HEADLINE NEWS ISSUE 6 AUGUST 2012 TARGET TARGET OnTrack ISSUE 6 AUGUST 2012 HEADLINE NEWS…1-3...

8
1 TARGET OnTrack ISSUE 6 2012 AUGUST HEADLINE NEWS1-3 PROJECT UPDATES ....... 4-5 SOMETHING TO THINK ABOUT. ............................ 8 Dear Colleagues, Well, six months have passed by and we have had 17 projects / service orders amounting to AED 830 Million in the first two quarters of this year. Major project amongst these is the Halul Accommodation Facilities for Qatar Petroleum (~ AED 450 Million), which is one of the largest projects ever awarded on Halul Island! This reflects the continued confidence, clients place on TARGET. While we would have hoped the project volume to be bigger, we are still on track and have been focusing on key prospective projects, which we believe will add to our ambition of continued growth. So it is time we put on our retrospective caps again and rekindle the spirit of growth and competition. Our multi‐ discipline, multi‐sector capabilities ought to be harnessed into a formidable force keeping up the true spirit of our company. The TARGET brand is well known for quality, safety, service and reliability of completion… it has also been known for its survival spirit; I therefore call upon all to give in their best and rally behind our management as we fight competition and the market forces into a brighter future. Ghazi Samir Qatar : Area Director and PIC Division Manager ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐HEADLINES‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ TARGET BEACH CLEANING HELPS SEA TURTLES FOR EARTH DAY AT SNC LAVALIN PROJECT: SNC Lavalin helped clean EMAL's beach from all its waste on May 24th 2012 in order to welcome the turtle nesting to come. During the next weeks, EMAL will install nets to prevent the sea turtles babies to go in the smelter direction after eggs hatching. Thanks to TARGET’s manpower and equipment for making this event a successful environment step towards protecting the seawater fauna. CONGRATULATIONS SWI‐3 PROJECT ACHEIVES 3 MILLION MAN HOURS WITHOUT LOSS TIME INCIDENT – This milestone was achieved due to the joint effort and cooperation by all Site Managers, HSE Team, Engineers, Supervisors/FM, Personnel and all site workers. Congratulations to all. "An optimist sees an opportunity in every calamity; a pessimist sees a calamity in every opportunity." ‐‐ Winston Churchill TARGET WISHES EVERYONE A RAMADAN KAREEM and EID MUBARAK. May God bless you and your family in this holy month. Executive Management

Transcript of HEADLINE NEWS ISSUE 6 AUGUST 2012 TARGET TARGET OnTrack ISSUE 6 AUGUST 2012 HEADLINE NEWS…1-3...

  1 

TARGET OnTrack 

ISSUE 6 2012 AUGUST HEADLINE NEWS…1-3

 PROJECT UPDATES ....... 4-5

SOMETHING TO THINK ABOUT. ............................ 8

Dear Colleagues,        Well, six months have passed by and we have had 17 projects / service orders amounting to AED 830 Million in the 

first two quarters of this year. Major project amongst these is the Halul Accommodation Facilities for Qatar Petroleum (~ AED 450 Million), which  is  one of  the  largest projects ever awarded on Halul  Island!    This  reflects  the  continued confidence,  clients place on TARGET.   While we would have hoped  the project  volume  to be bigger, we are  still  on track and  have  been  focusing on  key  prospective projects, which we believe will  add  to our  ambition of  continued growth. 

So it is time we put on our retrospective caps again and rekindle the spirit of growth and competition. Our multi‐discipline, multi‐sector  capabilities  ought  to  be  harnessed  into a  formidable  force  keeping  up  the  true  spirit of  our company. The TARGET brand is well known for quality, safety, service and reliability of completion… it has also been known for its survival spirit; I therefore call upon all to give in their best and rally behind our management as we fight competition and the market forces into a brighter future. 

Ghazi Samir Qatar : Area Director and PIC Division Manager 

‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐HEADLINES‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ TARGET BEACH CLEANING HELPS SEA TURTLES FOR EARTH DAY AT SNC LAVALIN PROJECT:  

SNC Lavalin helped clean EMAL's beach from all its waste on May   24th 2012 in order towelcome the turtle nesting to come. During the next weeks, EMAL will install nets to prevent the sea turtles babies to go in the smelter direction after eggs hatching. Thanks to TARGET’s manpower and equipment for making this event a successful environment step towards protecting the seawater fauna. CONGRATULATIONS 

SWI‐3 PROJECT ACHEIVES 3 MILLION MAN HOURS WITHOUT LOSS TIME INCIDENT – This milestone was achieved due to the joint effort and cooperation by all Site Managers, HSE Team, Engineers, Supervisors/FM, Personnel and all site workers. Congratulations to all. 

"An optimist sees an opportunity in every calamity; a pessimist sees a calamity in every opportunity." ‐‐ Winston Churchill 

TARGET WISHES EVERYONE A RAMADAN KAREEM and EID MUBARAK. May God bless you and your family in this holy month.  

– Executive Management 

user
Typewritten Text
user
Typewritten Text
user
Typewritten Text

  2 

TARGET HEADLINES CONTINUED: 

TARGET STARTS CONSTRUCTION AT ICAD 

 TARGET  Construction  has  begun  work  on 

TARGET workshops  located at  ICAD.    All  the works in  progress,  are  planned  to  be  handed  over  to  the Mechanical  Division  to  begin  work  on  the  steel structure. The  target date  for  the  completion of  the painting warehouses in ICAD is end August 2012.  

  

  3 

JGC Corporation sends letter of appreciation to TARGET for work on  BARZAN ONSHORE PROJECT ‐ QATAR 

   TARGET has received a letter of appreciation to the PIC Division on the completion of 11‐KV Power Distribution Network, Barzan Onshore Project in Qatar. In the letter JGC thanks the team “for the great endeavor and accomplishment on time with high standard for the successful completion and energization of 11 kV Power Distribution Network, Barzan Onshore Project under Engineering, Procurement & Construction, EPC contract. “     

They continue to state that, “the coordination, documentation and safe delivery of the power from 

upstream substation to the Ring Main Unit, RMU downstream has elucidated the fact that the project has been completed as per the standards desired by the clients JGC Corporation and Ras Gas Company.” 

   As a response, TARGET is thankful to work with JGC Corporation and appreciate their recognition of our dedication to the project    

TARGET has received Aproval and Registration to Bid for Projects with Emirates Nuclear Energy Company 

   TARGET has been approved and registered to bid on projects for the ENEC (Emirates Nuclear Energy Comany). The ENEC is a government authority that is working to develop an efficient nuclear energy source to the United Arab Emirates.   

As energy demand grows every year, the ENEC’s aim is to develop a reliable supply of electricity that will help in the growth of the nation.    TARGET’s registration to bid for these projects is a step forward and a recognition of TARGET’s reliability, capability, and safety record.  

TARGET’s Shining Tower Project is awarded GCC Tower of the Year  

   TARGET’ is proud to announce that its completed project, the Shining Tower has  been awarded  GCC Tower of the Year at the 2010 Construction Week Awards to Ramboll, the structural designers.  

  4 

TARGET MECHANICAL  Project   : Ruwais Refinery Expansion, Package 2 – Steel Structure,  Equipment Installation and Piping Works in SMP 05 Area  Client : TAKREER Value : AED 250 Million Progress : 43% Work Progress : Prefabrication & Erection of piping, Equipment  Installation and erection of structural works in progress. 

 Project : Structural, Mechanical and Piping Works   Client : GASCO Value : AED 325 Million Progress : 66% Work Progress: Piping including Pressure Testing, Structural and Equipment erection, Internal installation, Tank erection  incl. Hydro testing are ongoing.  

Project : Sea Water Intake – Phase III Client : TAKREER Value : AED 351 Million Progress : 94% Work Progress: Pre‐commissioning, Punch point Clearance & Commissioning works are under progress.   

 TARGET CIVIL  Project : Subcontract for Shah Gas Development  Project  ‐  Package 2 & 3 Civil & Building Works Client : Abu Dhabi Gas Development Co. / Saipem Value : AED 206 Million Progress : 66%  Work Progress : Structural works completed for buildings; blockworks  finishes and MEP works are in progress.  Project : Ruwais Refinery Expansion‐ Package 2 Civil Works Client : TAKREER / GS ENGINEERING Value : AED 178 Million Progress : 85% Work Progress: Footings and Pedestals complete. Cable Trenches,  manhole installations, paving works in progress  Project : 100 MBD Das Facilities Upgrade – Civil Construction Works Client : ADMA‐OPCO Value : AED 44 Million Progress : 1% Work Progress: Demolition works commenced. Mobilization of manpower and equipment in progress.  

PROJECT UPDATE: 

  5 

Project : Construction of New Training Centre, BOROUGE, Ruwais Civil Works Client : BOROUGE Value : AED 29 Million Progress : 28% Work Progress : Superstructure works is in progress and ahead of schedule. Blockworks and MEP works started.   TARGET ELECTRICAL  Project : BOROUGE 3 – Utilities & Offsites – Electrical Works Client : BOROUGE  Value : AED 66.7 Million Progress : 32% Work  Progress  :  Manual  and  mechanical  excavation  of  220  kV,  33kV, Cable  Trench  in  progress.  Cable  pulling  for  220  kV  Cable,  33kV  in progress. Mechanical Installation, oil filling of transformers in 220kV main substation completed. Cable tray and support  installation at 220kV Main substation in progress. Grounding system work at 220kV main substation, Effluent Treatment substation and main utility substation in progress.  Project : EPIC of Process Analyzers at QP Refinery, Qatar Petroleum Client : Qatar Petroleum Value : AED 4.3 Million Progress : 90% Work Progress : Manufacturing of Moisture Analyzers (2 nos.), H2/HC  Analyzers (2 nos.) & NIR Analyzer (1 no.) going on.    TARGET MARINE  Project : EPC for GASCO NGL 4 Train – Sea Water Cooling System  Client : GASCO Value : AED 475 Million Progress : 98% Work Progress : Fabrication & Installation of U/G & A/G 60" cooling  water bypass line from Pump house to NGL‐3 around 810 LM expected  to be completed by end of Sep‐2012. Static head test for cooling water  return pipeline from Sealing weir to outfall structure around 2.3 Km  will be completed by end of July‐12. Installation of discharge header pipes, valves & fitting from Lift pump to Thrust block will be completed by mid of Aug‐12. Pre‐commissioning for Pump house screening equipment will be completed by mid of Aug‐12. Project recorded 5. 26 million man ‐hours without any LTI.  Project : Construction of Sea Arm for Export Jetty, RRE‐ 7, Client : Takreer/ GS Engineering Value : AED 107 Million Progress : 21% Work Progress : Fabrication of service platform Cross beam assembly.  Fabrication of precast concrete for service platform & Loading  Platform‐ G 141 units completed. Installation of pile sleeve &  concreting for offshore driven pile 74 Nos completed. Installation of Cross beam for service platform 23 Ton completed. Installation of  shear key for inside face of pile sleeve & outside face of pile is on‐ going. Mobilized TMT 1801, 1802, 2202, Al‐Batros & Al‐Qalaa Barges to site. Batching plant barge TMT 2501 will be mobilized at site on 30‐Jul‐12.   

  6 

NEW PROJECTS: TARGET ON TRACK would like to highlight the new projects that TARGET has been awarded since the start of 2012.  

  DATE  DEPARTMENT  PROJECT NAME  CLIENT 1  24-1-2012 Target-Civil Construction of Site Services, Al Taweelah, Abu

Dhabi EMAL

2  24-1-2012  Target-Civil  Construction of New Training Centre  Borouge 3  01-02-2012  Target - Civil  Titenhurst Park Repairs  Private Department 4  01-02-2012  Target - Marine  Construction of Sea Arm for Export Jetty, RRE-7,

Ruwais  TAKREER/GS Engg 

5  01-02-2012 Target-Electrical Welding Workshop Power Distribution Board Replacement at ADCO Buhasa ADCO

6  01-03-2012 Target- Marine Construction of Centralized Industrial Area at Halul Island – Shoreline Protection Qatar Petroleum

7  01-03-2012 Target-Electrical Switching of Existing 11kV Network to 22kV MASDAR 8  01-04-2012  Target-Civil  Provision of Building Materials at Das Island  ADMA  9 

01-04-2012  Target-Civil Construction of Integrated Chiller, Freezer, Laundry, Dining and Accommodation Facilities in Halul. 

Qatar Petroleum 

10  01-07-2012 Target-Civil 100MBD Das Facilities Upgrade Project- EPC Works – Civil Construction Works ADMA/CCC

11  01-07-2012  Target- Marine  100MBD Das Facilities Upgrade Project- EPC Works – Marine Transportation  ADMA/CCC 

12 12-02-2012  Target-Electrical 

Installation, Connection and Commissioning of CWS P170A 6.6kV Motor Power Cable. Service Order No. 148360, dated 19/02/2012 (Misc.-ADMA) 

ADMA  

13 01-04-2012  Target-Electrical 

Installation of Fibre Optic Cables and Copper Cables for P-8364.for Installation of Fire Detection and Alarm System area B ZIRKU building 

ZADCO 

14  01-06-2012  Target Electrical  Relocation of Gas Detectors in NGL-1 and 2 LER, Gas Operations, Mesaieed  Qatar Petroleum 

15 11-06-2012  Target - Marine 

Shifting of T shped Marina from Villa 47 to 30 and Construction of U Shaped Marina for Villas 47 and 22 

ARABTEC CONSTRUCTION 

16  01-06-2012  Target Mechanical 

ADGAS OAG 1 Project - Mechanical and Electrical Works  ADGAS 

17 20-07-2012  Target Electrical  New Custody Transfer Metering Skid for

Shuweihat 3 Power Plant  GASCO 

* 17 projects totaling AED 830 Million 

6 Phases of a Construction Project: 1. Enthusiasm    4.  Search for the guilty 2. Disillusionment    5.  Punish of the innocent 3. Panic      6.  Praise and honor of the  

non‐participants 

Take a break…. 

  7 

5 tips to Staying Hydrated this Ramadan  

Thirst is a sign of dehydration. Whether or not this information comes as a surprise, the truth is, if you feel thirsty, you are already dehydrated. Basically that means that, in order to avoid dehydration, you need to avoid reaching the spot where you feel thirsty. Of course, during the long fasting days of Ramadan,  drinking  water  is  not  an  option.  Thirst  has  no  doubt  become  your  usual companion through these hot summer days of Ramadan. But there are a few little secrets and tricks that can help you avoid dehydration.                  Given  that  the  best  way  to  avoid  dehydration  is  by drinking enough fluids,  these secrets are not going to replace your need to drink water. They will, however, help you lessen your need for water between the last drink of sohour and that first sip at iftar.                                               Secret No. 1: Drink water.                   Prepare  for  your  day  of  fasting  by  drinking  enough water throughout the night. Keep a bottle of water close by during the evening, and try to drink a cup or two at least every  hour.  An  easy  way  to  remember  to  drink water  is  to  associate  it with  a  common,  daily  act.  Multiple health  websites  suggest  taking  a  drink  whenever  your  phone  rings.  We  suggest  drinking  water  when commercials come on during your  favorite TV show. Try to drink  three  liters of water a day, but  remember that  you  need  to  drink  more  water  when  you  have  sugary  drinks  (which  is  the  case  with  a  lot  of  typical Ramadan drinks) and caffeine.                           

Secret No. 2: Fashion matters.               Be careful when picking your daytime clothes during Ramadan. The color of your shirt, the fabric of your pants, and the layers of clothes all play an important role in keeping your body temperature as low as possible. If you work indoors, pick a light‐colored shirt; if most of your day is spent outside, a darker color will help protect you from the effects of  the sun. Black, however, is not advisable, as it  tends to attract  the heat and lock it close to your body. Some people believe that a cotton undershirt can help protect your body  from  the  sun. The truth  is,  an undershirt, especially with  the humidity in the UAE, can increase you risk of dehydration. The undershirt will absorb sweat, slowly becoming a wet, hot piece of cotton fabric that will increase your body 

temperature, especially if you are wearing an additional second layer of clothing. A loose cotton t‐shirt, which allows your sweat to evaporate, is a better idea.     

Secret No. 3: Cold showers.             Cold  showers help  in many ways  to rehydrate you during  the month of Ramadan. After couple of days of fasting, thirst becomes a normal feeling, so try to notice  other,  obvious  signs  of  dehydration:  cracked  lips,  flushed  skin,  fatigue, increased body temperature, and increased breathing and pulse rate, followed by dizziness, increased weakness, and labored breathing.       If you feel one or more of these symptoms, you should try to lower your body temperature in any way possible. Spend 5‐10 minutes with the base of your head under direct  cool water.  if  you  are  in an office, wet a  small  towel with  ice water and apply the towel to your forehead,  the area around your ears, the base of your neck, the upper back, and the chest.             

                              Secret No. 4: Plan your menu.        What  you  eat  plays  a  huge  part  in  dehydrating  or hydrating your body. Food that contains a lot of sugar (such as Ramadan sweets)  can  really  dehydrate  you,  while  fruit  is  perfect  for  providing extra water. So, instead of ending your iftar feast with piles of sweets, eat a couple of slices of watermelon or an orange. Green salads are another 

good source of extra water, so include them in your Ramadan diet.      

  8 

 

(continued…)                     Secret No. 5: Working out.             Because you  lose a  lot of water when you  sweat, working out  can undoubtedly cause  dehydration.  But  exercising  also  helps  your  body  dispose  of  toxins  and  other harmful  elements  that  might  cause  dehydration  later  on.  Pick  a  good  time  for exercise (two to three hours after iftar is advisable) and attend a cardio class, but try to counterbalance the amount of water lost by drinking water before you go to 

Something to think about… 

Me:  God, can I ask you a question?           God:  Sure.                 Me:  Promise you won't get mad.           God:  I promise.               Me:  Why did you let so much bad stuff happen to me today?     God:  What do you mean?             Me:  Well, I woke up late.             God:  Yes                  Me:  My car took forever to start.             God:  OK.                   Me:  At lunch they made my sandwich wrong, and I had to wait until someone else could get it right.   God:  Hmmm.                         Me:  On the way home, my phone went dead, just as I picked up a call.           God:  All right.                        Me:  And, on top of it all, when I got home I just wanted to soak my feet in my new foot massager and relax,     but it wouldn't work!!!  Nothing went right today! Why did you do that?           God:  Let me see, the Angel of Death was at your bedside this morning, and I had to send one of the other  angels to battle him for your life.  I let you sleep through that.           Me:  (humbled): OH ...                     GOD:  I didn't let your car start right away because there was a drunk driver on your route that would have  hit you if you were on the road at that moment.               Me:  (ashamed)                       God:  The first person who made your sandwich today was sick, and I didn't want you to catch what they  have, I knew you couldn't afford to miss work.             Me:  (embarrassed): OK …                 God:  Your phone went dead because the person that was calling was going to give false witness about what  you said on that call, I didn't even let you talk to them so you would be covered.       Me:  (softly) I see, God.                   God:  Oh, and that foot massager, it had an electrical short that was going to throw out all of the power in  your house tonight. I didn't think you wanted to be in the dark.           Me:  I'm sorry God.                     God:  Don't be sorry, just learn to trust me ... in all things, the good and the bad.       Me:  I will trust you.                   God:  And don't doubt that my plan for your day is always better than your plan.        Me:  I won't God.  And let me just tell you God, thank you for everything today.       God:  You're welcome child. It was just another day being your God, and I love looking after my children.