HD target. outline HD target overview TC leak test by He detector purify HD SC ( Storage Cryostat...
-
Upload
jesse-obrien -
Category
Documents
-
view
216 -
download
1
Transcript of HD target. outline HD target overview TC leak test by He detector purify HD SC ( Storage Cryostat...
HD target
outline
• HD target overview• TC leak test by He detector• purify HD• SC( Storage Cryostat )
– cooling system test– superconducting magnet test
HD target overview
Characteristics of polarized HD targetPolarization MethodHD target is polarized by the static method using “brute force” at low temperature (10 mK) and high magnetic field (17 T). It takes about 2-3 months to polarize the target.
Advantage and disadvantageHD molecule does not contain heavy nuclei such as Carbon and Nitrogen. Good for experiments observing reactions with small cross sectionThe HD target needs thin aluminum wires (at most 20% in weight) to insure the cooling.
Polarization H : 90 % D : 60 %
Relaxation Time30 days at 200 mK and 1 T during the experiment.
Target Size25 mm in diameter 50 mm in thickness
HD target transportationRCNP Osaka university
From RCNP to SPring-8
BL33LEP SPring-8
K+
K-
In Beam Cryostat
Transfer Cryostat 1
Transfer Cryostat 2Experiment
HD Target
Dilution Refrigerator
StorageCryostat
Dilution refrigeratorLeiden Cryogenics
DRS-3000 (He3-He4)
Cooling power
3000μW at 120 mK
Lowest temperature
6 mK
Magnetic Field
17 T
Homogeneity of Magnetic Field
5×10-4 for 15 cm
Two Transfer Cryostats
Right : used at RCNPLeft : used at SPring-8
SC( Storage Cryostat )
LN2 bath
LHe bath
main bath
outer vacuum chamber (OVC)
target
superconducting magnet
Al wire
2.5cm
IBC ( In Beam Cryostat ) for BL33LEP
TC leak test by He detector
He detector
Step0: turn to “0”, then wait until “P” saturate
closed
3
0
1
2
4
5OPEN
P
D
outside
Step1: turn to “1”, then wait until “P” zero
closed
3
0
1
2
4
5OPEN
P
D
outside
Step2: turn to “2”, then wait until green LED light
closed
3
0
1
2
4
5OPEN
P
D
outside
Step3: open “3”
opening
3
0
1
2
4
5OPEN
P
D
outside
Step4: turn “to 4”,if “P” increase now, the pipe is broken
then wait until “D” zero
opened
3
0
1
2
4
5OPEN
P
D
outside
Step5: turn on “5”,adjust the unit of concentrationstart measurement (see “D”)
opened
3
0
1
2
4
5OPEN
P
D
outside
purify HD
purify HD
Distillator
topD2 solid, H2 gas, HD liquid
middleD2 solid, H2 gas, HD gas
bottomD2 solid, H2 gas, HD gas
HD~ 96%
D2~ 2%
H2~ 2%
H2~ 50%
HD~ 50%
2 week
H2
H2~ 4~6%
HD~95%
2 week
HD~ 99.999%
principle of concentration sensor
• use filament to ionize gas
ionize gas here
H2+
D2+
HD+
sensor
digital data
AMP(amplifier)
In amplifier, use different gain for each gasPC
SC( Storage Cryostat )
cooling system test
SC( Storage Cryostat )
LN2 bath
LHe bath
main bath
outer vacuum chamber (OVC)
target
superconducting magnet
four thermometers in SC
Step 1
1. Evacuate the OVC for at least 24 hour before pre-cool system
For pre-cool LHe bath,we fill LN2 to LHe bath.
• The Allen Bradly carbon resistance sensor in liquid helium bath reached 388.81 ohm. It is close to 77 K
Transfer the LN2 from LHe bath to LN2 bath.we fill LHe to LHe bath.
• The level of liquid nitrogen rose from 9.2% to 80%.
• The Allen Bradly carbon resistance sensor in liquid helium bath reached 2691 ohm (around 6~7 K)
Transfer the LN2 from LHe bath to LN2 bath.we fill LHe to LHe bath.
• We start pumping gas from main bath. The Allen Bradly carbon resistance sensor in liquid helium bath reached 4033 ohm (around 4~5 K) ,the temperature in bottom of main bath reached 3.096 K, the temperature in top of main bath reached 4.025 K. Temperature cannot drop more. The level of helium gas drop down. We find the helium tank empty.
pumping the main bath
• We remove the helium gas from main bath. • The temperature in top of main bath rose from 3.441 K to 73.95 K. • The temperature in bottom of main bath drop down from 2.983 K to 1.509 K .• The temperature keep around 1.53 K.
Test of SC cooling system is finished.
SC( Storage Cryostat )
superconducting magnet test
Hall probe magnet sensor
1. Electrons (not Conventional current!) 2. Hall element, or Hall sensor3. Magnets 4. Magnetic field 5. Power source
We installed a Hall probe into main bath in SC.
superconducting magnet1. Zero the current. 2. Increase current, reach to middle current we set before ,then reach to max current we set b
efore (Heater on)3. Turn off Heater when reach the magnetic field intensity we need.4. Decrease the current to middle current we set before, then zero the current.5. Keep the persistent mode when we use superconducting magnet.6. Increase current, reach to middle current we set before ,then reach to max current we set b
efore (Heater off)7. Heater on (Quenches) (dangerous!!)8. Decrease the current to middle current we set before, then zero the current.9. turn off the heater. turn off the power supply. superconducting magnet test finish.
before we start test
• make the following electrical checks– magnet resistance– magnet to cryostat isolation– switch heater resistance– switch heater to cryostat isolation– magnet to switch heater isolation – (isolation values should typically be >1 MΩ unless oth
erwise stated)
• open all of doors in experiment building.• take off everything with magnetic.
Typical calibration curve of Hall probe
The magnetic field of about 1 Tesla was
confirmed by using a Hall probe.
Heater on15:38
Heater off15:53
Heater on16:21
persistent mode28Mins
Amps
mV
Heater on16:30
Bonus
Physics objectives1 To investigate the ss content in the nucleon by the p -> p (n -> n) reaction To know the structure of the proton and neutron correctly is the
fundamental desire.
2 To determine the spin-parity of + particle Although I do not follow recent theoretical studies, to fix the initial
nucleon spin and photon polarization must be important.
3 To study the reaction mechanism of the hyperon photoproduction
Recently some interesting results measuring the double polarization
observables appeared. Advanced studies need the polarized nucleon target.
concentration
sensor
pressure controller
pressuremonitorDistillator
top
middlebottom
throw gas out
concentration measurement
A
B
C
D
E
F
G
H I
1. open A, get gas for top of Distillator. J
2. close D, open B, then close B, now gas in C. 3. open D, then close D, now gas from C to E
4. control pressure by F, see J the pressure should be 9.0x10-7 mbar
6. close the software RGA
gas here
gas here
gas here
gas here
0. A ,B should closed, open D and G, measure background.
5. measure gas concentration by RGA (Residual gas Analyzer)
7. open G, then close G throw the gas away
gas outside
gas here