Heath Delzell – Engineering Bureau
IDNR Engineering
Progress to Date and Timeline for Project CompletionDesign and Construction Obstacles
![Page 2: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/2.jpg)
Construction ActivitiesPhase 1 – Dam and
Spillway RenovationPhase 2 - In-Lake
ConstructionSediment Retention
Basins Sediment RemovalShoreline ArmoringUniversally Accessible
Fishing PierPhase 3 – Boat Ramp
and Parking Lot
![Page 3: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/3.jpg)
Progress – Phase 1 History
1991 – Voids filled under spillway
2007 – Contracted French-Reneker Associates to determine cause
2008 – F-R concluded leak in weathered bedrock
Solution: Remove weathered bedrock
StatusF-R Design complete and
permitted for constructionFunding has been
securedCurrently out for bids –
Letting date October 21, 2010
![Page 4: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/4.jpg)
Timeline – Phase 1Winter 2010
Early Start Date: December 1, 2010
Portion of dam to be removed
Tree ClearingConcrete Removal
![Page 5: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/5.jpg)
Timeline – Phase 1Spring-Summer 2011
Excavate Core Trench
Construct Principal Spillway Outlet/Drawdown Pipe
Place Embankment Fill
![Page 6: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/6.jpg)
Timeline – Phase 1Summer-Fall 2011
Place Embankment FillConstruct Principal
Spillway InletAuxiliary Spillway
GradingClose Drawdown Pipe
Winter 2011 – No Construction
Spring 2012Final GradingProject Complete: May
31, 2012
![Page 7: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/7.jpg)
Progress – Phase 2Sediment Retention
BasinsUpper Arm Basin
Preliminary DesignDesigned as a
Sediment PondFilled with Dredge
Material1-2 feet deep
State Contract for completionFinish DesignApply For PermitWetland Mitigation Plan
![Page 8: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/8.jpg)
Progress – Phase 2Sediment Retention
BasinsCampground Arm
Design Complete Increasing Dam
HeightSame function as
Upper Arm Basin
![Page 9: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/9.jpg)
Progress – Phase 2Sediment Removal
Design CompleteRemoving sediment via
mechanical meansScrapers, Bulldozers,
Excavators, Etc.Shoreline Armoring
Design CompletePlacing Riprap in
normally inaccessible locations
Universally Accessible Fishing PierDesign 95% Complete
![Page 10: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/10.jpg)
Timeline – Phase 2Winter 2010
Design and permit application complete January 1Wetland mitigation
Spring 2011Bid Letting: March 17,
2011Early Start Date: May 1,
2011Summer-Fall-Winter 2011
ConstructionSpring 2012
Final Grading and SeedingProject Completion: March
15, 2012
![Page 11: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/11.jpg)
Progress – Phase 3Boat Ramp and
Parking LotDesign is 25%
completeSchedule dependant
on Phase 21-2 Months for
construction
![Page 12: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/12.jpg)
Construction ObstaclesRAIN!!!
Dam construction would slowLarge storms can severely erode a partially
constructed damSediment removal would stop
Green Valley <10% complete
![Page 13: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/13.jpg)
Construction ObstaclesPerspective:
Annual Precipitation for Brighton (inches)
1991 / 2008 1992 / 2009 1993 / 2010
44.0”
30.2”
55.3”
40.5”
54.3”
48.4”
![Page 14: Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.](https://reader035.fdocuments.us/reader035/viewer/2022070410/56649f045503460f94c185e7/html5/thumbnails/14.jpg)
ConclusionDam construction
begins in DecemberPhase 2 starts
Spring 2011Boat Ramp starts
Fall 2011 or Spring 2012
All phases should be complete and the lake nearly full by the end of May 2012