(Head of Partnerships)...BT’s Approach to Renewable Energy-The UK is committed to reducing its...
Transcript of (Head of Partnerships)...BT’s Approach to Renewable Energy-The UK is committed to reducing its...
1
BT Renewables
Leading by Example
Adastral Park
Friday 26th November 2010
Tom Martin
(Head of Partnerships)
BT’s Energy and Sustainability Record –
building on success...
• The company has reduced its carbon footprint by 59% in the UK from 1997 and targets 80% reduction worldwide by 2020.
• BT has a combination of environmental and energy reducing activities including:
– Recycling and cutting waste
– Car sharing schemes for employees
– Energy efficient BT building campaigns
– Implementing flexible working practices that reduce harmful energy impacts
– Identifying “environmental performance” as a key factor in „Green‟ procurement processes
– Purchasing low-carbon electricity
• BT has one of the largest low carbon energy contracts in the UK. Procuring 40% renewable electricity and 60% good quality CHP
3
BT’s Approach to Renewable Energy
-The UK is committed to reducing its fossil fuel consumption and increasing the amount of renewable energy it produces.
The UK Renewable Energy Strategy sets out the path for the UK to meet a legally-binding target to ensure 15% of its
energy (electricity, heat and transport) comes from renewable sources by 2020.
-BT is focused on:
-saving energy
-securing future supplies of renewable energy
-and reducing its exposure to rising energy prices
- playing a leading role in the transition to the low carbon economy
On Shore Wind Programme
In 2007 we announced plans to develop our own on - shore wind farms to produce around 25% (250 MW) of our current electricity needs from renewable sources by 2016.
The installed capacity is the equivalent to powering 143,250 homes or a city the size of Oxford
A wide range of wind sites are being progressed through the planning system
Our first major success has been to receive a „resolution to consent‟ for the Red Gap site – we are hopeful of receiving the formal planning certificate very soon!
4
Wind Farm Locations (in public domain)
5
Site Name No. Of
Turbines (typically 2.3 MW)
Location Status
Red Gap Farm 5 (11.5 MW) Hartlepool Resolution to
consent
Junction House 1 (2.3 MW) Durham Planning
application
submitted
Heysham 1 (2.3 MW) Lancaster Planning
application
submitted
Ilfracombe 3 (6.9 MW) North Devon Planning
application
submitted
Wingates (x2) 7 (9.2 MW) Northumberland Planning
application to
be submitted
shortly
Skeffling 5 (11.5 MW) East Riding Planning
application to
be submitted
shortly
Clare 6 (13.8 MW) Suffolk EIA in progress
• The site development
portfolio is very dynamic and
can change regularly
• Decisions have been made
not to pursue sites for different
reasons
• Sites can be in the planning
system for a long time before
„determination‟
• Early work has started on
new sites, though their
locations are not yet in public
domain
• Development budget has
critical bearing on what can be
achieved
6
The Planning and Environmental Impact
Assessment (EIA) Process
Stage 1: Preparation and submission of the Scoping
Report (site goes public!)
Stage 2: Pre-application consultations / baseline studies
Stage 3: Preparation and completion of Environmental
Impact Assessment
Stage 4: Preparation and completion of planning
application, comprising:
Environmental Statement
Planning Statement
Design and Access Statement
Transport Assessment
Statement of Community Involvement
Stage 5: Post-application consultations and scheme
amendments (as necessary)
7
Typical Planning and Environmental Issues for an EIA
• Planning Policy and Issues – the compliance of the proposal with the statutory and non-statutory policy
framework;
• Abnormal Load Routing – the delivery of the component parts of the WTGs and associated plant and equipment;
• Landscape and Visual Impact – the potential visual impact on the surrounding countryside;
• Ecology – the potential for the proposal to impact on species of flora and fauna that exist on site, as well as their wider habitats;
• Ground Conditions – the potential to disturb any contaminated soil on site, in the event that pollutants are identified;
• Archaeology and Built Heritage – the impact of the proposal on any cultural assets, including their setting within the vicinity of the site;
• Noise – the assessment of any potential noise impacts on local residents;
• ‘Shadow Flicker’ – a potential impact specific to wind turbines of the strobing effect of the light through the blades;
• Socio- Economic Impacts – the effect the proposal will have on the local economy and local communities
8
The Need for On Shore Wind Energy in East of England “No commercial scale wind turbines have been constructed in the region in
the past 6 months, or indeed in the whole of 2009, so the region still has 128MW of installed capacity (about 71 commercial scale turbines) generating electricity.”
Renewables East Annual Monitoring Report (January 2010)
• The specific need in the region was set out in a 2008 technical study „Placing
Renewables in the East of England‟, commissioned by EERA to establish the regional capacity for renewables.
• The Study recommended that (by 2010) onshore wind farm developments should
deliver some 647 MW of electricity.
• There is on this basis therefore, currently, a requirement for a substantial level of on-shore wind powered renewable energy development in the East of England.
9
The Proposed Site at Clare - Suffolk
• Located at Leys Farm, near Clare
• Currently comprises 66.9ha of mixed agricultural land
• 6 x 2.3 MW wind turbines – subject to a final design freeze
• A meteorological mast has been approved and has
Landscape Assessment is crucial for Clare
10
Proposed Grid Connection – a sensitive issue
11
•Grid connection routes
are often a very
sensitive issue to local
communities
• They also have
significant implications
on the commercial
viability of the
scheme(s) for BT
• Grid capacity in local
areas is another
significant issue
12
Consultee and stakeholder engagement
• Suffolk CC Highways
• Suffolk CC Ecologist
• Suffolk CC Landscape Officer
• Suffolk CC Archaeologist
• Neighbouring local authorities, specifically Essex County Council
• St Edmundsbury Borough Council
• Natural England
• English Heritage
• Environment Agency (EA)
• Anglian Water
• Royal Society for the Protection of Birds (RSPB)
• Suffolk Wildlife Trust
• Government Office for the East of England (GO-East)
• East of England Development Agency (EEDA)
• East of England Regional Assembly (EERA)
• Country Land and Business Association
• The Health and Safety Executive
• The Ministry of Defence (MoD)
• Campaign to Protect Rural England (CPRE)
• Joint Radio Company (JRC)
• Office of Communications (OFCOM)
• National Air Traffic Authorities (NATS)
• Civil Aviation Authority (CAA)
• Stansted Airport
• Norwich Airport
• Haverhill Chamber of Commerce
• Suffolk Chamber of Commerce
• Sudbury and District Ramblers Association
• Essex Gliding Club
• Clare Tourism Forum
• Friends of the Earth
• Stour Valley Action Group
• Clare Society
• Suffolk Preservation Society
• Local Parish Councils and residents
Consultees who have been approached or are proposed to be approached. This list is non exhaustive.
13
Abnormal Load Routing
Landscape and Visual Assessment
Project Coordination and Planning Policy
Ecology
Ground Conditions
Archaeology and Built Heritage
Noise
Shadow Flicker
Radar
Preparing Planning Applications - Specialist Support
Consultation
Wind Farm Site Screening and Constraints Mapping
14
•We have a rigorous screening
process before sites are introduced
into the portfolio
•Major constraints are mapped and
areas of opportunity are identified
15
Stakeholder Consultation – Our Approach
Publicity
– Adverts in local media
– Press and media interviews / press releases
– Letter to stakeholder group
– Resident and Business leaflet drop (5km of site)
– Website
• Listen, be open and factual
• Identify local Statement of
Community Involvement (SCI)
guidelines / good practice guides
(Renewables UK) / Good Practice
Guide to Public Engagement in
Development Schemes
• Meetings with LPA
• Identify stakeholders and potential
issues
• Develop the detailed consultation
approach
• Remain flexible
• Report back through a SCI
16
• Pre meeting with elected representatives / local interest groups / parish councils
• Display boards
• Photomontages / Wireframe modelling
• Maps
• Comment forms (capture names and addresses of those wishing to be kept informed)
• Children's activity
• Technical representatives from BT Wind for Change
Public Exhibitions – an important dialogue
• Very challenging at times; but varied
• Very broad set of questions and opinions
• Negative voices can dominate – but need to be listened to
• Planning Authorities expect high quality engagement with local communities
• The new Localism Bill in Parliament reinforces this
• BT does have a very good story to tell
• Broadband issues regularly feature
Working with Communities – BT being a good neighbour
. Community Benefit is a crucial part of our story to communities; what it is that we will put back into the area when a BT wind farm is built
One off „In Kind‟
support (£)
Annual Revenue
Fund (£ per MW)
Local Contracting
commitment
CSR related
initiatives
(inc. Education)
Wider BT
Opportunities
(inc. Broadband)
• Estimated 59MW of solar PV on BT estate, most
of which is roof mounted, on c. 400 properties
• Development process of projects and funding
strategy for build out very similar to wind projects
• Feed In Tariff provides £293 per MWh income,
degression of this from 1 April 2012
• Internal BT project management required to
coordinate relevant interests in buildings to allow
this project to succeed
• Very few planning issues and 3rd party consultee
barriers so considered highly deliverable
• ECU Strategy team completed a business plan
model demonstrating returns to BT by developing
solar PV on BT buildings
Erdington ATE,
Birmingham
Developing Solar Power for BT
Inverness TE
763 kWh/kWp
8.7% capacity
factor
Dial House,
Manchester
– 833
kWh/kWp
9.5%
capacity
factor
Faraday –
869
kWh/kWp
9.9%
capacity
factor
Goonhilly – 956
kWh/kWp
10.9% capacity
factor
Why Solar for BT – more detail
• Capacity factor is 8-11% in UK
• Installation Costs range from £2.3 - £2.8 million per MW.
Panels are ~60% of cost
• Annual Costs - 0.5% of capital cost (O&M), 3.5% of
capital cost (inc insurance, monitoring etc)
• Rules of Thumb - 8m² of Solar Panels for 1kWp, 25m² of
Flat Roof Space for 1kWp
• 59MW of solar PV on buildings will take 12-18 months to
install once all consents are in place on each site.
• Development programme needs to start now to ensure as
much as possible is installed prior to April 2012. Funding,
procurement and installation programme will run in parallel
with consenting programme
• 59MW solar PV will generate around 50,000MWh per
annum. At 20% energy cost reduction this equates to
savings of £470,000 per annum
• Feed in Tariff designed to give 8% ROI at various scales
of installation. Expert opinion is that 10% is achievable .
Solar Power at Adastral – Current Thinking
• Adastral Park is one of the principle sites being considered in the first phase of a solar PV programme on BT‟s estate
Proposed PV array sites
Car park B – 100% cover
Car park E – 100% cover and green car charging points
Car park G – 100% cover
Car Park U – 75% cover
Gemini B26 and B27 – 80% cover
Aquarius building B64 80% cover
Calisto House B81 – 80% cover
Columba House B83 – 80% Cover
Vega Building S1 – 100%cover
Ross Building S2 – 100% cover
Next Steps
• Detailed design of installations
• Start dialogue with Suffolk Coastal planning officers
• Prepare and submit planning application
BT Sprints – Energy Saving
• People across BT are now working on local sprint targets for a period of three
months with the aim of contributing to one of BT‟s three delivery priorities (customer
service delivery, cost transformation or future investments).
• Group CR, Group Property and the BT Energy & Carbon team are using the vehicle
of the 2012 sprints to engage with occupants of key BT buildings to reduce energy
consumption in those buildings.
• Sprint 3 (Sponsor: Liv Garfield) - people based in BT Centre were asked to take
action to reduce the energy consumption of the building by 10%. Overall a 17%
reduction in energy costs was achieved, saving BT £56k in the Sprint period.
• Sprint 4 (Sponsor: Mike Galvin) - 26 key buildings are taking part in Sprint 4 and the
ask is that they reduce energy consumption by 10%. If we reach the target we will
save over £420k in the three month period and reduce CO2 emissions by nearly
3000 tonnes.
How does the Sprint work?
Engagement
Managed by the LoB comms leads there is an engagement
campaign targeting the occupants of the sprint buildings to reduce
their energy consumption at work:
• Sprint 4 posters
• Energy campaign notice board
• Internal comms from sprint sponsors
• Formwise survey to measure engagement
• Building energy champions
• Competitions
Operational Delivery
Group Property and the Energy and Carbon team will work with
Monteray, Telereal Trillium, Vector and the BT Ireland Property
team to identify and deliver operational changes to the building to
reduce energy consumption.
Progress to date…..
Energy
move this
week
(£)
Energy
move to
date
(£)
Energy
move to
date
(%)
Forecast
out-turn
at current
run-rate
31/12/2010
(£)
ADASTRAL PARK -£137,125 -£666 -£4,252 -0.7% -£8,891
IPSWICH CC -£18,517 -£970 -£4,645 -5.4% -£9,712
ALEXANDER BAIN HOUSE -£11,888 £802 £5,199 10.6% £10,871
ALEXANDER GRAHAM BELL HOUSE -£8,143 -£582 -£4,210 -12.5% -£8,802
BAYNARD HOUSE -£47,799 -£172 £7,084 3.0% £14,812
BLACKBURN AMTE -£6,030 £656 £711 2.6% £1,487
CARDIFF STADIUM HSE -£30,255 -£1,769 -£11,206 -7.7% -£23,432
COLOMBO HOUSE -£30,825 -£911 -£5,861 -4.2% -£12,256
OSWESTRY WHITTINGTON HOUSE -£15,016 £300 -£1,224 -1.8% -£2,560
DONCASTER CALL CENTRE -£6,354 -£101 -£4,683 -16.4% -£9,792
NEWCASTLE CALL CENTRE -£5,298 -£58 £285 1.2% £596
WARRINGTON CALL CENTRE -£6,515 -£699 -£4,129 -16.1% -£8,634
SWANSEA CENTRAL ATE/TRS -£12,726 -£298 -£3,302 -5.6% -£6,905
WOLVERHAMPTON TELECOM HOUSE -£2,116 -£269 -£1,342 -20.9% -£2,806
FARADAY BUILDING -£14,792 £1,081 £6,678 9.6% £13,963
LANCASTER HOUSE ATE DXM -£19,088 -£269 -£1,342 -7.1% -£2,806
1 SOVEREIGN STREET -£10,404 -£467 -£5,652 -11.9% -£11,819
KELVIN HOUSE -£8,606 -£846 -£3,519 -8.9% -£7,357
BT CENTRE N/A -£802 -£5,160 -4.6% -£10,788
Total GB Sprint sites -£391,498 -£6,039 -£40,571 -2.4% -£84,831
BT Central TE -£20,455 -£854 -£2,875 -5.4% -£11,229
BT Riverside Tower -£8,044 -£1,219 -£5,006 -19.5% -£16,026
Carrickblacker Road -£5,997 £46 -£206 1.0% £603
Queens Quay -£3,501 -£45 -£227 -1.7% -£597
Mallusk GM7 -£1,382 -£83 -£644 -7.5% -£1,097
Enniskillen TE-GJF -£2,031 -£21 -£265 -1.4% -£278
Dundrum Blk -£6,902 -£253 -£1,795 -4.8% -£3,321
Grand Canal Plaza -£3,584 -£636 -£3,240 -23.1% -£8,359
Total Ireland Sprint sites -£51,895 -£3,067 -£14,259 -5.6% -£40,304
Peter Morris
Warren
Buckley
Ruth
Pickering
Andrew
Jones
Ralph
Steffens
Phil Dance
Building LOB
Sponsor
Sprint
Target
(£)
Year on Year Energy Savings
Adastral Park
Challenges facing the Sprint
• Engagement of resource to deliver the operational changes to achieve
savings
• Financing the saving opportunities
• Maintaining the momentum of employee engagement
• „Industrialisation‟ of the campaign for next phase
25
BT Renewables
Leading by Example
Thank you
Tom Martin
Head of Partnerships