HARYANA POWER SECTOR AN OVERVIEW - … POWER SECTOR AN OVERVIEW Haryana became the first fully...

24
HARYANA POWER SECTOR AN OVERVIEW ! ! ! ! ! ! ! ! ! ! Haryana became the first fully electrified State in November 1970. Generation capacity increased to 4072.30 MW in 2007 from 343 MW in 1967. Sub-Stations have increased to 560 in 2007 from 47 in 1967. Transmission and Distribution lines have increased to about 195000 KMs in 2007 from about 1800 KMs in 1967. Connected load has increased to 11693 MW in 2007 from 372 MW in the year 1967. Number of consumers increased to more than 41 lac in 2007 from about 3 lac in 1967. State has the maximum density of Agriculture tubewells in the country i.e. 10 tubewells per square Km area and has 475000 tubewells in 2007 compared to 20190 in 1967. About 50% of available power is provided to rural sector against national average of 26%. Average daily availability of power has increased to 665 LUs per day in 2007 from about 18 LUs per day in 1967. Per capita consumption of electricity has increased to 660 Units in 2007 from 57 Units in 1967. ! ! ! ! ! ! ! ! ! ! Haryana became the in November 1970. increased to in 2007 from in 1967. have increased to in 2007 from in 1967. have increased to about in 2007 from about in 1967. has increased to in 2007 from in the year 1967. increased to more than 41 lac in 2007 from about 3 lac in 1967. State has the maximum in the country i.e. 10 tubewells per square Km area and has tubewells in 2007 compared to in 1967. About of available power is provided to rural sector against national average of of power has increased to per day in 2007 from about per day in 1967. of electricity has increased to in 2007 from in 1967. first fully electrified State Generation capacity 4072.30 MW 343 MW Sub-Stations 560 47 Transmission and Distribution lines 195000 KMs 1800 KMs Connected load 11693 MW 372 MW Number of consumers density of Agriculture tubewells 475000 20190 50% 26%. Average daily availability 665 LUs 18 LUs Per capita consumption 660 Units 57 Units

Transcript of HARYANA POWER SECTOR AN OVERVIEW - … POWER SECTOR AN OVERVIEW Haryana became the first fully...

HARYANA POWER SECTORAN OVERVIEW

Haryana became the first fully electrified State in

November 1970.Generation capacity increased to 4072.30 MW in

2007 from 343 MW in 1967.Sub-Stations have increased to 560 in 2007 from

47 in 1967.Transmission and Distribution lines have

increased to about 195000 KMs in 2007 from

about 1800 KMs in 1967.Connected load has increased to 11693 MW in

2007 from 372 MW in the year 1967.Number of consumers increased to more than 41

lac in 2007 from about 3 lac in 1967.State has the maximum density of Agriculture

tubewells in the country i.e. 10 tubewells per

square Km area and has 475000 tubewells in 2007

compared to 20190 in 1967.About 50% of available power is provided to rural

sector against national average of 26%.Average daily availability of power has increased

to 665 LUs per day in 2007 from about 18 LUs per

day in 1967.Per capita consumption of electricity has

increased to 660 Units in 2007 from 57 Units in

1967.

Haryana became the in

November 1970.increased to in

2007 from in 1967.have increased to in 2007 from

in 1967.have

increased to about in 2007 from

about in 1967.has increased to in

2007 from in the year 1967.increased to more than 41

lac in 2007 from about 3 lac in 1967.State has the maximum

in the country i.e. 10 tubewells per

square Km area and has tubewells in 2007

compared to in 1967.About of available power is provided to rural

sector against national average ofof power has increased

to per day in 2007 from about per

day in 1967.of electricity has

increased to in 2007 from in

1967.

first fully electrified State

Generation capacity 4072.30 MW

343 MWSub-Stations 560

47Transmission and Distribution lines

195000 KMs

1800 KMsConnected load 11693 MW

372 MWNumber of consumers

density of Agriculture

tubewells

475000

2019050%

26%.Average daily availability

665 LUs 18 LUs

Per capita consumption

660 Units 57 Units

THE REFORM PATH�

Haryana was a pioneer in the

power sector reforms in the

country.

Unbundling of Haryana State

Electricity Board in August

1998.

Regulatory commission formed

inAugust 1998.

B i j l i L o k p a l , c o n s u m e r

grievances redressal fora

appointed.

Special courts notified for

power theft cases.

Setting up of Customer care

centers and Bijli Suvidha

Kendras to improve consumer

interface.

OpenAccess introduced.

Haryana was a

in the

country.

of Haryana State

Electricity Board in August

formed

inAugust

B i j l i L o k p a l , c o n s u m e r

grievances redressal fora

appointed.

for

power theft cases.

Setting up of

and

to improve consumer

interface.

introduced.

pioneer in the

power sector reforms

Unbundling

1998.

Regulatory commission

1998.

Special courts notified

Customer care

centers Bijli Suvidha

Kendras

OpenAccess

PERFORMANCE IMPROVEMENT ANDOPERATIONAL EFFICIENCY-GENERATION

HIGHLIGHTS OF PERFORMANCE

DURING THE YEAR

2006-07

• HIGHEST ANNUAL PLF OF 78.78% SINCE

FORMATION OF HPGCL.

• HIGHEST ANNUAL PLF OF 91.09% FOR 210/ 250

MW UNITS, PTPS, PANIPAT.

• LOWEST AUXILIARY CONSUMPTION OF 9.80%

SINCE FORMATION OF HPGCL.

• LOWEST SPECIFIC COAL CONSUMPTION OF 721

gm PER UNIT SINCE FORMATIOIN OF HPGCL.

• LOWEST SPECIFIC OIL CONSUMPTION OF 1.85 ml

PER UNIT SINCE FORMATION OF HPGCL.

HIGHLIGHTS OF PERFORMANCE

DURING THE YEAR

2006-07

• HIGHEST ANNUAL SINCE

FORMATION OF HPGCL.

• HIGHEST ANNUAL FOR 210/ 250

MW UNITS, PTPS, PANIPAT.

• LOWEST AUXILIARY CONSUMPTION OF

SINCE FORMATION OF HPGCL.

• LOWEST SPECIFIC COAL CONSUMPTION OF

PER UNIT SINCE FORMATIOIN OF HPGCL.

• LOWEST SPECIFIC OIL CONSUMPTION OF

PER UNIT SINCE FORMATION OF HPGCL.

PLF OF 78.78%

PLF OF 91.09%

9.80%

721

gm

1.85 ml

Parameters 2000-01 2006-07

Installed Capacity (MW) 863.30 1587.40

Generation (MUs) 3792 10780

Plant Load Factor (%) 49.73 78.78

Auxiliary Consumption (%) 11.80 9.80

Coal Consumption 816 721

(gms/kwh)

Oil Consumption 5.97 1.85

(ml/kwh)

Parameters 2000-01 2006-07

Installed Capacity (MW) 863.30 1587.40

Generation (MUs) 3792 10780

Plant Load Factor (%) 49.73 78.78

Auxiliary Consumption (%) 11.80 9.80

Coal Consumption 816 721

(gms/kwh)

Oil Consumption 5.97 1.85

(ml/kwh)

PERFORMANCE IMPROVEMENT ANDOPERATIONAL EFFICIENCY-TRANSMISSION�

DURING THE LAST 2 YEARS 42

NEW SUB-STATIONS WERE

COMMISSIONED 139 EXISTING

SUB-STATIONS AUGMENTED

AND 913 KM TRANSMISSION

LINES CONSTRUCTED BY

ADDING 2082 MVA CAPACITY

WITH AN INVESTMENT OF Rs.

340 CRORE.

TOTAL TRANSMISSION LOSSES

REDUCED FROM 5.91 % IN 2002

TO 4.83 % IN THE YEAR 2007.

INTRA STATE TRANSMISSION

LOSSES REDUCED FROM 4.11 %

IN 2002 TO 2.95 % IN 2007.

T R A N S M I S S I O N S Y S T E M

AVAILABILITY 99.62% IN 2006-07.

,

DURING THE LAST 2 YEARS

NEW SUB-STATIONS WERE

COMMISSIONED EXISTING

SUB-STATIONS AUGMENTED

AND KM TRANSMISSION

LINES CONSTRUCTED BY

ADDING MVA CAPACITY

WITH AN INVESTMENT OF Rs.

CRORE.

TOTAL TRANSMISSION LOSSES

REDUCED FROM IN 2002

TO IN THE YEAR 2007.

INTRA STATE TRANSMISSION

LOSSES REDUCED FROM

IN 2002 TO IN 2007.

T R A N S M I S S I O N S Y S T E M

AVAILABILITY IN 2006-07.

,

42

139

913

2082

340

5.91 %

4.83 %

4.11 %

2.95 %

99.62%

INITIATIVES TO REDUCE TECHNICAL &COMMERCIAL LOSSES-DISTRIBUTION

TECHNICAL LOSSESTECHNICAL LOSSES

IMPROVEMENT IN HT/LT RATIO AND SYSTEM TO

MATCH LOAD REQUIREMENTS.

DT METERING TO ENSURE ENERGYAUDIT.

IMPLEMENTATION OF HVDS.

INTRODUCTION OF AMORPHOUS CORE

DISTRIBUTIONTRANSFORMERS.

SEGREGATION OF RURAL DOMESTIC LOAD FROM

AGRICULTURE LOAD.

INSTALLATION OF CAPACITORS.

FEEDER WISE DEPLOYMENT OF STAFF.

REPLACEMENT OF BARE CONDUCTOR WITH ABC

CABLES/ARMOURED CABLE.

IMPROVEMENT IN HT/LT RATIO AND SYSTEM TO

MATCH LOAD REQUIREMENTS.

DT METERING TO ENSURE

IMPLEMENTATION OF

INTRODUCTION OF AMORPHOUS CORE

DISTRIBUTIONTRANSFORMERS.

OF RURAL DOMESTIC LOAD FROM

AGRICULTURE LOAD.

INSTALLATION OF CAPACITORS.

FEEDER WISE DEPLOYMENT OF STAFF.

REPLACEMENT OF BARE CONDUCTOR WITH ABC

CABLES/ARMOURED CABLE.

ENERGYAUDIT.

HVDS.

SEGREGATION

COMMERCIAL LOSSESCOMMERCIAL LOSSES

CHECKING OF CONSUMER PREMISES.

REGULARIZATION OF KUNDI CONNECTIONS.

METER SEALINGAND CALIBRATION.

DISCONNECTION OF DEFAULTING CONSUMERS.

VOLUNTARY DISCLOSURE SCHEME.

SHIFTING OF METERS OUTSIDE CONSUMER

PREMISES.

IMPROVING CONSUMER INTERFACE.

SPOT BILLING.

MULTI MODAL BILL COLLECTION FACILITY.

MONITORING LARGE CONSUMERS.

CHECKING OF

REGULARIZATION OF KUNDI CONNECTIONS.

METER SEALINGAND CALIBRATION.

DISCONNECTION OF DEFAULTING CONSUMERS.

VOLUNTARY DISCLOSURE SCHEME.

OUTSIDE CONSUMER

PREMISES.

IMPROVING CONSUMER INTERFACE.

MULTI MODAL BILL COLLECTION FACILITY.

MONITORING LARGE CONSUMERS.

CONSUMER PREMISES.

SHIFTING OF METERS

SPOT BILLING.

FIRST CFL VILLAGE OF HARYANABINOLA IN DISTT. GURGAON

• Load reduced to half during peakload hours.Deficiencies of distribution system automatically removed.Both transformers now have spare capacity.

••

700 Compact Fluorescent Lamps have been

provided in 98 houses to replace inefficient

incandescent bulbs.

Load has reduced to 50% during peakload

hours.

Binola has two distribution transformers for

power supply. After providing CFL, load on one

transformer has reduced from 120 Ampere to 70

Ampere and on the other from 98 Ampere to 48

Ampere.

The incidence of interruption in power supply

due to blowing off of fuses, damage of

transformer, and system contraints has been

reduced.

Voltage profile in all the three phases of both the

transformers is optimal, leading to quality

supply.

After the present load is met, capacity in the two

transformers is now available for new

connections.

CFL use in the households has reduced the

energy bills of the households.

700 Compact Fluorescent Lamps

Load has reduced to 50%

load

reduced from 120 Ampere to 70

Ampere from 98 Ampere to 48

Ampere

interruption in power supply

reduced

Voltage profile

optimal

capacity

now available

CFL use reduced the

energy bills

have been

provided in 98 houses to replace inefficient

incandescent bulbs.

during peakload

hours.

Binola has two distribution transformers for

power supply. After providing CFL, on one

transformer has

and on the other

.

The incidence of

due to blowing off of fuses, damage of

transformer, and system contraints has been

.

in all the three phases of both the

transformers is , leading to quality

supply.

After the present load is met, in the two

transformers is for new

connections.

in the households has

of the households.

FIRST ‘LVDS’ AND ‘CFL’ VILLAGE OF HARYANADHANI SANKRI DISTT. HISAR

ANALYSIS OF FOUR TRANSFORMERSINSTALLED IN THE VILLAGE

• 100% metering and 100% connection in the whole village• Uninterrupted power supply to the villagersduring predetermined hours

• Almost negligible complaints of power supply• Additional capacity on transformers became available• Distribution system became safe and reliable

.

..

..

• 100% metering and 100% connection in the whole village• Uninterrupted power supply to the villagersduring predetermined hours

• Almost negligible complaints of power supply• Additional capacity on transformers became available• Distribution system became safe and reliable

.

..

..

IMPROVEMENT IN POWER SUPPLYIMPROVEMENT IN POWER SUPPLY

LOADING POSITION (3 MONTHS DATA)LOADING POSITION (3 MONTHS DATA)

ParticularsParticulars

65 Amp65 Amp 62 Amp62 Amp 32 Amp32 Amp 33 Amp33 Amp

INNOVATIVE SCHEME FOR SETTLEMENT OFRURAL ELECTRICITY ARREARS

Govt. of Haryana announced thescheme for settlement of arrears ofrural domestic and agriculturalconsumers w.e.f 17.06.2005.Defaulting consumers given anopportunity to get their outstandingdues waived by regularly paying theircurrent electricity bills for a period of20 months.Out o f 13 .87 lac de fau l t ingconsumers, 9.2 lac consumers joinedthe scheme.88.2 % of defaulting agriculturalconsumers and 62% of defaultingdomestic consumers have returned tothe mainstream and become payingconsumers.Total amount frozen for the waiver isRs. 1206.18 crore*.The current dues recovered areRs.333.79 crore.

Govt. of Haryana announced thescheme for ofrural domestic and agriculturalconsumers .Defaulting consumers given anopportunity to get their

by regularly paying theircurrent electricity bills for a period of20 months.Out o f de fau l t ingconsumers,the scheme.

of defaultingand of defaulting

haveand become paying

consumers.Total for the waiver is

The are

settlement of arrears

w.e.f 17.06.2005

outstandingdues waived

13 .87 lac9.2 lac consumers joined

88.2 % agriculturalconsumers 62%domestic consumers returned tothe mainstream

amount frozenRs. 1206.18 crore*.

current dues recoveredRs.333.79 crore.

* As on 28.02.2007

PROJECTED LOAD GROWTHIN HARYANA

Year 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12

Projected Demand(MW) with 14%Growth

4951(base)

5644 6434 7335 8362 9533 10867

4951

5644

6434

7335

8362

9533

10867

PROJECTED CAPACITY AVAILABLILITY (MW)Year 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12

EXISTING CAPACITY

PROPOSED CAPACITY

State Owned 1587.40 1587.40 1587.40 1587.40 1587.40 1587.40 1587.40

Projects

Central sector 1514.40

& others

BBMB & IP 937.50

1514.40 1514.40 1514.40 1514.40 1514.40 1514.40

937.50 937.50 937.50 937.50 937.50 937.50

DCRTPP, 600 600 600 600 600

Yamuna Nagar

Hisar TPS 1100 1100 1100

Jhajjar Case-2 1150 1150

Aravali STPS, 750 750

Jhajjar

Faridabad Gas 432 432

Yamuna Nagar 300

Extn.

Additional 12 204 455 994 1231 2867

availability

through

PPA with

IPPs' CPSU

Total Capacity 4039.30 4051.30 4843.30 5094.30 6733.30 9302.30 11238.30

(MW)

LOAD & CAPACITY GROWTH(MW) CURVE

9302

9533

Demand with 14% Annual Growth

MW

11 FIVE YEAR PLAN INVESTMENTSTH

PROJECTS/SCHEMES

Generation

New Generation Projects

Renovation & Modernisation

Other Works

Total Generation

Transmission

Construction of 6 No. 400KV, 34 No. 220KV, 46 No. 132KV and 46 No. 66KV New Sub Stations

Augmentation of Existing Sub Stations

SLDC

Total Transmission

Distribution

773..19

2203.45

1946.45

1654.00

6577.09

24316.82

New 33 KV S/Stn., Aug. of 33 KV S/Stn., New 33 KV Lines and HT Capacitors.

Bi/Trifurcation of 11 KV Feeders, Aug. and addition of new DTs alongwith

11 KV and LT lines, Aug. of 11 KV and LT lines, strengthening of Dist. system

under RGGVY, providing AB cables, NABARD works and APDRP works

Segregeration of Rural domestic load from rural agriculture load, Providing

HVDS/LVDS, Providing Area Load Despatch Centre, Consumers metering,

DT metering, Feeders Metering, prepaid metering.

Demand side management activities

Total Distribution

Grand Total (Generation + Transmission + Distribution)

Amount(Rs. Crore)

9272.91

769.10

25.80

10042.01

7207.72

290.00

200.00

7697.72

Govt. of Haryana will provide equity support of Rs. 4687 crore

GENERATION CAPACITY ADDITIONPROGRAMME IN THE STATE

DURING 11 PLAN (2007-12)th

Sr.No.Sr.No. Name of ProjectName of Project Capacity in MWCapacity in MW CommissioningSchedule

CommissioningSchedule

1.1.

2.2.

3.3.

4.4.

5.5.

Deenbandhu Chootu RamThermal Power ProjectDeenbandhu Chootu RamThermal Power Project

Hisar Thermal Power ProjectHisar Thermal Power Project

Aravali Super Thermal PowerProject, Jhajjar (JV betweenNTPC, Delhi & Haryana)

Aravali Super Thermal PowerProject, Jhajjar (JV betweenNTPC, Delhi & Haryana)

Jhajjar Thermal PowerProject (Case-2)Jhajjar Thermal PowerProject (Case-2)

Yamuna Nagar ExtensionYamuna Nagar Extension

TOTAL CAPACITY ADDITIONTOTAL CAPACITY ADDITION

2×300 MW2×300 MW

2×600 MW2×600 MW

3×500 MW(Haryana Share750 MW)

3×500 MW(Haryana Share750 MW)

1150 MW1150 MW

300 MW300 MW

4000 MW4000 MW

2011-122011-12

2010-112010-11

Unit-I : 19.11.2007Unit-II : 19.02.2008Unit-I : 19.11.2007Unit-II : 19.02.2008

Unit-I : 28.12.2009Unit-II : 28.03.2010Unit-I : 28.12.2009Unit-II : 28.03.2010

Unit-I : 15.04.2010Unit-II : 15.06.2010Unit-III : 15.08.2010

Unit-I : 15.04.2010Unit-II : 15.06.2010Unit-III : 15.08.2010

PROCUREMENT OF POWER THROUGHTARIFF BASED COMPETITIVE BIDDING

UNDER CASE-1 AND CASE-2CASE-1

• TARIFF BASED COMPETITIVE BIDS

INVITED FOR 2000 MW POWER.

• 14 BIDDERS QUALIFIED.

• PROCESS OF CONSULTATION ON

F O R F I N A L I S AT I O N O F R F P

DOCUMENTS.

• LIKELY AVAILABILITY OF POWER

FROM THE PROJECTS : 2010-11

ONWARDS.

CASE-2

• TARIFF BASED COMPETITIVE BIDS

INVITED FOR SETTING UP A 1150 ±

15% MW COAL BASED PROJECT AT

JHAJJAR.

• 19 BIDS IN RESPONSE TO RFQ ARE

BEING EXAMINED.

• LIKELY AVAILABILITY OF POWER

FROMTHEPROJECT:DURING2010-11.

CASE-1

CASE-2

• TARIFF BASED COMPETITIVE BIDS

INVITED FOR 2000 MW POWER.

• 14 BIDDERS QUALIFIED.

• PROCESS OF CONSULTATION ON

F O R F I N A L I S AT I O N O F R F P

DOCUMENTS.

• LIKELY AVAILABILITY OF POWER

FROM THE PROJECTS : 2010-11

ONWARDS.

• TARIFF BASED COMPETITIVE BIDS

INVITED FOR SETTING UP A 1150 ±

15% MW COAL BASED PROJECT AT

JHAJJAR.

• 19 BIDS IN RESPONSE TO RFQ ARE

BEING EXAMINED.

• LIKELY AVAILABILITY OF POWER

FROMTHEPROJECT:DURING2010-11.

SALIENT FEATURES OF DEENBANDHUCHHOTU RAM THERMAL

POWER PROJECT, YAMUNA NAGAR

Rs. 2400 CRORERs. 2400 CRORE

YAMUNA NAGAR

PROJECT SCHEDULE - Unit-2

YAMUNA NAGAR

PROJECT SCHEDULE - Unit-1

SALIENT FEATURES OFARAVALI SUPER THERMAL

POWER PROJECT, JHAJJAR

Rs.Rs.

SALIENT FEATURES OF HISARTHERMAL POWER PROJECT

Rs.Rs.

**

**

BEST EFFORT SCHEDULEBEST EFFORT SCHEDULE

MILESTONE CHART FOR HISAR THERMAL POWER PROJECTS.No.S.No. MILESTONEMILESTONE UNIT-IUNIT-I UNIT-IIUNIT-II

PLANPLAN ACTUALACTUAL PLANPLAN ACTUALACTUAL

11 Zero DateZero Date 29.01.200729.01.2007 29.01.200729.01.2007

22 Soil Investigation Commencement(Common for Both Units)Soil Investigation Commencement(Common for Both Units)

02.02.200702.02.200702.02.200702.02.2007 02.02.200702.02.2007 02.02.200702.02.2007

33 Test Piling (Common for Both Units)Test Piling (Common for Both Units) 19.05.200719.05.200716.05.200716.05.2007 19.05.200719.05.200716.05.200716.05.2007

44 Working Pile CommencementWorking Pile Commencement 16.07.200716.07.2007 16.10.200716.10.2007

55 Boiler Election StartBoiler Election Start 01.02.200801.02.2008 01.05.200801.05.2008

66 Boiler Drum LiftingBoiler Drum Lifting 28.08.200828.08.2008 28.11.200828.11.2008

77 TG Erection StartTG Erection Start 01.12.200801.12.2008 01.03.200901.03.2009

88 Boiler Hydro TestBoiler Hydro Test 28.05.200928.05.2009 28.08.200928.08.2009

99 Turbine Box UpTurbine Box Up 15.09.200915.09.2009 15.12.200915.12.2009

1010 Boiler Light UpBoiler Light Up 01.10.200901.10.2009 01.01.201001.01.2010

1111 TG on Barring GearTG on Barring Gear 16.11.200916.11.2009 16.02.201016.02.2010

1212 SynchronizationSynchronization 28.11.200928.11.2009 28.02.201028.02.2010

1313 Commissioning/Provisional Taking overCommissioning/Provisional Taking over 28.12.200928.12.2009 28.03.201028.03.2010

HARYANA’S FIRST CFL FEEDERBHUNA

(DISTT. SIRSA)INFORMATION

Name of Villages on the feeder :Total number of consumers : 1250Total number of CFLs used : 5760Length of feeder : 18 kilometres

• Bhuna, Chakka, Gidara and Ghoranwali•••

BENEFITS OF INSTALLATION OF CFLSi. Load reduced to 50% during peak load hours.ii. All the 12 transformers have, now, spare capacity.iii. Complaints of interruptions in supply reduced considerably.iv. Increase in redundancy of the system.v. Sustainability of techno-economic system.vi. Stability of load.vii. Reduction in line losses.

Date

1

3

5

7

9

11

13

15

17

2

4

6

8

10

12

14

16

18

01.05.06

02.05.06

03.05.06

04.05.06

05.05.06

06.05.06

07.05.06

08.05.06

09.05.06

01.05.07

02.05.07

03.05.07

04.05.07

05.05.07

06.05.07

07.05.07

08.05.07

09.05.07

19.00. Hrs.

100

160

100

110

120

120

135

150

145

70

70

85

50

70

40

100

70

50

20.00 Hrs

110

160

120

110

120

120

100

130

125

60

90

80

100

60

80

80

60

80

21.00 Hrs.

100

160

120

110

120

120

100

130

125

60

60

60

70

60

60

90

60

70

Load in Amps

REDUCTION IN LOAD PATTERN COMPARED TO 2006

BEE Refrigerator Label

The Stars highlighted in color indicate therelative efficiency of the Refrigerator.More the savings in Energy and Money

This is the average amount of electricityused by the refrigerator in a year.

This is under standard testconditions, your energy use may varydepending on actual usage.

Addit ional information about therefrigerator:The Brand, Type, Model number, Year ofManufacture and the Volume.

is the total spaceenclosed within the refrigerator.

is the actual spaceavailable

(in kWhper year)

(See Energy Saving Tips on the backpage)

Gross volume

Storage volume

BEE E L RNERGY ABEL FOR EFRIGERATORS

• Refrigerator is likely to be one of the largest single power consumer in your home.Refrigerator efficiency has made enormous strides in the past few years. The most efficientmodels available today are significantly more energy efficient, and still improving. Thetypical refrigerator has a life span of 15 to 20 years. The cost of running over that timeperiod will easily be several times the initial purchase price, so paying somewhat moreinitially for higher efficiency offers a solid payback.

When you buy a new refrigerator, buy the most efficient model available. A listing ofenergy efficient appliances can be found at the Bureau of Energy Efficiency's website -

&

Smaller models will obviously use less energy than larger models. Generally, the largerthe refrigerator, the greater the energy consumption. Don't buy a refrigerator that's larger than you need. But onelarge refrigerator will use less energy than two smaller ones with the same total volume.

Models with top- or bottom-mounted freezers average 12% less energy use than side-by-side designs.

Features like through-the-door ice, chilled water, or automatic ice-makers increase the energy consumption,purchase price and also greatly increase energy use and are far more likely to need service and repair.Avoid thesecostly, troublesome options.

Be willing to pay a bit more initially for lower operating costs. A five-star refrigerator that costs more initially, but costs less per year tooperate due to better construction and insulation, will pay for itself in less than four years compared to a two-star refrigerator.

Recycle older or second refrigerators. Don't keep the old, inefficient refrigerator running in the occasional refreshments. It could costyou significantly more per year in electricity.

www.bee-nic.in www.energymanagertraning.com

BEE Refrigerator Label

The Stars highlighted in color indicate the relative efficiency of theRefrigerator. More the savings in Energy and Money

This is the average amount of electricity used by the refrigerator in a year.This is under standard test conditions, your energy use

may vary depending on actual usage.

Additional information about the refrigerator:

The Brand, Type, Model number, Year of Manufacture and the Volume.

is the total space enclosed within the refrigerator.

is the actual space available to you for use.

(in kWh per year)

(See Energy Saving Tips on the back page)

Gross volume

Storage volume

R E S TEFRIGERATOR NERGY AVING IPS

Setup

Operation

Maintenance

• Position your refrigerator away from a heat source such as an oven, a dishwasher, or direct sunlight from a window.• Leave at least 30 centimeters all around the refrigerator (or as recommended by the manufacturer) to allow air to circulate around the

refrigerator (condenser coils), and heat to escape from the compressor and condensing coil. If the heat can't escape, the refrigerator'scooling system will work harder and use more energy.

• Make sure the door seals are airtight. Check your refrigerator's door seal by closing the door on a clean piece of paper. If it's held tightlyin place, the seal's OK; if not, the door should be adjusted or the seal replaced. On fridges with magnetic seals, put a flashlight inside thefridge some evening, turn off the room lights, and check for light leaking through the seal. Replace the gasket if damaged.

• Allow hot foods to cool before putting them in the refrigerator.• Cover liquids and wrap foods stored in the fridge. Uncovered foods release moisture (and get dried out), which makes the compressor

work harder.• Don't set your refrigerator's temperature too low. The colder it gets the more it costs to run. Set the temperature for only as cold as you

need; check manufacturer's recommendations.• Don't overfill the refrigerator, as this blocks air circulation. Conversely, a full freezer will perform better than an empty one.• Minimize the amount of time the refrigerator door is open.• Open the fridge door as infrequently and briefly as possible to keep the cold air in. The more the door is opened, the more energy your

refrigerator will use.• Know what you're looking for when you open the refrigerator door. Open your fridge with a purpose. Do not spend time and waste

electricity by opening the refrigerator to browse through its contents.• Turn off the automatic ice maker. It's more efficient to make ice in ice trays.

• Clean your refrigerator's coils (back) and air intake grill (below the doors) every 3 months. When dust builds up on refrigerator'scondenser coils, the motor works harder and uses more electricity. With clean coils the waste heat is carried off faster, and the fridgeruns shorter cycles

• Don't let freezers build up more than 6 mm of frost. Defrost regularly to keep freezers working their best. (For Direct Cool Refrigerators)• Clean the door gasket and sealing surface on the fridge.• Check to see if you have a power-saving switch or a summer-winter switch. Many refrigerators have a small heater (yes, a heater!)

inside the walls to prevent condensation build-up on the fridge walls. If yours does, switch it to the power-saving (winter) mode.