergency response plan for

the entire operation shall be prepared in advance. The contractor shall get the excavation plan so

prepared, duly approved by the environmental officer, RE of the construction supervision consultant

and/or head CMU, prior to commencement of the site clearance and/or excavation activities. All

construction waste materials shall be disposed of at locations identified under project as debris/muck

disposal sites or approved locations by the District administration for construction debris.

All types of excavated materials/construction debris from work/operational areas are to be transported

either to work camp sites for reuse and /or to approve locations for safe disposal at approved

locations/sites by the District administration. After the completion of construction works of road and

bridge and prior to opening of the road for traffic, the entire operational areas are to be cleaned and

all waste materials/ debris are to be removed and disposed at approved locations/sites by the District

The construction debris from all operational areas shall be regularly scavenged and disposed off at

disposal sites identified under the project or those approved by District administration. Prior to debris

collection, a fine spray of water shall be sprinkled with pressurized fine spray to contain/limit dust

levels at source. The excess portion of excavated material will have to be safely disposed in order to

minimize the impacts. Following are the locations identified for disposal od debris during excavation or

demolition process.

S. No. Chainage (Km) Type of Land Capacity (m3)

1 0+900 (RHS) Govt Land 14,000 (L=70m; W=40m; H=5m)

2 3+350 (RHS) Private Land 2200 (L=30m; W=15m; H=5m)

3 4+950 (RHS) Govt Land 4500 (L=30m; W=30m; H=5m)

4 5+650 (RHS) Govt Land 1500 (L=30m; W=25m; H=2m)

5 5+900 (RHS) Govt. Land (PWD) 1200 (L=40m; W=10m; H=3m)

6 10+700 (RHS) Govt Land (Revenue

department) 38500 (L=110m; W=50m; H=7m)

7 13+100 (RHS) Govt. Land (PWD) 4200 (L=40m; W=15m; H=7m)

Prior to disposal, all excavated materials shall be screened for recovery of good soil, which can be

used in the construction of sub grade, shoulders and rock boulders for gabions and or noise barrier

masonry walls. All the construction debris generating from construction works shall be segregated,

collected and safely disposed.

Stakeholder’s consultations/local enquiries has indicated that the disposal sites are available along the

project road, which can be used for disposal of require large quantities of construction debris/soil. As

Page 60: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

57 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

per the Construction and Demolition Waste Management Rules, 2016, the district administration also

have mandate to establish facility to receive and process the construction waste and debris.

All tipper trucks, carrying construction debris shall be covered with net cloth and wetted prior to

dispatch of every trip, to prevent en-route spills as well as airborne dust during transit. Tipper trucks

shall not be overloaded beyond designated capacities, to avoid en-route spills. The dust levels during

collection and loading operations of construction debris shall be controlled through periodical sprinkling

of water through 6000 litres capacity mobile water tankers stationed at operational areas and fitted

with pressurized fine spray with hose reels. Pressurized water spray will conserve water and avoid

unwarranted use of water for sprinkling at work sites/operational areas.

The noise levels during operations can be reduced through deployment of well- maintained and

relatively newer (less than 5-year old vehicles) and all excavation operations are conducted at normal

work pace.

18 Accessibility

The Contractor will provide safe and convenient passage for vehicles, pedestrians and livestock to and from roadsides and property accesses connecting the project road, providing temporary connecting road. The Contractor will also ensure that the existing accesses will not be undertaken without providing adequate provisions. After completion of the work damaged accesses will be restored by the Contractor.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

19 Planning for Traffic Diversions and Detours

Temporary diversions will be constructed with the approval of the Resident Engineer and Environmental Specialist of PMC. Detailed Traffic Control Plans will be prepared by the Contractor and submitted to Environmental Specialist and Resident Engineer of PMC for approval seven days prior to commencement of works on any section of road. The traffic control plans shall contain details of temporary diversions, traffic safety arrangements for construction under traffic, details of traffic arrangement after cessation of work each day, safety measures for night-time traffic and precaution for transportation of hazardous materials and arrangement of flagmen.

The Contractor will ensure that the diversion/detour is always maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow.

The Contractor will also inform local community of changes to traffic routes, conditions and pedestrian access arrangements with assistance from PMC and ESMU. The temporary traffic detours will be kept free of dust by sprinkling of water three times a day and as required under specific conditions (depending on weather conditions, construction in the settlement areas and volume of traffic).

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

PROCUREMENT OF CONSTRUCTION MATERIAL

20 Earth from Borrow Areas for Construction

No borrow area will be opened without permission of the Environmental Specialist of PMC. The location, shape and size of the designated borrow areas will be as approved by the Environmental Specialist of PMC and in accordance to the IRC recommended practice for borrow pits for road embankments (IRC 10: 1961). The borrowing operations will be carried out as specified in the guidelines for siting and operation of borrow areas. Following are the potential locations, which have been identified for contractor to borrow earth. Approval of these location will be dependent on Resident Engineer, PMC during construction stage after fulfilling all technical and environmental

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

Page 61: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

58 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

requirements by Contractor.

If The unpaved surfaces used for the haulage of borrow materials, passing through the settlement areas or habitations; will be maintained dust free by the Contractor. Sprinkling of water will be carried out twice a day to control dust along such roads during their period of use.

During dry seasons (winter and summer) frequency of water sprinkling will be increased in the settlement areas and Environmental Specialist of PMC will decide the sprinkling time depending on the local requirements.

Contractor will rehabilitate the borrow areas as soon as borrowing of soil is over from a borrow area in accordance with the approved borrow area Redevelopment Plan.

21 Quarry Operations Crushers

The Contractor shall obtain materials for quarries only after consent of the Department of Mining and District Administration. In view of the special situation of excavation of the hill ward side, Contractor will get an opportunity to use the same material for road construction. For the project one quarry has already been identified and is located 15 Km away from Dadhol, which is the beginning of the project road. The Contractor will develop a Comprehensive Quarry Redevelopment plan, as per the HP Mineral Policy 2013/guidelines as provided in appendix-4 and submit a copy to ESMU and PMC prior to opening of the quarry site. The quarry operations will be undertaken within the rules and regulations in force. The establishment of crusher will be done as per the existing guidelines (HP Mineral Policy 2013) for setting up of stone crushing units in Himachal Pradesh.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

22 Blasting

Except authorized by the Engineer, the Contractor will not use explosives. Where the use of explosives is so provided or ordered or authorized, the Contractor will comply with the requirements of the following Sub-Clauses of MoRTH 302 besides the law of the land as applicable.

The Contractor will always take every possible precaution and will comply with appropriate laws and regulations relating to the importation, handling, transportation, storage and use of explosives. The contractor will always when engaged in blasting operations, post enough warning flagmen, to the full satisfaction of the Engineer.

The Contractor will always make full liaison with and inform well in advance and obtain such permission as is required from all Government Authorities, public bodies and private parties whomsoever concerned or affected or likely to be concerned or affected by blasting operations.

Blasting will be carried out only with permission of the Engineer. All the statutory laws, regulations, rules etc., pertaining to acquisition, transport, storage, handling and use of explosives will be strictly followed.

Blasting will be carried out during fixed hours (preferably during mid-day) or as permitted by the Engineer. The timing should be made known to all the people within1000m (200m for pre-splitting) from the blasting site in all directions

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

23

Transporting Construction Materials and Haul Road Management

Contractor will maintain all roads (existing or built for the project), which are used for transporting construction materials, equipment and machineries as précised. All vehicles delivering fine materials to the site will be covered with tarpaulin to avoid spillage of materials.

All existing roads used by vehicles of the Contractor or any of his subcontractor or suppliers of materials and similarly roads, which are part of the works, will be kept clear of all dust/mud or other extraneous materials dropped by such vehicles. Contractor will arrange for regular water sprinkling as necessary for dust suppression of all such roads and surfaces. If a community/village road is to be

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

Page 62: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

59 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

used as a haulage road then drivers and other involved workers will be sensitized by imparting a training (quarterly) about “How to deal with community”. Community will be consulted by Contractor to fix the timings of road usages and should be avoided at peak hours.

24 Water requirement of project

The contractor shall not over depend on any one single source and shall identify multiple sources (at

least more than one), to avoid conflict of interest between pre-existing users of water sources and the

contractor. Water requirements of project are to be met from only existing tube/dug wells, with prior

approval of EMU. Contractor shall have more than one source to avoid over dependence on single

source and affect pre-existing users.

Project area and entire Bilaspur district is not categorized as over exploited area and therefore

contractor can even construct new tube wells specially for the water requirements of the project, if

required.

Water for construction should not be sourced from any waterbody/source used for drinking purpose,

but can be taken from waterbodies, which are neither used for drinking water or domestic purposes.

However, before abstracting the water the contractor has to obtain written permission from the

panchayat/letter and are from the irrigation and public health department. The Contractor shall

consider development of new surface water bodies at suitable places in the vicinity of the project road

and or renovation of existing surface water bodies with prior permission of the village panchayat for

harvesting of water during rainy season. This water can be used for construction purpose and on

completion of the construction the same can be handed over to the community for maintenance and

use. During the pre-Construction stage the contractor should preferably identify local depressions

along the alignment in consultation with the local panchayat to be developed as water storage areas.

The CMU can enter into an agreement with the panchayat for development of this water body and

using the water stored on it for construction purpose.

The Contractor should identify suitable water sources for meeting the construction water demand

including the construction of dedicated tube wells and take prior permissions for sourcing of water

from competent authorities like IPH and other local bodies. Overall, as there are no major and

perennial surface water bodies along and/or in the vicinity of the project road, the project road

construction cannot completely depend on surface water bodies and may have to largely depend on

ground water sources. Construction water would not be sourced from any tube wells, without prior

permission of the owners or the authorities or local bodies. The permission of IPH shall be obtained in

case new tube wells are to be constructed;

Adopt use of plasticizers/super plasticizers in concrete production to reduce water consumption. The

road construction by itself does not involve any operations, which lead to generation of

effluents/emissions that may directly or indirectly impact either surface and/or ground water

resources. All other off-site operational areas like camp site, work force camp sites, which are likely to

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

Page 63: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

60 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

have potential for pollution, are to be provided with on-site mobile sanitary facilities, the

effluents/waste discharges of which will be transported to nearest sewage treatment plants through

mobile tankers. Alternatively, the camp site and work force camp sites shall be provided with septic

tank with soak pit arrangement of adequate capacity. The oil/lube storage will be under roofed areas

with impermeable cement concrete surfaces. Thus, the project operations will not have any significant

scope for soil or surface and/or ground water contamination. Thus, road construction project will not

impact ground water sources.

The water usage pattern within the construction camps can be minimized by adopting following best practices:

i. Use buckets for washing purposes instead of using running water; ii. Use of auto shut off taps (without sensors) in labour accommodation; iii. Install water meters with main supply pipes/water tanks/bore well to assess quantity of

consumed water. iv. Create awareness among the camp site, work force camp sites at all levels.

25

Vulnerability aspects at all Construction and Operation sites

The overall vulnerability of Bilaspur district including the project road is categorized as moderate. In

order to ensure safety of work force during any kind of natural calamity (vulnerable situation) like

earthquake, landslide, flood, wind, an emergency response plan must be prepared by contractor,

which shall be duly approved by CMU.

In order to ensure the safety of work force at operational sites during natural calamities, emergency

response plan shall be followed. All work force irrespective of levels, are to be provided with training

to respond in an emergency and periodic mock drill will be conducted to ensure the preparedness to

respond any emergency situations.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

26

First Aid Facilities and Documenting Safety at all Construction and Operation sites

All labour shall be provided with safety instructions daily, depending upon the work, for which they

are likely to be deployed for the day/shift. Labour shall be provided with PPEs at no cost and ensure

that same is always being used by work force, while at work. In case of the damaged or lost PPEs,

same shall be replaced without any cost to labour. Labour shall be instructed to report, irrespective

of small or major or fatal injury to the supervisory staff and all such incidents shall be documented,

and ensure such incidents are not repeated by taking adequate precautions. All Supervisory staff

shall be provided with mobile phones for better communication across all operational areas, in case

of emergency or otherwise

First aid facilities and free emergency care shall be provided to all workforce, irrespective of their

rank/level and no cost shall be recovered from them on this account. Further, no wages shall be cut

for period of absence as a result of injury – The contractor shall mandatorily have Contractor All Risk

(CAR) policy to cover workers of main contractor and as well as all sub-contractors and third party.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

Page 64: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

61 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

CONSTRUCTION WORK

27

Floods, drainage including storm water management at Operational areas

Provision of enough cross-drainage structures with adequate capacities will reduce both the chances

as well as impacts of floods. In case of seasonal streams along project road, ensure construction of

check dams on the upstream side of seasonal streams and channelized the water on the

downstream side with protection measures to control erosion of soil, which in turn reduce floods on

downstream areas.

EPC Contractor shall ensure that no construction materials like earth, stone, or are disposed off in a

manner that can block the flow of drainage in and around the operational areas. Ensure that no site

clearance soil/debris are dumped into the drain prior to commencement of road construction

operations and the drain is to be periodically checked and cleaned throughout the construction

phase for deposition of construction debris during construction phase and follow it up with final clean

up just prior to opening of the road for traffic and handing over of road.

Also, it needs to be ensured that no water logging occurs along road construction operational area

during rainy days/ season and in turn affect the adjacent landowners. In case of excess water

logging, the same shall be emptied using dewatering pump or any other means as may be required,

to ensure adjacent landowners are not unduly affected.

Environmental

officer/health &

safety officer and

Project Manager of

the Contractor

Environment

Specialist and

Resident Engineer of

Project Management

POLLUTION PREVENTION

28

Potential water pollution from use of fuel, lubricants, and their storage/handling areas at material stock yards

EPC Contractor shall take pre-cautionary measures to ensure that no water pollution occurs through

surface runoff from construction vehicle parking areas, fuel/lubricants storage sites, vehicle, and

machinery/equipment maintenance sites. Contractor shall ensure that all vehicle/machinery and

equipment operation, maintenance and refueling shall be carried out in such a manner that spillage of

fuel and lubricants do not contaminate soil and groundwater. Areas used for handling of fuel and

lubricants, wherever applicable shall be impermeable surfaces and under roof to prevent groundwater

and soil contamination in the event of accidental spills.

Environmental

officer/health &

safety officer and

Project Manager

of the Contractor

Environment Specialist

and Resident Engineer of

Project Management

29 Dust Pollution

The Contractor will take every precaution to reduce the level of dust from construction plants, construction sites involving earthwork by sprinkling of water, encapsulation of dust source.

The Contractor will procure the construction plants and machinery, which will conform to the pollution control norms specified by the MoEF/CPCB/HPPCB.

The concentration of suspended particulate matter at 40m from a construction plant located in a cluster of industries should be less than 500 µg. The environmental monitoring is to be conducted as per the monitoring plan by the contractor. Alternatively, only crushers licensed by the HPPCB shall be used.

Environmental

officer/health &

safety officer and

Project Manager

of the Contractor

Environment Specialist

and Resident Engineer of

Project Management

30 Emission from Construction

Contractor will ensure that all vehicles, equipment and machinery used for construction are regularly maintained and confirm that pollution emission levels comply with the relevant requirements of CPCB

Environmental

officer/health &

Environment Specialist

and Resident Engineer of

Page 65: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

62 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

Vehicles, Equipment and Machineries

and/ Motor Vehicles Rules.

The Contractor will submit PUC certificates for all vehicles/ equipment/ machinery used for the Project.

safety officer and

Project Manager

of the Contractor

Project Management

31

Noise Pollution: Noise from Vehicles, Plants and Equipment Construction of Noise barriers at selected sensitive Receptors (Schools and Hospitals)

The Contractor will confirm the following:

All Construction plants and equipment used in construction shall strictly conform to the MoEF/CPCB noise standards. All vehicles and equipment used in construction will be fitted with exhaust silencers. Servicing of all construction vehicles and machinery will be done regularly and during routine servicing operations, the effectiveness of exhaust silencers will be checked and if found defective will be replaced.

The equipment available in the market should be procured, if the Contractor plans to purchase new equipment. For the old equipment, necessary or possible alterations must be carried out to reduce the noise levels to the possible extent.

Maintenance of vehicles, equipment and machinery shall be regular and up to the satisfaction of the Environmental Specialist of PMC to keep noise levels at the minimum.

At the construction sites within 150 m of the nearest habitation, noisy construction work such as crushing, operation of DG sets, use of high noise generation equipment will be stopped during the night-time between 10.00 pm to 6.00 am.

The school authorities at Bharari (6+520) were consulted as part of stakeholder consultations and the

authorities acknowledged that the school buildings have inadvertently extended into the right of way

more than a decade ago. At present, the school authorities are willing to return the land, provided the

existing facilities within such encroached RoW land are reconstructed elsewhere within the school

complex but at no cost to school. Therefore, clearance of the encroached RoW will require pushing

back these illegal structures and reconstruct the boundary cum retaining wall (also serve as noise

barrier) along with school utility buildings like drinking water counter, kitchen of mid-day meal

scheme, seating arrangement at basketball court, reconstruction of toilet blocks at selected locations

within the school complex.

Noise barrier and structures, which are to be reconstructed as part of vacating the encroached RoW

shall be completed prior to the road construction work at the respective location of the sensitive

receptor.

The details of the locations, where mitigation measures are provided near sensitive receptors is given

in below table.

Chainage Sensitive Location

Specific Measures Reference drawing

1+130 Km

Govt High School Gahar

Provision of Noise barrier (RHS); Masonry boundary wall (of 60m length and 3m height) over the edge of the road & 20 nos tree plantation along the wall.

Drawing no; HP/DAD-LAD/NB-01 (Appendix-15)

Environmental

officer/health &

safety officer and

Project Manager

of the Contractor

Environment Specialist

and Resident Engineer of

Project Management

Page 66: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

63 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

Provision of two pits (having configuration of 2m X 4m X 1.2m) for disposal of solid and liquid wastes within School.

4+520 Km

Govt Primary School

Provision of Noise barrier (RHS); Masonry boundary wall (of 30m length and 3m height) & 20 nos tree plantation along the wall and access road.

Drawing no; HP/DAD-LAD/NB-01 (Appendix-15)

6+470 Km

Govt Primary School, Bharari

Provision of Noise barrier (RHS); Masonry boundary wall (of 60m length and 3m height) over the edge of the road & 30 nos tree plantation along the wall. Provision of two pits (having configuration of 2m X 4m X 1.2m) for disposal of solid and liquid wastes within School.

Drawing no; HP/DAD-LAD/NB-01 (Appendix-15)

6+640 Km

Govt Hospital, Bharari

Provision of Noise barrier at Hospital at Bharari (RHS); Masonry wall boundary 40-meter long and 3-meter height. 15 nos trees plantation along the wall and access road.

Drawing no; HP/DAD-LAD/NB-01 (Appendix-15)

Ensure no conflicting situation develop/occur with the concerned school authorities as well as local

people during the entire road construction phase through a responsive grievance redressal mechanism

and conflict management initiatives.

SAFETY

32

Personal Safety

Measures for Labour

Contractor will provide:

Protective footwear, protective goggles and nose masks to the workers employed in asphalt works, concrete works, crusher etc.

Welder’s protective eye-shields to workers who are engaged in welding works

Earplugs to workers exposed to loud noise, and workers working in crushing or compaction

The Contractor will comply with all regulations regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations, trenches and safe means of entry and egress.

The Contractor will comply with all the precautions as required for ensuring the safety of the workmen as per the International Labour Organization (ILO).

The Contractor will make sure that during the construction work all relevant provisions of Building and other Construction Workers (regulation of Employment and Conditions of Services) Act, 1996 are

adhered to.

The Contractor will not employ any person below the age of 14 years for any work and no woman will be employed on the work of painting with products containing lead in any form.

The Contractor will also ensure that no paint containing lead or lead products is used except in the

Environmental

officer/health &

safety officer and

Project Manager

of the Contractor

Environment Specialist

and Resident Engineer of

Project Management

Page 67: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

64 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

form of paste or readymade paint.

Contractor will provide facemasks for use to the workers when paint is applied in the form of spray or a surface having lead paint dry is rubbed and PMC rapped.

The Contractor will mark ‘hard hat’ and ‘no smoking’ and other ‘high risk’ areas and enforce non-compliance of use of PPE with zero tolerance. These will be reflected in the Construction Safety Plan to be prepared by the Contractor during mobilization and will be approved by PMC and ESMU.

To promote and encourage a Safety culture, senior most engineers in Contractors and consultants’ teams shall wear helmets and safety jackets

33 Traffic and Safety

Ensure, traffic diversions are in place, to minimize the inconvenience to the existing road users during the road construction phase. Wherever required, adequate number of uniformed traffic wardens with reflective batons shall the deployed to manage the traffic for the entire construction phase.

Road construction schedule near sensitive receptors like schools and hospitals shall be informed to the concerned authorities well in advance. All works near sensitive receptors shall be adequately well planned and works shall be completed in shortest possible time, with minimal inconvenience to users of sensitive receptors locations. If warranted, steel barricades shall be used to minimize the inconvenience to the road users as well as occupants of the sensitive receptors.

Adequate traffic diversions near sensitive receptors shall be planned with adequate number of uniformed traffic wardens with reflective batons shall the deployed to manage the traffic, to ensure safety and minimal inconvenience to users of sensitive receptors location.,

Environmental measures such as construction of noise barriers etc shall be constructed for the identified sensitive receptors, well in advance of commencement of road construction works.

Dust suppression measures like regular sprinkling of water shall be carried out with more precaution near sensitive receptors to ensure dust levels kept to minimum. The construction debris and spills cleared of all construction debris daily near sensitive receptors.

While undertaking, road construction works near the natural water bodies and/or water sources along the project road, steel barricades shall be used to completely avoid trespassing of the construction labour and to avoid/prevent spills of the construction waste (solid or liquid) into the water body.

Extreme care shall be taken to ensure that no damage occurs to such natural water bodies and/or water sources along the project road due to the road construction works. All work forces shall be specifically oriented to strictly follow these instructions.

Environmental

officer/health &

safety officer and

Project Manager

of the Contractor

Environment Specialist

and Resident Engineer of

Project Management

34

First Aid Facilities and Documenting

Safety at all Construction and Operation sites

All labour shall be provided with safety instructions daily, depending upon the work, for which they are

likely to be deployed for the day/shift. All labour shall be provided with PPEs at no cost and ensure

that same is always being used by work force, while at work. In case of the damaged or lost PPEs,

same shall be replaced without any cost to labour

All labour shall be instructed to report, irrespective of small or major or fatal injury to the supervisory

staff and all such incidents shall be documented, and ensure such incidents are not repeated by taking

adequate precautions. All Supervisory staff shall be provided with mobile phones for better

communication across all operational areas, in case of emergency or otherwise

First aid facilities and free emergency care shall be provided to all workforce, irrespective of their

Environmental

officer/health &

safety officer and

Project Manager

of the Contractor

Environment Specialist

and Resident Engineer of

Project Management

Page 68: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

65 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

rank/level and no cost shall be recovered from them on this account. Further, no wages shall be cut

for period of absence as a result of injury – The contractor shall mandatorily have Contractor All Risk

(CAR) policy to cover workers of main contractor and as well as all sub-contractors and third party.

35 Informatory Signs and Hoardings

The Contractor will provide, erect and maintain informatory /safety signs, hoardings written in English and local language (Hindi), wherever required or as suggested by the Environmental Specialist of PMC.

After construction Information boards shall be erected for the tourism enhancement. These boards should be of international standards.

Health & safety

officer and Project

Manager of the

Contractor

Environment Specialist

and Resident Engineer of

Project Management

36 Risk from Electrical Equipment(s)

The Contractor will take all required precautions to prevent danger from electrical equipment and ensure that -

No material will be so stacked or placed as to cause danger or inconvenience to any person or the public.

All necessary fencing and lights will be provided to protect the public in construction zones.

All machines to be used in the construction will conform to the relevant Indian Standards (IS) codes, will be free from patent defect, will be kept in good working order, will be regularly inspected and properly maintained as per IS provision and to the satisfaction of the Environmental Specialist of PMC.

Environmental

officer/health &

safety officer and

Project Manager

of the Contractor

Environment Specialist

and Resident Engineer of

Project Management

BIO-DIVERSITY MANAGEMENT

37 Bio-diversity Management

In order to limit the impacts on the flora due to the road construction, the following measures are

considered:

Compensatory Plantation, in lieu of trees felled (at least 3 saplings for every tree cut with 90%

survival rate with three years maintenance) is to be taken up either along the project corridor or at

places identified by the department of forests, GoHP in order to compensate for the tree felled. With

this compensatory plantation measures, the tree cover lost could be regained in 5 to 7 years and thus

the impacts could get mitigated. Only local species, which are less water consuming and approved by

the forest department shall be used for plantation. Normally, all such afforestation will be undertaken

by the department of forest and maintained for three years as a deposit work. Therefore, cost

provision for Compensatory Plantation is included in ESMP Budget.

In order to limit the propagation of invasive species, firstly all such invasive species within the corridor

of impact and/or right of way shall be removed/cleared and replanted with local species. The

department of forests, GoHP has framed a procedure for removal of invasive species and replanting of

local species. The same is given in Annexure -9 of ESIA report. Normally, all such activities will be

undertaken by the department of forest and maintained for three years as a deposit work. Therefore,

cost provision for corridor plantation is included in ESMP Budget. As part of the project design, 0.3 Ha

of land has been identified within the RoW, which will be used for avenue plantation and/or

landscaping to improve the aesthetics of road corridor. In order to limit the impacts on the fauna due

Environmental

officer and Project

Manager of the

Contractor

Environment Specialist,

Bioengineering Expert

and Resident Engineer of

Project Management

Page 69: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

66 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

to the road construction, the following measures are considered:

The camp sites and work force camps shall be access controlled and well-lit to avoid/prevent

entry of stray or wild animals.

No pet animals shall be allowed to be raised / kept within the camp sites or work sites, which

in turn may attract the wild animals like leopard.

The work force shall be oriented not to feed monkeys

All work force shall be oriented to keep calm and walk away from the scene, in case, wild

animals are sighted either during work hours/night-time.

Work force shall be strictly instructed not to harm / kill wild animals under any circumstances

Work force shall be strictly prohibited like hunting of wild animals like wild boar etc., either

for consumption or for pleasure.

The Work force shall be strictly prohibited from entering into forest areas or private lands

under any circumstances.

The Construction camp and work force camp sites shall not be established in the

vicinity/nearby forest areas. Atleast 500m distance shall be kept from such areas under

unavoidable circumstances.

The construction work shall be restricted to day hours only and work shall not be carried out in the late evening hours/night hours /early mornings.

38

Ancient and Historical Monuments and Chance Finds

Project road corridor does not have any Ancient and Historical Monuments and therefore no measures

are warranted. Hence cultural heritage expert is not required to be deputed by ESMU.

All fossils, coins, articles of value of antiquity, structures and other remains or archaeological interest discovered on the site shall be the property of the Government and shall be dealt with as per provisions of the relevant legislation.

The Contractor will take reasonable precautions to prevent his workmen or any other persons from removing and damaging any such article or thing. He will, immediately upon discovery thereof and before removal acquaint the Environmental Specialist of PMC of such discovery and carry out the PMC’s instructions for dealing with the same, waiting which all work shall be stopped.

The PMC will seek direction from the Archaeological Survey of India (ASI) through HPRIDC before instructing the Contractor to recommence the work in the site.

Environmental

officer and Project

Manager of the

Contractor

Environment Specialist

and Resident Engineer of

Project Management

CONTRACTOR’S DEMOBILIZATION

39 Environmental Conditions

The Contractor will undertake seasonal monitoring of air, water, noise and soil quality through an approved monitoring agency. The parameters to be monitored, frequency and duration of monitoring

Environmental

officer and Project

Environment Specialist,

and Resident Engineer of

Page 70: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

67 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

as well as the locations to be monitored will be as per the Monitoring Plan prepared. National Standard of Air, Noise and Water given in Appendix-8.

Manager of the

Contractor

Project Management

40 Continuous Community Participation

The Environmental Specialist of PMC will have continuous interactions with local people around the project area to ensure that the construction activities are not causing undue inconvenience to the locals residing in the vicinity of project site under construction due to noise, dust or disposal of debris etc. The stakeholder’s engagement plan will be followed for community participation procedures.

Environmental

officer and Project

Manager of the

Contractor

Environment Specialist,

and Resident Engineer of

Project Management

41

Clean-up Operations, Restoration and Rehabilitation

Contractor will prepare site restoration plans, which will be approved by the Environmental Specialist of PMC. The clean-up and restoration operations are to be implemented by the Contractor prior to demobilization. The Contractor will clear all temporary structures; dispose all garbage, night soils and POL (Petroleum, Oil and Lubricants) wastes as per Comprehensive Waste Management Plan and as approved by PMC.

All disposal pits or trenches will be filled in and effectively sealed off. Residual topsoil, if any will be distributed on adjoining/ proximate barren land or areas identified by the Contractor and approved by the Environmental Specialist of PMC in a layer of thickness of 75 mm-150 mm.

All construction zones and facilities including culverts, road-side areas, camps, Hot Mix plant sites, Crushers, batching plant sites and any other area used/affected due to the project operations will be left clean and tidy, at the Contractor’s expense, to the entire satisfaction to the Environmental

Specialist of PMC.

Environmental

officer, Health and

safety officer and

Project Manager

of the Contractor

Environment Specialist,

and Resident Engineer of

Project Management

OTHER SPECIFIC ENHANCEMENT MEASURES

42 Specific enhancement measures

There are some site specific enhancement measure provided on project road. These include enhancement of existing community property (crematorium) at km 12+500 and provision of 6 toilets units (3 each for male and female).

Chainage Feature Specific Measures Reference drawing

12+500 km

Existing Crematorium

Improvement of access, Construction of water tank and provision of benches proposed as enhancement measures for the roadside crematorium; Retaining wall with dimensions (L= 15m, a water tank & H=4m and 15 numbers of

benches (3-seater).

Drawing no; HP/DAD-LAD/CR-01 (Appendix-15)

13+100 km

Market area without toilet facilities

Provision of 6 Toilets (3 male & 3 female) at identified location in Ladrour bazar.

Drawing no; HP/DAD-LAD/TOILET-001

Environmental

officer and Project

Manager of the

Contractor

Environment Specialist,

and Resident Engineer of

Project Management

Page 71: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

68 | P a g e

S. No Project Stage/Activity

Mitigation Management Measures/GIIP Measures

Responsibility

Planning and Execution

Supervision/ Monitoring

(Appendix-15)

The maintenance and water management for toilets during operation stage will be done by Ladrour Vyapar Mandal (assurance to do so is given in writing by the Organization/Mandal).

OPERATION STAGE

43 Monitoring Operation Performance

The ESMU will monitor the operational performance of the various mitigation/ enhancement measures carried out as a part of the project.

The indicators selected for monitoring include the survival rate of trees; utility of enhancement provision made under the project; status of rehabilitation of borrow areas; and effectiveness of noise barriers.

ESMU ESMU/PWD

44 Maintenance of Drainage

PWD will ensure that all drains (side drains, median drain and all cross drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding.

ESMU ESMU/PWD

45 Pollution Monitoring

The periodic monitoring of the ambient air quality, noise level, water (both ground and surface water) quality, soil quality in the selected locations as suggested in pollution monitoring plan through the HPCB or its approved monitoring agency.

Pollution Monitoring Agency

ESMU/PWD

46 Soil Erosion and Monitoring of Borrow Areas

Visual monitoring and inspection of soil erosion at borrow areas, quarries (if closed and rehabilitated), embankments and other places expected to be affected, will be carried out once in every three months as suggested in monitoring plan.

ESMU ESMU/PWD

47 Changes in Land Use Pattern

Necessary hoardings will be erected indicating the availability of ROW and legal charges for encroachment of RoW. Budgetary provisions are to be made to control the ribbon development along project road.

ESMU, Revenue Department and Local Civic Bodies

ESMU/PWD

48

Public awareness on Noise levels and Health Affects

However, the public will be advised to construct the noise barriers such as walls, double glazed windows and tree plantation between the roads and their property the public awareness is necessary regarding the human health through the newspapers and consultations and distribution of pamphlets during the operation stage.

ESMU ESMU/PWD

Page 72: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

69 | P a g e

Figure. Septic Tank Specifications

Page 73: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

70 | P a g e

Figure. Oil Interceptor

Page 74: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

71 | P a g e

4. ENVIRONMENTAL MONITORING PROGRAMME

4.1 GENERAL

The monitoring and evaluation are critical activities in implementation of the Project. Monitoring involves periodic checking to ascertain whether activities are going according to plan or not. It provides the necessary feedback for project management to ensure that the project objectives are met and on schedule.

The reporting system is based on accountability to ensure that the environmental mitigation measures are implemented.

Environmental monitoring program has the underlying objective to ensure that the intended environmental mitigations are realized and these results in desired benefits to the target population causing minimal deterioration to the environmental parameters. Such program targets proper implementation of the EMP.

The broad objectives are:

1. To evaluate the performance of mitigation measures proposed in the EMP.

2. To evaluate the adequacy of environmental assessment.

3. To suggest ongoing improvements in management plan based on the monitoring and to devise fresh monitoring based on the improved EMP.

4. To enhance environmental quality through proper implementation of suggested mitigation measures.

5. To meet the requirements of the existing environmental regulatory framework and community

obligations.

4.2 PERFORMANCE INDICATORS

Environmental components identified of a significance in affecting the environment at critical locations have been suggested as performance indicators (PIs). For example, near the construction site, a thick layer of dust over the nearby vegetation/leaf is an indication that the dust control measures are not

effective. The performance indicators shall be evaluated under three heads as;

Environmental condition indicators to determine efficacy of environmental management measures in control of air, noise, water and soil pollution.

Environmental management indicators to determine compliance with the suggested environmental management measures.

Operational performance indicators have also been devised to determine efficacy and utility of the proposed mitigation measures.

The performance indicators and monitoring plans prepared for the Dadhol-Ladrour road section are presented in table 4-1. Details of the performance indicative parameters for each of the component have to be identified and reported during all stages of the implementation.

Table 4-1: Performance Indicators

S No. Description of Item Indicator Stage Responsibility

1

No. of Borrow Areas identified and verified No. of sites for which Restoration Plans

have been prepared No. of Site Restored and Rehabilitated

No. of Sites handed over

Borrow Area and Quarries

Pre-Construction

Contractor

2 No. of Quarry Areas identified & verified No. of sites Restoration Plans are required

and have been prepared

Borrow Area and Quarries

Pre-Construction

Contractor

Page 75: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

72 | P a g e

S No. Description of Item Indicator Stage Responsibility

No. of Site Restored and Rehabilitated No. of Sites handed over

3

Quantity of Debris and Spoils to be disposed off No. of locations Approved for Debris

disposal

Quantity disposed off at each location No. of locations for which Rehabilitation

works have been completed

Disposal sites Construction Contractor

4

No. of location/s identified for the Construction camp and Construction Plant sites

No. of location/s approved Lay-out/s Approved No. of sites for which Site Restoration and

Rehabilitation has been completed

Construction Camps and Plant Sites

Pre-Construction

Contractor

5 No. of Trees to be Cut No. of Trees cut % Progress on the tree removal

Tree cutting

Pre-Construction

ESMU

6 No. of Locations identified for temporary storage areas for storage of the excavated materials to be used in embankment and sub grade

Storage of excavated materials

Pre-Construction and

Construction

Contractor

7

Before the onset of monsoon all the debris/excavated material shall be cleaned from the work sites and disposed of at the pre-identified approved locations.

Silting of Water bodies

Construction Contractor

8 Implementation of enhancement measures for Noise Barrier at sensitive locations

Enhancements Construction Contractor

9 Drainage Length (by type)

No. of Locations

Work sites Construction Contractor

10

Safety Provisions Signage (by type and no.) Crash barriers footpath

Work sites Construction Contractor

11

Soil erosion prevention measures Construction of retaining walls Downstream at culvert locations ( No. of

Locations & length)

Work sites Construction Contractor

12 No. of HIV awareness sessions conducted - Construction Contractor

13 No. of safety awareness sessions conducted - Construction Contractor

14 Accidents No of accidents recorded

Along project road

During construction

Contractor

15

Environmental parameter monitoring in accordance with the frequency and duration of monitoring as well as the locations as per the Monitoring Plan given in Table 4.2

Air Quality Noise Quality Soil Quality Water Quality

Construction and Operation

Contractor through NABL Accredited agency.

16

No. of Training Sessions Organised for i. Departmental Staff ii. Contractors iii. Combined

No. of People Trained iv. Departmental Staff v. Contractors

Training Imparted

Construction /Operationa

l face

ESMU

17 No. of awareness sessions for educating the public about road safety and other environmental aspects

- Construction/ Operation

ESMU

Page 76: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

73 | P a g e

S No. Description of Item Indicator Stage Responsibility

(Such as waste dumping, preservation of enhanced sites, pollution and health impacts etc.)

Stage

18

No. of Trees Planted (Total) No. of Trees under Compensatory

Afforestation No. of Trees Planted along Roadsides No. of Trees planted at other locations

(such as camps, borrow areas, debris disposal sites and plant areas)

No. of trees planted at enhancement sites

Roadside and other plantation areas

Post construction stage

Forest Department and ESMU

19

Survival Rate Trees Planted (Average) Compensatory Afforestation Roadside Plantation Other locations (such as camps, borrow

areas, debris disposal sites and plant areas)

Enhancement sites

Roadside and other plantation

areas

Post construction

stage

Forest Department and

ESMU

4.3 MONITORING PLAN FOR ENVIRONMENTAL CONDITIONS

For each of the Environmental Conditions, the Monitoring Plan specifies the parameters to be monitored,

location of the monitoring sites, frequency and duration of monitoring. The monitoring plan also specifies

the applicable standards, implementation and supervising responsibilities. The monitoring plan and details

of monitoring locations for environmental condition indicators of the project during the construction and

operation stage are presented in Table 4-2.

The monitoring will be carried out by Contractor through the NABL approved agency and will be

supervised by the Environment Specialists of the PMC and ESMU.

Page 77: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

74 | P a g e

Table 4-2: Environmental Monitoring Plan for Air, Water, Noise and Soil

Attribute Timing Paramet

er Special Guidance Standards Frequency Duration Location

No of Samples/ Year

Implementation

Air

Construction CO, NOx,

PM10, PM2.5 and

SO2

High Volume sampler to be located 50 m

from the plant in the down wind direction. Use

method specified by CPCB for

Analysis

CPCB Guidelines (NAAQMS/ Volume-

I/2013-14)

Every month at 3 locations

24 hours sampling

3 locations (Construction Plant Sites,

settlements and Work Zones)

36 Contractor

Operation

Once in summer and

winter for three years

Roadside 4 ESMU

Water

Constructio

n As per

Drinking Water

Standards

Grab sample

collected from source and

analyse as per standard methods for examination

Indian standards for inland surface

waters (IS:2296,1982

) and for drinking water

(IS:10500-2012)

Every month at 3 locations

As per Grab

Sampling guidelines

Drinking water samples from

the labour camps and from

hand pumps

Surface water from the water

courses near the work site and

River.

36 Contractor

Operation Surface water

sources 4 ESMU

Noise

Construction

Noise Levels on

dB (A) scale

Equivalent noise levels using, and integrated noise

level meter kept at 15 m from edge of

pavement

Noise rules 2000 by CPCB

Every month at 3 locations

Leq in dB(A) of daytime

and night-time

Near the

working zones, sensitive

receptors and construction plant sites

36 Contractor

Operation

Once every season for 5 year after

completion of construction

activity

Sensitive receptors

4 ESMU

Page 78: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

75 | P a g e

Attribute Timing Paramet

er Special Guidance Standards Frequency Duration Location

No of Samples/ Year

Implementation

Soil

Construction

Monitoring of Pb, SAR

and Oil and

Grease

Sample of soil collected to acidified and

analysed using absorption spectrum

(IS): 2720 for 'Method of Test

for Soils'

During the pre & post monsoon

season each year

Grab Sampling

Construction Camp/ plant

sites & productive agricultural

lands abutting traffic detours

and traffic diversions and

major

intersections.

18 Contractor

Operation Surface water

sample 4 ESMU

Page 79: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

76 | P a g e

4.4 REPORTING SYSTEM

Reporting system for the suggested monitoring programme operates at two levels:

1) Reporting for environmental condition indicators and environmental management indicators

2) Reporting for operational performance indicators at the ESMU level.

Environmental monitoring involves regular checking of the environmental management issues detailed in

the EMP and to ascertain whether the mitigation measures are achieving their objectives, according to the

EMP, with the progress of the works. It provides the necessary feedback for Project management to keep

the programme on schedule.

The Contractor, PMC and ESMU operate the reporting system for environmental conditions and

environmental management indicators. The reporting system is presented in table 4-3. Reporting formats

for Contractors have been prepared, which will form the basis of the implementation by the Contractor

and monitoring by the PMC and ESMU. The list of reporting formats prepared for the Project is presented

in Table 4-4 and Formats are presented in Appendix-7.

The reporting system will start with the Construction Contractor who is the main executor of the

implementation activities. The Contractor will report to the Project Management Consultant, who

in turn shall report to the ESMU.

The Contractor will submit monthly and quarterly environmental compliance reports

along with formal monthly and quarterly reporting to the PMC.

The PMC will submit separate quarterly environmental monitoring reports to ESMU in addition to

submission of the summary of the activities of the month in the formal monthly report including

any deviations and corrective actions

ESMU/PMC will be responsible for the preparation of the targets for identified non-compliances.

Solutions for further effective implementation may also emerge as a result of the compliance

monitoring reports.

Environmental Management Compliance Certificate (appendix 15) will be issued by Environment

Specialist of PMC during the submission of each Interim Payment Certificate (IPC). This certificate

will be based on compliance status of environmental measures during that tenure for which IPC

has been produced.

Photographic records will be kept to provide useful environmental monitoring tools. All material

source locations, debris disposal locations, plants locations, Construction camp locations, Crusher

locations etc. will have a complete photographic record. Photographs for all these establishments

will be taken prior to establishment activities begin, during the establishment and operation

process and after rehabilitation. The record will be submitted to PMC half yearly and will also be

availed to PMC/ESMU, as and when required.

A full record of construction activities will be kept as a part of normal Contract monitoring system.

The operation stage monitoring reports may be annual, provided the Project Environmental

Completion Report shows that the implementation was satisfactory.

This reporting will be as follows:

Reporting by the Contractor to the PMC.

Reporting by PMC to ESMU.

Reporting by ESMU for the information of all interested parties.

Page 80: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

77 | P a g e

Table 4-3: Reporting System

Items

Contractor Project Management Consultant ESMU World Bank (WB)

Implementation & Reporting to PMC

Supervision Reporting to

HPRDIC

Oversee Compliance Monitoring

Report to WB

Desired Supervision

Construction Stage

Monitoring of Construction Site and Construction Camp

Before start of work Regular Quarterly Quarterly Quarterly

Pollution Monitoring As required As required Quarterly Quarterly Quarterly Quarterly

Debris Disposal Area Weekly Regular Quarterly Quarterly Quarterly Quarterly

Monitoring of Enhancements Implementation As required Quarterly Quarterly Quarterly Yearly

Topsoil Preservations Weekly As required Monthly Quarterly Quarterly

Yearly

Borrow Area/Quarry

Area/Debris Disposal Area Regular As required Monthly Quarterly Quarterly Yearly

Tree Cutting - - - Quarterly Quarterly

Yearly

Tree Plantation - - - Quarterly Quarterly

Yearly

Operation Stage

Pollution Monitoring As per monitoring

plan - -

Table 4-4: Summary Details of Reporting Formats

Format No. Item Stage

Contractor Project Management Consultant (PMC)

Implementation &

reporting to PMC Supervision Reporting to ESMU

RF 1 Approval of Construction Camp/ Plant Site and its Management Plan

Pre-Construction One Time One Time One Time

RF 2 Approval of Borrow Management Plan (General & Specific)

Pre-Construction General -One Time Specific re- development plan - one for each borrow area

Regular Quarterly

RF 3 Construction Camp and Plant Site Management

Construction Monthly Regular Quarterly

RF 4 Topsoil Management Construction Monthly Regular Quarterly

RF 5 Pollution Control and Construction Construction Monthly Regular Quarterly

Page 81: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

78 | P a g e

Format No. Item Stage

Contractor Project Management Consultant (PMC)

Implementation & reporting to PMC

Supervision Reporting to ESMU

Plants

Pollution Monitoring Construction and Operation

- Quarterly

RF 6 Vehicles and Pollution Control Construction Monthly Regular Quarterly

RF 7 Details of the DG Sets and Pollution Control

Construction Monthly Regular Quarterly

RF 8 Details of Oil Storage Construction Monthly Regular Quarterly

RF 9 Working at Water Courses & Pollution Control

Construction Monthly Regular Quarterly

RF 10 Details of Water Extraction Construction Monthly Regular Quarterly

RF 11 Details of Personal Protective Equipment

Construction Monthly Regular Quarterly

RF 12 Status of Consent for Water Extraction

Construction Quarterly Quarterly Quarterly

RF 13 Deviations and Corrective Actions Construction — Monthly Quarterly

RF 14 Implementation of Enhancement Measures for Cultural Properties, Water Harvesting Structures

Construction Monthly Regular Quarterly

RF 15 Debris generated by the hill ward side widening, cutting of hill slopes

During construction Throughout the construction period during widening

Regular Quarterly

RF 16 Grievance Redressal Mechanism during Construction

During Construction Monthly Regular Quarterly

RF 17 Work Force Management

During Construction Monthly Regular Quarterly

RF 18 Occupational Health Safety Measures During Construction Monthly Regular Quarterly

RF 19 Road Safety Measures During Construction Monthly Regular Quarterly

RF 20 Accidents Reporting During Construction Monthly Regular Quarterly

RF 21 Monthly Reporting During Construction Monthly Regular Monthly (as an annexure to MPR)

Page 82: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

79 | P a g e

The Environment Specialist of PMC can make required changes in the formats specified in Appendix 10 of

EMP to ensure effective reporting of environmental issues. For making any required changes in the

frequency of reporting and change in the contents of the report for effective and simple for

implementation and monitoring, PMC should discuss the reporting formats with the Contractor and ESMU.

This will not only ensure that the environmental provisions are addressed but also link the satisfactory

compliance to environmental procedures prior to approval of the Interim Payment Certificate (IPC) by the

Engineer. In the regular monthly meeting, the environmental aspects should also be discussed and the

staff responsible for the implementation of the environmental management from the Contractor, ESMU

and PMC should also be present.

4.5 INSTITUTIONAL ARRANGEMENTS

Institutional arrangements are intended to achieve certain level of quality in the project during

implementation of various project components by the Government of Himachal Pradesh (GoHP) as

specified by the various conditions of loan agreement between the World Bank and the GoHP. These are

basically to meet the World Bank ESS (Environment and Social Standards) that in turn will make sure

that the country laws (Indian laws and regulations) are not violated during the pre-construction,

construction and Operational (defect liability period) stages of the project.

ESMU is headed by the Chief Engineer, who will be responsible for the successful implementation of the

Project. The Chief Engineer is also the Project Director in the ESMU set up for the implementation of the

project. The Project Director (PD) will be assisted by Superintendent Engineer of ESMU, who further will

have support from Construction Management Unit (CMU) at site and Experts (Nodal Environmental

Officer, Social Development officer, Horticulture Officer) at the head office. The Nodal Environmental

officer at the HQ will coordinate with CMU for the implementation of the Environmental Management Plan

at ESMU headquarters. Roles and responsibilities of ESMU in HPRIDC is given below in table 4-4.

Table 4-5: Roles and responsibilities of the staff in ESMU of HPRIDC

Position Roles & Responsibilities

Project Director

Chief Engineer-cum-Project Director will be overall in-charge of the Road and other Projects in HPRIDC. He is responsible to the Board and the State Government for efficiently carrying out of all preparatory studies, works in his administration and

accounts pertaining to all such studies and works

Superintendent Engineer

Superintending Engineer (Planning & Design) will be assisting the Chief Engineer-cum-Project Director in efficient functioning of the Project Implementation Unit of HPRIDC.

Nodal Environmental Officer, ESMU

Nodal Environment Officer will be directly responsible to the CE-cum-PD for the efficient discharging of duties. He will deal with matters pertaining to integration of EA/EMPs into project design, construction management during project implementation, reporting and documentation etc. He will interact with CMUs for collecting information on environment management.

He will be assisted by Junior Engineer.

Social Development officer

Social Development Officer will be directly responsible to the CE-cum-PD for the efficient discharging of duties. He will be overall responsible for coordinating with Land Acquisition Officers (LAOs), Public Works and Revenue Departments for land acquisition for upgrading works. He will coordinate the activities of NGOs on board and RRO of CMUs for implementation of Resettlement Action Plans (RAPs) and R & R assistance.

Horticulture Specialist

Nodal Forest Officer will be directly responsible to the CE-cum-PD for the efficient discharging of duties. He will be responsible for regulatory clearances, plantation works including compensatory afforestation, biodiversity management and coordination with the concerned departments/agencies.

Page 83: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

80 | P a g e

For PMC, Environment Specialist (full time) at PMC, Head Quarter (HQ) will look after the EMP

implementation and report to Resident Engineer on site. Bio-Engineering Expert and Horticulture

Development Officers at PMC, HQ will have intermittent input and will visit sites as per requirements. At

site PMC will have an EHS officer to implement EMP.

For Contractor, Project manager will be assisted by one Environmental Officer and one Health and Safety

officer who will coordinate with PMC and ESMU staff for implementation of EMP.

ESMU will hire a NGO or any other agency for the implementation of RAP on site. The agency will support

Social development officer, ESMU and will coordinate with R&R and Revenue officer posted in CMU at site.

Page 84: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

81 | P a g e

Institutional arrangements for Implementation of Environmental and Social Management Plan (ESMP & RAP)

Page 85: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

82 | P a g e

5. CAPACITY BUILDING AND TRAINING

5.1 CAPACITY BUILDING AND TRAINING

Capacity building and training would be required especially for the CMU and PIU staff associated with

the project as the Environmental Safeguards. The training and capacity building would not only be

project specific but would also target and develop long term capacities in the ESMU.

5.2 TRAINING PROGRAMMES

The training programme will be implemented as per training modules provided in table 5-1. These

training programmes are not part of the Contractors plan and estimates but will be a part of the

project cost that includes institutional strengthening, capacity building and training. Training module

can be changed during construction phase based on requirements by ESMU. Total earmarked training

& capacity building cost is estimated 10 lakhs. Out of this amount, seven lakhs have been proposed

for Trainings sessions for 9 days (in complete project cycle) as given in table 5-1. Three lakhs have

been proposed for Crash Courses on Focused Themes Relating to Environmental Management as

suggested in table 5-2.

The basic objective of giving training to different Stakeholder is to enhance their capabilities for

implementation of Environmental Management and Monitoring Plan. It is recommended that training

be given at least 4 times both offsite and on site.

Before Start of Construction Work During Construction Before de-mobilization of Contractor After Construction before Start of Monitoring

Page 86: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

83 | P a g e

Table 5-1 Training Module

S. No. Training Recipients Mode of Training Environmental Aspects to be covered in

training modules

Training Conducting

Agency

(Before Start of Construction Work by ESMU)

One day

1 Staff of ESMU and CMU Lecture Session, presentation & discussion

World Bank’s Environment and Social Management Framework

Environment Specialist, ESMU

2 Staff of ESMU and CMU Lecture Session, presentation & discussion

Legal requirements of the project

Environment Specialist, ESMU

3 Staff of ESMU and CMU Lecture Session, presentation &

discussion

Specific Environment and Social Management

Plan

Environment Specialist, ESMU

(Before Start of Construction Work)

Day-1 (Session-I)

1 Staff of ESMU, staff of PMC, Engineering Staff of Contractor and Collaborating Government Agencies

Lecture Sessions, Presentation and discussion

Overall generic Environment Issues, Regulations & Statuary requirements and Mitigation Measures

PMC

2

Staff of ESMU, staff of PMC, Engineering

Staff of Contractor and Collaborating Government Agencies.

Lecture Sessions, Workshops & Presentation

Institutional Set Up, Role and Responsibility of Stake Holders and Contractual obligations

PMC

Day-1 (Session-II)

3 Staff of ESMU, staff of PMC, Engineering Staff of Contractor and Collaborating Government Agencies.

Lecture Sessions, Workshops & Presentation

Bioengineering; Introduction, Scope, institutional Set Up, methods etc

PMC

4 Staff of ESMU, staff of PMC, Engineering Staff of Contractor and Collaborating Government Agencies.

Lecture Sessions, Workshops & Presentation

Biodiversity Management; Concept, scopes and measures in the project

PMC

Day-2 (Session-I)

Page 87: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

84 | P a g e

S. No. Training Recipients Mode of Training Environmental Aspects to be covered in training modules

Training Conducting Agency

1 Staff of ESMU, staff of PMC, Engineering Staff of Contractor and other Concerned Agencies.

Lectures; Demonstration sessions

Project related Project related environmental issues and mitigation measures

PMC

2 Staff of ESMU (Nodal Level), staff of PMC, Engineering Staff of Contractor.

Group Discussions and action plan for the project

Environmentally Sound Construction Management & Environmentally, Sustainable operations of Highways

PMC

Day-2 (Session-II)

3 Staff of ESMU staff of PMC, Engineering Staff of contractor.

Lectures; Group Discussions Supervision and Monitoring, Reporting Formats PMC

4 Staff of ESMU, staff of PMC, Engineering Staff of Contractor and Collaborating Government Agencies.

Lecture Sessions, Workshops & Presentation

Occupational Health and Safety Community Health and Safety

PMC

Module for Training During Construction (Immediately after Commencement of Construction activities)

Day-1

1 Staff of ESMU involved in the project, staff of PMC, involved in construction, contractor

Lecture Sessions, Presentation & Workshops

Implementation of Environment Management Plan, Environment friendly Construction Methodology and Workers Safety during Construction

PMC

2 Staff of ESMU involved in the project, staff of PMC, involved in construction, contractor

Lecture Sessions, Workshops & Presentation

Interactive discussion, Monitoring and Reporting System

PMC

3 Staff of ESMU staff of PMC, Engineering Staff of contractor.

Lectures; Bio-engineering types and various methods

PMC

Day-2

4 Staff of ESMU staff of PMC, Engineering Staff of contractor.

Lectures; Biodiversity Management; Concept, scopes and measures in the project

PMC

5 Staff of ESMU staff of PMC, Engineering Staff of contractor.

Lectures; Occupational and Community Health and Safety; Introduction, Scope and management measures

PMC

6 Staff of ESMU staff of PMC, Engineering Staff of contractor.

Lectures; Stake holder’s engagement procedures, Grievance redressal mechanism

PMC

Module for Training during Construction

One day

1 ESMU, Staff of PMC, All Staff of

contractor

Lecture Sessions, Workshops &

Presentation

Environment friendly Construction Methodology

and Workers Safety PMC

2 ESMU, Staff of PMC, All Staff of contractor.

Practical on Site Traffic and Safety Management during construction;

PMC

Page 88: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

85 | P a g e

S. No. Training Recipients Mode of Training Environmental Aspects to be covered in training modules

Training Conducting Agency

Safety Practices

3 ESMU, Staff of PMC, All Staff of contractor.

Practical on Site Demonstration of Bioengineering techniques to be used in project on site

PMC

Module for Training before Contractor Demobilization

One day

1 ESMU Staff, Staff of PMC, Engineering Staff of Contractor.

Lecture, Presentation Sessions Restoration of Site PMC

2 ESMU Staff, Staff of PMC, Engineering Staff of Contractor.

Lecture Sessions, Presentation, Workshop and lesson learned

Reporting Formats for Restoration PMC

After Construction before Start of Monitoring

One day

1 ESMU Lecture Sessions, Presentation and Workshop

Environment Monitoring PMC

2 ESMU Lecture Sessions, Presentation, Workshop

Reporting Formats PMC

Table 5-2 Crash Courses on Focused Themes Relating to Environmental Management

S. No Training Institutions Target groups Contents of the training

1 Indian institute of Remote sensing, Dehradun PWD Executive Engineers Geographic information Systems (GIS)

2 National Environmental Engineering Research Institute

(NERI) Nagpur Junior Engineers Air, Water Noise Quality modelling

3 National Remote Sensing Agency, Hyderabad Assistant Engineers Application of satellite imageries in road planning

4 Indian Institute of Ecology and Environment, New Delhi Selected Engineers from all levels Himalayan Ecology

5 Forest Research Institute, Dehradun Environmental Engineers Training programme on environmental

management relating to transport projects

6 Centre of Environmental Education, Ahemadabad Selected Engineers from all levels Legal dimension of Environmental management

7 Wadia Institute of Himalayan Geology Junior Engineers Himalayan Geology and seismicity

8 National Institute of Training for Highway Engineers

(NITHE), Noida Junior and Assistant Engineers Environmental Management in Transport Projects

9 Environment Protection Training and Research Institute,

Hyderabad Junior Engineers

Theoretical aspects of environmental

management

Page 89: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

86 | P a g e

S. No Training Institutions Target groups Contents of the training

10 Tata Energy Research Institute (TERI) Assistant Engineers Hydro Energy and ecological systems

11 Centre for Water Resources Development and

Management, (CWRDM) Kozhikode, Kerala Selected group of Engineers Water Resources Management in hilly terrain

12 Centre for Earth Science Studies, Thiruvananthapuram,

Kerala Selected Group of Engineers Tectonic and Seismic forces in Himalayan Region

13 Kerala Forest Research Institute (KFRI) Trichur, Kerala Senior Engineers Biodiversity and forest ecosystems

14 Hind swaraj trust, Ahmed Nagar Pune Junior and Assistant Engineers Soil and water conservation

These training programmes are expected to impart in-depth knowledge from experienced professional working at geographically distant locations.

However, these training programmes are only indicative and can be considered in coordination with the respective institutes in geographically distant

areas of the Indian sub-continent.

Page 90: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

87 | P a g e

6. IMPLEMENTATION SCHEDULE

Generally, the construction of project is of about 18 months. Tentative implementation schedule of the project is listed below.

Table 6-1: Inductive Framework of Implementation Schedule

S. No Description Indicative Time Frame

1 Project Implementation April 2020

A Detailed Design and Bidding Documents Month of Nov 2019

B Procurement March 2020

C Construction commencement August 2020

D Project Completion 18 months (January 2022)

E Defects Liability Period One year after completion (February 2022 to January 2023)

2 Environmental Management

A Design Review and Technical Audit Consultant of PMC Starting (intermittent inputs whenever necessary)

B Project Management Office’s (Contractor) submission

of Environmental monitoring report (EMR)

In the month of July and January every

year

C Monthly EMR for Project's Monthly Progress Report 8th day after effective month

D Semi-Annual EMR during construction for submission to World Bank

8th day after effective 6-months

E Semi-Annual EMR for submission to World Bank during Construction.

15th day after effective year

G Finalization of environmental management plan (EMP), After disclosure of the draft EIA

H World Bank review and approval of revised EIA and

EMP. After disclosure of the draft EIA

I Obtaining Government’s approval of EIA Report After disclosure of the draft EIA

J Community preparation (including disclosure of Final

EIA and its EMP) After disclosure of draft EIA

K Establishment of baseline data (as set out in the EMP) (shall have been done before award of contract)

L Preparation of Site-specific Environmental Management Plan (SEMP) by selected Contractor, review of SEMP

Before start of works on site

M Against Safeguard Policy Statement (SPS)-compliant EMP.

Before establishment of construction- related facilities.

3 Construction Phase

A Mobilization to Demobilization

B Implementation of mitigation measures and conduct of environmental effects monitoring following the ESMP.

After award of the contract

C Submission of EMR (Environment Management Report) Monthly, by Contractor

Every month 5th day of the month following the effective month

4 Operation Phase

A Implementation of mitigation measures and monitoring activities as Specified in the EMP

Semi annual

B Submission of EMR by Operator Semi annual

Page 91: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

88 | P a g e

Table 6-2: Indicative Implementation Schedule

Activity

Timeline (Months)

Construction Phase

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Mobilization of Environmental Representative by Contractor/ PMC

Review of Environmental Management Plan Contractor/ PMC

Identification/ Establishment of Construction

camp sites (HMP, Crusher, Batching plant, WMM Plant, and Labour Camp etc)

Identification of Sites for Debris Disposal and Borrow Areas/Quarry areas

Preparation of Project specific Environmental Management Plan by Contractor

Training by PMC as per training Plan

EMR Reporting on EMP compliances by Contractor/PMC

Compensatory Afforestation

Implementation of EMP

Operation Phase

Timeline (Months)

Activity 1 2 3 4 5 6 7 8 9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

Implementation of mitigation measures and monitoring activities as Specified in the EMP

Submission of EMR by Operator

Page 92: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

89 | P a g e

7. EMERGENCY RESPONSE PLAN

7.1 Introduction

Road Construction sites, construction camps, labour camps are the places prone to different kind of

emergencies and should have Emergency Response Plan, so that quick and effective action can be

taken in the event of a problem to ease the severity of the situation and to limit the consequences.

An emergency plan comprises agreed, recorded and rehearsed strategies, enabling those on site to

respond effectively and reliably. Based on project location and various activities taken up during

project execution different types natural and manmade risks/hazards (but not limited to) have been

identified. These hazards are; Earthquake, Landslides, Floods, Fire at workplaces, Electrical accidents,

Physical and Occupational Health & Safety and Hazardous material/wastes or oil spill.

7.2 Risk Assessment

The objective of the risk assessment study is to identify and quantify the major hazards; the risk

associated with various operations of the proposed project, which may lead to emergency

consequences (disasters) affecting the public safety and health. Following is the risk assessment

matrix (table 7-1) to establish the potential risk of the identified hazard. The potential risks associated

with each type of hazards have been established and provided in table 7-2. Controlled measures for

identified risk are given in Table no 7-3.

Table 7-1: Risk Assessment Matrix

Consequences

Likelihood

Risk

5 Severe: Death or

Permanent disability to one or more persons

A Almost certain:

Expected to occur in most circumstances

Consequences

1 2 3 4 5

Lik

elih

oo

d A M H H VH VH

B M M H H VH

C L M H H VH

D L L M M M

E L L M M M

4 Major: Hospital admission required

B Likely: will probably occur in most circumstances

3 Moderate: Medical treatment required

C Possible: Might occur occasionally

2 Minor: first aid required D Unlikely: Could happen at some time

1 Insignificant: Injuries not requiring first-aid

E Rare: May happen only in exceptional circumstances

L- Low; M- Medium; H- High; VH- Very High

Table 7-2: Potential Risks Associated with different Types of Hazards

Hazards Likelihood Consequences Risk

Earthquake (The project lies in high damage risk zone, as per seismic area zoning map of the state)

D 4 H

Landslide (Project area falls in High risk zone of landslide (as per HP-State Disaster Management Authority)

D 3 M

Floods (Presence of two river streams along project roads poses a threat of flooding)

D 2 L

Fire at working places/material store yard etc. E 4 M

Electrical D 5 M

Hazardous Material or Oil spill D 4 M

Physical/ Occupational Safety and Health C 4 H

Page 93: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

90 | P a g e

Table No. 7-3. Controlled Measures for /Identified Risks:

Hazards Task/Scenario Associated Harm Control Measures

Earthquake Construction Phase Operation Phase

Injuries Human Life Infrastructure collapse

Educate workers on do’s and don’ts during and after earthquake (through trainings and mock drills).

Safety measures like first-aid, emergency contacts, other dept. etc. to be maintained

Landslide Construction Phase Operation Phase

Injuries Human Life Infrastructure collapse

Provision of Trainings and Awareness programmes Have an emergency kit ready and necessary communications facility in

construction/working sites.

Fire at Working Places/Material Store yard etc.

Short-Circuits Combustible Materials Fuel Storage

Injuries Economic loss Human life Infrastructure damage

Personnel orientation/ awareness sessions Fire-fighting equipment of sufficient numbers to be kept. Safety measures like fire extinguishers, sand buckets, fire blankets etc. to be

kept at prominent places. Staff training and mock drills to be conducted.

Emergency fire exits to be maintained. (Ref Appendix 12)

Electrical Construction and Operation Phases

Injuries Human life

Personnel orientation/ awareness sessions Electrical cables and lighting works to be done at a specified place/area. Proper grounding works to avoid static electricity build up. Certified appliances to be tried and tested before use. Use of intrinsically safe electrical installations and non-sparking tools

(Ref Appendix 12)

Hazardous Material or Oil Spill.

Construction Phase (while handling material)

Injuries Human life

Personnel orientation/ awareness sessions Ensure safe handling, storage, use and disposal of hazardous materials (ref

Appendix 13). During the complete construction phase, an estimated 104 used batteries are

likely to be discarded, which are to be disposed of in accordance with the battery management rule.

The hazardous waste generated at camp sites is to be collected in steel drums and stored in a segregated roofed area and periodically disposed at approved waste disposal facilitates by HPSPCB. The nearest such facility is located at Baddi Barotiwala Nalagarh Industrial Area (BBN) in the adjoining Solan District. The discarded batteries shall be disposed only through authorized recyclers from HPSPCB

Physical/ Occupational Safety and Health

Collisions, Lifting operations, Noise, Material handling, Welding operations

Injuries Human Life

Personnel orientation/ awareness sessions Implement strict use of PPE Rotation of workers, use of better hand tools, equipment uses for stacking and

movement of goods Proper ventilation and entry/exit signs to be placed

Ref Appendix -12

Page 94: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

91 | P a g e

General rules/guideline for Emergency Response Mechanism to be followed by Contractor;

To deal with any types of emergency in project following procedures/setup will be followed.

There will be an EHS induction room in the Construction camp area. This room will also act as

emergency control room. Environmental and Health & Safety Officer will conduct all sorts of

required trainings and awareness programmes in the induction room.

An area will be identified and marked as an assembly area. Preferably, assembly area should

be a raised point in the camp premises and should be clear from all hindrances and easily

accessible to vehicles.

A hooter/siren will be placed near assembly area, blowing of which will indicate that there is

an emergency, and everybody must gather at assemble area. If hooter or siren is not

working, then guards or other workmen are required to shout to alarm about incident.

Trainings and awareness programme on various types of emergencies, preparedness (mock

drill) and on rescue needs to be organized by Contractor. If some additional hazard other than

already identified is noticed, then a training on that will also be imparted to workmen.

Information Boards will be displayed near labour camp, outside office work area/ laboratory/

store area and assembly area, which will have list of the emergency contact numbers (follow

table no 7-4).

Different signage marked with exit routes must be displayed in the camp premises.

Suitable and enough Fire extinguishers and sand buckets will be placed at applicable areas in

the Camp.

First aid box will be provided at fixed locations (store yard, laboratory, Office, labour camp

and all other identified working units) to provide first aid in case of injury.

Workers will be trained regularly for first aid training and CPR procedures.

Third party checking of the tools and tackles will be ensured by contractor.

Emergency contact details (Personnel of Contractor, ESMU, PMC and different govt.

departments) will be shared with workmen.

Supervisor or any other workmen on site will communicate with desired people and will inform

about emergency. Driver of the emergency vehicle deployed by the Contractor will be called

up for rescue. The emergency contact details will also be shared to these people on site and

Supervisor or any other workmen will contact required personnel/department for any help.

First aid kit will also be provided to at all construction zones.

Table No 7-4 Display board with emergency contact numbers:

Sr No Name of person/ department Telephone no

1 Contractor’s Project Manager ……………….

2 Contractor’s Environment Officer ……………….

3 Contractor’s Safety Officer ……………….

4 Executive Engineer, CMU ……………….

5 Environmental Specialist, PMC ……………….

6 EHS Officer, PMC ……………….

7 Nearby Fire Station ……………….

8 Nearby Police Station ……………….

9 Nearby Hospital ……………….

10 Ambulance ……………….

11 Forest Department ……………….

12 Fire Station ……………….

13 Driver (Vehicle attached for emergency)

Page 95: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

92 | P a g e

8. ENVIRONMENTAL BUDGETORY PROVISIONS

The budgetary provisions for the implementation of the environmental management plan of the

Project is categorised in to two types and summarised below in table 8-1 and 8-2. The complete

breakups of the budgetary provisions are provided in Appendix 16.

EMP works to be implemented by the Contractor as per the Civil Works BOQ (Table 8-1).

EMP works to be implemented by the Contractor as per the EMP BOQ (not included in civil works BOQ) (table 8-2).

Table 8-1: EMP Works to be implemented as per Civil Works BOQ

S.No Description Reference Amount

1 Disposal of Excess debris Material with an

average lead of 1 Km

Bill no 2.09 of Civil Works BOQ

Cost included under Civil Works

2 Construction of cross drainages structure including erosion control measures downstream of the culvert locations

Bill No 5 (culverts) & 6 (bridge) of Civil works BOQ

Cost included under Civil Works

3 providing surface line drain on roadsides to channelize the water into nearby cross drainage structures

Bill No 7.02 to 7.06 of Civil works BOQ

Cost included under Civil Works

4 Providing protection measures (retaining & breasts walls) to restrain the soil to slopes

Bill No 7.15 to 7.21 of Civil works BOQ

Cost included under Civil Works

5 Provision of Gabion Walls to retain debris at 7 identified debris disposal sites

Bill no 7.22 of Civil Works BOQ

Cost included under Civil Works

6 Provision of traffic safeguards measures on the road (information/caution boards, chevrons etc.)

Bill No 8.02 of Civil works BOQ

Cost included under Civil Works

7 Traffic and Safety Management During Construction

Bill No 9.06 of Civil works BOQ

Cost included under Civil Works

Table 8-2: BoQ summary of the EMP works to be implemented by the Contractor as per the

EMP BOQ (not included in civil works BOQ)

The total budget for ESMP is sum of budget for implementation of EMP and RAP, which works out to

INR 391.42 lakhs (INR 391, 42,350)

Table 8-2 : Budgetary Provisions for Specific Environmental Impact Mitigation /

Enhancement Measures (additional Requirements to be implemented by Contractor against

budget)

S. No Description Amount in

INR Amount in

lakhs

1 Management of Excess Debris (56251 cum) Disposal on site. 1128050 11.28

2 Provision of Noise Barriers and other enhancement measures at Sensitive receptors (at km 1+130, 4+520, 6+470, 6+640)

1449000 14.49

3 Provisions of enhancement measures for Community property (Crematorium) at Km 12+500 including 25 precast cement concrete benches and 6000 litres water tank

1086840 10.86

4 Provision of Toilets at specified location (13+100 Km) 900000 9

5 Bio Engineering Interventions at selected locations along the project road as pr EMP

7730684 77.31

Page 96: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

93 | P a g e

S. No Description Amount in

INR Amount in

lakhs

6

Clearance/Removal of Invasive Species like Lantana and Sea Ruthenium etc. form the road corridor and Plantation of Indigenous local vegetation and Maintenance and upkeep for 70% survival rate for 6 months (16 km both sides up to width of 1.5 m)

4860000 48.6

7 Provision of plantation and maintenance ( tree guard) of 1500 Avenue trees along roadside and in RoW

2700000 27

8 Monitoring Cost as per CPCB Standard Procedures 1296000 12.96

9 Provision for Compensatory Afforestation in lieu of Tree felling for road construction

Cost shall be paid by HPRIDC to forest Department of GoHP

10

Provisions of Environmental specialist (full time), EHS Officer (fulltime), Bio-Engineering Specialist (intermittent input), Horticultural specialist (intermittent input) and Training sessions for implementation of EMP

To be included by CSC

11 Land acquisition and Resettlement & Rehabilitation Cost Covered in RAP Budget

12 Relocation and construction of hand pumps, water storage tanks, OHTs, open wells & water taps as per directions of the Engineer.

Covered in Utility Shifting Budget

13 Cost for institutional strengthening, capacity building and training by HPRIDC

Miscellaneous cost

14 Contingencies 10% 2115057.4 21.150574

Grand Total 23265631.4 232.656314

Table 8-3: Budgetary Provisions for Specific Mitigation Measures (Social Impact mitigation

and management measures (RAP))

S.No Cost Items Amount (in Rs.)

1 Compensation for Land 0

2 Multiplication factor value as per rule 28 Chapter IV of Act 30/2013 is 1 time of the land value (rural area)

0

3 Structure Value 2127796

4 100% Solatium 4255592

5 12% addl. market value on Col.1 from date of 11(1) to passing of award (Probable for one year)

0

A-Sub -total 6383388

6 Provision in case of Displacement - Choice of Annuity / Employment - /Loss of Livelihood PAF's -5 Lakh onetime payment or 2000/- per month for 20 years

0

7 DP - Subsistence Grant for one year 0

8 Transportation Cost 0

9 Cattle Shed or Petty Shop 0

10 Resettlement Allowance 0

11 Vulnerability Allowance 150000

12 DP- Subsistence Grant for SC/ST 300000

13 CPR Rehabilitation Cost 3000000

B- Sub-total: R&R Entitlement's 3450000

A+B: Compensation and R&R Entitlement 9833388

Page 97: Himachal Pradesh State Roads Transformation …himachalservices.nic.in/hpridc/ESMP for Dadhol-Ladrour...Kherva, Gozaria –Sama–Churada -Kuvadara section of NH68 and terminating

94 | P a g e

S.No Cost Items Amount (in Rs.)

14 Hiring of NGO for Implementation (Lum sum) 1800000

15 Hiring of Independent Agency for Monitoring and Evaluation 1100000

16 Grievance and Redress (Lump Sum) 200000

17 Stakeholder Engagement Plan Implementation 1500000

C. Sub-total: Implementation Support Cost 4600000

Total (A+B+C) 14433388

18 Add- 10% Contingency of total compensation , Entitlement and Administration Cost 1443338.8

Total Budget for Implementation of Resettlement Plan (Say 1.58 Cr.) 15876726.8