Hillcrest School TN35 5DN · Plus programme – a collaboration with a company run by Ninestiles...

23
Planning Statement East Sussex County Council 1 Hillcrest School Rye Road Hastings East Sussex TN35 5DN East Sussex County Council Planning Statement Revision D Application for the demolition of existing Hillcrest School (excluding the Sports Centre) and construction of two storey Academy Complex (Class D1), including dining hall, performance areas, and adaptable teaching spaces, extension to sports hall, along with a floodlit all weather pitch, associated car and cycle parking, and new vehicular and pedestrian accesses. November 2010

Transcript of Hillcrest School TN35 5DN · Plus programme – a collaboration with a company run by Ninestiles...

  • Planning Statement    East Sussex County Council 

     

     

     

     

     

     

    Hillcrest School Rye Road Hastings East Sussex  TN35 5DN  

     

     

     

    East Sussex County Council  

     

     

    Planning Statement Revision D 

      

    Application for the demolition of existing Hillcrest School 

    (excluding the Sports Centre) and construction of two 

    storey Academy Complex (Class D1), including  dining hall, 

    performance areas, and adaptable teaching spaces, 

    extension to sports hall, along with a floodlit all weather 

    pitch, associated car and cycle parking,  and new vehicular 

    and pedestrian accesses. 

     

     

     

     

     

     

     

    November 2010 

  • Planning Statement    East Sussex County Council 

    CONTENTS  SECTION 1 – Introduction...................................................................................................... 3

    The Application................................................................................................... 3 Hastings Academy .............................................................................................. 3 Scope and Structure of the Planning Statement ................................................ 4

    SECTION 2 ‐EDUCATIONAL NEED .......................................................................................... 5 SECTION 3 ‐THE APPLICATION SITE AND SURROUNDING AREA ........................................... 8 SECTION 4 ‐APPLICATION PROPOSALS .................................................................................. 9

    Layout and Design ............................................................................................ 10 Phasing and Construction................................................................................. 12

    SECTION 5 ‐ TENDER PROCESS ............................................................................................ 13 Pre‐Application Consultation............................................................................ 13

    SECTION 6 ‐PLANNING POLICY ............................................................................................ 14 National Policy .................................................................................................. 14 Development Plan ............................................................................................ 14 The South East Plan .......................................................................................... 15 Local Plan.......................................................................................................... 15 Transport .......................................................................................................... 15 Energy, Water Pollution and Waste ................................................................. 16 Design, safety and the quality of development................................................ 17 Community facilities ......................................................................................... 17 Nature Conservation and the Countryside....................................................... 18

    SECTION 7 ‐PLANNING CONSIDERATIONS........................................................................... 19 Design ............................................................................................................... 19 Visual Impact .................................................................................................... 19 Landscaping ...................................................................................................... 19 Lighting ............................................................................................................. 19 Access for All..................................................................................................... 19 Sustainability .................................................................................................... 20 Traffic Generation, Access and Parking ............................................................ 20 Flood Risk and Drainage ................................................................................... 21 Plant and Machinery......................................................................................... 21 Construction Management............................................................................... 21 Consultation and Community Involvement...................................................... 22

    SECTION 8 ‐SUMMARY AND CONCLUSION ......................................................................... 23

  • Planning Statement    East Sussex County Council 

     SECTION 1 – Introduction 

     

    The Application 

    1.1 This Planning Statement has been prepared in support of a full planning application submitted by East Sussex County Council Children’s Services Authority for:  

     

    Application for the demolition of existing Hillcrest School (excluding the Sports 

    Centre) and construction of two storey Academy Complex (Class D1), including  

    dining hall, performance areas, and adaptable teaching spaces, extension to sports 

    hall, along with a floodlit all weather pitch, associated car and cycle parking,  and 

    new vehicular and pedestrian accesses. 

     

    1.2 Kier Regional has been chosen by East Sussex County Council Children's Services Authority (the Council) as the preferred contractor for the construction of The 

    Hastings Academy following a competitive tender process.  

     

    1.3 As a planning application is being submitted, a Screening Opinion has been sought from the Council to consider whether or not the proposals would require an 

    Environmental Impact Assessment (EIA).  Confirmation has been received from East 

    Sussex County Council that an EIA is not required. 

    Hastings Academy  

    It is proposed to create an Academy offering the highest standards of education in place of 

    Hillcrest School.  The Academy will build upon the recent progress already made in 

    education standards at the School, particularly through the implementation of the Ninestiles 

    Plus programme – a collaboration with a company run by Ninestiles School which was 

    designed to significantly raise standards and pupil attainment. 

     

    1.4 Academies are free, government‐funded schools that provide a fresh approach to 

    learning in state‐of‐the‐art buildings to raise standards of achievement among all 

    students whatever their abilities. 

    1.5 Each Academy is individual and develops to reflect local needs.  They each have a sponsor who provides vision, leadership and expertise to enrich the experience of all 

    the students. The sponsor invests money in an endowment fund to provide financial 

    support for additional activities at the Academy.  The Hastings Academy is jointly 

    sponsored by the following parties: ‐ 

  • Planning Statement    East Sussex County Council 

     

    1. The University of Brighton (Lead sponsor) 2. East Sussex County Council (co‐sponsor) 3. British Telecom (co‐sponsor) 

     

    1.6 Each Academy has at least one specialism.  Hastings will have two specialisms – English and Information Communications Technology.  

    Scope and Structure of the Planning Statement  

    1.7 The proposal is promoted having regard to national planning policy guidance as set out in the relevant PPGs and PPSs; the relevant polices of the Development Plan and 

    associated supplementary guidance. 

     

    1.8  The statement comprises eight sections: ‐ 

    • Section 2 identifies the educational need.  • Section 3 describes the site and surrounding area   • Section 4 describes the planning history and the competitive tender process.  • Section 5 reviews all relevant planning policy in relation to the proposal.   • Section 6 identifies and addresses the principal planning considerations of 

    relevance to the planning application and demonstrates that the proposed 

    development accords with policy at all levels.  

    • Section 7 provides a summary of the proposal and concludes that it is entirely acceptable and should be granted planning permission. 

     

    1.9  In addition to this statement (Document 1), the application is supported by the 

    following documents and drawings:  

     

    •   A Design and Access Statement prepared by Feilden Clegg Bradley and Edco 

    (Document 2);  

    •   A Transport Assessment prepared by WSP (Document 3)  

    •   Construction Environmental Management Statement and SMART Waste Plan 

    including Construction Methodology, prepared by Kier Regional (Document 4)  

    •    Sustainability Report (incorporating a BREEAM pre‐assessment, Sustainable 

    Technologies Assessment and Environmental Design Review) prepared by WSP 

    (Document 5)  

    •   Ecology Assessment prepared by ECUS (Document 6)  

    •   Drainage Strategy and Flood Risk Statement prepared by WSP (Document 7)  

    •   Statement of Community Involvement prepared by Feilden Clegg Bradley Studios 

    (Document 8)  

  • Planning Statement    East Sussex County Council 

    •   External Lighting Design prepared by WSP (Document 9) 

    •   Acoustics Report prepared by WSP Acoustics (Document 10) 

    •   Archaeological desk‐based assessment by ASE (Document 11) 

    •   Phase 1 Desk Study (geotechnical and preliminary contamination risk assessment) by 

    Ashdown Site Investigation Ltd. (Document 12) 

    •   Application drawings prepared by Feilden Clegg Bradley Design and EDCO.  

     

    SECTION 2 ‐EDUCATIONAL NEED  

    2.1  Hillcrest School was built and completed in 1953, where it opened as a girls 

    secondary school. At this time the school campus was made up of what is now called 

    B‐Block and the sports fields. With the closure of the boys school in Priory Road in 

    the late seventies, Hillcrest accepted both male and female students. The A‐Block 

    was built circa 1970 with the later additions of the Languages Block, Art Extension 

    and the Sports Centre.  A detailed conditional survey of the buildings has concluded 

    that they are generally sound and serviceable, but the roof covering and original 

    windows to main building are in poor condition. The 'A' Block roof is in life expired 

    condition, and the remaining original cladding panels are poor. Mechanical: The 

    majority of the installations are life‐expired.  The electrical installations are of 

    varying ages and with continuing maintenance would only be serviceable for 

    another 5 years.  

    The existing buildings are not suitable for teaching under the arrangement of the 

    new Academy. 

     

    2.2  The Hastings Academy is part of the transformation of education and learning within 

    Hastings. Together with The St Leonards Academy in the west of the town, the two 

    academies will provide the co‐educational secondary school provision in Hastings. 

    The Hastings Academy will continue to serve the community currently served by 

    Hillcrest School. The Hastings Academy will be able to accommodate up to 900 

    students aged between 11 and 16 (the same size as the current Hillcrest 

    accommodation). Reflecting the academy’s very strong commitment to inclusion, 

    and as part of ESCC’s strategic provision for students with special educational needs, 

    the academy will include an additional provision for 20 students with speech, 

    language and communication difficulties.  

     

    2.3  The two academies are sponsored by the University of Brighton with BT and ESCC as 

    co‐sponsors. These organisations have reputations for excellence, for research, for 

    high aspirations and expectations, and for community leadership. The academies 

  • Planning Statement    East Sussex County Council 

    will reflect these values and will drive up aspiration, achievement and attainment, 

    and progression of students from secondary school into further and higher 

    education. Alongside the investment in Sussex Coast College and University Centre 

    Hastings, the academies are a clear statement of intent to place outstanding 

    learning and opportunity at the heart of the regeneration of the town.  

     

    2.4  The academies, both as institutions and physical facilities, will be a catalyst for 

    raising the aspiration and achievement of young people in the town. They will be 

    centres of excellence, where student want to attend and expect to succeed. The 

    collaboration between the academies will allow them to develop and share best 

    practice, to enhance the curriculum and enrichment activities available to students, 

    and to reach out beyond the academies into the primary schools and broader 

    community to raise skills and aspiration.  

     

    2.5  The academies are themselves the second phase of the improvement of secondary 

    education in the town. The first phase has involved the three predecessor schools 

    working increasingly closely together through a federation under the executive 

    leadership of Sir Dexter Hutt. Its success is evident in the significant and rapid impact 

    on pupil achievement and attainment. GCSE and equivalent results at all three 

    predecessor schools have increased significantly. The academies expect to build on 

    this foundation. 

     

    2.6  The capital project for The Hastings Academy is central to the vision of the sponsors 

    to raise aspirations, expectations, and achievements. The existing buildings do not 

    provide the physical environment or the facilities that are required to achieve the 

    transformation that the town needs and the students deserve. The existing buildings 

    are poorly positioned on site, have condition issues, and are ‘of a time’ in terms of 

    the layout and facilities available for teaching and learning. 

     

    2.7  The sponsors vision for the building is a school: 

    • Structured through ‘schools within schools’ that reduce pupil movement, increase community belonging and pastoral support, and ensure every child is known and 

    supported individually. The design creates four ‘honeycombs’ for these schools 

    within the overall academy. For younger students in particular they will provide their 

    home base.  

    • Has outstanding specialist facilities for subjects such as science, technology, music and performing arts  

  • Planning Statement    East Sussex County Council 

    • Has a curriculum that inspires and challenges all students, including more ability for ‘stage not age’ progression for students and increasing ability to personalize a 

    students’ experience through technology and learning in more flexible styles rather 

    than just in classroom groups of 30.  

    • Has outstanding ICT infrastructure and equipment to enable flexible learning • Has a structural and servicing approach that provides sufficient flexibility in the 

    design to accommodate future curriculum or pedagogical changes to ensure that it 

    continues to provide outstanding opportunities for students for the life‐span of the 

    building 

    • Is fully inclusive for all students, including those with additional needs and sensory impairments, in a way that the existing Hillcrest accommodation can not achieve.  

     

    2.8  The Hastings Academy will have a significant and positive impact on the local 

    community. The existing sports centre will be refurbished and there will be a strong 

    sports strategy supported by a landscape providing an AWP and restored existing 

    pitches. The Academy will operate extended hours all year in order to provide the 

    opportunity for the wider Hastings community to learn new skills through a range of 

    subjects. In addition, it is anticipated that the extended opening hours in the 

    evenings and at weekends will allow for both school activities and community 

    events to take place. The proposed accommodation is designed to facilitate this 

    vision through its layout and configuration. 

  • Planning Statement    East Sussex County Council 

    SECTION 3 ‐THE APPLICATION SITE AND SURROUNDING AREA  

    3.1  Hillcrest School is sited approximately 3.1 miles north east of Hastings town centre 

    and located on the A259 road to Rye. 

     

    3.2 The school campus extends to 6.4 ha, including playing fields, parking and access roads and sits at the northern edge of of a residential area, adjacent to an area of 

    the High Weald which borders the eastern boundary.  This is an Area of Outstanding 

    Natural Beauty (AONB).  To the west of the site is the predominantly two storey 

    residential development in the Ore area. 

     

    3.3  There are four existing main buildings occupying the site, and they are referred to as 

    the A‐Block, B‐Block, Languages Block and Sports Centre buildings.  Hillcrest School 

    was built and completed in 1953, where it opened as a girls secondary school. At this 

    time the school campus was made up of what is now called B‐Block and the sports 

    fields. With the closure of the boys school in Priory Road in the late seventies, 

    Hillcrest accepted both male and female students.   The existing school buildings are 

    neither listed locally or nationally and the site does not lie within a designated 

    Conservation Area. 

     

    3.4  The topography of the site is one that rises up from the Rye Road the back of the 

    site. The main school building lies on a steep gradient, and current access 

    arrangements to all the existing buildings are very steep and exceed current 

    guidelines.   

  • Planning Statement    East Sussex County Council 

    SECTION 4 ‐APPLICATION PROPOSALS 

    4.1  A full application is submitted for the Hastings Academy complex.  This chapter sets 

    out a full description of the proposals.   

     

    Amount and Use  

    4.2  The Academy has been design to provide accommodation for 900 students and 

    associated teaching and support staff (100 full‐time employees).  This will comprise 

    of 900 11‐16 year old students (180 per year). 

     

    4.3  The building will incorporate facilities to meet the teaching needs of 21st century 

    educational curriculum.  The facilities that will be accommodated in the new 

    building include the following:  

    • A dining and main hall;  

    • New configuration for playing fields;  

    • The SEN Centre;  

    • A learning resource centre;  

    • Flexible and adaptable teaching spaces;  

    • Gathering spaces and honeycomb presentation spaces 

    • Multi‐agency facility 

    • Specialist speech and language facility 

    • Staff offices and administration 

     

    4.4  In order to incorporate these facilities the building will have a gross external 

    floorspace of 7,310 sqm 

     

    4.5  As well as its use for education purposes it is also intended that the Academy’s 

    facilities will be made available for public and community use including the main 

    hall, performing arts centre, sports hall and entrepreneurship centre as part of the 

    Extended Schools Programme. 

     

    4.6  The Academy has been designed to respond to its setting adjacent to the High 

    Weald AONB whilst creating a landmark civic building which is easily recognisable 

    and unique.  The scale and size of building is determined by its educational 

    requirements. However, the design has sought to respond to its setting by providing 

    a prominent and public face towards the Rye Road and a more private and enclosing 

    face to the High Weald.   

  • Planning Statement    East Sussex County Council 

    10 

    4.7  The building will be two storeys in height.  Through the sensitive use of simple and 

    durable materials the building will fit comfortably in to the landscape. 

     

    Layout and Design  

    4.8  Steep Gradient – The predominant feature of the topography of the site is the way it 

    rises up sharply from the Rye Road.  There is a fall of approx 15m from east to west 

    in the short direction across the site.  Although the site is at the top of a very steep 

    hill – hence the school’s current name – there is only a relatively shallow gradient 

    from north to south of the site in the direction of the town centre.   The Sports Hall, 

    in the north‐east corner of the site, is approx 10m higher than the gymnasium of the 

    main block. 

    Considerations of the steep topography have strongly influenced the planning and 

    design of the landscape masterplan.  The design team have completely replanned 

    the entrance and approach sequence to the existing retained buildings in order 

    create an entrance sequence which is compliant with best‐practice DDA access 

    standards.  The location of the new Academy on the site has been determined by 

    undertaking a detailed analysis of level changes, both on the pedestrian approach to 

    the building, and changes of level within the two storeys of the building. 

     

    4.9 Entrances to the site– There is a desire to segregate pedestrian and vehicular traffic.  At present at the Hillcrest School there are undesirable crossovers between 

    pedestrian and vehicular traffic.  The new masterplan separates these two types of 

    flow as much as possible.  A new vehicular entrance is proposed with a separate 

    pedestrian entrance.  Furthermore, there is a dedicated entrance at the southern 

    end of the site to the service yard with the intention that delivery traffic is separated 

    from the school traffic. 

    4.10  Landscape Setting ‐ It is proposed that the Academy building will be set in a 

    comprehensively landscaped setting. This is explained in detail in the landscape 

    drawings prepared by EDCO and the Design and Access Statement.  The main 

    elements of the landscaping strategy can be summarised as follows:  

    • Quiet external breakout areas to the east of the building;  

    • Extensive planting incorporating a high proportion of native species which will 

    provide a diverse habitat;  

    •  Honeycomb outdoor social areas  

    •  The provision of a Woodland Garden, wildflower meadows and formal tree and 

    shrub planting 

     • New all weather pitch 

  • Planning Statement    East Sussex County Council 

    11 

    • New layout for playing fields. 

     

    4.11  Retention of Sports Centre Building – This building, currently managed by Freedom 

    Leisure, occupies a difficult position at top and rear of the site.  The intention, with 

    the masterplan for the site, has been to make the Sports Centre a new focal point of 

    a zone of sport and activity that runs around the north and eastern boundaries of 

    the site. 

     

    4.12  Relocation of Sports Pitches as part of a cohesive masterplan for sport and activity.  

    The existing All Weather Pitch is located in a position behind the existing main block 

    of the school.  The proposal is to relocate and increase the size of the AWP on the 

    western boundary adjacent to the Rye Road.  Community access in this position will 

    be much easier to manage. 

     

    4.13  Proximity to Houses at South of Site – Because of the elevated position of the site in 

    relation to the adjacent residential area, the new Academy building is located no 

    closer than 12m to the rear gardens of the four semi‐detached houses immediately 

    to the southwest of the southern corner of the proposed building. 

     

    4.14  Provision of secure cycle storage in line with the requirements of the travel plan ‐ 

    The East Sussex Parking Standards stipulate that there should be 180 long‐term 

    bicycle parking spaces provided as part of the new development these spaces should 

    be under‐cover and vandal proof.  A secure cycle store is proposed adjacent to the 

    Sports Centre.  This number is also in line with the recommendations of the 

    transport assessment (see document 3). 

    However, the school and the sponsors have a concern, based on their current 

    experience of the cycle journeys made to school, that the cycle store will be severely 

    under‐utilised and become a maintenance problem. 

    Therefore at the opening of the fully completed school it is proposed to have a cycle 

    store in operation to cater for 100 bicycles.  In addition we will make allowance for 

    the future provision of an additional 80 spaces directly adjacent to the existing store 

    (see Edco drawing C428D111A).  Foundations, hard landscaping and services will be 

    provided to this additional store, but we’re proposing that the cycle storage 

    structure itself, will not be installed until there is a demonstrable need for these 

    additional spaces once the school is operational. 

    The school will regularly monitor the usage of the cycle parking during the first few 

    months of the school’s operation and report back to ESCC planning so that a view 

    can be taken on whether the additional 80 spaces need to be completed. 

  • Planning Statement    East Sussex County Council 

    12 

     

     4.15  The scheme will also include level access to the building and playing fields.  The 

    lighting strategy has been prepared by WSP to ensure that light pollution and any 

    ecological impacts are minimised.  The external lighting to the all‐weather pitch is to 

    be designed at a future design stage by an all‐weather pitch specialist, however the 

    lighting levels and direction of lights shall be in accordance with all‐weather pitch 

    design guidance and shall carefully consider the neighbouring properties, taking due 

    account of eliminating light spill and upward light. 

    Phasing and Construction   

    4.16   The Academy building and service yard will be constructed in a single phase to the 

    east of the existing Block B building.  Once completed the pupils will be decanted in 

    to the new facility and the existing building will be demolished.  This will then allow 

    the car park and landscape areas to the north of the building, the improved access 

    to the Sports Centre and the all weather playing pitch to be constructed. 

     

    4.17   The construction compound will be created in the south east of the site 

    incorporating the existing languages building as site accommodation.  A dedicated 

    construction access will also be created on the playing fields to the existing access 

    road so as to minimise conflict with pedestrians and cyclists.  The management of 

    the construction works is dealt with in the Construction Environmental Management 

    and SMART Waste Plan including Construction Methodology, which has been 

    prepared by Kier Regional.  

     

  • Planning Statement    East Sussex County Council 

    13 

    SECTION 5 ‐ TENDER PROCESS 

     

    5.1   The Council invited twelve framework contractors to an open day prior to entering 

    into the Preliminary Invitation to Tender (PITT) phase.  This involved a detailed series 

    of questions to be answered by way of a submission (on 7th April 2010) which was 

    then followed up by an interview of four contractors.  Based upon the submissions 

    and interviews the Council took two contractors into the full Invitation to Tender 

    (ITT) phase. 

     

    5.2   The two contractors were afforded 14 weeks to develop their design solution.  For 

    Kier this involved five client design briefing meetings, a mid tender interview, and 

    submission of our tender which addressed a series of questions posed by the 

    Council.  Towards the end of the evaluation period a final interview was held with 

    each chosen contractor.  Kier was announced as the preferred bidder in October 

    2010. 

     

    Pre‐Application Consultation  

    5.3   Kier engaged in a pre‐application public consultation exercise with Members of the 

    Public, officers at the Council and external statutory and non‐statutory consultees.  

    This process has sought to obtain feedback on the revised design so that this can be 

    fed in to the proposals prior to the submission of the revised application.  This is 

    explained in detail in the accompanying Statement of Community Involvement. 

     

  • Planning Statement    East Sussex County Council 

    14 

    SECTION 6 ‐PLANNING POLICY 

    6.1   In order to understand the planning policy context against which this application is 

    to be considered, the relevant policies at national, regional and local level with 

    particular reference to the development plan are set out below.   

    National Policy  

    6.2   The proposals embrace the principles of PPS1 (Delivering Sustainable Development) 

    through the redevelopment of an existing school site to provide a new state of the 

    art facility which will be highly accessible, highly sustainable (achieving BREEAM 

    Excellent) and which will enhance the adjacent area of AONB. The proposals have 

    been developed through consultation with the community and are supported by a 

    Statement of Community Involvement.  

     

    6.3   PPS9 (Biodiversity and Geological Conservation) seeks to enhance and protect 

    biodiversity. The proposals maximise the opportunities for biodiversity on the site 

    through the landscaping scheme and ecological mitigation measures highlighted in 

    detail in the Ecological Assessment Report.   6.4   The proposal is entirely consistent with the aims of PPG17 (Planning for Open Space, 

    Sport and Recreation) by virtue of the re‐provision of facilities of greater value, 

    which include the Sports hall, hard court areas and an all‐weather football pitch of 

    greater size than the current provision.  6.5   The proposals include low energy technologies such as air‐source heat pumps and 

    gas‐absorption heat pumps, consistent with the advice in PPS22 (Renewable 

    Energy).  6.6   Also relevant to this proposal, national policy sets out requirements for dealing with 

    potential noise impacts in PPG24 and Flood Risk in PPS25. Each are considered 

    within the supporting documents.  

    Development Plan  

    6.7   Section 38 (6) of the Planning and Compulsory Purchase Act 2004 states that, in 

    determining planning applications, regard is to be had to the Development Plan and 

    the determination of applications should be in accordance with that Plan unless 

    material considerations indicate otherwise. 

  • Planning Statement    East Sussex County Council 

    15 

    6.8   The Development Plan for the area consists of the South East Plan (still current) and 

    the saved policies of the Hastings Borough Plan and the East Sussex and Brighton & 

    Hove Waste Local Plan.  

    The South East Plan  

    6.9   One of the key policies of the South East Plan is Policy S3 its aim is to ensure the 

    adequate provision of pre‐school, school and community learning facilities.    6.10   Paragraph 15.16 states that consideration should be given to the use of school and 

    college buildings after hours, to support learning among the wider community.    6.11   The proposal, while not of strategic importance to the region, is consistent with the 

    aims of the South East Plan and in particular Policies S3, CC4 and NRM11. The 

    proposal will allow much greater opportunity to open up the school facilities to the 

    local community in the evenings.   

    Local Plan  

    6.12   The Proposals Map for the Local Plan does not allocate the land for any particular 

    purpose (“white land”) although it is within the defined boundary of the built‐up 

    area of Hastings. To the east of the site is the designated an AONB.   6.13   The following sections set out the relevant policies in the Local Plan against which 

    this proposal will be assessed. These have been divided in accordance to their 

    generic chapter in the Local Plan for ease of reference:   

    Transport  

    6.14   In accordance with Policy DG2 and TR7 a Transport Assessment has been submitted 

    with this proposal.  The document sets out how the proposal meets the various 

    policy requirements such as the requirement in Policy DG2 to assess the level of 

    public transport accessibility and provide an appropriate level of parking.  The 

    proposal site is reasonably well served by public transport, and also provides the 

    maximum level of parking in accordance with standards in SPG4 and the County 

    Council’s Supplementary Planning guidance for East Sussex‐Feb 2002, including the 

    appropriate level of disabled parking.  It also provides covered secure cycle parking 

    close to the main entrance to the building which is in accordance with the 

    requirements of and the County Council’s Supplementary Planning guidance.   6.15   The application is supplemented by Heads of Terms of a Travel plan in accordance 

    with Policy DG2 of the Local Plan. The Travel Plan will be agreed with East Sussex 

  • Planning Statement    East Sussex County Council 

    16 

    County Council and written in conjunction with “Travelling to School: A Good 

    Practice Guide” and the Department for Transport Guidance on School travel. Safe 

    Routes to school will be considered as part of this in accordance with the County 

    Council’s Supplementary Planning guidance.   6.16   The layout of the proposals for access ensure that vehicles and pedestrians are 

    separated to ensure safety is not compromised (Policy DG1).  New pedestrian links 

    have been created across the site which will be illuminated in accordance with the 

    lighting plan, and will remain attractive and safe in accordance with Policy SP2.  

    Energy, Water Pollution and Waste  

    6.17   This proposal seeks to achieve a high level of sustainability and to achieve a BREEAM 

    rating of Excellent. In accordance with Policy CC2 of the South East Plan measures to 

    seek reduced energy and water consumption are incorporated into the design. This 

    is explained in detail in other parts of the application such as the Design and Access 

    Statement and the Sustainability Report.  Similarly the details of how the proposal 

    meets the requirements set out in Policies DG27 (Surface water run‐off and flood 

    risk) are included within the Flood Risk Assessment.   6.18   In meeting the requirements of Policy DG4 (Noise nuisance) a separate document on 

    the proposed plant and machinery is submitted as document 10. 

     

    6.19  In line with policy CC6, construction materials will be sourced locally where possible.  

    Kier also operate a policy of employing local employees where possible to reduce 

    the distance of travel for construction staff to the site.  6.20   Policy WLP11 (Minimisation and re‐use of construction industry waste) is addressed 

    in the Construction Management Plan (Document 4). This incorporates a Site Waste 

    Management Data Sheet in accordance with the recommendations of the East 

    Sussex and Brighton and Hove Waste Local Plan.   6.21   The design of the proposal incorporates a recycling store which is next to the service 

    yard. This is located in an area that is easily accessible, does not harm the amenity of 

    nearby occupiers or the local environment and should not cause harm to the general 

    character of the area.   6.22   Finally, as the proposal is for the redevelopment of an operational school, there is 

    already substantial infrastructure in place and it therefore complies with Policy 

    DG25.  

  • Planning Statement    East Sussex County Council 

    17 

    Design, safety and the quality of development  

    6.23   The Design and Access Statement (Document 2) sets out how the proposals are of a 

    quality to meet the requirements of Policy DG7 (Quality of development and design 

    statements).   6.24   Prior to the submission of the application,a key view have been agreed with the 

    Authority and in drawing 1483/P/404  the proposal has been superimposed on a 

    photograph to demonstrate that it will not have a detrimental impact on this view.   6.25   In accordance with Policy NC9 (Landscape Design), comprehensive landscaping 

    drawings have been submitted with the proposal. The proposed landscape plan also 

    makes up part of the design and access statement. This statement also identifies 

    trees to be removed and protected as requested via Policy NC8.  The document has 

    been prepared with consideration of the SPD06 Trees and Development Sites and 

    the British Standard BS5837:2005.   6.26   Policy NC9 (Protection and integration of nature conservation features) requires that 

    the nature conservation features are protected, compensated for, and where 

    possible enhanced. The measures proposed in the Landscaping Plan,and the 

    Ecological Assessment are intended to protect, mitigate and enhance the nature 

    conservation features of the site. The Ecological Assessment concludes that no 

    significant losses of habitat will occur as a result of the proposals.  6.27   In line with Policy NC9 (Species Protection), the Ecological Assessment identifies a 

    number of species under a National Designation and proposes mitigation measures 

    to ensure that they are maintained.  There is an addendum to the Ecological 

    Assessment by ECUS which specifically addresses the issue of presence of bats.  6.28   In accordance with Policy DG6 (External Lighting), a lighting scheme is submitted 

    with the application including details of the floodlighting for the all‐weather pitch 

    (Policy SP2, Floodlighting). The lighting report demonstrates that the issues of light 

    pollution, trespass, nuisance and environmental management can be appropriately 

    treated.  

    Community facilities  

    6.29   Policy CN8 considers the provision of new community facilities. Whilst the proposal 

    is for the redevelopment of an existing school, it will bring about the benefit of new 

    community facilities which are available in the evenings and on weekends. The detail 

    of the application demonstrates that the proposal is accessible to all, has suitable 

  • Planning Statement    East Sussex County Council 

    18 

    facilities, is accessible by various modes of transport and has adequate parking and 

    cycle facilities including facilities for people with disabilities. 

    Nature Conservation and the Countryside  

    6.30  Policy L2 of the Local Plan states that development will not be permitted within or 

    adjacent to an Area of Outstanding Natural Beauty (AONB) except where:  

    • Planning permission will not be granted for development that would adversely affect the natural beauty of the Area of Outstanding Natural 

    Beauty (AONB). 

    • Permission for major development proposals will not be granted unless there is a compelling case for them in the public interest. 

    6.31  The Design and Access Statement explains the design development process and how 

    the AONB designation was central to the final design of the buildings. It is 

    considered that the proposal meets the first of these points by virtue of the 

    improvements in the landscaping around the site.   In addition, the Local Plan 

    highlights a Wildlife Corridor that runs along the eastern boundary of the site.  The 

    current route of this corridor is not apparent so the landscape design has been 

    designed to clearly demarcate this corridor through the use of native planting and 

    wildflower meadow. 

     

    6.32  In accordance with Policy SP1 there is a nett gain of hard and grassed recreation 

    space.  The existing MUGA will be replaced by a larger all‐weather pitch. 

    The external sports provision will include: 

     • 1 x Senior football pitch • 1 x Senior rugby union pitch • 1 x Junior cricket pitch • 1 x Long jump • 1 x Cricket wickets • 1 x Softball diamond • 1 x 300m grass running track • 1 x 100m grass running track • 2 x Rounders • 3 x Tennis courts • 2 x Netball courts • 1 x Basketball courts 

     

  • Planning Statement    East Sussex County Council 

    19 

    SECTION 7 ‐PLANNING CONSIDERATIONS 

    Design  

    7.1   The design of the building responds to the requirement to provide an accessible and 

    energy efficient building which meets the educational needs of the Academy. 

    Visual Impact  

    7.2 The design responds to specific comments from ESCC Development Control, made 

    during the bid process and during the period up to the submission of this 

    application.  The design responds to these comments in the following ways: ‐ 

    • Proximity to Rye Road – The building should have a strong presence without being overbearing. 

    • Building Height – The design is two storeys throughout which was advised to be the optimum height. 

    • Proximity to Houses and Residential gardens  at the southern site boundary.  Overlooking of these areas has been avoided.  

    • Relocation of the Site Entrance –Retention of the Wildlife Corridor – The siting of the building respects the clear requirement for a Wildlife Corridor 

    which runs along the eastern boundary of the site. 

    Landscaping  

    7.3   The landscaping scheme and masterplan is key to the overall acceptability of this 

    proposal. The plan successfully integrates the building into its surroundings and 

    provides a number of different outdoor spaces for students and staff to enjoy. 

    7.4  The landscaping scheme also allows for the introduction of new habitats and the 

    opportunity to increase biodiversity across the site. 

    Lighting  

    7.5   An external lighting design has been set out in Document 13 of the application 

    submission. This report demonstrates that issues of light pollution, trespass, 

    nuisance and environmental management have been considered and appropriately 

    treated. The report contains details of the full specification of lighting proposed.  

    Access for All  

    7.6   The proposals are fully DDA compliant and will offer a much more welcoming 

    experience for students, staff and visitors with mobility impairment. 

  • Planning Statement    East Sussex County Council 

    20 

    Sustainability  

    7.7   The principles of sustainability have been at the heart of the proposal throughout 

    the design process leading up to tender.  A Sustainability Report supports the application 

    (Document 5) which incorporates a “Sustainability Statement”, an “Energy Statement” and a 

    “BREEAM (Buildings and Research Establishment Environmental Assessment Method) Pre 

    Assessment”.  

    7.8   The report explains how the proposal achieves sustainability credits under the 

    BREEAM accreditation and a reduction in fuel use and greenhouse gas emissions via 

    the following:  

    • Passive Design – daylight/sunlight, orientation, building form and natural 

    ventilation;  

    • Measures to reduce water consumption;  

    • Use of low energy Sources – including air source heat pumps;  

    • The use of sustainable and where possible recycled materials during construction;   

    • The provision of on‐site facilities such as cycle facilities and areas for recycling; and  

    • Landscaping to improve ecological value and reduce the peak rate of water runoff.  

    7.9   The report concludes that the requirements of Local Plan Policy have been observed 

    and the recommendations set out in Supplementary Planning Guidance 

    implemented. The Pre Assessment demonstrates that the scheme should achieve a 

    BREEAM rating of Excellent. 

    Traffic Generation, Access and Parking  

     7.10   Access to the site will change, with all traffic entering and exiting via a new entrance 

    onto Rye Road. The layout of pedestrian and cycle routes into and throughout the 

    site are also proposed to be modified to provide a more attractive, welcoming and 

    organised environment.  Visibility and sight lines have been assessed as part of the 

    addendum of the Transport Statement to ensure that all access roads are safe. 

     

    7.11  The addendum to the Transport Statement demonstrates that a large 3 axle refuse 

    vehicle, a single decked bus and a fire engine could satisfactorily enter, manoeuvre 

    and service the proposed development. 

     

    7.12   As discussed in the addendum to the Transport Statement, and agreed with the 

    Highways Authority, the proposal is unlikely to generate much of an increase in 

    traffic to the previous proposal. This is based upon an analysis of TRICS data and the 

    relatively small increase in the expected number of students. 

     

  • Planning Statement    East Sussex County Council 

    21 

    7.13   The redevelopment proposals include a total of 74 no. spaces of on site parking 

    which meets the recommendations of the travel plan.  The majority of the parking 

    provision (58 no. spaces, including 1 no. disabled space) is situated on the existing 

    lower car park plateau with the remaining (16 no. spaces, including 5 no. disabled 

    spaces) located in the existing upper car park near the Sports Centre.  

    This is within the maximum permitted standards set out in the Local Plan and 

    Supplementary Guidance.  

    Flood Risk and Drainage  

    7.14   The site is located in Flood Zone 1 (areas with little or no potential risk of flooding) 

    and therefore the proposed redevelopment is appropriate for the location in 

    accordance with PPS25 and the Strategic Flood Risk Assessment (FRA) for the area. 

    The potential sources of flooding are therefore identified as being from overland 

    surface water, or the failure of site drainage systems.  

     

    7.15   To mitigate this, the surface water drainage design will make use of infiltration 

    provided using pervious paving (to the car park). This will provide water quality 

    benefits through the removal of urban runoff pollutants.  

     

    7.16   The supplementary FRA concludes that the proposed development will not 

    adversely affect onsite, neighbouring or downstream developments and their flood 

    risk. The proposed surface water drainage system is also likely to offer significant 

    betterment in terms of water quality recharge to the underlying aquifer. 

    Plant and Machinery  

    7.17   As agreed during pre application discussions, it is necessary to provide details of the 

    plant and machinery proposed for the building in order that it could be fully 

    assessed for the effects of noise, emissions, odour and pollution. This assessment 

    has been undertaken and is included as a supporting application document 

    (Document 10). The report identifies the locations of all plant, sets maximum criteria 

    and concludes that the proposed development would be comfortably within the 

    limits set by the Local Authority and the Clean Air Act for plant noise and emissions 

    (including odour). 

    Construction Management  

    7.18   A Construction and Environmental Management Plan has been prepared by Kier and 

    will be implemented during construction. This includes a SMART Waste Plan in line 

    with the requirements of SPD03. This Plan identifies the potential impacts from 

    construction and sets out control measures to mitigate them. Kier have been 

  • Planning Statement    East Sussex County Council 

    22 

    involved in the construction of educational buildings on a number of recent 

    occasions and are aware of the areas where disruption may occur. Procedures have 

    been set out in the plan to address these points. 

    7.19   As part of their “good neighbour” approach, Kier will inform, advise and invite 

    constructive help from local residents with regard to issues of possible concern. Kier 

    has been a keen participant in the construction industry’s Considerate Constructors 

    Scheme since its inception and will be registering this site with the scheme. 

    7.20   The Construction Management Plan sets out the various phases of construction, 

    illustrating where the site compounds will be located and how construction traffic 

    will be dealt with. The plan also deals with site security, fire precautions and 

    includes a programme and construction sequence.  

    Consultation and Community Involvement  

    7.21   A separate Statement of Community Involvement has been prepared to accompany 

    this application. This document explains how best practice procedure has been 

    followed in undertaking public consultation.  Students, staff and interest parties 

    have been made aware of this proposal throughout the design process and 

    comments have been given consideration during the design process.  

  • Planning Statement    East Sussex County Council 

    23 

    SECTION 8 ‐SUMMARY AND CONCLUSION  

    8.1   This application follows on from a competitive tender process during which the 

    design of the building now under consideration was chosen as the preferred design 

    for the Academy. 

    8.2   The building will incorporate facilities to meet the teaching needs of 21st century 

    educational curriculum. 

    8.3   The proposal represents a design which can be implemented with minimum 

    disturbance to the operation of the school.   

    8.4   This proposal has received support in the local community and represents a unique 

    opportunity to provide a quality community facility.  The proposal represents a 

    significant improvement from the outline scheme put forward previously and is 

    supported by a raft of supporting documentation which demonstrates that all of the 

    Council’s development plan policies have been met and that the proposal should 

    therefore be found to be acceptable.