HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status...

23
HF 2008: Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

Transcript of HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status...

Page 1: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

HF 2008: Status and Plans

CMS Week, February 2008

Aldo Penzo

HCAL Commissioning Status

(INFN-Trieste, Italy)

(23 February 2008)

Page 2: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

HF TO-DO JAN-APR 2008 • Commissioning HF- (R/O, Ped, LED)

– Mapping checks– Light-leaks– Compare UX5 to B186

• Complete HF± services:– N2 inertion system – C-rails – Laser, RADDAM– Source tubing and drivers

• Integration TOTEM/CASTOR/BSC• Source calibration• Ready to move

Page 3: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

HF 2008 Schedule, Draft #4 (AP+SP+KC+IS)HF 2008 Schedule Draft # 4 (A.P+S.P+K.C+I.S)HF Coordinator: Aldo PenzoHCAL Glimos: Pawel De Barbaro

Name of activity Name of subactivity Current status People involved Start date End date Location Comments

0)Complete installation ( HF-):Installation of source tubes started Ianos, Olga beginning of March~1 week. Garage Olga away for week 25-3rd.Installation of laser cables starting Sorina, Vasken 30-janv 03-févr GarageInstallation of laser splitter starting Sorina, Vasken ~January 30 03-févr GarageFinal safety modifications -a)power supplies etc… not started Magnus, Serghei + ??? 23-janv few hours GarageC-rails mounting in preparation Sorina,Olga, Russian Techs 22-janv one week. surface, garageInstallation of Robox machine not started Phil, Nural, Sorina 15-févr 2 weeks Garage C-rails must be mountedHF/HCAL RADmon installation ready to install Ershov/Dubna 25-févr ~1 week Garage,USC to be coordinated with commissioning effortBSC counters N.Zeeland team to be coordinatedRADDAM (Online Radiation Monitor Fibers) – laser connections Kerem, Numan, Jean-Pierre to be coordinatedLabeling of "on-detector" cables (except laser) ? ASAP ~1 week Garage Labels have been printed.Labeling of "on-detector" laser cables Sorina ASAP ~2 days Garage Labels have been printed.Re-routing of source driver cables started Ianos ~2 hrs. End feb. GarageTermination of source driver cables Vladimir/Vitali's crew ~1 week ~2 days GarageClean up of and storage of fiber and cable overlength GarageConenction of LED voltage cables to CAEN supply ~2 hrs. GarageInstall small nitrogen hoses (copper to ROB) ~1 day Garage Requires nitrogen to be connected to copper tubes.Install nitrogen distribution panels Sasha V. +? ~1 day GarageInstall near to far side nitrogen distribution hose ~2 hrs. GarageInstall nitrogen hose splitter ~ 1 hr. Garage Parts need to be procured.Inspection of cables in trench at end of cable chain ~1 hr. cable trench Incident may have caused damage. Requires access to trench.Route LVTMM cables+install LVTMM systemVerification of rack placement and fixation of racks Ianos, Lusin... After rerouting of source driver and LVTMM cables.

0)Complete installation (HF+):Installation of source tubes started Ianos, Olga Feb.13 2008 beginning of MarchGarage Documentation provided, work started. Olga away for week 25-3rd.Installation of laser cables started Sorina, Vasken 30-janv 03-févr GarageInstallation of laser splitter started Sorina, Vasken ~January 30 03-févr GarageFinal power supply (AC-DC) not started German, Sorina ASAP unkown? Garage depends on CAENFinal safety modifications -a)power supplies etc… not started Magnus, Serghei + ??? 23-janv few hours GarageC-rails mounting in preparation Sorina,Olga, Russian Techs 22-janv one week. surface, garageInstallation of Robox machine not started Phil, Nural, Sorina 15-févr 2 weeks Garage Done Feb 19,2008HF/HCAL RADmon installation ready to install Ershov/Dubna 25-févr ~1 week Garage to be coordinated with commissioning effortBSC counters N.Zeeland team to be coordinatedRADDAM (Online Radiation Monitor Fibers) – laser connections Kerem, Numan, Jean-Pierre to be coordinatedFinal installation of DCS hubs and related cables. ? to be coordinated with commissioning effortLabeling of "on-detector" cables (except laser) ? ASAP ~1 week Garage Labels have been printed.Labeling of "on-detector" laser cables Sorina ASAP ~2 days Garage Labels have been printed.Termination of source driver cables Vladimir/Vitali's crew ~1 week ~2 days GarageClean up of and storage of fiber and cable overlength GarageInstall small nitrogen hoses (copper to ROB) ~1 day Garage Requires nitrogen to be connected to copper tubes.Install near to far side nitrogen distribution hose ~2 hrs. Garage

Install nitrogen hose splitter ~ 1 hr. Garage Parts need to be procured.Route LVTMM cables and install LVTMM systemVerification of rack placement and fixation of racks Ianos, Lusin... After routing of LVTMM cables.

Misc. items:

Page 4: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

HF 2008 Schedule, Draft #4 (Ct’d)Misc. items:

Clean up of HF's for open day All Make posters?Evaluate Rack cover options and start procurement.Properly tie up/route HV cable is USC rack ~6 hrs USCProduction of nitrogen distribution panels Started Sasha V.+ Vitali's crew ? Parts ordered, first panel production started.Specify ground straps between HF tables and D's Ianos, LusinKeep up on evolution of cooling system. IanosEstablish location and mounting of LVTMM module and sensors AlexiEstablish connection of source driver interlock system IanosInvestigate crazy routing of RADMON tap box cables. IanosReview/update of equipment code barcode labels.

HF- commissioning 1) Hardware functioning;Cables checks Labeling, documentation of cables (ex DCS cable) incomplete not finished

a) LV check finished Alexi, Kerem, Numan, Sorina 2 days Garage one module A3100 found bad, replaced by German b) HV check done Alexi, Serguei as Alexi wants Garage 2 board found bad, replaced by Sergueic) DCS check done Serguei, Alexi, Keremd) DAQ configuration for HF done Arnoe) RADDAM tests not started Kerem, Numan, Jean-Pierre

2)HF- detector connection to CR DAQ1) all cables and communication in position(s) done Kerem, Dmitriy, Alexi, Pawel,.....2) channel by channel check done Kerem, Dmitriy, Alexi, Pawel,.....3)TTC clock signal finished Sorina, Dick4) Software done Arno (Jeremy??) LED and Pedestal configuration done

DCSall cables and communication in position(s) done Serguei unkown?Channel by channel check not finished? Serguei unkown?Software installed and running done? Serguei unkown?

3)Pedestal run HF - map started HF team 28-janv 3-4 days CRcheck output signal globally done Alexi, Kerem, Numancheck channel-by-channel in progress Alexi, Kerem, Numancheck HF- configuration in progress Kerem, DmitriyStability …during long run not started Numan, Dimitry, Kerem, Salimcomparison with B186 in progress Salim, Dmitriy, Kerem, NumanLigth leaks in progress Kerem, Numan, Dimitry

4) LED run check fiber status started Alexi 30-janv 3-4 days CRCable connectors+panel in progress AlexiRuns with "standard" LED level not started HF teamRuns with "low" LED level not started HF teampoint 8) not started HF team

5)Laser calibration runs check laser signal channel by channel not started Sorina, Vasken 30-janv 3-4 days CRInstall HF fibers in progress Sorina, Vaskeninstall HF splitters in progress Sorina, VaskenCheck overall signal not started HF teamcheck PMT output not started HF teamset the correct timing not started HF teamtake laser runs not started HF team Run control has to be createdpoints 8)RADDAM splitters and laser tests not started Kerem, Numan, Jean-Pierre

6)Source calibration source tubing installation into indexer started Olga, Ianos End february?? 20 days??? garageverification of the correct tube installation not started Olga, Ianos unkown? unkown? garageInstall source drivers started Ianos, Olga unkown? unkown? garageinstall radiation protected area in discussion RP, Pawel, Aldo, Christof unkown? unkown? garagecheck with dummy source not started Ianos, Alexi, Sorina unkown? unkown? CRtransport and install sources not started RP, Pawel, Ianos, Sorina unkown? unkown? garagecheck of controls with source not started RP, Ianos, Alexi, Sorina unknown? unknown? CR

7)Overall infrastructure final checkmechanical fixation of components(ex racks) to be completedfinal electrical check to be plannedgas connection to final distribution to be plannedelectrical grounding final scheme to be plannedbeam monitors ready to install?radiation monitor ready to install?Integration of Totem and Castor components big job!!!

8)Create/update database for Pedestal, LED, Laser, Sourcepreparing data in progress Dmitriy, Kerem

9)HF+ repowered point 5) to be done not plannedpoint 6) to be done not planned

10)Comparison of commisioning data for HF+/- with previous commisioning first pass comparison with B186 in progress Dmitriy, Salim, Kerem

11)Participation into Global runs and weekly runs

Total

Modification notes: 30 Jan 08: 1st version Sorina05 Feb 08: 2nd draft Aldo06 Feb 08 : modified by Kerem Added Items to the commissioning and RADDAM sectionsmodified feb.22 08 by Ianos Added Items to the "complete installation" section, and made separate section for HF+ and HF-. Also added misc. to do section.

Page 5: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

HF task assignements• HF ± Services:

– N2 final assembly (panels, flowmeters) [Ianos, Sasha]– Source tubing and drivers installation [Ianos, Olga]– Rad Monitors installation [MSU - Ershov]– C-rails and ROBox extractor [TTU - Sorina]– Laser fibers [Sorina, Vasken]– RADDAM implementation [UoI – JeanPierre]

• HF - commissioning [Alexi, Kerem]– Compare data samples [Salim, Dmitry]– HF - commissioning team:

Aldo, Alexi, Kerem, Dmitry, Numan, Salim, Sorina

+ Ianos, Olga, German, Serguei, Sasha, Vitali, … + Lisa, Ferhat, Efe, Jean-Pierre, Arjan, Richard(s)

[Report to /(advice by) Andris, Pawel,…]

Page 6: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

HF- commissioning status• Pedestals:

– Initially 4 channels bad

– black cables (ROBOX’s – QIE) cause – 3 repaired/1 replaced

- Now all 864 pedestals OK

• Mapping/cabling: – found mismatch between HF- e-map and HF- cabling (20-01-08)

– temporary cabling change, then map change (cabling restored)

– still debating…,

However:

• Pedestal comparison (B186 vs UX5) ≈OK!• HV switched on:

– progressively (possible light leaks) @ 1100 V

• LED timed in:– Found 4/864 missing LED channels (investigating…)

Page 7: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

Pedestal comparison betwen B186 and UX5HFminus, ROBOX: 1,2,3

Plots from Dima Vishnevskiy: Blue squares – B186 measurements, green triangles -- UX5 measurements, run 34826

Missing one channel

Appears in next ROBOX

HF crate 1, roboxes 1,2, and 3 Has to be

here

Page 8: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

Pedestal comparison between B186-UX5

Plots from Salim Cerci

Page 9: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

During commissioning @ 1100 V

Plots from Kerem Cankocak

Problematic channels fixed (cable problem)

Page 10: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

LED HV @1150 V Run 35696

• Improve timing & pedestal subtraction

• No LED from 4 channels • Comparison with B186

ASAP

DQM plots :http://cmsmon.cern.ch/hcal/hf/

Page 11: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

Source tubing & driver

Ianos +Olga +Russian techs

Page 12: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

C-rails& ROBox extractor tool

• C-rails (pre-Sorina)

• C-rails & extractor tool (post-Sorina)

2008/02/22

Page 13: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

Sourcing in garage:preparations

• First meeting with RP (Pawel+Vitali+Aldo)• Preparing sourcing procedures• Installation safety controlled doors• Establish interlock systems• RP rough estimate of dose rate:

– source: Co-60 185 MBq - shielding: 20cm plexi, 2 cm Fe, 4cm Pb

– distance: – at contact ~25 µSv/h – at 40 cm ~4 µSv/h

(sounds good, but no distance given from Pb to the garage doors...) • Reminder: - Before the first run, non-designated area, people don't

wear dosimeters, the ambiant dose rate should be below 0.5 µSv/h • - After the first run, at least supervised area, people will have to

wear a valid dosimeter, the ambiant dose rate should remain below 3 µSv/h

Page 14: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

HF Calibration Optical Fiber Path

• 9 PMT Boxes / Quad• 24 PMT Tubes / Box• 216 PMTs / Quad• 864 PMTs / Side• 1728 PMTs Total

N2 Laser

300 QQ 150m

HF

HF +

9 PMT Boxes

9 PMT Boxes

9 PMT Boxes

9 PMT Boxes

9600 QP

Calib

Box

1 4

Counting Room

300 mJ 337 nm

Bottom Rack

Calib

Box

Top Rack

Calib

Box

Calib

Box

Bottom Rack

Top Rack

9

99

600 QP

300 QQ

Done: Sorina+Vasken+German+Maurizio

Page 15: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

HF RADDAM System

• Splitters, adaptors, WLS Scintillator OK• Some long fibers broken → repaired• Assemble, install, test

150m

HF

HF +

9 PMT Boxes

9 PMT Boxes

9 PMT Boxes

9 PMT Boxes

1 → 4

Scintillator/WLS

N2 Laser300 mJ 337 nm

Page 16: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

Nitrogen system for HF+ or HF- (Ianos+Alexandre Vishnevski)

Pressure reducer

Ball valves

Near side

Rubber hose

Far side

Panels with flow meters

(200 l/h)

6 – 8 bar

1 – 2 bar

•Manifolds have independent fluxes •Flux in any manifold can be increased many times in respect to nominal one•Possibility to control flux in Gas Room•Ball valve on supply pipe provides cutting of flux in chosen manifold.

Page 17: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

Other Items

• RAD Monitors ready to install

• RADDAM : Main issue transmission fibers;

• BSC ready for installation?

• CASTOR/TOTEM infrastructures?

Page 18: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

HF - : risky situation noticed…

Cables in standard chain Cables loose on bottom of trench

Page 19: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

Rad Monitors

Page 20: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

CASTOR/TOTEM

infrastructures

• Support table • Gas rack

Page 21: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

HF in UXC55

Coming OUT and UP! When?

Page 22: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

Backup?

Page 23: HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)

The HF group is rather chaotic, but in general well-intentioned, and heading in the right direction…