HF UPGRADE PROJECT

16
HF UPGRADE PROJECT Y. Onel PM June 11, 2012 1

description

HF UPGRADE PROJECT. Y. Onel PM June 11, 2012. Recent Highlights and News-I. - PowerPoint PPT Presentation

Transcript of HF UPGRADE PROJECT

Page 1: HF UPGRADE PROJECT

HF UPGRADE PROJECT

Y. Onel PM June 11, 2012

1

Page 2: HF UPGRADE PROJECT

Recent Highlights and News-I• The PMT deliveries are now completed. Testing is going well. We had a meeting with

Hamamatsu regarding our reject tubes. We have shipped back about 10 PMT’s ( low gain, high dark current and black cover problems) to be tested by them. The Base Board production is also going well.

• Working on the New HV testing system and forming a committee to evaluate the RFP responses. Bulgarian new module testing is completed. (there were some problems- we are working on this- We expect the reworked proto will be at CERN soon).Waiting a detailed report from German and Alexi. Both power supplies will be tested and evaluated at CERN E-pool using professional equipment and high expertise level of pool technicians.

• The HV RFP and decision committee is now formed. Members are: Germain, Alexi, Ianos, S.Los, M.Miller, D.Winn from HF and Magnus and S. Lusin from CMS Coordination.

• We have decided on the shield length- 54 mm (looks good !! the presentation by Ianos during HF meeting on May 14th) we will inform Mike Fountain to start with the production.

• Gain Sorting Proposal by Ugur is now ready. -A uniform gain distribution for one HF is outlined from the foist 900 PMT sample. Other than the fringes at the edge of the sample, we can get gain uniformity within2% -EM and HAD, and 4 Quadrant separation would work if we can deliver different HV for each group (total 24 groups). -As the operation gain is decided, we can develop sorting and HV distributions for each group.2

Page 3: HF UPGRADE PROJECT

CAEN and Bulgarian PSU’sTwo modules from CAEN A1535 and A1511. Both floating ground. A1535 – to power cathode circuit, A1511 – two last dinodesBoth modules shows perfect performance up to the 3 mA current (max for these module). Presently A1535 has up to 3kV output. Needs to be reworked to have lover Voltage and higher current

A1535 A1511Modified Bulgarian Power Supply – Power supply was modified to meet needs of new m-anode PMT’s. Lower voltage. Current up to the 10 mA. New firmware to fix the spike problems.

Both power supplies will be tested and evaluated at CERN E-pool using professional equipment and high expertise level of pool technicians

Between two oscillators within the same channel cross-talk was detected during the tests of Bulgarian PSU. Unit is back to Sofia, will be fixed and will be back at CERN by June 8th

LV part High frequency oscillator HV partHigh frequency

oscillator

HV Board

Page 4: HF UPGRADE PROJECT

Recent Highlights and News-IIThere is an agreement for a new cable purchases– Thanks Chris Tully, Jeremy Mans and Pawel De Barbaro for this. There is also a strong support from Austin and Magnus on this.Decision is to purchase all ROBOX inside cables and 1/8 of 5m cables FEE and connector cables to the existing FEE and start installing these and purchase the remaining by Mid-2013 that we have all cables installed during LS1. This will enable us to go to the 2 channel readout option by LS1.5 or YETS (2014-15).This means that the HF FEE design and construction will go rather fast (att. to our Turkish and Brazilian groups).HF new front end integration will be presented by Ianos. HF Electronics Packaging as well as the agreement within HCAL that we should pursue the Winchester Cables presented by Terry Shaw.Developing our “Project Org Chart” adding Brazilian Universities and ITU, Istanbul. Alberto Santoro and Gilvan-Augusto Alves are named as Co-L2’s for Brazil in our org chart. E.Gulmez BU-Istanbul is L2 for Turkey.

4

Page 5: HF UPGRADE PROJECT

HF2012 Organization Chart

5

C M S H F U P G R AD E 2 0 1 2 O R G A N IZ A T IO N C H A RT

J . N a ch tm a n /C .T u llyH F F E

E .G u lm ezT R C M S L 2 P M

N e u h au s (U I)C a n did a te P M T S tu d ies

J ia (U I)P ro du c tion T es tin g Io wa

F u n k (U I)B a tc h P M T Te s t ing

T ira s (U I )S p e c ia lity T e st

D u m a n og lu (C U )P ro du c tio n Te s t ing A d a na

Jo sh i (F N A L)D a tab a se

C o rs e / K in g sto n (U I)D a tab a se

P M T Ch a ra c teriza tionA kg un

1 .1.2 .1 .3

K e n t, D e b b ins (U I)S le e ve M e ch a n ics

C re m a ld i (M iss )S c in tilla tio n T e s ts

A kg u n (U I)R a d ia tio n D a m a ge

W in n (Fa ir)N e w S le e ve M a te ria l

C re m a ld i (M iss )S le ev e P ro d uc tion

S le ev e s A nd L ig h t G u id esW inn

1 .1 .2 .1 .4

S ch m id t (U I)D e s ign

F o u n ta in (U I)P re -P ro d uc tion

F o u n ta in (U I)P ro du c tion

D e b b in s (U I)M e ch an ica l Te s ting

L o s (F N A L)D e s ign

M ille r (U I )P ro du c tion

L o s (FN A L ), N e u h au s (U I)P M T B a s e Bo a rds

B u lg a ria n H VS o fia G ro up

M a rtin e z (F IU)C A E N H V

R O B O X De s ig n a n d P ro d .S ch m id t1 .1 .2 .1 .6

T e rry, S h a w (F N A L)C a b le D e s ign

F e rm i T ec h . T B AC a b le /C o nn e c tor T e st

F e rm i Te ch T B AC a b le P ro d uc t ion

P M T C a b lingT e rry S h a w (F N A L)

1 .1 .2 .1 .5

A kg un , N eu h a us (U I)Io w a T e s ts

K a ya , Is ild a k (B U -T R)9 0 4 T e s ts

M e s tv iris h v ili, S c h m id t (U I)In s ta lla tio n in U X C

S u la k (B U -U S )T e s t B ea m 2 0 11

D e m o B o x , L ig ht G uid e P h i3Ye tk in

1 .1 .2 .1 .8

B a k irc i,C e rc i,O zo k (T R )T e s t S ta nd s in S X 5

D e b b ins , K en t (U I)R O B O X R e s em b ly A n d T e st

H F C E R N T e am

H F Tu rk is h T e am

C a n ko ca k,K a ya ,Isild a k (T R )R O B O X T es t in g in S X 5

F e rm i Te ch T B AR O B O X C a b ling

H F C E R N T e amR O B O X B u rn in

In s ta lla tio n A n d C o m m issio n ingM e s tv irishv ili. P e n zo

1 .1 .2 .2

O n e lC M S H F P R O J E C T

1 .1 .2

S .T ka czyk /T .Y e tk inU S C M S L 2 P M

G . A . A lve s /A .S an to roB ra z il C M S L 2 PM

O n e lH F U P G R A D E P M

P .D e B arb a roH C A L P M

Page 6: HF UPGRADE PROJECT

New Advanced Schedule

6

Page 7: HF UPGRADE PROJECT

PCB production

12x Jumper base board production/checking jumper board testing PCB production Board assembly/testing Testing and QC at IowaFirst shipment of PCB's to CERN50% board production doneAll done, tested and delivered to CERN

3/1/12 --- 4/15/124/15/12 ---5/15/125/15/12—6/15/126/15/12– 12/1/126/30/12 - 7/15/127/31/12 (Int. Milestone)10/1/12 (Int. Milestone)12/7/12 (Int. Milestone)

SLSL, IS, AMSLSLMM, JC, DS, ZJ, GF, JKZJSLSL

Page 8: HF UPGRADE PROJECT

PMT's

Delivery dates at CERNSet 1Set 2Set 3Set 4Set 5Set 6Set 7Set 8

05/15/1206/01/1206/15/1207/01/1208/01/1208/14/1209/01/1209/14/12

Page 9: HF UPGRADE PROJECT

Test stand setupTest new box ( set-up new ROB) Produce and assemble test equip Establish Testing Procedures Produce Test stand equipment

AM Tests new BoxNew ROBOX at 904- operating New ROBOX at SX5- operating Test Stands at SX5—operating

4/23/12 - 5/15/123/31/12 - 6/30/124/23/12 - 7/31/124/15-6/30

5/15 - 6/7/127/31/12 - 8/31/127/31/1212/23/12

IS, AMIS, MF, PD, TKAM, IS, APIS, MF, PD, TK

AM, HB, EBAM, IS, AP, GA, YGAM, IS, AP, GA, YGAM, IS, AP, GA, YG, SD, YOz, FO, SS, SC, NB

Adding two students Marcos and Thiago from Brazil.

9

Page 10: HF UPGRADE PROJECT

ROB mechanicsFinalize Shield dimensions & All materials orderedQN + Iowa students pre-assembly Ship to CERNCERN SetupHF+ mechanics pre-assembly/cable prep.

ROB Completion Dates25% completion50% completion75% completion100% completionProduction contingency

04/01/12 - 05/14/12

06/01/12 - 07/01/1209/01/1209/14/12 - 10/01/1210/01/12 - 03/01/13

05/01/12 - 06/31/1207/01/12 - 08/31/1209/01/12 - 10/31/1211/01/12 - 12/21/1212/22/12 - 02/28/13

PB, MT, IS, PD, TKZJ, ET, GF, JC, JK, DSOlga, TK, PD, (+2 crews x2)Olga, TK, PD, (+2 crews x2)

10

Page 11: HF UPGRADE PROJECT

11

Assembly and Testing

Base board population learning/training

Populate and test baseboardsHF+ Q1 (27)HF+ Q2 (54)HF+ Q3 (81)HF+ Q4 (108)HF- Q1 (135)HF- Q2 (162)HF- Q3 (189)HF- Q4 (216)

07/31/12 - 08/21/12

08/22/12 - 09/07/1209/07/12 - 09/22/1209/22/12 - 10/07/1210/07/12 - 10/22/1210/22/12 - 11/07/1211/07/12 - 11/22/1211/22/12 - 12/07/1212/07/12 - 12/22/12

AM, IS, DK, MK, OK

AM, IS, DK, MK, OK, EE, OO, BU, MY, SD, YOz, HO, KD

Page 12: HF UPGRADE PROJECT

Activities on HF (HF+ HF-)

HF +HF+ ROB’s outDisassembleReassemble + testing

HF -HF- ROB’s outDisassembleReassemble + testing

12/03/12 - 12/18/1212/19/12- 02/03/1302/04/13 - 04/08/13

12/19/12 - 01/15/1301/16/13 - 03/19/1303/20/13 - 06/25/13

12

Page 13: HF UPGRADE PROJECT

Back-up

13

Page 14: HF UPGRADE PROJECT

PMT test in 2012-I

• Iowa is planning is to have all PMT's at CERN sometime in Sept 2012.

• All of the PMT's and base boards will be tested in 2012 at CERN

• We are in process of defining all test-stand setups and needed equipment to handle the testing of the base boards and PMT's. WE plan on having setups to test the equivalent of two boxes worth of PMT's at a time.

• Burn in HF Plus Side ROBOXs in Garages 210 days Mon 3/12/13 - Mon 1/14/14 and Burn in HF Minus Side ROBOXs in Garages 9/21/13 (as defined by the HF Project Schedule).

14

Page 15: HF UPGRADE PROJECT

PMT test in 2012-II• Functionality test – All base boards will be equipped with PMT’s and PMT

+ base board assembly will be tested at CERN.• Primary readout is with HCAL DAQ and HF QIE etc.• We will have four light distribution boxes (three in addition to existing one).

Number augmented to allow base board + PMT testing in parallel with new ROB test development.

• Two will be set up for testing of PMT’s + base boards (6 base boards tested at a time). In addition to light distribution unit, setups will have:

• “Dark box” cover• Signal and HV cables ( At the moment we only have cables for the

one upgraded box.)• Support for Base boards + PMT’s (using production ROB parts)

All the necessary equipment components are designed currently at Iowa.15

Page 16: HF UPGRADE PROJECT

PMT test in 2012-III• Before majority of PMT’s will be shipped, we will have 24 m-anode PMT’s + three

baseboards at CERN to assemble and test one more “upgraded” ROBOX for test-stand/testing development Most mechanics already assembled at CERN. Needs cables from Fermi box. Will be assembled and ready for use by May.

• This ROBOX will be used to define all the test procedures –LED and PED runs, SPE runs. We will define what info goes to database, traveler runs etc.

16