HDPE Pipeline Installation and Design

download HDPE Pipeline Installation and Design

of 13

description

HDPE Pipeline Installation and Design

Transcript of HDPE Pipeline Installation and Design

  • Pipeline Technology Conference 2015

    1

    1. Introduction

    Most power plants require a circulating water system to transfer the waste heat

    generated by steam cycle into the ambient environment. Recently three kinds of pipe

    materials have been used widely; these are steel, GRE (Glass Reinforced Epoxy),

    and HDPE materials.

    HDPE pipe is selected for the Ras Djinet Combined Cycle Power Plant Project to

    intake sea water from the intake head located 1 km away shoreline. Ultra large size

    of 2500 mm diameter of HDPE pipeline was successfully installed by Daewoo

    Engineering & Construction Co., Ltd. through rigorous analysis with respect to design

    and installation. A bird's-eye view of the project is shown in Figure 1. This paper

    covers the design of HDPE pipeline and the procedures of its installation.

    Figure 1. A Birds-Eye View of the project

    2. Material and Design Consideration

    The seawater intake system of a power plant has the function of delivering cooling

    water to condenser and auxiliaries. The objective of the design process for pipeline of

    intake and outfall system is therefore to determine the size of pipeline which ensure

    flow rate which systems required. The intake system for the project is designed to

    intake seawater of 108,240 m3 per hour with HDPE pipeline and finally designed to

  • Pipeline Technology Conference 2015

    2

    162,360 m3 per hour considering safety factor of 1.5. The design velocity in the each

    pipeline is limited less than 2.5 m/sec and leads to the size of diameter 2500 mm with

    4 pipelines.

    2.1 Material Selection

    The HDPE pipeline adopted for the project has been increasingly used for various

    marine applications such as water intake, effluent outfalls, river and lake crossings,

    apart from oil and gas industries. There are various benefits of HDPE such as

    immunity to galvanic corrosion, light weight and flexibility, which have become

    excellent solution for water intake system in power plant.

    Table 1 and Table 2 present the key characteristics of the as designed HDPE pipeline

    and material properties, and Figure 2 presents its schematic configuration.

    Table 1. HDPE Pipeline Key Design Characteristics

    Description Intake Pipeline A Intake Pipeline B

    Type SDR30 SDR26

    Material HDPE HDPE

    Material Grade PE100 PE100

    Pipeline Outer Diameter mm 2500 2500

    Service Raw Sea Water Raw Sea Water

    Pressure Regime LP LP

    Wall Thickness mm 83.3 96.2

    Design Pressure bar(g) 5.5 6.4

    Design Temperature C 40 40

    Operating Temperature C 24 24

    Minimum Required Strength (MRS) MPa 10 10

    Table 2. High Density Polyethylene Properties for HDPE100

    Property Value Unit

    Density 960 kg/m3

    Tensile Yield Strength 23 MPa

    Elongation at Yield 8 %

  • Pipeline Technology Conference 2015

    3

    Tensile Break Strength 37 MPa

    Coefficient of Thermal Expansion 2.4x10-4

    m/m /C

    Poissons Ratio 0.4 -

    Minimum Required Strength at 20C (MRS) 10.0 MPa

    Hydrostatic Design Stress at 23C (HDS) 7.7 MPa

    Figure 2. Schematic of HDPE pipeline with concrete collar

    2.2 Design Issues

    After completion of pipeline sizing, the mechanical design is performed so that the

    pipeline could be protected from internal and external loads. General key design

    tasks performed in this project can be summarized as follows:

    1. Wall Thickness Design 2. On-Bottom Stability 3. Pipeline Free-Span Analysis 4. Concrete collar structural analysis 5. Sinking Analysis International codes and standards are applied to these design tasks such as DNV,

    DEP, AWWA, API and CEM (Coastal Engineering Manual). Each of these design

    activities for the pipeline is discussed in more detail in the following subsections of

    the paper.

    2.2.1 Wall thickness design

    The wall thickness of pipeline is core resistant factor to endure internal pressure and

    external loads. While this task involves various technical aspects related to different

    design cases, primary design loads relevant to the containment of the wall thickness

    Upper concrete collar

    Lower concrete collar

    2500 HDPE pipeline

    Anchor bolt

  • Pipeline Technology Conference 2015

    4

    for HDPE pipelines are as follows:

    Bursting criteria under internal pressure

    Pipe ring deflection under hydrostatic pressure

    Compressive stress under burial load and buckling criteria under installation

    load.

    The wall thickness of SDR 30 and 26 pipes is checked to be enough margins to the

    wall thickness calculated based on the pressure containment because water intake

    system does not require high internal pressure.

    To check the pipes reaction to external load, the pipe must be within its safe

    allowable limit for each of these three reactions deflection, buckling and ring

    compression. Ring deflection is a crucial response of flexible pipes to soil load. The

    modified Iowa Formula is used as specified in the AWWA Manual. For non-pressure

    applications, a 7.5 percent deflection limit provides a large safety factor against

    instability. The ring deflection in the pipe caused by the applied external pressure of 2

    m soil cover depth is 3.29 %, which is within the limit of recommended deflection

    7.5%. Compressive hoop wall stress was calculated to 2.70 MPa and is less than the

    allowable long-term compressive stress of 3.53 MPa.

    2.2.2 On-bottom stability

    HDPE pipeline resting on the seabed are significantly subjected to the forces in both

    the horizontal and vertical directions due to wave and current loads. If a pipeline is

    not stable then it will move under the actions of waves and currents. In the initial

    stages after finishing installation of HDPE pipeline before backfilling, the pipeline is

    exposed to the risk of these movements which may cause damage to pipeline.

    On-bottom stability was performed to keep the pipeline safely no movement based

    on DNV standards. The pipeline on-bottom stability analysis comprises of both lateral

    and vertical stability of the pipelines during their design life. The lateral stability

    analysis is carried out to determine the concrete ballast weight (i.e., concrete collars)

    required to make pipeline stable during installation and operation against the

    environmental loading caused by waves and currents. The vertical stability analysis is

    carried out to assess the floatation and/or settlement potential of the pipeline.

    The absolute lateral static stability method is a design wave approach, i.e. it

    ensures absolute static stability for a single design (extreme) wave-induced

    oscillation. Absolute lateral static stability approach is based on force equilibrium

    ensuring that the hydrodynamic loads are less than the soil resistance under a

    design extreme oscillatory cycle in the seastate considered for design.

  • Pipeline Technology Conference 2015

    5

    In order to keep the pipelines stable vertically, the submerged weight of the pipeline

    shall be enough large with the safety factor of 1.1 to avoid floatation refer to DNV.

    (ref). Settlement of the pipeline in the seabed should be then checked not to sink into

    the seabed, considering with maximum content density, e.g. water-filled. If the

    specific weight of the pipe is less than that of the soil (including water contents), no

    further analysis is required to document the safety against sinking.

    The concrete collar volume is designed to 6.7 m3 with 6 m span which is equivalent

    to 135 mm of concrete coating thickness all the way along the pipeline. From on-

    bottom stability analysis, the vertical stability both upward and downward meets the

    requirements and lateral stability also is above required safety factor as shown Table

    3.

    Table 3. On-bottom Stability Example Results

    Load Case Water Depth (m)

    Specific Gravity

    Lateral Stability (Vertical)

    Lateral Stability (Lateral)

    Collar Volume (m3)

    Installation 15 1.251 7.272 2.485 6.7

    Operation 15 1.251 14.247 4.528 6.7

    2.2.3 Free-span analysis

    Pipeline spans are caused by a variety of seabed features, the most common of

    which is an uneven seabed on the selected route. The route for HDPE pipeline was

    trenched and leveled before installation, but the concrete collars inevitably make

    spans between them. The allowable span lengths are calculated to maintain the

    pipelines within the allowable stress limit and to prevent the onset of vortex induced

    vibrations (VIV).

    The maximum span length based on static stress considerations are governed by

    self-weight of the pipe and coatings and the environmental loads. The allowable

    static span length for a pipeline is calculated by limiting the equivalent stress in the

    span to allowable bending stress based on the Von Mises equation incorporating the

    axial stress.

    The second mode of failure for spans is a fatigue failure due to vortex-induced

    vibrations (VIV). Vibrations may occur in the pipeline due to vortex shedding because

    of the flow of water passing a free span. Normally two types of oscillations are

    encountered:

    Oscillations in line with the velocity vector (in-line).

    Oscillations perpendicular to the velocity vector (cross flow).

  • Pipeline Technology Conference 2015

    6

    For certain flow velocities the vortex shedding frequency may coincide with or be a

    multiple of the harmonic or sub harmonic excitations. The span length will be

    selected such that the harmonic frequency or natural frequency of the span will be

    less than the vortex shedding frequency either for in-line or cross flow oscillations.

    The pipelines are designed such that no oscillation is allowed and to that effect, the

    maximum allowable span for the VIV criteria shall be less than that for the onset of

    in-line oscillation requirements. As in-line oscillations are not allowed, a fatigue

    analysis will not be required. The static and dynamic free spanning analysis is

    performed for installation condition because backfilling will be followed to installation.

    For conservative approach, fully restraint condition is considered. The summary of

    free span analysis for installation case is presented in Table 4.

    Table 4. Free Span Analysis Results

    Description Unit Design Condition

    Installation Hydrotest

    Max. Allowable Static Span Length m 10.42 10.42

    Max. Allowable Dynamic Span Length

    Inline flow VIV m 33.72 34.74

    Cross flow VIV m 34.66 35.68

    Governing Span Length m 10.42 10.42

    Recommended Allowable Span m 6 6

    2.2.5 Concrete collar Structure Analysis

    Previously explained, the concrete collar is attached on the pipeline with 6 m span by

    combining upper and lower parts of precast concrete collar.

    The standards of CBA 93 and BAEL 91 are applied for design concrete structures.

    The type of cement was determined to CPA with C3A to be contained less than 10 %

    considering full immersion conditions for seawater. The concrete is designed to 35

    MPa of the compressive concrete strength and 2.55 ton/m3 of dry density.

    To prohibit that the pipe is rotating when floating on the water surface, the bottom

    part of the collar should be heavier than the upper part. Accordingly, the concrete

    collar volume comprises 2.4 m3 in the upper part and 4.0 m3 in the lower part.

    The blocks are attached on the pipes with 4 bolts. Bolt forces are controlled by

    means of measuring the compression of the rubber compensators on each bolt. In

    order to secure that the block will not slide on the pipe during the submersion of the

    pipes a sliding test was performed. A minimum bolt force at the assembly of collars

    on the pipes is expected to be around 8 ton. But, based on 0.5 friction coefficient

    between rubber pad and HDPE pipe, considering more than 4 times safety factor for

  • Pipeline Technology Conference 2015

    7

    uncertainty during bolt tightening & sinking pipe and etc., a maximum bolt force at the

    assembly of blocks on the pipes is designed to be around 33.5 ton (335kN). As a

    result M33 size of bolt is used.

    The overall structure modeling and analysis are performed using Midas Civil, finite

    element analysis (FEA) software. From the concrete collar structural analysis, it could

    be learned that the most critical engineering parts are not concrete structure integrity

    such as bending moment, shear stress, and crack is not critical, but the bolts

    combining each parts of the collar and rubber part making the gap between the pipe

    and concrete. These parts are shown in the figure 3.

    Figure 3. Precast Concrete Collar

    2.2.6 Installation Analysis

    The HDPE pipeline installation method for this project adopted the float-and-sink

    method, so-called, Rentis installation. It has been used widely for near shore

    underwater pipeline installation. In traditional Rentis method, the required pipe string

    length is fabricated onshore and fitted with buoyancy devices at a given spacing,

    then is launched and finally towed to the desired offshore location. After positioning

    and aligning of the pipe string, the buoyancy devices are stripped in a control manner

    so that the pipeline settles to seabed due to its own weight in a controlled manner.

    The main difference between HDPE pipeline and traditional Rentis installation is that

    HDPE dont have to consider buoyancy devices because HDPE is buoyant itself.

    Critical issues are therefore to attach concrete collar to submerge pipeline and pump

    water into the pipeline to change it from positive buoyancy to negative. Accordingly

    pipeline settles on seabed due to its own weight including concrete collar in a

    controlled manner.

    The commercial software Orcaflex was used to perform the analysis of Rentis

  • Pipeline Technology Conference 2015

    8

    installation. Orcaflex developed by Orcina have been used widely for static and

    dynamic analysis of a wide range of offshore systems including all types of marine

    riser, floating facilities, moorings, installation and towed systems. Orcaflex is a fully

    3D non-linear time domain finite element program capable of dealing with arbitrarily

    large deflection of the flexibles from the initial configuration.

    The sinking analysis model consists of HDPE pipeline, concrete collar, buoyancy

    tank and winch as shown Figure 4. As Orcaflex is limited to simulate change of pipe

    content from empty to flooded condition, Pipeline was modeled as flooded status with

    seawater in the beginning but attached additional buoyancy tanks to compensate the

    initial flooded water weight inside the pipe. Analysis was then performed by removing

    the attached buoyancy tanks, which could simulate sinking of HDPE pipeline in the

    offshore site. The weather condition is assumed as Calm-day working.

    As a result of analyses minimum bending radius along pipeline length is larger than

    50m of the pipeline as shown in Figure 5. According to AWWA Manual (Ref), the

    minimum short-term bending radius shall be larger than 20 times pipe OD i.e., 50m

    for this project in a short-term period. Maximum von-Mises stress was calculated to

    21.2 MPa which is within the tensile yield strength of 23 MPa refer to Figure 6. These

    results are based on the tension from pulling boat with the magnitude of 70 ton.

    Figure 4. Simulation Progress with Time (a) Initial floating out

    (b) Sinking gradually by remove buoyancy tank

    (c) Sinking completion

  • Pipeline Technology Conference 2015

    9

    Figure 5. Maximum/Mean/Minimum Curvature along Offshore Intake Pipeline Length

    Figure 6. Maximum/Mean/Minimum von Mises Stress along Offshore Intake Pipeline Length

  • Pipeline Technology Conference 2015

    10

    3. Construction and Installation

    3.1 Manufacturing of 2500mm OD of HDPE & Accessories

    The manufacture and production of long module 2500m OD HDPE pipe and

    accessories required for the project were carried out by PipelifeNorge The pipes are

    produced in Norway where fabrication yard is located and then delivered to Algeria.

    3.2 Towing of pipe from factory, receiving and storage

    The pipelines are towed to the port near the site in Algeria under responsibility of

    Pipelife. The towing plan was prepared to ensure that pipes to be towed are free from

    damages and not exposed to extreme hazards during transport. To increase visibility

    of the cargo, a standard yellow color is painted every 5 meters on the HDPE pipe and

    blinking light at the end of the tow is attached as shown in Figure 7. Tug boat usually

    travels with the speed under 7~8 knots and a 1 knot per minute acceleration would

    be permitted for increasing the speed.

    Figure 7. Towing of HDPE Pipeline (PIPELIFE)

    When long module HDPE pipes approach to the port, the harbor authority grants

    permission to proceed. The harbor tug holds the pipes and the assisting vessels

    position and secure them.

    3.4 Installation of concrete weights

    The concrete weight production was carried out in parallel with the delivery of HDPE

    pipe by pre-cast method. The upper collar and the lower collar were fixed to the

    HDPE pipe by using a lift frame. The lifting frame will then be loaded with a set of the

  • Pipeline Technology Conference 2015

    11

    collar weight, the upper and the lower section, and then it is carefully lowered to the

    marked area on the HDPE where the collar weights will be put in place. The upper

    collar will then be slowly lowered to connect the two sections by hot dip galvanized

    bolts and nuts. This procedure is repeated until installation of all collar weights is

    completed. Figure 8 shows the installation of concrete collar performed in the site. .

    Figure 8. Setting of Collar using Lift frame

    3.5 Sinking process of weighted HDPE pipe

    After installation of concrete collar with other required accessories to the long module

    pipe, it was towed from the port to the site. The most important thing is to know the

    local weather condition because sea condition must be calm to sink the HDPE

    pipeline.

    The pipeline to be sunk is positioned in the designated route by the use of tug boats,

    barges and small boats. The inmost end is connected to the flange, and there must

    be an entry pipe so that seawater can be allowed to enter during sinking. The

    outmost end is fitted with a hose connected to the compressor to serve controlling air

    pressure inside the pipe if required.

    To be ready to sink, the location of the pipe route should be pre-determined and

    marked by buoys using GPS equipment. The first end to be sunk is the inmost part

    and it is anchored to concrete anchors by the use of a wire to the end flange of the

    pipe. This is to ensure inmost end of the pipe string settles to a suitable distance from

    the end of the onshore distance.

    The flooding of the pipe start by opening one of the valves for inflow of water, and as

  • Pipeline Technology Conference 2015

    12

    the water flows into the pipe, the inshore end become sink down to rest on the

    seabed. Initial stage of the sinking shows an inverse J-figure and continuous inflow of

    water inside of the pipe leads gradually to the shape of S-bend configuration. The

    configuration of the pipeline is controlled to maintain curvature above 60 OD using

    the valve and pulling force. It is very important that pull on the offshore is maintained

    to prevent the sudden significant increase of curvature to the pipe. Maintaining the

    pull force applied at the offshore end will control the buckling failure to the pipe.

    When the air in the pipe are fully evacuated, and the offshore end of the pipe is fully

    submerged, the pulling force applied is gradually reduced until the offshore end of

    pipe reaches the seabed, and the installation of the pipe could be said to be

    successful. The configuration during sinking of the HDPE pipeline and process are

    shown in Figure 9 and Figure 10.

    Figure 9. S-shape Configuration of HDPE Pipeline

    Figure 10. Initial Sinking

  • Pipeline Technology Conference 2015

    13

    3.6 Spool piecing and connection works

    To connect the two pipe strings which are inshore and offshore section respectively,

    the pipe spools are required. The length is measured before as per the actual

    distance between the ends of the pipe to be spool pieced. There must be a clearance

    for the spool piece in between flanges but not wide, the gap shall be minimized in

    order to prevent excessive longitudinal strain to the pipe in the flanging operation

    when bolts are tighten.

    Sinking of spool piece to join submerged pipe carried by the use of barge with crane.

    The bolts were completely tightened by pneumatic type under water.

    4. Conclusion

    There are many advantages to use HDPE pipeline for seawater intake and outfall in

    power plant projects. Continuous manufacture of long module has the pipeline more

    integrity by reducing the welding joint in the site and contributes saving time requiring

    installation.

    The engineers should make a careful assessment in design and installation for

    HDPE to be installed with no harm and keep safe during its operation. In terms of

    design large diameter HDPE pipeline might adopt traditional offshore pipeline

    engineering procedures. But on-bottom stability analysis is to be performed most

    critically when assessing the pipeline movement underwater. For rigorous approach

    the projected area of submerged concrete collar should be considered in calculating

    the force caused by currents and waves. These forces are not much small to be

    neglected. The connection between lower and upper part of concrete collar is also be

    stringently checked because of possibility to breaking and loosening of bolts in the

    harsh condition. Daewoo Engineering & Construction Ltd., have been conducting

    research about optimizing concrete collar and miscellaneous parts.

    In addition to design, the installation of HDPE pipeline should be analyzed and

    investigated previously before start up the sinking so that it could be controlled

    delicately. The results of simulation could provide information such as what tension

    would be required to hold the pipeline to keep the S-shape and to avoid buckling.

    These meticulous engineering analyses and controlling performed in the site lead the

    pipeline to be finally said installed successfully.