HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008...

51
HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT JBIC Loan IP-541 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS INTERNATIONAL IN ASSOCIATION WITH INTEM CONSULTING INC PT.CAKRA MANGGILINGAN JAYA PT. DUTA HARI MURTHI CONSULTANTS GOVERNMENT OF INDONESIA MINISTRY OF NATIONAL EDUCATION DIRECTORATE GENERAL OF HIGHER EDUCATION HASANUDDIN UNIVERSITY

Transcript of HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008...

Page 1: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

HASANUDDIN UNIVERSITYENGINEERING FACULTY DEVELOPMENT PROJECT

( JBIC Loan IP-541 )

7th Aug 2008

Quarterly Progress ReportApril-July 2008

PACIFIC CONSULTANTS INTERNATIONAL

IN ASSOCIATION WITHINTEM CONSULTING INC

PT.CAKRA MANGGILINGAN JAYAPT. DUTA HARI MURTHI CONSULTANTS

GOVERNMENT OF INDONESIAMINISTRY OF NATIONAL EDUCATIONDIRECTORATE GENERAL OF HIGHER EDUCATIONHASANUDDIN UNIVERSITY

Page 2: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

HASANUDDIN UNIVERSITYENGINEERING FACULTY DEVELOPMENT

PROJECT

Activities

1. Campus Master Plan (Finalization)

2. Preliminary Design (Package-1)

3. Detailed Design (Package-1)

4. Prequalification (Package-1)

Page 3: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

CAMPUS MASTER PLAN AT GOWA

Page 4: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Bird Eye View Perspective of Gowa Campus

Page 5: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Landscape Image

Page 6: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Design Principle

Research Based Campus Creating campus

life atmosphere through integration of

activities and space

Futuristic and Traditional

Eco and Green Campus

East-West Axis, Natural ventilation, Save

energy

Easy Operation and Maintenance

Page 7: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Research Based CampusCOT + Academic Zone (Department Laboratories)

Page 8: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

COT (Center of Technology)

• Function: to promote linkage and collaboration among UNHAS-FE, industrial sector, other universities and academic institutions.

• Operation: has own organization and collects information for UNHAS-FE’s research activities.

Page 9: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Academic Zone = Research Zone• The Laboratory Buildings for 6 departments are

planned in the east area of Gowa Campus.• Individual department buildings are linked to

each other by the Campus Mall.• This planning concept makes university’s

activities smooth and promotes each department’s uniqueness.

• Open spaces behind 6 department laboratory buildings are the future extension areas where future laboratory buildings will be planned.

Page 10: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Design of Entrance Gate

Page 11: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Facade Design

• Façade of Entrance Gate• Buildings are designed

futuristically using glass and metal based on present technology and contemporary design

Page 12: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Identitiesof Department Laboratories

The department laboratory buildings are being created so as to have a special identity of them own.

The components of these design policies will create an attractive campus with an identity and

a sense of unity.

Page 13: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Pedestrian Deck Layout

Page 14: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Historical Symbols

Existing administration building will be renovated and utilizing as a museum for the new campus. The history and the tradition of UNHAS-FE will be memorized in this preserved building

The existing Tugu Ayam will be preserved at the same location and symbolized in a roundabout on the axis of access road.

Page 15: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Eco (eco-friendly and economical)

and Green Campus

• To maximize utilization of the natural climatic benefits of the project site, and to produce innovative design that will optimize the use of natural wind, daylight and temperature swings, reducing reliance on mechanical and electrical systems, thereby saving resources and reducing emission of greenhouse gases.

Eco ConceptEco Design ⇒ Eco

Design

Page 16: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

function EDO Design

(Japanese Traditional Eco Style) ECO Design for UNHAS-FE

Sunshade + Natural Ventilation

(Double Skin)

SUDARE

GRC-louver

Natural Lighting

TORINIWA

ATRIUM

Cooling

NAKANIWA

GROVE

Page 17: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Eco Campus

• Save energy:East-West Axis, Natural ventilation , Natural lighting , Solar shading

• Use Natural Energy (Solar Panel)• Bicycle Network:

To encourage the use of bicycles, rent-free-bicycle is recommended to promote the use of bicycles.

Page 18: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

East-West Axis

Page 19: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Natural ventilation

• The Atrium provides excellent ventilation by chimney effect which exhausts hotter air from inside and intakes colder air from outside through outside windows facing towards the atrium.

Page 20: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Reduction of heat load & Natural lighting

• The heat load of the building is reduced by solar shading

• The building is planned to utilize atrium to reduce daytime illumination load using natural lighting in all occupied rooms.

Page 21: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Solar Shading & Natural lighting

Page 22: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Green Campus

The landscape concepts are to make the modern technological campus more green and shaded as well as a good environmental system  by increasing the planting species and conserving rare plants and indigenous plants of Sulawesi Island.

Page 23: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Green Campus

Page 24: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Green Campus

Page 25: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Package- 1 Detailed Design

Page 26: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

1. Building’s Room Layout Feature

1) Research room Unit: Prof, AP, Assist, Graduate,

Meeting

2) Laboratory: Experimentation, Laborant

3) Design Studio

(1) Architecture Department (9,422㎡ )

Page 27: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

GF

1F

2F

3F

Page 28: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Meeting Graduate S AP

Ass P

Page 29: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

1. Building’s Room Layout Feature

1) 2-stories Laboratory: Lower floor for experiment

Upper floor for staff room

2) Professor room

3) Research room (capacity 26 or 14)

(2) Civil Engineering Department (8,248 ㎡ )

Page 30: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

GF

1F

2F

3F

Page 31: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Professor x 18 room

Page 32: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

1. Building’s Room Layout Feature

1) 2-stairs and wide corridor

2) 2 classroom special designed with LCD

3) Basic Science Laboratory

(3) Classroom Building (11,701 ㎡ )

Page 33: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

with LCD

2-Stairs

W=3.6m

Basic Science Lab

GF

1F

Page 34: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

1. Building’s Room Layout Feature

1) 2 Entrance at Ground Floor: for Pedestrian and Vehicle user (with 8 Parking Space) 2) Common space: Entrance hall,

Reception, security, mushola,pantry, garden, etc

3) Dean Floor with Special design 4) Showcase: GF-3F for Dep., 4F for

Dean

(4) COT Building (6,925 ㎡ )

Page 35: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

2 Entrance

GF

4F

ReceptionSecurity

Dean Area

Dean Hall

Page 36: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

1. Building’s Room Layout Feature

1) General entrance and service access

2) Complex: Clear zone division

3) Library: Security systemo

4) Lecture Theater: Acoustic and special

design

(5) Library Building (6,829 ㎡ )

Page 37: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

1F

4F

Security

Lecture Theater

Page 38: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Library ImageLecture Theater Image

Page 39: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

2. Elevation 1/ ConceptThe UNHAS-FE Campus is

projected an appropriate identity and image of "futuristic and traditional". And also the department laboratory buildings are being created so as to have a special identity of them own. The components of these design policies will create an attractive campus with an identity and a sense of unity.

Page 40: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

2. Elevation 2/ Building Identity

Architecture Department: Traditional style of Gowa such as Independent Column and Tower

Civil Engineering Department: Dynamic Structure, Strength COT and Library : “Entrance Gate”.

Page 41: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.
Page 42: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Department

Page 43: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

COT & Library

Page 44: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

COT and Library make ‘GATE’

Page 45: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Phasing Program

Page 46: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Development Phasing Schedule

Page 47: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Packaging (JBIC Yen Loan Portion)

Page 48: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Implementation Schedule (Local Government Portion)

2008: Demolition of PKG (“1.5 months behind” up to today) Delay of demolition will influence implementation schedule 2009: Completion of Inner Campus Road,

Parking, Landscaping 2010: Completion of Auditorium, Student

Center, Sport Hall, Canteen, Parking, Landscaping

2011: Completion of Outdoor Sport Facilities, Parking, Landscaping

2012~: Completion of Dormitory for Students, Hostel for Lecturers, Mosque, etc.

Page 49: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Package-1 Bidding Schedule

June 18: PQ Announcement July 29: PQ Application submission Aug 2008: P/Q result concurrence by JBIC Sep 2008: Bidding Documents concurrence by

JBIC Sep 2008: Distribution of Bidding Documents Sep 2008: Pre-bid Meeting & Site Visit Nov 2008: Submission of Proposal Dec 2008: Financial Proposal Opening Jan 2009: Notice of Award Jan 2009: Contract Signing Jan 2009: Construction Starting Ceremony

Page 50: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

1 2 3 4 5 6 7 8 9 # # # 1 2 3 4 5 6 7 8 9 # # # 1 2 3 4 5 6 7 8 9 # # # 1 2 3 4 5 6 7 8 9 # # # 1 2 3 4 5 6 7 8 9 # # #

PREPARATION OF IMPLEMENTATION1 Land aqucition Feb-06 Ok2 Demobilisation of Ex. PKG by the End of 2007 (not yet)3 Selection of Fellowship Candidate Batch I Nov 2007 - Feb 2008 Ok3 Consultant Selection for PMC May - Dec 2007 Ok4 Consultant Selection for Fellowship Consultant June 2007 - Jan 2008 Ok

DESIGN STAGES1 Detailed Design Development Stage Jan - Dec 2008 Started

Pre-design including Master Plan Jan - Jun 2008 Finished DD-01 Preliminary Design (P-1) Feb - Apr 2008 Finished DD-02 Detailed Design (P-1) Apr - Jul 2008 On-going DD-03 Preliminary Design (P-2 & P-3) DD-04 Detailed Design (P-2 & P-3) DD-05 Preliminary and Detailed Design (P-4) Apr - Sept 2008 On-going DD-06

2 Procurement and Contracts Stage Marc 2008 - Dec 2009 Started Pre-qualifications Jun - Aug 2008 On-going PC-01 JBIC Concurrence on Pre-qualifications PC-02 Preparation of Bidding Documents Jun - Jul 2008 On-going PC-03 JBIC Concurrence on Bidding Documents PC-04 Bid Period PC-05 Evaluation of Bids PC-06 JBIC Concurrence on Bid Evaluation Results PC-07 Contract Negotiations PC-08 JBIC Concurrence on Contracts PC-09 Signing on Contracts PC-10 L/C Opening, L/Com Effectuate PC-11

CONSTRUCTION STAGES (Not yet)3 Building Construction Supervision Stage Jan 2009 - May 2011

Package-1 SV-01 Mobilization and Preparation Works SV-01-01 Shop Drawings Review & Approval SV-01-02 Construction of Dean Office, Center of Technology, SV-01-03 Construction of Library, Central Computer, Lecturer Theater SV-01-04 Construction of Classroom and Laboratory for Basic Science SV-01-05 Architecture and Civil Department Buildings SV-01-07 Supply of Equipment SV-01-08 Supply of Furniture SV-01-09 Defects Liability Period SV-01-10

Package-2 SV-02 Mobilization and Preparation Works SV-02-01 Shop Drawings Review & Approval SV-02-02 Electrical and Mechanical Department Buildings SV-02-03 Supply of Equipment SV-02-04 Supply of Furniture SV-02-05 Defects Liability Period SV-02-06

Package-3 SV-03 Mobilization and Preparation Works SV-03-01 Shop Drawings Review & Approval SV-03-02 Naval and Geology Department Buildings SV-03-03 Supply of Equipment SV-03-04 Supply of Furniture SV-03-05 Defects Liability Period SV-03-06

Package-4-1 SV-04 Procurement and Conracts Stage (LCB) PC-01~11 Mobilization and Preparation Works SV-04-01 Shop Drawings Review & Approval SV-04-02 Construction of Workshop SV-01-06 Electrical Power Supply Works SV-04-03 Water Supply Works SV-04-04 Drainage Works SV-04-05 Defects Liability Period SV-04-11

Package-4-2 Procurement and Conracts Stage (LCB) PC-01~11 Mobilization and Preparation Works SV-04-01 Shop Drawings Review & Approval SV-04-02 Electrical Power Supply Works SV-04-03 Water Supply Works SV-04-04 Drainage Works SV-04-05 Defects Liability Period SV-04-11

Critical Points

IMPLEMENTATION SCHEDULE

DESCRIPTION OF SERVICE / WORK Date Action Code No.2008 2009 2010 2011 2012

Page 51: HASANUDDIN UNIVERSITY ENGINEERING FACULTY DEVELOPMENT PROJECT ( JBIC Loan IP-541 ) 7 th Aug 2008 Quarterly Progress Report April-July 2008 PACIFIC CONSULTANTS.

Implementation Schedule (JBIC Yen Loan Portion)

2008: Campus Master Plan, Preliminary Design, Detailed Design and Tendering

2009: Completion of Center of Technology, Library and Classroom Buildings, Power supply, Water supply, Drainage

2010: Completion of Architecture Dept., Civil Dept., Electrical Dept. and Mechanical Dept. Buildings

2011: Completion of Naval Architecture Dept. and Geology Dept. Buildings