HEURTEY PETROCHEM ARA 2016 - afrra.org · PDF fileMain Reasons: Lack of local instrumentation...
Transcript of HEURTEY PETROCHEM ARA 2016 - afrra.org · PDF fileMain Reasons: Lack of local instrumentation...
PROCESS OVERVIEW
3
Process heater = direct fired heating equipment used to raise
the temperature of a feed flowing through the coil
Used in various industries
Jamnagar refinery (India) 50 Heurtey’s furnaces in operation
Total petrochemical complex (Belgium) Deok Yang hydrogen unit (South Korea)
REFINING PETROCHEMICAL SYNGAS
PROCESS OVERVIEW
Reheat process fluid without change in phase
HOT OIL FURNACES
CATALYTIC REFORMER
HYDROTREATER/HYDROCRACKER
Reheat a liquid with partial vaporization
COLUMN CHARGE (CDU, VDU, …)
COLUMN REBOILERS
Reheat a fluid with chemical reaction
VISBREAKING
STEAM CRACKER
STEAM REFORMER
EDC CRACKER
4
LESSONS LEARNED
7
Description: Rupture of a tube located in the shock zone due to combined corrosion by Polythionic acids (creating fractures), Oxydation/Sulfuration (reducing the wall thickness) and slow creeping due too very high local wall temperature (coking)
Main Reasons: Lack of local instrumentation (skin thermocouples to detect coking), poordesign resulting in high local heat flux
Acccident: Fire
Consequences: Economical loss and environmental damages
Date: June 26th 2004
Plant: Total Feyzin, Feyzin(France)
Unit: HDS
Heater: Reactor feed heater
Aria : Retour d’expérience sur les accidents technologiques
http://www.aria.developpement-durable.gouv.fr/accident/27459/
LESSONS LEARNED
8
Description: The heater was in the process of being restarted and had been operated for several hours with a single burner. As additional burners were lit over a period of severalminutes, insufficient air resulted in oxygen-depleted/fuel rich mixture in the firebox. Subsequent opening of the individual burner air registers was followed by an explosion
Main Reasons: Defficient start-up/operating procedure
Acccident: Explosion & Fire
Consequences: 1 fatality, economicaldamage
Date: November 15th 2013
Plant: Pascagoula Chevron, USA
Unit: Catalytic cracking
Heater: Splitter Reboiler
US Chemical Safety Board (CSB)
www.csb.gov
MITIGATING THE RISK OF…
10
IMPROPER COMBUSTION
CAUSES CONSEQUENCES DESIGNSAFETY & CONTROL
OPERATION PROCEDURES
LOW/HIGH DRAFTUNSTABLE FLAME
(PULSATING/LIFTING)STACK DESIGN
DRAFT
MEASUREMENT
VISUAL
INSPECTION OF
FLAMES
LOW EXCESS AIRINCOMPLETE
COMBUSTION
BURNER DESIGN
MARGINS
FLUE GAS
ANALYZERS
(O2, CO, UNBURNT)
REDUCE FUEL
BUT DO NOT
INCREASE AIR
FUEL OUTSIDE OF
SPECIFICATION
INSUFFICIENT AIR
SUPPLY
DENSIMETER, WOBBE METER
Charles E Baukal
(2012). John Zink
Hamworthy
Combustion
Handbook
MITIGATING THE RISK OF…
11
TUBE RUPTURE
CAUSES CONSEQUENCES DESIGN SAFETY & CONTROL
OPERATION PROCEDURES
FLAME IMPINGEMENT
(BURNER TO TUBES)HIGH LOCAL TEMPERATURE
AND ACCELERATED
DETERIORATION OF TUBES
BURNER
SPECIFICATIONS
TUBE SKIN
THERMOCOUPLES
VISUAL INSPECTION OF
FLAME SHAPES
COKING HIGH LOCAL TEMPERATURE
AND ACCELERATED
DETERIORATION OF TUBES
HEAT FLUX
HEATER GEOMETRY
PROCESS VELOCITY
TUBE SKIN
THERMOCOUPLES
REGULAR VISUAL
INSPECTION OF TUBES
(CHANGING COLOR, QUICK
TUBE SCALING)
CAPACITY EXCEEDING
DESIGN
OVERHEATING OF
TUBES/CAST PIECES AND
ACCELERATED DETERIORATION
FUEL PRESSURE, RADIANT
CHAMBER
TEMPERATURE & PRESSURE
(ESD TRIP)
Charles E Baukal (2012). John Zink
Hamworthy Combustion HandbookCharles E Baukal (2012). John Zink
Hamworthy Combustion Handbook
MITIGATING THE RISK OF…
12
TUBE RUPTURE
CAUSES CONSEQUENCES DESIGN SAFETY & CONTROL
OPERATION PROCEDURES
SUPPORTING FAILURE TUBE BOWING AND BREAKING DESIGN MARGINS AND
APPROPRIATE
MATERIAL CHOICE
VISUAL
INSPECTION TO
LOOK FOR CRACKS
CORROSION
(FLUE GAS OR FLUID)ACCELERATED DETERIOTATION
OF TUBES/CAST PIECES
PROPER CHOICE OF
MATERIAL
PROPER DESIGN
TAKING CARE OF ACID
DEW POINT
INSTRUMENTATION & CONTROL
International standards give recommendationsfor instrumentation and control such as:
EN746
API556
NFPA86
13
INSTRUMENTATION – HEATER
15
Draftmeasurement
TTs & PTs linkedto alarm and trip
TSTK Radiant coil
TSTK Shockcoil
O2 & CO analyzers
SAFE START-UP PROCEDURE
16
Fuel line leak testing Check tightness of the fuel valves Important to check potential deterioration of the valves
Purging Crucial for removal of possible remaining flammable from radiant chamber
prior to ignition EN746-2 advises to renew the radiant chamber volume 5 times prior to
ignition sequence For natural draft heaters, the atmosphere shall be check with explosimeter
Pilot/Main gas ignition Start on low fuel pressure Pilots must be ignited one by one Pilot flame presence shall be proved by flame detection Only burners whose pilot is lit can then be ignited
Ramp up Heater firing shall be increased slowly 50°C/h to avoid damaging the
refractory and cast pieces Air flow shall be increased prior to fuel flow
PREVENTIVE MAINTENANCE
Casing thermography to identify hot spots and potential failure of refractory. Rapid repair must be done.
Tubes bowing or sagging gives indication of uneven temperature distribution, flame impingement or supporting problem or support failure. Replacement of the defective supports will help ensuring a long lifetime of the coil
Tube external diameter (tape) and thickness (ultrasonic) must be checked at every maintenance turnaround.
Tube skin scaling is the witness of corrosion under high temperature (slow process). If fast corrosion is locally observed, check for flame impingement/inside tube coking.
17
Heater & coil thermography
www.Petroval.com
Tube UT
www.Olympus-ims.com
ADEQUAT MAINTENANCE
Burner tips / nozzles and all other surfaces exposed to radiated heat should be checked to be free of carbon, or heat erosion.
Burners must be cleared of debris
Tips alignement must be checked
Burner muffle block should be inspected for general condition and examined to be free of carbon deposit, or any other form of deterioration.
Pipework to be checked for leaks, particularly on flanges joints and connections ("bubble tested" for gas lines).
Instruments should be checked to be operative and if necessary, re-calibrated or replaced.
Increased pressure drop or increase of local skin temperature can be the result of high coking in the coils. Mechanical or steam air decocking to be performed
18
Charles E Baukal (2012). John Zink
Hamworthy Combustion Handbook