HCL Project

129
PROJECT REPORT “A STUDY ON PERFORMANCE MANAGEMENT” At HCL INFOSYSTEMS LTD. NOIDA Submitted towards partial fulfillment of the Requirements for the award of the PGDM Programme 2009-2010 Approved by AICTE (Equivalent to MBA) ACADEMIC SESSION 2009 - 2010 Submitted to :- Submitted by:- 1

Transcript of HCL Project

Page 1: HCL Project

PROJECT REPORT

“A STUDY ON PERFORMANCE MANAGEMENT”At

HCL INFOSYSTEMS LTD.NOIDA

Submitted towards partial fulfillment of the

Requirements for the award of the

PGDM Programme 2009-2010

Approved by AICTE

(Equivalent to MBA)

ACADEMIC SESSION 2009 - 2010

Submitted to :- Submitted by:-

Prof. Shweta Mittal Akansha Jaiswal 09022HR Department Neha Singh IMS Ghaziabad Prerna Paul

Priyanka pathak Ragiv Jalan

Rupal Azmani Vikas Darbari

IMS GHAZIABAD

LALKUAN

1

Page 2: HCL Project

Contents

1. Introduction

1.1. HCL an overview

1.2. HCL DNA

1.3. Employer spotlight:

1.4. About HCL

1.5. Strong SAP Capabilities

1.6. Vision statement

1.7. Mission Statement

1.8. Quality Policy

1.9. Objective

1.10. Core Values

1.11. A Snapshot Of HCL

Infosystems Ltd.

2. Literature Review - PMS

2.1. An Introduction of

Performance Management

2.2. Levels of performance

management

2.3. Value for money

2.4. Measures and metrics

2.5. Processes

2.6. Objectives of a Performance

Management System

2.7. Overall Goal and Focuses of

Performance Management

2.8. Perfor

mance

Improv

ement

of the

Organi

zation

or a

Subsyst

em is

an

Integrat

ed

Process

2.9. Ongoin

g

Activiti

es of

Perfor

mance

Manag

ement

7

7

12

13

15

2

Page 3: HCL Project

16

16

16

16

17

17

17

20

22

23

24

25

29

30

30

30

2.10. Basic Steps

2.11.Project Performance

Management

2.12. Managing Performance

Effectively

2.13. Feature of good PMS

3. Project

3.1. Objective of the project –

Introduction of the

proble

m

3.2. Signific

ance of

the

Project

3.3. Definiti

on - A

Theoret

ical

Perspec

tive

3.4. Prepara

tion

and

Plannin

g for

perfor

mance

manage

ment

3.5. Perfor

mance

Manag

ement

and

Develo

pment

3.6. Perfor

mance

Assess

ment

3

Page 4: HCL Project

and Development Plan In

HCL INFOSYSTEMS LTD

4. Research Methodology

4.1 Research Design

4.2 Data Collection Method

4.3 Analysis of PMS

5. Recommendation

6. Conclusion

7. Bibliography

8. Appendix

31

33

37

37

44

44

45

47

47

48.

51

52

53

60

61

62

63

31

31

31

32

32

4

Page 5: HCL Project

31

31

31

32

32

36

36

36

37

37

56

57

5

Page 6: HCL Project

58 5

9

Acknowledgment

The project of this nature is arduous task stretching over a

period of time, completing a project like this one takes the

effort and cooperation of many people.

Although this project report is being brought in my name, it

bears an imprint of guidance and cooperation of many

individuals. Several persons with whom I integrated have

contributed significantly to the successful completion of the

project study. In the successful & trouble free completion of

my final term project titled “PERFORMANCE

MANAGEMENT”, I am graceful to Institute of Management

and Technology, Ghaziabad for helping us towards the

completion of the project.

I extend my deepest and sincere thanks to my project guide,

Mr. Ram Krishn and other HR Executives HCL Infosystems

Ltd. for the unflinching support and guidance through out the

project

I would also like to thank all the executives who shared their

precious time and experience with me.

Last but not the least, I extend my sincere thanks to all the

staff members of HCL Infosystems Ltd. for their cooperation.

6

Page 7: HCL Project

Executive summary

Performance management is the process of bringing people in

to the organization making very sure that new entrants have

the potential and willingness to contribute to organizational

success. In today’s scenario without effective performance

management the organization will meet the considerable

resistance when introducing change. Without organizational

change and development survival become very uncertain so in

order to make the industry survive it is very important to

adopt the different performance management practices in all

organizations so as to understand the employees or workers

need and satisfy them. There should be effective people

utilization in every industry. All these practices in an

organization will make the organization to grow at a faster

speed. The study will be empirical and primary research will

be done by using the questionnaire which will administer to

sales, service and support function employee. The date will be

collected and assimilated by using statistical tool like median

and date will be analyzed by using Bar Chart. The analysis

will be to find the effectiveness of current PMS.

7

Page 8: HCL Project

1. INTRODUCTION

1.1. HCL an overview

Born in 1976, HCL has a 3-decade rich history of inventions

and innovations. In 1978, HCL developed the first indigenous

microcomputer at the same time as Apple and 3 years before

IBM's PC. During this period, India was a black box to the

world and the world was a black box to India. This

microcomputer virtually gave birth to the Indian computer

industry. The 80's saw HCL developing know-how in many

other technologies. HCL's in-depth knowledge of Unix led to

the development of a fine grained multi-processor Unix in

1988, three years ahead of Sun and HP.

HCL's R&D was spun off as HCL Technologies in 1997 to

mark their advent into the software services arena. During the

last eight years, HCL has strengthened its processes and

applied its know-how, developed over 30 years into multiple

practices - semi-conductor, operating systems, automobile,

avionics, bio-medical engine HCL's R&D was spun off as

8

Page 9: HCL Project

HCL Technologies in 1997 to mark their advent into the

software services arena. During the last eight years, HCL has

strengthened its processes and applied its know-how,

developed over 30 years into multiple practices - semi-

conductor, operating systems, automobile, avionics, bio-

medical engineering, wireless, telecom technologies, and

many more.

Today, HCL sells more PCs in India than any other brand,

runs Northern Ireland's largest BPO operation, and manages

the network for Asia's largest stock exchange network apart

from designing zero visibility landing systems to land the

world's most popular airplane.

.

9

Page 10: HCL Project

1976 Hindustan Computers Limited (HCL) born.

1977 Distribution alliance formed with Toshiba for copiers.

1978 HCL successfully ships in-house designed

microcomputer at the same time as Apple. The Indian

computer industry is born.

1980 HCL introduces bit sliced, 16-bit processor based

microcomputer.

1983 Indigenously develops an RDBMS, a Networking OS

a Client Server architecture, at the same   time as global IT

peers.

1986 HCL becomes the largest IT company in India.

 

1988 HCL introduces fine-grained multi-processor Unix-3

years ahead of “Sun” and “HP”.

 

1990 Data Quest marks HCL No.1 amongst top ten

computer giants.

 

1991 HCL Ltd. and Hewlett Packard, USA, partner to form

HCL-Hewlett Packard Ltd.

JV develops multi-processor Unix for HP-heralds HCL’s

entry into contract

1994 Distribution alliances formed with Ericsson Switches

and Nokia Cell phones.

10

Page 11: HCL Project

1997 HCL Info systems are formed. HCL's R&D spun-off

as HCL Technologies- marks advent into software services.

JV with Perot Systems, stake divested in 2003.

1999 Initial Public Offering made by HCL Technologies

Ltd.Formation of Global Board of Directors.

 

2000 Large contracts won from Bankers Trust, KLA Tenor,

Cisco, GTech, NEC among others.

 

2001 JV with Deutsche Bank- DSL software formed. HCL

BPO Incorporated. Acquired British Telecom Apollo’s

contact center in Belfast, Northern Ireland. HCL Info systems

become largest hardware company.

 

2002 Strong pursuit of nonlinear strategy to widen services

portfolio; several JVs and alliances formed. Strategic alliance

forged with Jones Apparel Group, Inc. a fortune 500

company. Infrastructure services division launched to address

emerging global needs.

Software businesses of HCL Info systems and HCL

Technologies merged.

2003 Largest BPO order ever outsourced to an Indian BPO

firm, won from British Telecom. Landmark deals signed with

Airbus and AMD. HCL manpower crosses the 20,000 mark..

 

2004 Accorded leader status by Meta Group in Offshore

Outsourcing. HCL is India’s No.1 PC 4th year in a row.

2005

11

Page 12: HCL Project

HCL signs Software Development Agreement with

Boeing for the 787 Dream liner program.

JV with NEC, Japan

HCL sets up first Power PC architecture design center

outside of IBM.

Completes buy-out of JVs with Deutsche Bank and

British Telecom Apollo Contact Center.

HCL integrates all group employees under HCL in

domain.

Sets up a dedicated Offshore Design Center for

leading Tier-1 Aerospace supplier, Hamilton

Sundstrand.

HCL Info systems launches sub Rs.10, 000 PC. Joins

hands with AMD, Microsoft to bridge the digital

divide.

2006

75,000+ machines produced in a single month.

HCL Info systems in partnership with Toshiba expand

its retail presence in India by unveiling   'shop

Toshiba'.

HCL Info systems & Nokia announce a long-term

distribution strategy.

HCL the leader in Desktops PCs unveils India's first

segment specific range of notebooks brand -   'HCL

Laptops'.

HCL Info systems showcase Computer Solutions for

the Rural Markets in India.

12

Page 13: HCL Project

HCL Support wins the DQ Channels-2006 GOLD

Award for Best After Sales Service on a   nationwide

customer satisfaction survey conducted by IDC.

HCL AND ZEE - Dish TV team up to take DTH TV

to its next level of growth in India

HCL Info systems First in India to Launch the New

Generation of High Performance Server   Platforms

Powered by Intel Dual - Core Xenon 5000 Processor.

HCL Forms a Strategic Partnership with APPLE to

provide Sales & Service Support for iPods in   India.

HCL is one of the leading global Technology and IT

enterprises with annual revenues of US$ 4 billion. The HCL

Enterprise comprises two companies listed in India, HCL

Technologies (http://www.hcltech.com/) and HCL Info systems

(http://www.hclinfosystems.in/)

The 30 year old enterprise, founded in 1976, is one of India's

original IT garage start ups. Its range of offerings span R&D

and Technology Services, Enterprise and Applications

Consulting, Remote Infrastructure Management, BPO

services, IT Hardware, Systems Integration and Distribution

of Technology and Telecom products in India. The HCL team

comprises 45,000 professionals of diverse nationalities,

operating across 17 countries including 360 points of presence

in India. HCL has global partnerships with several leading

Fortune 1000 firms, including several IT and Technology

major.

13

Page 14: HCL Project

1.2. HCL DNA:

Fueled by the entrepreneurial zeal of its founders, HCL

developed the first indigenous microcomputer in 1978, at the

same time as Apple. Since then, HCL has had a 3-decade rich

history of inventions and innovations. Entrepreneur is the

term that best describes the HCL employees. The TIME

magazine has referred to HCL as an "intellectual clean room

where its employees could imagine endless possibilities."

Ever since HCL entered into an alliance in 1970s,

partnerships and HCL have been inseparable. Bonds have

14

Page 15: HCL Project

been forged with partners to co-create value. Strong inorganic

growth is a testimony to the spirit of partnerships.

This entrepreneurial and win-win relationship driven culture

continues to guide HCL in all its endeavors.

1.3. Employer spotlight:

HCL is one of India’s leading global IT Services companies,

providing software-led IT solutions, remote infrastructure

management services and BPO. Having made a foray into the

global IT landscape in 1999 after its IPO, focuses on

Transformational Outsourcing, working with clients in areas

that impact and re-define the core of their business. The

company leverages an extensive global offshore infrastructure

15

Page 16: HCL Project

and its global network of offices in 16 countries to deliver

solutions across select verticals including Financial Services,

Retail & Consumer, Life Sciences Aerospace, Automotive,

Semiconductors, Telecom and MPE (Media Publishing &

Entertainment)

HCL in India:HCL has evolved from a dream of eight youngsters in 1977 to

the country's top IT group today. Our well-balanced portfolio

of turnkey solutions across equipments, software and services

make our offerings end-to-end for all IT needs of the Indian

customers. Our recognitions speak of our dominant position

in India. V&D100 2005, No. 1 Security service provider in

India by DQ Annual 2004, No.1 Infra service provider by

CMP 2005, and No.1 PC Brand recognize us as No.1

Network Management service provider in India for the last 5

years in India.

HCL is known to be the harbinger of technology in the

country. Our partnerships with technology leaders like JDA,

Oracle, SAP, KANA, Intel, Microsoft go back to the time

when India was being recognized as a growing and strategic

market. Along with global capability, HCL has leveraged

such relationships to create value for Indian customers - the

comprehensive integrated market surveillance solution for

SEBI being one such example.

16

Page 17: HCL Project

Our services are backed by an extensive direct support

infrastructure spread across 170 locations nationwide, which

offer 24-x7 support offering for critical sites. With more than

70 SAP implementations till date, HCL has been rendering

service to key Indian players in Banking, Retail and

Government.

We are committed to the Indian Market and will continue to

invest more to further enrich our end-to end IT offerings for

this market. Our flexible engagement models, rich heritage of

technology solutions and over 29 years of leadership across

service areas give us a strategic advantage to meet the nation's

IT needs.

1.4. About HCL

HCL Enterprise is a leading Global Technology and IT

enterprise that comprises two companies listed in India - HCL

Technologies & HCL Info systems. The 3-decade-old

enterprise, founded in 1976, is one of India’s original IT

garage start-ups. Its range of offerings span Product

Engineering, Technology and Application Services, BPO,

Infrastructure Services, IT Hardware, Systems Integration,

and distribution of ICT products. The HCL team comprises

approximately 42,000 professionals of diverse nationalities,

who operate from 16 countries including 300 points of

presence in India. HCL has global partnerships with several

leading Fortune 1000 firms, including leading IT and

Technology firms. HCL Technologies is one of India’s

17

Page 18: HCL Project

leading global IT Services companies, providing software-led

IT solutions, remote infrastructure management services and

BPO. Having made a foray into the global IT landscape in

1999 after its IPO, HCL Technologies focuses on

Transformational Outsourcing, working with clients in areas

that impact and re-define the core of their business. The

company leverages an extensive global offshore infrastructure

and its global network of offices in 16 countries to deliver

solutions across select verticals including Financial Services,

Retail & Consumer, Life Sciences Aerospace, Automotive,

Semiconductors, Telecom and MPE (Media Publishing &

Entertainment). For the quarter ending 31st December 2006,

HCL Technologies, along with its subsidiaries had revenue

(TTM) of US $ 1.155 billion (Rs.

5220 crore) and employed 38,317 professionals.

1.5. Strong SAP Capabilities: 

HCL Technologies is one of the largest global SAP service

providers in India, providing a spectrum of SAP services.

HCL Technologies has developed strong capabilities on the

SAP Net Weaver platform and drives market demand in the

SAP world through unique market propositions and upgrade

offerings to my SAP ERP. HCL is a value added reseller and

services partner across multiple geographies. With a track

18

Page 19: HCL Project

record of successful engagement in this space, HCL has

received prestigious awards from SAP - distinguished partner

award 2005, best my SAP HCM implementation award 2005,

Sap’s "outstanding partner” award for

implementation/upgrade project 2004, and more. Forrester has

lauded HCL Technologies is one of a number of firms in this

space and is a viable candidate for multinational firms that are

contemplating global outsourcing and are interested in SAP

implementation and maintenance services.

1.6. VISION STATEMENT

Together we create enterprises of tomorrow.

1.7. MISSION STATEMENT

To provide world class information technology solution

and services to enable our customers to serve their customer

better’.

1.8. QUALITY POLICY STATEMENT

“We will deliver defect-free products, service and

solutions to meet the requirements of our external and internal

customers the fist time, every time.’

1.9. OUR OBJECTIVE

19

Page 20: HCL Project

OUR MANAGEMENT OBJECTIVE

To fuel initiative and foster active by allowing individuals

freedom of action and innovation in attaining defined

objectives.

OUR PEOPLE OBJECTIVE

To help HCL Infosystem people share in the company’s

success, which they make possible to provide job security

based on their performance; to recognize their individual

achievements and to help them gain a sense of satisfaction

and accomplishment from their work.

1.10. CORE VALUES

We shall uphold the dignity of individual

We shall honor all commitments.

We shall be committed to Quality. Innovation and growth

in every endeavor.

We shall be responsible Corporate Citizens.

20

Page 21: HCL Project

1.11. A SNAPSHOT OF HCL Infosystems Ltd.

India’s leading IT company

HCL In say is India’s largest information technology (IT),

transnational conglomerate. With its-depth expertise in

developing solution spanning diverse technologies.

HCL Insys aims to propel its course on to the high growth

Path total Technology Integration. Towards capturing two

Ends of market spectrum - enterprise solution and PCs.

HCL Insys has made significant strategic infrastructure

investments in the professional services Organization (PSO),

the Support Services Organization (SSO) and its

manufacturing plant at Pondicherry. Thus it is the

manufacturer of general purpose computer and provides

services in the areas of IT Consultancy, system integration,

Software Development and Training.

It makes true technology integration possible across

multiple platforms, this was possible because of the in-depth

expertise in developing state-of-the-art indigenous hardware

solution; thorough understanding of networking technology.

As a part of this plan to market more and more technology

integration services world-wide, HCL in sys has already taken

a step in the direction of export by localizing its service

comprising software, hardware design and development,

value added support service networking abs repair services

and overseas integration projects to meet the demands of the

global clients.

21

Page 22: HCL Project

Company’s continuous and consistent anticipation of the

requirement of the IT Industry has led it to undertake the

acquisition of the business of HCL Info solutions limited

(now known as Frontline Division), HCL Peripherals Limited

(now known the acquisition of Customer Support

Organization (CSO) activities of HCL Office Automation

Limited (now know as office Automation Division)

FRONTLINE DIVISION

Frontline Division, formerly HCL Info solution Ltd. (HCL

Insol) started with the aim of increasing market penetration by

handing segments not covered by HCL Insys and creating

new niches. Today it specializes.

22

Page 23: HCL Project

2. PMS

2.1. An Introduction of Performance

Management

2.1.1. What is performance management?

Performance management is the activity of tracking

performance against targets and identifying opportunities for

improvement - but not just looking back at past performance.

The focus of performance management is the future - what do

you need to be able to do and how can you do things better?

Managing performance is about managing for results.

Performance-based management at any level in the

organization should demonstrate that

You know what you are aiming for

You know what you have to do to meet your

objectives

You know how to measure progress towards your

objectives

You can detect performance problems and remedy

them

2.1.2. Why is it important?

The Modernizing Government agenda sets challenging new

performance objectives for organizations, from the delivery of

high quality services that meet the needs of their customers

and stakeholders, to doing more within the constraints of

23

Page 24: HCL Project

available resources, through to continuous improvement in

how the organization itself operates. Performance

management underpins the operations and processes within a

strategic change program framework. Sound practices and

targets, which are both flexible and reactive to change, are

needed to achieve performance improvement.

The effective performance of your organization depends on

the contributions of activities at all levels - from top

management policy development through to efficiently run

operations.

In response to the pressures and opportunities for improving

organizational performance, you need to understand how to

define and measure performance as part of a concerted

strategy for relevant, successful and cost-effective operations.

2.1.3. Critical factors for success

Focusing on outcomes that meet business objectives,

rather than outputs

Managing performance by cascading down from the

top and building bottom-up

Defining and using measures that evolve over time

Using a mix of short and long term measures, and

selecting measures that link cause and effect

Measuring effectiveness (doing the right things) and

efficiency (doing things right) in parallel

Relating individuals' reward and remuneration with

achievement of outcomes.

24

Page 25: HCL Project

2.1.4. Who is involved?

Business managers are responsible for setting targets and

managing performance against those targets; contract

managers monitor service performance from the customer

viewpoint; service providers supply performance information.

2.1.5. Principles

Performance management should be an integrated part of a

business lifecycle helping an organization to mature through

evolving and changing performance measures, from their

definition through to monitoring and review in addition, by

including the IS/IT component throughout this lifecycle,

rather than just considering it as a 'downstream' cost of

provision, there should be enhanced benefits from an

increased and more effective contribution from any

investment made in IS/IT.

You will need to ensure that you have adopted sound

practices in commissioning and acquiring IS/IT services to

achieve performance improvement. Performance management

identifies opportunities for maximizing improvements in

managing service delivery in the future. Performance

management helps you to make decisions about investment

routes, affordability and setting investment priorities in the

face of competing demands for resources.

2.1.6. Managing for results

25

Page 26: HCL Project

Managing for results requires the organization to focus on the

outputs of the processes and activities undertaken by the

organization at varying levels. Together these outputs will

contribute to the achievement of the outcomes desired by the

organization and those of the government as a whole.

2.2. Levels of performance management

1. The effective performance of your organization depends

on the contribution of activities at all levels - from top

management policy development through to efficiently

run operations. There are three or four levels of

performance management in the model framework below,

some organizations may combine the strategic level with

the organization’s priorities level.

2. Organization’s priorities: at the highest level performance

management is rooted in the organization’s long term

business strategy. Measures at this level are of impact,

resource utilization and public service improvement.

3. Strategic level performance management: at this level the

management concern is from an "outside in" as well as an

internal perspective. Measures are of outcome, such as

volume and value of service take-up, upward trends for

inclusion, staff and users' satisfaction.

4. Program level performance management: performance

management at this level is focused on the desired results

of programs of change, to demonstrate what has been

accomplished. The measures used would include those

26

Page 27: HCL Project

stated in individual business cases. Benefits management

would help to determine if these are achieved.

5. Tactical or operational service level performance

management: here the management focus is concerned

with service delivery and outputs, using conventional

service level agreement approaches and related measures

of aspects such as volumes and quality.

Although performance measures and indicators may be

different at each level, they will need to be.

Directional - to confirm that you are on track to reach the

goals.

Quantitative - to show what has been achieved and how

much more is to be done.

Worthwhile - adding more value to the business than they

cost to collect and use.

2.3. Value for money

You must be able to demonstrate that you have achieved

value for money in your operations. Value for money is taken

to cover three measures of performance:

Economy - Minimizing the cost of resources used for an

activity, having regard to appropriate quality

Efficiency - the relationship between outputs, in terms of

goods, services or other results and the resources used to

produce them

27

Page 28: HCL Project

Effectiveness - the extent to which objectives have been

achieved, and the relationship between the intended

impacts and actual impacts of an activity.

2.4. Measures and metrics

You should use these evaluation criteria for measures and

metrics:

Are you measuring the right thing?

Do you have the right measures?

Are the measures used in the right ways?

Do you determine the quality of a particular performance

metric using the SMART test (Specific, Measurable,

Attainable, Relevant, Timely)?

The procedures and measures used in performance

management will depend, among other factors, on the type of

business process which is being measured. A business process

is assumed to be made up of a number of activities which

transform inputs into outputs and contribute to the realisation

of outcomes. The customers for a process may be external

(for example, members of the public) or internal, within the

same organisation or elsewhere in the public sector.

2.4.1. Business processes can be distinguished by:

The extent to which the activities involved are people-

oriented as opposed to automated

28

Page 29: HCL Project

Whether the activities are primarily 'front-office' or 'back-

office' - that is, the amount of direct contact which the

staff have with the customers or recipients of the process

Whether the process itself is the important feature of the

activity - for example, in delivering consultancy - or

whether the activities are concerned primarily with the

generation of defined outputs

The extent to which the activity is customized or tailored

to the needs of each customer, as opposed to being routine

and procedural

The amount of discretion which needs to be exercised in

the activities

The duration of the contact with the customer.

 

2.5. Processes

You will need to review the effectiveness of your procedures

for:

Setting performance targets

Designing measures of performance relevant to the targets

Systematically and accurately measuring outcomes

Assessing the performance of external service providers

Using results for informed decision-making

Improving performance.

Research shows that most organizations have the components

of performance management in place, but they are not always

used to overall advantage. A possible five-step approach that

could help organizations in improving the performance

management of the IS/IT contribution is outlined below, with

suggested techniques.

29

Page 30: HCL Project

Step 1: Identify your level of maturity in performance

management

Look at how the organization is performing in all its

aspects of performance management - from direction

setting through to review and measurable improvement.

Do an assessment; this will help to identify your

organization’s maturity and the strengths and weaknesses.

Establish where you are now as a series of baselines,

looking at performance management at strategic program,

tactical and operational levels.

Bottom-up measures of economy and efficiency are likely

to be reasonably strong and have good management. This

may not be so well developed for effectiveness measures

Innovation, process improvement, customer satisfaction,

and contribution to policy objectives. Most organizations

have a good understanding of financial measure; this level

of understanding needs to be developed for other

measures.

Techniques: Assessment; baseline

Step 2: Identify where performance management is

important to your organization

Is it in setting direction or ensuring the delivery of

required benefits or improving the alignment,

performance and contribution of the internal and external

resources used by the organization?

Identify the values for your organization.

Key values for safety critical operational services are

speed and integrity of information. A different

organization might place high value on information flows

30

Page 31: HCL Project

or on single points of access to information at a

contact/call centre.

Techniques: Value chain analysis; benchmarking with

other organizations (which may identify things you had

not thought of)

Step 3: Resolve any mismatch between steps 1 and 2

Review performance management at each of the four

levels - (organization, strategic, program and tactical). Are

there weaknesses in areas that are important to your

organization?

Techniques: to become more outward looking and

customer-focused, use the well established balanced

scorecard and EFQM® techniques.

To answer questions about where IT makes a contribution,

use Goals, Questions and Metrics (GQM) to identify and

define measures.

Step 4: Establish where you want to be and begin to build

performance management into business processes and into

the culture

The aim is to have target, measurement and review

processes for those things that the business considers

important such as product, process, service and staff.

You will have lots of measures which need to be

prioritised against your particular perspective on

31

Page 32: HCL Project

effectiveness, efficiency and economy and against your

values.

establish benefits management as a norm

Use databases to collect Techniques performance

information and analyse trends

Include performance management in the business,

programme and project lifecycle

Step 5 : Feed information back into performance

improvement

Monitor and take action on:

We achieve what we set out to do?

Where are the opportunities to improve?

What can we do to improve? You are seeking answers to:

What is achievable?

What is important for our organization?

What was achieved?

Techniques: Process assessment; your own targets, looking at

benchmarks from the outside world.

 

32

Page 33: HCL Project

The process of performance management

33

Page 34: HCL Project

2.6. Objectives of a Performance Management

System

Performance management is an integral part of a

comprehensive human resource management strategy. Its

objective is to maximize individuals' performance and

potential with a view to attaining organizational goals and

enhancing overall effectiveness and productivity.

A staff performance management system aims at:

-

To help achieve departmental objectives through

staffDepartments formulate strategies and objectives to support

their vision, mission and values. To achieve these broad

objectives, departments have to turn them into specific

objectives and targets for the divisions, sections, units and

subsequently individual job objectives and targets for

implementation. As individual job objectives are linked to

those of departments', the performance of individual officers

contributes to the delivery of departmental objectives.

To evaluate performance and improve

communication between managers and staff on

managing performanceThe staff performance management system provides a

mechanism to monitor and evaluate staff performance.

Performance objectives are set at the beginning of the

34

Page 35: HCL Project

performance management cycle through open discussion

between the supervisors and the appraisees. Progress is

monitored regularly and feedback from staff and supervisors

is collated to help clarify objectives and output expectation;

and to enhance performance.

To provide opportunities for developmentThe staff performance management system serves as a multi-

purpose management tool. It provides valuable information to

help identify individual training needs so as to enhance

performance and to develop the potential of the staff for

further advancement.

The following figure provides an illustration of how

performance management links with other human resource

functions.

2.7. Overall Goal and Focus of Performance

Management

The overall goal of performance management is to ensure that

the organization and all of its subsystems (processes,

departments, teams, employees, etc.) are working together in

an optimum fashion to achieve the results desired by the

organization.

2.8. Performance Improvement of the

Organization or a Subsystem is an Integrated

Process

Note that because performance management strives to

optimize results and alignment of all subsystems to achieve

35

Page 36: HCL Project

the overall results of the organization, any focus of

performance management within the organization (whether on

department, process, employees, etc.) should ultimately affect

overall organizational performance management as well.

2.9. Ongoing Activities of Performance

Management

Achieving the overall goal requires several ongoing activities,

including identification and prioritization of desired results,

establishing means to measure progress toward those results,

setting standards for assessing how well results were

achieved, tracking and measuring progress toward results,

exchanging ongoing feedback among those participants

working to achieve results, periodically reviewing progress,

reinforcing activities that achieve results and intervening to

improve progress where needed. Note that results themselves

are also measures.

Note: these general activities are somewhat similar to several

other major approaches in organizations, e.g., strategic

planning, management by objectives, Total Quality

Management, etc. Performance management brings focus on

overall results, measuring results, focused and ongoing

feedback about results, and development plans to improve

results. The results measurements themselves are not the

ultimate priority as much as ongoing feedback and

adjustments to meet results.

The steps in performance management are also similar to

those in a well-designed training process, when the process

can be integrated with the overall goals of the organi zation.

Trainers are focusing much more on results for performance.

36

Page 37: HCL Project

Many trainers with this priority now call themselves

performance consultants.

2.10. Basic Steps

Various authors propose various steps for performance

management. The typical performance management process

includes some or all of the following steps, whether in

performance management of organizations, subsystems,

processes, etc. Note that how the steps are carried out can

vary widely, depending on the focus of the performance

efforts and who is in charge of carrying it out. For example,

an economist might identify financial results, such as return

on investment, profit rate, etc. An industrial psychologist

might identify more human-based results, such as employee

productivity.

The following steps are described more fully in the topics Performance Plan,

Performance Appraisal and Development Plan, including through

use of an example application. The steps are generally

followed in sequence, but rarely followed in exact sequence.

Results from one step can be used to immediately update or

modify earlier steps. For example, the performance plan itself

may be updated as a result of lessons learned during the

ongoing observation, measurement and feedback step.

NOTE: The following steps occur in a wide context of many

activities geared towards performance improvement in an

organization, for example, activities such as management

development, planning, organizing and coordinating

activities.

37

Page 38: HCL Project

1. Review organizational goals to associate preferred

organizational results in terms of units of performance,

that is, quantity, quality, cost or timeliness (note that the

result itself is therefore a measure)

2. Specify desired results for the domain -- as guidance,

focus on results needed by other domains (e.g., products

or services need by internal or external customers)

3. Ensure the domain's desired results directly contribute to

the organization's results

4. Weight, or prioritize, the domain's desired results.

5. Identify first-level measures to evaluate if and how well

the domain's desired results were achieved

6. Identify more specific measures for each first-level

measure if necessary

7. Identify standards for evaluating how well the desired

results were achieved (e.g., "below expectations", "meets

expectations" and "exceeds expectations")

8. Document a performance plan -- including desired results,

measures and standards

9. Conduct ongoing observations and measurements to track

performance

10. Exchange ongoing feedback about performance

11. Conduct a performance appraisal (sometimes called

performance review)

12. If performance meets the desired performance standard,

then reward for performance (the nature of the reward

depends on the domain)

13. If performance does not meet the desired performance

standards, then develop or update a performance

38

Page 39: HCL Project

development plan to address the performance gap* (See

Notes 1 and 2)

14. Repeat steps 9 to 13 until performance is acceptable,

standards are changed, the domain is replaced,

management decides to do nothing, etc.

Note 1: Inadequate performance does not always indicate a

problem on the part of the domain. Performance standards

may be unrealistic or the domain may have insufficient

resources. Similarly, the overall strategies or the organization,

or its means to achieving its top-level goals, may be

unrealistic or without sufficient resources.

Note 2: When performance management is applied to an

employee or group of employees, a development plan can be

initiated in a variety of situations E.g.

a. When a performance appraisal indicates performance

improvement is needed, that is, that there is a

"performance gap"

b. To "benchmark" the status of improvement so far in a

development effort

c. As part of a professional development for the employee or

group of employees, in which case there is not a

performance gap as much as an "growth gap”

d. As part of succession planning to help an employee be

eligible for a planned change in role in the organization, in

39

Page 40: HCL Project

which case there also is not a performance gap as much as

an "opportunity gap"

e. To "pilot", or test, the operation of a new performance

management system.

2.11. Performance management mainly include

following things:

Performance management is the systematic process by which

an agency involves its employees, as individuals and

members of a group, in improving organizational

effectiveness in the accomplishment of agency mission and

goals.

Planning work and setting expectations,

Continually monitoring performance,

Developing the capacity to perform,

Periodically rating performance in a summary fashion, and

Rewarding good performance.

40

Page 41: HCL Project

The revisions made in 1995 to the Government wide

performance appraisal and awards regulations support sound

management principles. Great care was taken to ensure that

the requirements those regulations establish would

complement and not conflict with the kinds of activities and

actions practiced in effective organizations as m after of

course.

Additional background information on performance

management can be found in the following

2.11.1. Planning

In an effective organization, work is planned out in advance.

Planning means setting performance expectations and goals

for groups and individuals to channel their efforts towards

achieving the organizational objectives. Getting employees

involved in the planning process will help them understand

the goals of the organization, what needs to be done, why it

needs to be done, and how well it should be done.

The regulatory requirements for planning employees'

performance include establishing the elements and standards

of their performance appraisal plans. Performance elements

and standards should be measurable, understandable,

verifiable, equitable, and achievable. Through critical

elements, employees are held accountable as individuals for

work assignments or responsibilities. Employee performance

plans should be flexible so that they can be adjusted for

changing program objectives and work requirements. When

used effectively, these plans can be beneficial working

documents that are discussed often, and not merely paperwork

41

Page 42: HCL Project

that is filed in a drawer and seen only when ratings of record

are requirement

2.11.2. Monitoring

In an effective organization, assignments and projects are

monitored continually. Monitoring well means consistently

measuring performance and providing ongoing feedback to

employees and work groups on their progress toward reaching

their goals.

Regulatory requirements for monitoring performance include

conducting progress reviews with employees where their

performance is compared against their elements and

standards. Ongoing monitoring provides the opportunity to

check how well employees are meeting predetermined

standards and to make changes to unrealistic or problematic

standards. And by monitoring continually, unacceptable

performance can be identified at any time during the appraisal

period and assistance provided to address such performance

rather than wait until the end of the period when summary

rating levels are assigned.

2.11.3. Developing Employees

In an effective organization, employee developmental needs

are evaluated and addressed. Developing in this instance

means increasing the capacity to perform through training,

giving assignments that introduce new skills or higher levels

of responsibility, improving work processes, or other

methods. Providing employees with training and

developmental opportunities encourages good performance,

strengthens job-related skills and competencies, and helps

42

Page 43: HCL Project

employees keep up with changes in the workplace, such as the

introduction of new technology.

Carrying out the processes of performance management

provides an excellent opportunity to identify developmental

needs. During planning and monitoring of work, deficiencies

in performance become evident and can be addressed. Areas

for improving good performance also stand out, and action

can be taken to help successful employees improve even

further.

2.11.4. Rating

From time to time, organizations find it useful to summarize

employee performance. This can be helpful for looking at and

comparing performance over time or among various

employees. Organizations need to know who their best

performers are.

Within the context of formal performance appraisal

requirements, rating means evaluating employee or group

performance against the elements and standards in an

employee's performance plan and assigning a summary rating

of record. The rating of record is assigned according to

procedures included in the organization's appraisal program.

It is based on work performed during an entire appraisal

period. The rating of record has a bearing on various other

personnel actions; such as granting within-grade pay increases

and determining additional retention service credit in a

reduction in force.

43

Page 44: HCL Project

Note: Although group performance may have an impact on an

employee's summary rating, a rating of record is assigned

only to an individual, not to a group.

2.11.5. Rewarding

In an effective organization, rewards are used well.

Rewarding means recognizing employees, individually and as

members of groups, for their performance and acknowledging

their contributions to the agency's mission. A basic principle

of effective management is that all behavior is controlled by

its consequences. Those consequences can and should be both

formal and informal and both positive and negative.

Good performance is recognized without waiting for

nominations for formal awards to be solicited. Recognition is

an ongoing, natural part of day-to-day experience. A lot of the

actions that reward good performance — like saying "Thank

you" — don't require a specific regulatory authority.

Nonetheless, awards regulations provide a broad range of

forms that more formal rewards can take, such as cash, time

off, and many no monetary items. The regulations also cover

a variety of contributions that can be rewarded, from

suggestions to group accomplishments.

2.12. Managing Performance Effectively

In effective organizations, managers and employees have

been practicing good performance management naturally all

their lives, executing each key component process well. Goals

are set and work is planned routinely. Progress toward those

44

Page 45: HCL Project

goals is measured and employees get feedback. High

standards are set, but care is also taken to develop the skills

needed to reach them. Formal and informal rewards are used

to recognize the behavior and results that accomplish the

mission. All five-component processes working together and

supporting each other achieve natural, effective performance

management.

2.13. Features of a Good Performance

Management System

A good staff performance management system normally

consists of the following features:

Fair and open Objective -The system designed should aim

to facilitate objective and fair assessment by the

management and encourage frank and constructive

feedback of appraises. These can be achieved through:

Setting clear targets and standards;

Providing opportunities for supervisors to inform

appraises of their performance regularly, to be

accompanied by timely coaching and counseling;

Permitting the appraise to have access to the entire report

and to review the appraisal before the appraisal interview;

and

Where necessary an assessment panel should be formed to

ensure fairness in performance rating.

Adopting such an open system for staff performance also

supports the spirit of the Personal Data (Privacy) Ordinance.

45

Page 46: HCL Project

2.13.1. Competency-Based

Competency refers to the knowledge, attributes, attitude and

skills required to perform a job effectively. There are two

broad categories of competencies: core competencies and

functional competencies. Core competencies are the generic

competencies associated with effective performance required

by a group of job holders in a department across different

divisions/sections. An example is managerial competencies

required for staff in managerial positions. Functional

competencies are the competencies specific to certain job

functions, such as computer programming skills for

programmers in the Computer Section and classroom skills

for trainers in the Training Division of a department.

Competencies are reflected in a set of desirable behavior

patterns which are observable, measurable and can be tracked

and monitored.

Developing and using a competency-based approach enables

departments to use a common language and structured way to

define and describe appropriate job behaviors at different

ranks as officer’s progress through the grade. The approach

help to assess staff's potential and promo ability to the next

higher rank and identify development needs of the staff. It

also enhances the objectivity and transparency of performance

assessment.

When core competency-based approach is adopted,

departments need to ensure that the competencies are

developed properly by :

46

Page 47: HCL Project

Aligning individual performance objectives with

departmental ones,

Securing senior management's commitment, and

Involving staff in the process.

Furthermore there should be a clear differentiation in

competency descriptions among different ranks in the same

grade. An unduly long list of competencies may adversely

affect the effectiveness of the system.

For competencies to effectively serve the needs of a

department, they should be department-specific and reflect the

missions, values and culture of the department. Any list of

competencies cannot be exhaustive. It only provides the

common language and understanding of the key dimensions

and descriptions that warrant attention.

Upon implementation, there should be proper and adequate

training for the staff on the implementation of the

performance management system

Performance planning starts with a session between the

appraising officer and the appraisee to agree on the list of

objectives/responsibilities for the coming appraisal period.

The agreed list will include the objectives of the section/unit

and the broad areas of responsibilities of the appraisees, that

is key result areas (KRAs).

47

Page 48: HCL Project

2.13.2. A Continuous Process

Staff performance management cycle is a continuous process

which involves :

Performance planning

Continuous coaching and development

Interim review

Performance appraisal

48

Page 49: HCL Project

2.13.3. Performance planning

Performance planning starts with a session between the

appraising officer and the appraisee to agree on the list of

objectives/responsibilities for the coming appraisal period.

The agreed list will include the objectives of the section/unit

and the broad areas of responsibilities of the appraisees, that

is key result areas (KRAs).

Examples of KRAs are:

Timely completion of caseloads

Customer satisfaction and relations

Staff development

Resource management

Project management

Specific, measurable, achievable and time bound targets will

then be set on the basis of the KRAs. The appraising officer

should ensure that these targets are in alignment with the

overall departmental objectives and that they are clearly

understood by the appraisee.

Depending on the nature of the job, appraising officers may

alternatively agree with appraises a list of key responsibilities

with specific performance results. This list provides the

appraisees and the appraising officers with the yardstick to

objectively discuss, monitor and assess performance. The list

should be kept under frequent review and be revised

whenever there are changes in the job.

49

Page 50: HCL Project

2.13.4. Continuous coaching and development

The performance management system is a on-going process.

After work targets and standards have been decided and

performance objectives agreed upon, the appraising officer

should start the coaching and development process which

threads through performance planning, regular feedback and

guidance, interim reviews and performance appraisal.

Coaching is about providing regular feedback to staff on their

performance. It aims at:

Giving recognition to encourage and reinforce good

performance; and

Providing advice and counseling to help improve

performance, and where appropriate, take corrective

action.

Through the coaching sessions, training needs should also be

identified and followed.

2.13.5. Interim review

An interim review is a scheduled, formal discussion between

the appraising officer and the appraisee to review the latter's

progress in meeting the agreed objectives/responsibilities.

This usually takes place in the middle of the appraisal period.

An interim review should take the form of a structured session

to provide an opportunity for additional coaching, for problem

solving, and for updating objectives/responsibilities.

50

Page 51: HCL Project

An interim review aims to: Identify performance results that are below, on or above

target and determine appropriate responses on corrective

measures. Supervisors should use this occasion to

recognize and encourage good performance. On the other

hand, performance below targets is to be pointed out and

guidance for improvement to be given;

Assess and follow up development or training need of

staff to assist them in achieving their

objectives/responsibilities;

Ascertain whether there are potential problems that may

affect the appraiser’s performance in the latter half of the

reporting cycle and put in place preventive measures; and

Review whether adjustments to the agreed

objectives/responsibilities are required.

2.13.6. Performance appraisal

Performance appraisal is the formal assessment on the

appraisee’s performance for the appraisal period. It covers the

following aspects:

How effectively the agreed objectives/responsibilities

have been carried out and targets met;

Whether the effectiveness has been adversely affected by

any constraints or obstacles;

The strengths and weaknesses of the appraisee which

affected or will affect the officer's further development;

And what sort of personal/career development and

training actions should be taken.

51

Page 52: HCL Project

2.13.7. To maintain an open system

The appraisee should be shown the assessment by the

appraising and countersigning officers before the appraisal

interview.

Countersigning officers are encouraged to complete the

appraisal form before the appraisal interview is

conducted; and

An interview record has to be prepared and signed by both

parties.

For training and career development proposals put forward in

the appraisal, the grade management must take the initiative

to ensure any necessary follow up actions are taken in a

timely and appropriate manner. These proposals will also

provide useful reference for the supervisors to develop the

staff's competencies. Common themes on training and

development identified should be consolidated for

incorporation into the training and development plans of the

department and the grade.

To ensure consistency in assessment standards and fairness in

performance rating in staff appraisals, heads of

departments/grades may consider if an assessment panel

should be set up. An assessment panel is a management tool

to help departments cross moderate appraisal ratings.

An assessment panel is usually chaired by the head of

branch/division or head of grade with members drawn from

section/unit heads. At the start of a reporting cycle, the

assessment panel will meet to discuss the marking criteria and

52

Page 53: HCL Project

standard. Staff will be informed of these criteria and standard

and clear guidelines will be issued to appraising officers.

The assessment panel will review the completed reports on

the basis of panel members' knowledge about the performance

of the appraisees. If the assessment panel disagrees with the

assessment of a report, the reviewing officer and the

appraising/countersigning officer, where necessary, may be

requested to explain before the panel. Amendments may be

made to the appraisal reports to ensure parity of assessment, if

necessary.

3. PROJECT

53

Page 54: HCL Project

3.1. Objective of the Project – Introduction of

the Problem

3.1.1. Primary Objective

To understand the basic features of performance management

plan or performance assessment in HCL and their

contribution in the success of HCL Infosystems Ltd. within a

short span of previous years.

3.1.2. Secondary objective

To identify which of the functional aspects/ Parameters are

low and which dysfunctional aspects/ Parameters are high in

order to put some suggestion for increasing the former and

reducing the latter in other words to move from dysfunctional

to functional performance assessment.

3.2. Significance of the Project

The six weeks of summer training at HCL Infosystems Ltd.

gave me a complete exposure to the organizational work life.

It was unique opportunity to explore the realities of India’s

leading companies as a researcher and gather knowledge from

its vast repertoire of experience.

It was great learning experience to know the duties performer,

responsibilities taken and the skill regained by the executives

of the organization to reform heir jobs effectively and

efficiently. The project not only helps me to enhance my

practical knowledge but it also help me to understand how

54

Page 55: HCL Project

performance management work into the organization and how

executives assess their own employee into the organization.

The summer project, also made me realize the worth of an HR

manager. I got to know the importance of employee

assessment and communication and interpersonal skill in

getting things done from other. In a net shell, it was a very

fulfilling and fruitful period of my life as a management

student.

3.3. Definition - A Theoretical Perspective

Performance Management is the process of crating a work

area setting in which people are enabled to perform to the best

of their abilities. Performance Management is a whole work

system that begins when a job is defined as needed. System

includes the flowing actions-

1. Development job description

2. Select appropriate people with an apply selection process.

3. Negotiate requirement and accomplishment based

performance standards

4. Outcomes measures.

5. Provide effective orientation training.

6. Provide ongoing coaching and feedback.

7. Conduct quarterly performance development discussions.

55

Page 56: HCL Project

8. Design effective compensation and recognition systems

that reward people for their contribution.

9. Provide promotional/crier contributions.

10. Assist with exit interviews to understand why valuable

employees leave the organization.

3.4. Preparation and Planning for performance

management

Much work is invested, on the front end, to improve a

traditional employee appreciate process, Infect managers can

feel as if the new process is too time consuming ones the

function of developmental goal is in place however time to an

administrator the system decreases. Each of these steps to

taken with the participation and cooperation of the employee

for best results.

3.5. Performance Management and

Development

Define the purpose of the job, job duties.

Define the performance goals with measurable outcomes.

Define the each job responsibilities a goal.

Define the performance standards for key components of

the job,

56

Page 57: HCL Project

Hold interim discussions and provide feedback abuts

employee performance.

Maintain a record of performance through critical incident

reports.

Provide opportunity for broaden feedback. Use 360`

performance feedback system.

Develop administer a coaching and implement plan if the

employee is not meeting expectation

3.6. Performance Assessment and Development

Plan In HCL INFOSYSTEMS LTD.

3.6.1. Prior to filling the form please read

carefully Instructions to the Appraiser

Appraise the employee in related to the positions held

during the period under appraisal.

Be objective, Avoid any personal prejudice.

Do not evaluate on the basis of isolated incidents, but base

your judgment on the entire period under review.

Consider each independently, uninfluenced by the rating

given for other factors.

This from will not be treated as complete and processed

further until all selections are filled up.

3.6.2. Performance appraisal guidelines

57

Page 58: HCL Project

3.6.2.1. Appraisal procedurePerformance appraisal encompasses the on-going work-

related discussions, which take place between appraisals and

appraisees throughout the year. The formal performance

appraisal meeting is normally attended by the employee and

manager only; but when relevant, another manager will also

participate (e.g. functional head / HR person).

3.6.2.2. The Form And Its Contents The guide for the performance / achievement rating is as

follows.

Outstanding – Consistently exceeds the requirement of job.

Exemplary performance - Far exceeds the requirement of job.

Growth potential unlimited.

Very good: - Handle assignments with thoroughness and

perfection, effective discharge of responsibilities to the

satisfaction of superiors completes assignment in time. With a

little more initiative could have performed better.

Good: - Just meets the normal requirements of the job, needs

substantial improvement in all areas of work to meet

requirement of complete employee.

Not Up to the Expectation - Not likely to meet the

requirements of complete employee.

Section 1 : Quarterly Self appraisal forms:

58

Page 59: HCL Project

a) General notes on goals /target setting Key responsibility areas relate to the key result area on going

and inherent in the achievements and performance again each

one. Targets and achievements are also to be filled after

discussing with the manager. Target related to the priority

activates normally are within the key responsibility areas.

Target must be agreed between the manager and the

subordinate. Each target should be specified in such a way

that it will be clear when it is met and must include the time

frame in which it elements to ensure consistence as

summarized in the acronym SMART (S-specific, M-

measurable, A-achievable, R-relevant, T-timer related).

Although it is anticipated the performance against the target

will be assessed quarterly, it is responsibilities are reviewed at

appropriate in travels every quarterly. The manager should

ensure that at all times the subordinate has a clearly defined

set of agreed Target.

Target for the period under review: -

In section 1 KRA/ assignment for the period under review

should be stated. In some cases it will be necessary for the

objective to be amplified on a separate sheet and this

documents should be referenced on the form..

b) Achievement against TargetWere the target / expectations for the period under review

achieved? Comments and reasons for the success or failure

should be given at the end of the review quarter period.

c) Target for the next quarterAt the beginnings of the quarter the target should be decided

in Section –1. The aim is to achieve sustainable improvement

59

Page 60: HCL Project

in the subordinate’s performance. Enter the date by which the

target should be achieved.

d) Overall View Of PerformanceThis is the Appraisee/manager’s view of the overall

performance. Assessment must be made on the overall rating

listed above and in terms of the trend in performance.

Section – 2 : Annual Appraisal Form

To the filled up by the appraisee at the end of the annual

review year.

Section – 3 : Potential And Qualitative Assessment

The objective is to provide an opportunity to the employee

and the manager to discuss the strengths that the individual

brings to the job and examine the limitations, which may

require attention. The aim is to improve performance and

development of the individual.

Section – 4 : Overall Performance / Potential

AssessmentSpace for other comments by the manager (if required for any

issues with regard to constraints to effective performance

and / or supporting actions to achieve target).

a) Ratings / Final Recommendation

60

Page 61: HCL Project

Rating has to be given by the Regional Manager / General

Manager / Functional Head after a through appraisal of the

performance of the employee and in accordance with the

parameters given. Mention if any promotion / salary

discrepancy / rewards / movement is recommended.

b) SignatureThe managers and employees should sign the form at the end

of the discussion acknowledging that the objectives of the

appraisal have been achieved and emphasizing a joint

commitment to implement and actions agreed upon.

Signatures are to confirm that the form has been read and the

key points have been noted.

Section- 5 : Assessment For Development And

Growth

Training for improvement and career development the

training plan for the employee for the coming year should be

discussed.

The training identification form has to be filled and returned

to the HR department. In the month of the April for the

preparation of the training calendar for the forth coming year.

The manager should return the complete field form within ten

days hence from the completion of the Annual Review period

to the HRD Dept. in order to attain consistency of the

appraisal standards and relevant follow – up action.

61

Page 62: HCL Project

4. RESEARCH METHODOLOGY

4.1. Research Design

In general terms research methodology is the process of

carrying out research in a formalized and scientific way. It is

one manner in which one proceeds with his research design

adopted. The research done is exploratory and analytical in

nature. The major emphasis in studies was on discovery of

new ideas and insights. Research is done as-

Firstly to understand the concept of performance

management.

What is the area of performance management?

How it is being implemented in HCL?

What is the assessment process of performance

management?

Did questionnaire survey with the sample size of 30.It

was conducted for three main departments-Sales, Support

and Service?

Did analysis and prepared Column charts according to

the questionnaire survey response?

62

Page 63: HCL Project

The assessment is then done to bring out what is the process

being followed in HCL Infosystems Ltd. regarding

performance management.

63

Page 64: HCL Project

4.2. Data Collection Method

a. Secondary Data - It refers to the data that has already

been collected, the secondary data, which has been used to

carry out this study, are as follows:

* Performance assessment and development plan manual.

* Company’s Internet site (www.hcl.in)

* Other relevant study materials and websites.

evidence, in the form of a hypothesis test, indicates otherwise

— that is, when researcher has a certain degree of

confidence, usually 95% to 99%, that the data does not

support the null hypothesis. It is possible for an experiment to

fail to reject the null hypothesis.

H0 = the null hypothesis

Assumption: The Performance Management System in

HCL Infosystems is not effective.

64

Page 65: HCL Project

4.3. Analysis of PMS – Processes & Components

4.3.1. Planning

In an effective organization, work is planned in advance. This

includes setting performance expectation and goals for

individual in order to channel effort towards achieving the

organizational objectives. Involvinng employee in planning

process is essential to their understanding of the goals of the

organization, what needs to be done, why it needs to be done,

and expectation of accomplishing the goals.

2.61

2.89 2.83

2.47

2.2

2.3

2.4

2.5

2.6

2.7

2.8

2.9

Score

Overall Sales Service Support

Function

Series1

The PMS in terms of planning in HCL fairs around average,

where they need to put planning system in a very scientific

way. They need to design the entire planning session taking

65

Page 66: HCL Project

into consideration the aspiration and need of the people whose

performance needs to be planned.

4.3.2. Monitoring

Designing effective feedback into a performance management

programme will improve individual and team performance

and will make your organization more effective. With

effective feedback process, employees can see their progress

and that motivates them to reach their performance goals

effectively.

3.022.93

2.54

2.95

2.3

2.4

2.5

2.6

2.7

2.8

2.9

3

3.1

Score

Overall Sales Service Support

Function

Series1

66

Page 67: HCL Project

The PMS of HCL stand in between for monitoring, where

they need to develop a feedback channel into the system,

which will capture the feedback in holistic way and must be

part of organizational culture.

4.3.3. Developing Employees

Providing employees with training and development

opportunities encourages the good performance, strengthen

job related skills and competencies , and help employee keep

up with changes in the work place.

1.531.84

1.52 1.37

00.20.40.60.8

11.21.41.61.8

2

Score

Overall Sales Service Support

Function

Series1

67

Page 68: HCL Project

The Employee development in HCL is fairly better, where the

feedback from PMS is implemented by the way of training

and development. Where the organization equips people with

the skill which will be required in future.

4.3.4. Rating

Within the context of formal appraisal performance

requirement, rating means evaluating the employee

performance against the element and standard in an employee

performance appraisal plan and assigning a rating of record.

68

Page 69: HCL Project

2.99 2.563.00 3.25

0

0.5

1

1.5

2

2.5

3

3.5

Score

Overall Sales Service Support

Function

Series1

The rating of Performance appraisal system in HCL is

satisfactory , ratings are more objective for sales , which

people in service and support don’t view as more subjective.

69

Page 70: HCL Project

4.3.5. Action Based Performance

A Basic principle of effective management is that all

behavior is controlled by its consequences. Those

consequences should be both formal and informal and both

positive and negative. Positive consequences include rewards

and recognition.promotion.Negative consequences means

may include counseling, reassigning, removing or

downgrading.

1.78 1.97

1.301.64

00.20.40.60.8

11.21.41.61.8

2

Score

Overall Sales Service Support

Function

Series1

The PMS in HCL fairs in terms of action based performance.

HCL administers positive and negative consequences with

apt.

70

Page 71: HCL Project

4.3.6. Analysis

If we look at the following graph, which measures the

effectiveness of PMS in HCL, we find out that it is quite

effective and are continually achieving the purpose of

enhanced performance.

4.3.7. Effectiveness

Sign of a good system is that, it achieves what it has been

designed to achieve. The principle of execution achieves the

end with best means and delivers the best result.

1.61

2.571.82 1.64

0

0.5

1

1.5

2

2.5

3

Score

Overall Sales Service Support

Function

Series1

The effectiveness score of HCL is fairly high where the

employees seem to be happy with current PMS system .HCL

71

Page 72: HCL Project

need to work for sales, where they need to design the new

PMS system.

The PMS of HCL is very effective on action based

performance and developing employees, which clearly shows

that as an organization HCL is highly progressive

organization which continually develop people and provides

negative and positive feedback.

While, it need to work in the area of planning, monitoring and

rating , where they have to get into more systematic and have

a separate session on planning , mid year review , and need to

teach appraiser how to provide rating objectively. They need

to plan and devise KRA sessions for each employee by taking

an objective of getting all the KRA in Month , which need to

discussed jointly and must be agreed between the Appraiser

and Appraisee

72

Page 73: HCL Project

5. RECOMMENDATIONS

5.1. Recommendations

1. Though the employees are free in all respects, there

should be more Employee Empowerment.

2. Employees should be encouraged to do work creatively

and innovate to improve the growth rate of organizations.

3. While posting employee in different departments their

personal choices should also be taken into consideration.

4. Executives must be given jobs where they are creative

rather than following orders of the boss and obeying them

willingly.

5. The career growth of employees should be planned on the

long-term basis.

6. The (candidates) not considered for promotion, should be

informed about their weaknesses so that they can work on

it.

73

Page 74: HCL Project

7. Separate session on planning the KRA should be taken up

and must be discussed and signed jointly between the

appraiser and the appraisee.

8. HCL should introduce mid year review into the system

and must rate the employee and provide them with

necessary training and development.

6. CONCLUSION

HCL Infosystems Ltd. though seems to be an open

organization but has a conservative approach towards its

performance management policies. There are many worker

policies provided for them. Besides this, their policies are

quiet rigid.

There is no proper formation of grievance cell. Only basic

amenities are being provided to workers. Thus the strengths

and weaknesses of the organization can be listed below.

Strengths

High concern for excellence in performance.

Continuous development of workforce.

No place for displacing personnel power.

A strong desire for making an impact on others for the

well being of the organization.

A good teamwork.

A desire to change adverse situations.

74

Page 75: HCL Project

Weaknesses

Under utilization of decision-making power.

Rigid hierarchy level.

7. BIBLIOGRAPHY

Books

Organizational behavior - Robbins, Stephen P

Personnel Management and Human Relations -

Venkata Ratnam, C S and Srivastava, B K

Human Resource Management - Ashwathappa, K

Human Resource Management - Rao, V S P

Web sites

www.google.com

www.hrmguide.net

www.managementscience.org

www.londonexternal.ac.uk

www.hr.com

www.wikipedia.com

75

Page 76: HCL Project

8. APPENDIX 1

Performance Assistance & Development Plan

Important

Nothing hurts more then the felling of the employee that

his/her performance is not evaluated properly. The whole

exercise would be futile if the appraisals are not done

objectively based on actual performance during the

assessment period. Scant regard to this exercise may

denotative the willing and committed employees and rated

their growth and development in the organization.

Name: Ec No:

Grade: Date of joining:

Designation: Department:

76

Page 77: HCL Project

Region:

Last Change of grade in (mm/yy):

Personal & Educational qualification (with Year and

Institute):

1.

2.

3.

Appraisal period in (mm/yy) from to

Appraisal Record

(To be filled by HRD)

Quarter Period Name of the Appraisal Rating

1.

2.

3.

4.

Annual

Performance Assistance & Development Plan

77

Page 78: HCL Project

Section – 1 Quarterly self appraisal form

Goal setting

(To be filled after discussing with your manager. In case you

have had change in the assignment, or manager, have the

figure attested by your former manager wherever possible.)

Name of Appraisee :

EC. No.:

Appraisal Period : QTR – (JAS/OND/JFM/AMJ)

Tick whichever Qtr is applicable

KRA’s/Assignments Target for the QTR Achievements Rating

       

       

       

       

       

       

78

Page 79: HCL Project

Guide for Achievement Rating

(1) – Outstanding, (2) – Very Good, (3) – Good, (4) – Not up

to the Expectation

Performance Assistance & Development Plan

I. Specify one achievement which is beyond target /

expectations during the quarter and reason for that

achievement.

II. In case of shortfalls (if any), list the assistance/help

you require to remove the same in the next Quarter.

III. If you are working in a team list down your team

members.

79

Page 80: HCL Project

IV. Overall performance rating during the Quarter:

(To be filled by Appraise)

Appraiser’s Rating

Guide for performance Rating

(1) – Outstanding, (2) – Very Good, (3) – Good, (4) – Not up to the Expectation

(To be filled by Appraise)

Appraiser’s Rating

Guide for performance Rating

(1) – Outstanding, (2) – Very Good, (3) – Good, (4) – Not upto the Expectation

Signature of the Appraise_____________ Signature of the

Appraiser______________

Date :

80

Page 81: HCL Project

Performance Assistance & Development Plan

Section – 2 Annual appraisal form

Name of Appraisee: ____________________________

Ec. No.: ___________________

Appraisal Period From: __________________To:

______________________________

Self-Appraisal:

1. Does your role fully utilize your knowledge skills?

Qualitatively

Qualitatively

2. What additional responsibilities would you like to handle?

3. List significant educational attainments during the period

under review.

__________________________________________________

__________________________________________________

__________________________________________________

__________________________________________

4. List if you have undergone any training during this period.

81

Page 82: HCL Project

__________________________________________________

__________________________________________________

__________________________________________________

__________________________________________

5. List the location you don’t mind moving to.

a.)_________________________b)__________________c)._

_______________

6. List three major issues which are bothering you.

__________________________________________________

__________________________________________________

__________________________________________________

__________________________________________

7. List there major factors you are proud of working for the

organization:

__________________________________________________

__________________________________________________

__________________________________________________

__________________________________________

Signature of the Appraisee _______________________ Date:

Performance Assistance & Development Plan

SECTION – 3 POTENTIAL AND QUALITIVE

ASSESSMENT

(To filled by the Appraiser/Manger)

82

Page 83: HCL Project

S. No. Qualities/Areas Rating

1. Quality of Work

2. Cost Saving

3. Assist Others

4. Creative Thinking

5. Team Leader/Team player

6. Independent Working

7. Dependability

8. Internal Customers Satisfaction

9. Farsightedness

10. Analytical/Logical Approach

11. Interaction with seniors/cross function

12. Problem Solving Capability

13. Communication

14.

15.

Professional/Technical knowledge

Behavior/Attitude

Guide for Rating

(1) Outstanding, (2) Very good, (3) Good, (4) Not up to the

expectation

2. List specific strengths/ areas to be focused for individual’s

development.

STRENGTHS AREAS OF DEVELOPMENT

83

Page 84: HCL Project

3. What are the other areas where individual’s potential can

be explored?

84

Page 85: HCL Project

Performance Assistance & Development Plan

OVERALL PERFORMANCE/ POTENTIAL

ASSESSEMENT

Comments by immediate manager

Signature of the Appraise_________________ Signature of

the Appraiser___________

Date:

(This part not to be discussed with the employee)

Rating by Regional Manager/General Manager/Functional

Head

Rating: Top 25% Next 45% Next

25% Bottom 5%

If employee is rated in top 25% then please specify the

exception achievements during the appraisal period.

(Authorized Signatory)

85

Page 86: HCL Project

Overall view of performance

Trend

Declining Stable Improving

(Please tick whichever is applicable)

Final Recommended with respect to (If any):

1 Promotion:

2 Salary Discrepancy:

3 Exceptional reward:

4 Movement:

New Structure

(To be filled by HRD)

Confirmation/probation/increment

w.e.f. :_____________________

Compensation level/basic/designation:

________________________

86

Page 87: HCL Project

Performance Assistance & Development Plan

SECTION-5 ASSESSEMENT FOR DEVELOPMENT

AND GROWTH

(Identification of training and Development Need .To be sent

to HRD in the first week of April)

(For the use of HRD)

NAME:

EC.NO.

DEPARTMET:

GRADE:

DESIGNATION:

LOCATION:

Training History (Information on the Soft Skill/Technical Training undertaken by the

Appraise in the previous years)

Courses/training underwent Effectiveness/impact on the appraiser’s performance

1.

2.

3.

4.

Training Needs Identification (Specify on the type of Soft Skills like Communication/

Presentation skills, supervisory Development, selling skills, Motivation & team building,

attitudinal skills and Technical Training you will like the appraise to under to order

To improve his/ her performance on the job to meet future needs)

87

Page 88: HCL Project

1.

2.

3.

4.

5.

6.

Signature of the appraise__________________ Signature of

the appraiser___________

Date: Date:

88