HASANUDDIN UNIVERSITYENGINEERING FACULTY DEVELOPMENT PROJECT
( JBIC Loan IP-541 )
7th Aug 2008
Quarterly Progress ReportApril-July 2008
PACIFIC CONSULTANTS INTERNATIONAL
IN ASSOCIATION WITHINTEM CONSULTING INC
PT.CAKRA MANGGILINGAN JAYAPT. DUTA HARI MURTHI CONSULTANTS
GOVERNMENT OF INDONESIAMINISTRY OF NATIONAL EDUCATIONDIRECTORATE GENERAL OF HIGHER EDUCATIONHASANUDDIN UNIVERSITY
HASANUDDIN UNIVERSITYENGINEERING FACULTY DEVELOPMENT
PROJECT
Activities
1. Campus Master Plan (Finalization)
2. Preliminary Design (Package-1)
3. Detailed Design (Package-1)
4. Prequalification (Package-1)
CAMPUS MASTER PLAN AT GOWA
Bird Eye View Perspective of Gowa Campus
Landscape Image
Design Principle
Research Based Campus Creating campus
life atmosphere through integration of
activities and space
Futuristic and Traditional
Eco and Green Campus
East-West Axis, Natural ventilation, Save
energy
Easy Operation and Maintenance
Research Based CampusCOT + Academic Zone (Department Laboratories)
COT (Center of Technology)
• Function: to promote linkage and collaboration among UNHAS-FE, industrial sector, other universities and academic institutions.
• Operation: has own organization and collects information for UNHAS-FE’s research activities.
Academic Zone = Research Zone• The Laboratory Buildings for 6 departments are
planned in the east area of Gowa Campus.• Individual department buildings are linked to
each other by the Campus Mall.• This planning concept makes university’s
activities smooth and promotes each department’s uniqueness.
• Open spaces behind 6 department laboratory buildings are the future extension areas where future laboratory buildings will be planned.
Design of Entrance Gate
Facade Design
• Façade of Entrance Gate• Buildings are designed
futuristically using glass and metal based on present technology and contemporary design
Identitiesof Department Laboratories
The department laboratory buildings are being created so as to have a special identity of them own.
The components of these design policies will create an attractive campus with an identity and
a sense of unity.
Pedestrian Deck Layout
Historical Symbols
Existing administration building will be renovated and utilizing as a museum for the new campus. The history and the tradition of UNHAS-FE will be memorized in this preserved building
The existing Tugu Ayam will be preserved at the same location and symbolized in a roundabout on the axis of access road.
Eco (eco-friendly and economical)
and Green Campus
• To maximize utilization of the natural climatic benefits of the project site, and to produce innovative design that will optimize the use of natural wind, daylight and temperature swings, reducing reliance on mechanical and electrical systems, thereby saving resources and reducing emission of greenhouse gases.
Eco ConceptEco Design ⇒ Eco
Design
function EDO Design
(Japanese Traditional Eco Style) ECO Design for UNHAS-FE
Sunshade + Natural Ventilation
(Double Skin)
SUDARE
GRC-louver
Natural Lighting
TORINIWA
ATRIUM
Cooling
NAKANIWA
GROVE
Eco Campus
• Save energy:East-West Axis, Natural ventilation , Natural lighting , Solar shading
• Use Natural Energy (Solar Panel)• Bicycle Network:
To encourage the use of bicycles, rent-free-bicycle is recommended to promote the use of bicycles.
East-West Axis
Natural ventilation
• The Atrium provides excellent ventilation by chimney effect which exhausts hotter air from inside and intakes colder air from outside through outside windows facing towards the atrium.
Reduction of heat load & Natural lighting
• The heat load of the building is reduced by solar shading
• The building is planned to utilize atrium to reduce daytime illumination load using natural lighting in all occupied rooms.
Solar Shading & Natural lighting
Green Campus
The landscape concepts are to make the modern technological campus more green and shaded as well as a good environmental system by increasing the planting species and conserving rare plants and indigenous plants of Sulawesi Island.
Green Campus
Green Campus
Package- 1 Detailed Design
1. Building’s Room Layout Feature
1) Research room Unit: Prof, AP, Assist, Graduate,
Meeting
2) Laboratory: Experimentation, Laborant
3) Design Studio
(1) Architecture Department (9,422㎡ )
GF
1F
2F
3F
Meeting Graduate S AP
Ass P
1. Building’s Room Layout Feature
1) 2-stories Laboratory: Lower floor for experiment
Upper floor for staff room
2) Professor room
3) Research room (capacity 26 or 14)
(2) Civil Engineering Department (8,248 ㎡ )
GF
1F
2F
3F
Professor x 18 room
1. Building’s Room Layout Feature
1) 2-stairs and wide corridor
2) 2 classroom special designed with LCD
3) Basic Science Laboratory
(3) Classroom Building (11,701 ㎡ )
with LCD
2-Stairs
W=3.6m
Basic Science Lab
GF
1F
1. Building’s Room Layout Feature
1) 2 Entrance at Ground Floor: for Pedestrian and Vehicle user (with 8 Parking Space) 2) Common space: Entrance hall,
Reception, security, mushola,pantry, garden, etc
3) Dean Floor with Special design 4) Showcase: GF-3F for Dep., 4F for
Dean
(4) COT Building (6,925 ㎡ )
2 Entrance
GF
4F
ReceptionSecurity
Dean Area
Dean Hall
1. Building’s Room Layout Feature
1) General entrance and service access
2) Complex: Clear zone division
3) Library: Security systemo
4) Lecture Theater: Acoustic and special
design
(5) Library Building (6,829 ㎡ )
1F
4F
Security
Lecture Theater
Library ImageLecture Theater Image
2. Elevation 1/ ConceptThe UNHAS-FE Campus is
projected an appropriate identity and image of "futuristic and traditional". And also the department laboratory buildings are being created so as to have a special identity of them own. The components of these design policies will create an attractive campus with an identity and a sense of unity.
2. Elevation 2/ Building Identity
Architecture Department: Traditional style of Gowa such as Independent Column and Tower
Civil Engineering Department: Dynamic Structure, Strength COT and Library : “Entrance Gate”.
Department
COT & Library
COT and Library make ‘GATE’
Phasing Program
Development Phasing Schedule
Packaging (JBIC Yen Loan Portion)
Implementation Schedule (Local Government Portion)
2008: Demolition of PKG (“1.5 months behind” up to today) Delay of demolition will influence implementation schedule 2009: Completion of Inner Campus Road,
Parking, Landscaping 2010: Completion of Auditorium, Student
Center, Sport Hall, Canteen, Parking, Landscaping
2011: Completion of Outdoor Sport Facilities, Parking, Landscaping
2012~: Completion of Dormitory for Students, Hostel for Lecturers, Mosque, etc.
Package-1 Bidding Schedule
June 18: PQ Announcement July 29: PQ Application submission Aug 2008: P/Q result concurrence by JBIC Sep 2008: Bidding Documents concurrence by
JBIC Sep 2008: Distribution of Bidding Documents Sep 2008: Pre-bid Meeting & Site Visit Nov 2008: Submission of Proposal Dec 2008: Financial Proposal Opening Jan 2009: Notice of Award Jan 2009: Contract Signing Jan 2009: Construction Starting Ceremony
1 2 3 4 5 6 7 8 9 # # # 1 2 3 4 5 6 7 8 9 # # # 1 2 3 4 5 6 7 8 9 # # # 1 2 3 4 5 6 7 8 9 # # # 1 2 3 4 5 6 7 8 9 # # #
PREPARATION OF IMPLEMENTATION1 Land aqucition Feb-06 Ok2 Demobilisation of Ex. PKG by the End of 2007 (not yet)3 Selection of Fellowship Candidate Batch I Nov 2007 - Feb 2008 Ok3 Consultant Selection for PMC May - Dec 2007 Ok4 Consultant Selection for Fellowship Consultant June 2007 - Jan 2008 Ok
DESIGN STAGES1 Detailed Design Development Stage Jan - Dec 2008 Started
Pre-design including Master Plan Jan - Jun 2008 Finished DD-01 Preliminary Design (P-1) Feb - Apr 2008 Finished DD-02 Detailed Design (P-1) Apr - Jul 2008 On-going DD-03 Preliminary Design (P-2 & P-3) DD-04 Detailed Design (P-2 & P-3) DD-05 Preliminary and Detailed Design (P-4) Apr - Sept 2008 On-going DD-06
2 Procurement and Contracts Stage Marc 2008 - Dec 2009 Started Pre-qualifications Jun - Aug 2008 On-going PC-01 JBIC Concurrence on Pre-qualifications PC-02 Preparation of Bidding Documents Jun - Jul 2008 On-going PC-03 JBIC Concurrence on Bidding Documents PC-04 Bid Period PC-05 Evaluation of Bids PC-06 JBIC Concurrence on Bid Evaluation Results PC-07 Contract Negotiations PC-08 JBIC Concurrence on Contracts PC-09 Signing on Contracts PC-10 L/C Opening, L/Com Effectuate PC-11
CONSTRUCTION STAGES (Not yet)3 Building Construction Supervision Stage Jan 2009 - May 2011
Package-1 SV-01 Mobilization and Preparation Works SV-01-01 Shop Drawings Review & Approval SV-01-02 Construction of Dean Office, Center of Technology, SV-01-03 Construction of Library, Central Computer, Lecturer Theater SV-01-04 Construction of Classroom and Laboratory for Basic Science SV-01-05 Architecture and Civil Department Buildings SV-01-07 Supply of Equipment SV-01-08 Supply of Furniture SV-01-09 Defects Liability Period SV-01-10
Package-2 SV-02 Mobilization and Preparation Works SV-02-01 Shop Drawings Review & Approval SV-02-02 Electrical and Mechanical Department Buildings SV-02-03 Supply of Equipment SV-02-04 Supply of Furniture SV-02-05 Defects Liability Period SV-02-06
Package-3 SV-03 Mobilization and Preparation Works SV-03-01 Shop Drawings Review & Approval SV-03-02 Naval and Geology Department Buildings SV-03-03 Supply of Equipment SV-03-04 Supply of Furniture SV-03-05 Defects Liability Period SV-03-06
Package-4-1 SV-04 Procurement and Conracts Stage (LCB) PC-01~11 Mobilization and Preparation Works SV-04-01 Shop Drawings Review & Approval SV-04-02 Construction of Workshop SV-01-06 Electrical Power Supply Works SV-04-03 Water Supply Works SV-04-04 Drainage Works SV-04-05 Defects Liability Period SV-04-11
Package-4-2 Procurement and Conracts Stage (LCB) PC-01~11 Mobilization and Preparation Works SV-04-01 Shop Drawings Review & Approval SV-04-02 Electrical Power Supply Works SV-04-03 Water Supply Works SV-04-04 Drainage Works SV-04-05 Defects Liability Period SV-04-11
Critical Points
IMPLEMENTATION SCHEDULE
DESCRIPTION OF SERVICE / WORK Date Action Code No.2008 2009 2010 2011 2012
Implementation Schedule (JBIC Yen Loan Portion)
2008: Campus Master Plan, Preliminary Design, Detailed Design and Tendering
2009: Completion of Center of Technology, Library and Classroom Buildings, Power supply, Water supply, Drainage
2010: Completion of Architecture Dept., Civil Dept., Electrical Dept. and Mechanical Dept. Buildings
2011: Completion of Naval Architecture Dept. and Geology Dept. Buildings