Hartleys has assisted in the completion of capital ... · Hartleys Limited ABN 33 104 195 057 (AFSL...
Transcript of Hartleys has assisted in the completion of capital ... · Hartleys Limited ABN 33 104 195 057 (AFSL...
Page 1 of 8
Gascoyne Resources Ltd (GCY)
Gold
: D
evelo
per
/ E
xp
lore
r
GCY.asxSpeculative Buy
Share Price
Valuation $0.77
Price Target (12 month) $0.86
Brief Business Description:
Hartleys Brief Investment Conclusion
Chairman & MD
Top Shareholders
Board & Management 9.5%
Commonw ealth Bank of Australia 5.8%
Company Address
Issued Capital 433.8m
- fully diluted
Market Cap
- fully diluted
A$41.6m
A$20.0m
A$40.0m
EV
EV/Resource Au oz A$68/oz
EV/Reserve Au oz A$262/oz
Prelim. (A$m) FY17a FY18e FY19e
Prod (koz Au) 0.0 9.6 112.0
Op Cash Flw -2.3 -6.6 52.0
Norm NPAT -0.7 -15.2 61.4
CF/Share (cps) -0.7 -1.6 12.0
EPS (cps) -0.5 -2.9 10.9
P/E -90.6 -14.6 3.9
A u
Resources (Moz) 2.35
Reserves (Moz) 0.61
Mike Millikan
Resources Analyst
Ph: +61 8 9268 2805
West Perth, WA, 6005
WA gold developer & explorer focused on the
+1.3Moz Dalgaranga project and the +1Moz
Glenburgh project. Near-term gold producer.
Mike Joyce (Chairman)
8 Dec 2017
$0.420
Gold developer and explorer
Mike Dunbar (MD)
Level 1, 41-47 Colin Street
Hartleys has assisted in the completion of capital
raisings in the past 12 months for Gascoyne
Resources Limited ("Gascoyne"), for w hich it has
earned fees. Hartleys has also provided corporate
advice w ithin the past 12 months and continues to
provide corporate advice to Gascoyne, for w hich it
has earned fees and continues to earn fees.
441.6m
A$182.2m
A$185.5m
A$160.6m
Cash (31 Dec 17e)
Debt (31 Dec 17e)
Debt (undrawn)
GASCOYNE RESOURCES LTD (GCY)
Dalgaranga debt executed with construction on track The construction of the Dalgaranga gold project in the Murchison region of WA
remains on schedule and within budget, with GCY targeting first gold
production in Q2 CY18.
The Company recently completed a capital raise for A$21.5M to provide
additional working capital during the construction period and for regional
exploration, and has now executed a debt facility for A$60M.
The completion of the debt facility has taken longer than we had previously
anticipated but pleasingly the loan allows for early repayments, has assumed
low interest rates and some flexibility on the use of free cash generated during
the loan period. The term of the loan is 4.5 years and includes a hedging
obligation, both mandatory (~40koz for first 4 years) and discretionary. GCY
has already forward sold 82koz at an average gold price of A$1,660/oz,
providing floor protection to gold price (AUD) volatility and is ~13% of the
current mine plan.
Total pre-production capital costs for Dalgaranga is estimated at ~A$98M, with
the new debt facility to provide ~63% of funds and the balance from cash
reserves. We would estimate construction spend through to the end of
December to be ~A$48M and now forecast cash at CY17 end to be ~A$42M,
with debt of ~A$20M, as such a further ~A$50M is required to complete
construction. First debt drawdown has been flagged for mid December 2017.
We would estimate a cash position of ~A$22M and debt ~A$60M (net debt
A$38M) upon production, assuming normal admin and increased exploration
spend (A$4M/Q) in 1H CY18 and construction costs within or under budget.
Improved mine plan through Sly Fox addition The Dalgaranga mine plan has been updated by the addition of the Sly Fox
deposit. The mining inventory now contains 16.2Mt grading 1.3g/t Au for
652koz from Gilbeys, Golden Wings and Sly Fox, with 94% from reserves
(15.3Mt @ 1.25g/t Au for 612koz) and 6% from Inferred resources within the
pits (40koz @ 1.4g/t Au). We continue to assume a mine life in excess of 7
years.
The maiden Sly Fox reserve (26koz @ 1.3g/t Au) is considered interim, with
further growth anticipated as the deposit remains open. The upper parts of the
deposit are expected to be mined in the first 17 months of production,
providing additional oxide ores to lift throughput capacity in the early years
(from 2.5Mtpa towards 3Mtpa) and deferring some open pit waste movement
for improved capital payback. The increase in softer material in the early
production years is expected to lift annualised production with potential to
grow to +120koz from ~100koz in the first few years.
Construction progressing well for gold production Q2 CY18 Construction is progressing well at Dalgaranga with the site works currently
on schedule and within budget. NRW Holdings has been selected as the
preferred mining contractors for the open pit operation, which is expected to
commence in March 2018.
We maintain our Speculative Buy recommendation on GCY with a price target
of $0.86/s. Our GCY NAV is $0.77/s, and spot NAV is $0.81/s. With first gold
production targeted for Q2 CY18, the Company remains one of the best value
AUD gold developers on the ASX.
Hartleys Limited ABN 33 104 195 057 (AFSL 230052) 141 St Georges Terrace, Perth, Western Australia, 6000
Hartleys does and seeks to do business with companies covered in its research reports. As a result, investors should be aware that the
firm may have a conflict of interest that could affect the objectivity of this report. Investors should consider this report as only a single
factor in making their investment decision. Further information concerning Hartleys’ regulatory disclosures can be found on Hartleys
website www.hartleys.com.au
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
.
.5
1.
1.5
2.
2.5
3.
3.5
Dec-17Aug-17Apr-17Dec-16
Volume - RHS
GCY Shareprice - LHS
Sector (S&P/ASX SMALL RESOURCES) - LHS
A$ M
Gascoyne Res Ltd
Source: IRESS
Hartleys Limited Gascoyne Resources Limited (GCY) 8 December 2017
Page 2 of 8
SUMMARY MODEL
Gascoyne Res Ltd Share Price
GCY $0.420 Speculative Buy
Key Market Information Directors Company InformationShare Price $0.420 Mike Joyce (Chairman) Level 1, 41-47 Colin StreetMarket Capitalisation - ordinary A$182m Mike Dunbar (MD) West Perth, WA, 6005Net Cash (debt) $22m Ian Kerr (Executive Director) +61 8 9481 3434
Market Capitalisation - fully diluted A$182m Stan Macdonald (Non-Exec Director) +61 8 9481 0411
EV A$156m Graham Riley (Non-Exec Director) www.gascoynesources.com.au
Issued Capital 433.8m Gordan Dunbar (Non-Exec Director)Options 7.85m John den Dryver (Non-Exec Director) Peter Sperring (Registered Manager) Karl Webber (Exploration Man)Issued Capital (fully diluted inc. all options) 441.6m Sally-Anne Layman (Non-Exec Director) Julian Goldsworthy (Geology Manager) David Lim (CFO)Issued Capital (fully diluted inc. all options and new capital) 441.6m
Top Shareholders (est) m shares %Valuation $0.77 Board & Management 41.2 9.5%
12month price target $0.86 1 Commonwealth Bank of Australia 25.0 5.8%2
P&L Unit 30 Jun 15 30 Jun 16 30 Jun 17 30 Jun 18 30 Jun 19 3
Net Revenue A$m 0.1 0.1 0.0 15.6 194.7 4 Reserves & Resources Mt g/t Au KozTotal Costs A$m -3.4 -1.3 -3.1 -12.4 -123.6 5 TOTAL RESOURCE 52.6 1.4 2,347 EBITDA A$m -3.2 -1.2 -3.1 3.2 71.1 6 Measured 5.7 1.8 324 - margin - - - 21% 37% 7 Indicated 20.5 1.4 915 Depreciation/Amort A$m 0.0 0.0 0.0 -14.1 -21.8 8 Inferred 26.3 1.3 1,108
EBIT A$m -3.3 -1.2 -3.1 -10.9 49.3 9 Dalgaranga 31.1 1.3 1,320 Net Interest A$m 0.0 0.0 -0.1 -0.8 -2.1 Glenburgh 21.3 1.5 1,000 Pre-Tax Profit A$m -3.3 -1.2 -3.2 -11.7 47.2 10 Reserve 15.3 1.25 612 Tax Expense A$m 0.3 0.3 1.8 0.0 0.0 Mining Inventory 16.2 1.3 652 Normalised NPAT A$m -3.5 -1.0 -0.7 -15.2 61.4Abnormal Items A$m 0.6 0.1 -0.8 3.5 -14.2 Production Summary Unit Jun 15 Jun 16 Jun 17 Jun 18 Jun 19Reported Profit A$m -2.9 -0.9 -1.5 -11.7 47.2 Mill Throughput Mt 0.0 0.0 0.0 0.3 2.8Minority A$m 0 0 0 0 0 Mined grade g/t - - - 1.3 1.4Profit Attrib A$m -2.9 -0.9 -1.5 -11.7 47.2 Combined Recovery & Payability % 0% 0% 0% 92% 92%
Gold (koz) 0.0 0.0 0.0 9.6 112.0
Balance Sheet Unit 30 Jun 15 30 Jun 16 30 Jun 17 30 Jun 18 30 Jun 19 Gold Equiv (koz) 0.0 0.0 0.0 9.6 112.0
Cash A$m 1.2 14.9 41.8 22.1 49.2 M&I Resource Conversion (non-reserve) % 0.0% 0.0% 0.0% 69.3% 73.6%
Other Current Assets A$m 0.1 0.3 1.3 2.3 26.3 Mine Life yr 7.3 7.3 7.3 7.3 6.3
Total Current Assets A$m 1.3 15.1 43.1 24.5 75.4Property, Plant & Equip. A$m 0.0 0.0 18.6 91.0 71.3 Costs Unit Jun 15 Jun 16 Jun 17 Jun 18 Jun 19Exploration A$m 21.2 24.5 38.4 46.4 55.4 Cost per milled tonne $A/t - - - 40.0 40.0
Investments/other A$m 0.1 0.0 3.8 0.0 0.0 EBITDA / tonne milled ore $A/t - - - 12.8 25.4
Tot Non-Curr. Assets A$m 21.3 24.6 60.8 137.4 126.7 Total cash costs $A/oz - - - 1,288 1,104
Total Assets A$m 22.5 39.8 103.9 161.9 202.1 C1: Operating Cash Cost = (a) $A/oz - - - 1,040 1,000 (a) + Royalty = (b) $A/oz - - - 1,121 1,087
Short Term Borrowings A$m - - - - - C2: (a) + depreciation & amortisation = (c) $A/oz - - - 2,502 1,195
Other A$m 0.6 2.0 7.3 1.2 10.4 (a) + actual cash for development = (d) $A/oz - - - 1,872 1,099
Total Curr. Liabilities A$m 0.6 2.0 7.3 1.2 10.4 C3: (c) + Royalty $A/oz - - - 2,583 1,281
Long Term Borrowings A$m - - - 60.0 46.0 (d) + Royalty $A/oz - - - 1,953 1,185
Other A$m 0.0 0.0 0.5 0.4 0.4 All In Sustaining Costs (AISC) A$/oz - - - 2,253 1,289
Total Non-Curr. Liabil. A$m 0.0 0.0 0.5 60.4 46.4Total Liabilities A$m 0.7 2.1 7.8 61.6 56.7 Price Assumptions Unit Jun 15 Jun 16 Jun 17 Jun 18 Jun 19Net Assets A$m 21.9 37.7 96.1 100.3 145.4 AUDUSD A$/US$ 0.81 0.74 0.75 0.79 0.76Net Debt A$m -1.2 -14.9 -41.8 37.9 -3.2 Gold US$/oz 1187 1182 1239 1280 1325
Gold A$/oz 1473 1608 1643 1624 1738
Cashflow Unit 30 Jun 15 30 Jun 16 30 Jun 17 30 Jun 18 30 Jun 19 Hedging Jun 15 Jun 16 Jun 17 Jun 18 Jun 19Operating Cashflow A$m -0.3 -0.4 -2.5 -3.9 56.3 Hedges maturing? No No No No NoIncome Tax Paid A$m 0.0 0.0 0.0 0.0 0.0Interest & Other A$m 0.0 0.0 0.1 -2.8 -4.2 Sensitivity AnalysisOperating Activities A$m -0.3 -0.4 -2.3 -6.6 52.0 Valuation FY19 NPAT
Base Case 0.77 47.2Property, Plant & Equip. A$m 0.0 0.0 0.0 -86.5 -2.0 Spot Prices 0.81 (6.2%) 39.0 (-17.3%)Exploration and Devel. A$m -1.5 -2.6 -7.6 -8.0 -9.0 Spot USD/AUD 0.75, Gold $1248/oz.
Other A$m -0.1 0.0 -15.9 0.0 0.0 AUDUSD +/--10% 0.61 / 0.96 (-20.9% / 25.4%) 30.1 / 61.5 (-36.2% / 30.1%)
Investment Activities A$m -1.5 -2.6 -23.5 -94.5 -11.0 Gold +/--10% 0.94 / 0.59 (22.9% / -23.0%) 60.1 / 28.4 (27.2% / -39.8%)Production +/--10% 0.95 / 0.58 (23.9% / -24.0%) 60.7 / 27.5 (28.6% / -41.9%)
Borrowings A$m 0.0 0.0 0.0 60.0 -14.0 Operating Costs +/--10% 0.67 / 0.86 (-12.3% / 12.3%) 35.8 / 55.1 (-24.1% / 16.6%)Equity or "tbc capital" A$m 2.0 16.7 52.7 21.5 0.0Dividends Paid A$m 0.0 0.0 0.0 0.0 0.0 Unpaid CapitalFinancing Activities A$m 2.0 16.7 52.7 81.5 -14.0 Year Expires No. (m) $m Avg price % ord
30-Jun-17 0.0 0.0 0.00 0.0%
Net Cashflow A$m 0.2 13.7 26.9 -19.6 27.0 30-Jun-18 0.0 0.0 0.00 0.0%30-Jun-19 0.0 0.0 0.00 0.0%
Shares Unit 30 Jun 15 30 Jun 16 30 Jun 17 30 Jun 18 30 Jun 19 30-Jun-20 7.9 4.3 0.55 1.8%Ordinary Shares - End m 158.3 252.7 377.2 433.8 433.8 TOTAL 7.9 4.3 0.55 1.8%Ordinary Shares - Weighted m 158.3 205.5 314.9 405.5 433.8Diluted Shares - Weighted m 158.3 205.5 314.9 405.5 433.8 Share Price Valuation (NAV) Risked Est. A$m Est. A$/share
100% Dalgaranga (pre-tax NAV at disc. rate of 12%) 241.4 0.55
Ratio Analysis Unit 30 Jun 15 30 Jun 16 30 Jun 17 30 Jun 18 30 Jun 19 100% Glenburgh (pre-tax NAV at disc. rate of 14%) 90.7 0.21Cashflow Per Share A$ cps -0.2 -0.2 -0.7 -1.6 12.0 Other Exploration 75.0 0.17Cashflow Multiple x -201.8 -244.7 -57.3 -25.7 3.5 Corporate Overheads -10.3 -0.02Earnings Per Share A$ cps -1.8 -0.4 -0.5 -2.9 10.9 Net Cash (Debt) 21.6 0.05Price to Earnings Ratio x -22.8 -95.1 -90.6 -14.6 3.9 Tax (NPV future liability) -82.1 -0.19Dividends Per Share AUD - - - - - Options 2.3 0.01Dividend Yield % 0.0% 0.0% 0.0% 0.0% 0.0% Hedges 0.0 0.00Net Debt / Net Debt + Equity % -6% -65% -77% 27% -2% Total 338.5 0.77Interest Cover X 179.7 25.5 na na 23.4Return on Equity % na na na na 42%
Analyst: Mike Millikan+61 8 9268 2805"tbc capital" could be equity or debt. Our valuation is risk-adjusted for how this may be obtained.Sources: IRESS, Company Information, Hartleys Research
8 December 2017
Last Updated: 08/12/2017
Hartleys Limited Gascoyne Resources Limited (GCY) 8 December 2017
Page 3 of 8
DALGARANGA – NEAR TERM PRODUCER The Dalgaranga project is located ~65km northwest of Mt Magnet in the Murchison
region of Western Australia. The Dalgaranga project (100% GCY) covers the
majority of the Dalgaranga Greenstone Belt with the key deposits of Gilbeys, Golden
Wings and Sly Fox contained within a granted Mining Lease.
Fig. 1: Dalgaranga Project Location (LHS) and Site Layout (RHS)
Source: Gascoyne Resources Limited
Gilbeys has previously been mined as an open pit to a depth of ~120m below
surface, and represents a bulk mining open pit, with ~70m of largely free dig oxide
material with very soft ore providing low mining and processing costs. Golden Wings
is a planned higher grade open pit, which lifts the head grade at the start of the
operation.
The Dalgaranga mine plan has now been updated by the addition of the Sly Fox
deposit. The mining inventory now contains 16.2Mt grading 1.3g/t Au for 652koz
from Gilbeys, Golden Wings and Sly Fox, with 94% from reserves (15.3Mt @ 1.25g/t
Au for 612koz) and 6% from Inferred resources within the pits (40koz @ 1.4g/t Au).
We continue to assume a mine life in excess of 7 years.
The maiden Sly Fox reserve (26koz @ 1.3g/t Au) is considered interim, with further
growth anticipated as the deposit remains open. The upper parts of the deposit are
expected to be mined in the first 17 months of production, providing additional oxide
ores to lift throughput capacity in the early years (from 2.5Mtpa towards 3Mtpa) and
deferring some open pit waste movement for improved capital payback.
The increase in softer material in the early production years is expected to lift
annualised production with potential to grow to +120koz from ~100koz in the first
few years.
GCY has100% interest
in the Dalgaranga
Gold Project
The Dalgaranga mine
plan has now been
updated by the
addit ion of the Sly Fox
deposit
Hartleys Limited Gascoyne Resources Limited (GCY) 8 December 2017
Page 4 of 8
VALUATION – UPDATED Our sum of parts valuation for GCY is largely based on the Dalgaranga FS and latest
mine plan and the Glenburgh PFS. The Company’s FS for the Dalgaranga project was
based on a 2.5Mtpa CIL processing plant, but the mill is expected to be able to process
soft oxide and transitional ores at higher throughput rate nearing 3.0Mtpa. The current
mine plan has some 652koz (now includes Sly Fox) from a reserve of 612koz. The
additional softer ores are expected to increase production in the first couple of years
at ~120kozpa. The pre-production capital costs are estimated at A$98M.
Fig. 2: Dalgaranga Initial Production Profile
Source: Gascoyne Resources Ltd; Hartleys Estimates; FS with simulated upside yet to be included
Our Dalgaranga production forecast is for average production +102kozpa at AISC of
~A$1,065/oz from mid CY18 for an initial mine life of just over 7 years, justified in our
opinion due to the recent resource/reserve updates and expectation of growing mining
inventory. We model GCY’s next development asset, Glenburgh, in-line with the PFS
(2013) producing ~70Kozpa at AISC of ~A$1,015/oz from CY20 for ~5 years mine life
(although we see potential upside).
Fig. 3: GCY Model Assumptions
Source: Hartleys Estimates
0
0.5
1
1.5
2
2.5
3
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Gra
de
(g
/t)
and
Mill
Th
rou
ghp
ut
Go
ld P
rod
uct
ion
Oz
Production Profile - Dalgaranga
Upside Oz Produced Gold (FS) Grade g/t (FS) Mtpa (FS) Upside Mtpa Grade g/t (new)
Dalgaranga Glenburgh
Capex - Total ($m) 100 80
Life of mine (LOM) Strip Ratio (x) 7.0x 8.0x
LOM ave head grade 1.3g/t 2.0g/t
LOM ave mill feed (Mt pa) 2.6Mt pa 1.2Mt pa
LOM Gold recovered grade g/t 1.2g/t 1.8g/t
LOM Au combined recovery & payability 91% 92%
Total Gold Sold 712Koz 355Koz
Total Gold Sold pa 102Koz pa 71Koz pa
Current Assumed Mine Life (yrs) 7yrs 5yrs
Commencement Date (qtr) Jun-18 Mar-20
LOM ave selling price (A$/oz gold ) A$1610 /oz A$1578 /oz
LOM ave C1 cash costs (A$/oz gold) A$792 /oz A$880 /oz
LOM ave AISC (A$/oz gold) A$1045 /oz A$1016 /oz
LOM annual net cash flow (A$m pa) A$40m pa A$18m pa
NPV12 - pre-tax (A$m) A$241.4m A$90.7m
We model Dalgaranga
with an average
throughput of 2.6Mtpa
plant producing over
+100kozpa at AISC of
~A$1,045/oz
We model Glenburgh
producing ~70Kozpa
at AISC of
~A$1,016/oz
We see good upside
potentia l to our
model l ing
Hartleys Limited Gascoyne Resources Limited (GCY) 8 December 2017
Page 5 of 8
We believe GCY is well positioned for further brownfield exploration success at both
Dalgaranga and Glenburgh. We value the exploration upside potential with a nominal
(unchanged) A$75m.
Fig. 4: Hartleys Sum of Parts Valuation for GCY
Source: Hartleys Estimates
PRICE TARGET Our price target is based on our sum of parts valuation for Dalgaranga and Glenburgh,
weighted for our valuations at spot and consensus pricing.
Fig. 5: GCY Price Target Methodology
Source: Hartleys Estimates
Share Price Valuation (NAV) Risked Est. A$m Est. A$/share
100% Dalgaranga (pre-tax NAV at disc. rate of 12%) 241.4 0.55
100% Glenburgh (pre-tax NAV at disc. rate of 14%) 90.7 0.21
Other Exploration 75.0 0.17
Corporate Overheads -10.3 -0.02
Net Cash (Debt) 21.6 0.05
Tax (NPV future liability) -82.1 -0.19
Options 2.3 0.01
Hedges 0.0 0.00
Total 338.5 0.77
Price Target Methodology Weighting Spot 12 mth out
55% $0.77 $0.83
NPV base case at spot commodity and fx prices 45% $0.81 $0.89
Risk weighted composite $0.79
12 Months Price Target $0.86
Shareprice - Last $0.420
12 mth total return (% to 12mth target + dividend) 104%
NPV base case
We assume a nominal
A$75m value for
explorat ion upside
Our latest GCY NAV is
A$0.77/s
Our latest spot NAV is
also $0.81/s
Hart leys 12 month
price target is $0.86/s
Hartleys Limited Gascoyne Resources Limited (GCY) 8 December 2017
Page 6 of 8
EV/EBITDA BANDS
Fig. 6: Using Hartleys base case commodity forecasts
Source: Hartleys Estimates, IRESS
Fig. 7: Using spot commodity prices
Source: Hartleys Estimates, IRESS
.00
.50
1.00
1.50
2.00
2.50
GCY Actual
Hartleys Target
8x EV/EBITDA
6x EV/EBITDA
4x EV/EBITDA
2x EV/EBITDA
1x EV/EBITDA
Shareprice
.00
.50
1.00
1.50
2.00
2.50
GCY Actual
8x EV/EBITDA
6x EV/EBITDA
4x EV/EBITDA
2x EV/EBITDA
1x EV/EBITDA
Shareprice
Hartleys Limited Gascoyne Resources Limited (GCY) 8 December 2017
Page 7 of 8
RECOMMENDATION & RISKS
RISKS
Fig. 8: Key assumptions and risks for valuation Assumption Risk of not realising
assumption Risk to valuation if
assumption is incorrect
Comment
Dalgaranga Project Low Meaningful GCY is leveraged to the success of the Dalgaranga project. We model in line with the Dalgaranga FS but have made adjustments to
early plant throughputs and mining inventory as per the latest mine plan. If the project varies
largely from these metrics our valuation will be at risk
Model parameters Moderate Meaningful We have made a number of assumptions, largely
based of development studies, in our valuation of GCY, changes in these assumptions can change
our valuation to both the upside and downside
Exploration upside potential Moderate Low We assume exploration upside at Dalgaranga
and Glenburgh. Some downside risk to our valuation exists if GCY has no further exploration
success
Development Risk Moderate High All development projects have risks. Dalgaranga
is somewhat negated by previous operating data and mining. The FS is to a high quality and is
considered robust to enable funding.
Funding Risk Moderate High GCY has raised new equity to fund some of the project development costs for Dalgaranga. Debt financing is nearing completion with financiers
mandated. At this stage first production is targeted for Q2 CY18.
Conclusion GCY is trading at a discount to our sum of parts valuation, with project valuations based largely on development studies. Dalgaranga is development ready, but construction is subject to financing
(debt) which we believe should be achieved in the near-term.
Source: Hartleys Research
Page 8 of 8
HARTLEYS CORPORATE DIRECTORY Research Trent Barnett Head of Research +61 8 9268 3052
Mike Millikan Resources Analyst +61 8 9268 2805
John Macdonald Resources Analyst +61 8 9268 3020
Paul Howard Resources Analyst +61 8 9268 3045
Aiden Bradley Research Analyst +61 8 9268 2876
Michael Scantlebury Junior Analyst +61 8 9268 2837
Janine Bell Research Assistant +61 8 9268 2831
Corporate Finance Dale Bryan Director & Head of
Corp Fin.
+61 8 9268 2829
Richard Simpson Director +61 8 9268 2824
Ben Crossing Director +61 8 9268 3047
Ben Wale Associate Director +61 8 9268 3055
Stephen Kite Associate Director +61 8 9268 3050
Scott Weir Associate Director +61 8 9268 2821
Scott Stephens Associate Director +61 8 9268 2819
Rhys Simpson Manager +61 8 9268 2851
Registered Office
Level 6, 141 St Georges TcePostal Address:
PerthWA 6000 GPO Box 2777
Australia Perth WA 6001
PH:+61 8 9268 2888 FX: +61 8 9268 2800
www.hartleys.com.au [email protected]
Note: personal email addresses of company employees are
structured in the following
manner:[email protected]
Hartleys Recommendation Categories
Buy Share price appreciation anticipated.
Accumulate Share price appreciation anticipated but the risk/reward is
not as attractive as a “Buy”. Alternatively, for the share
price to rise it may be contingent on the outcome of an
uncertain or distant event. Analyst will often indicate a
price level at which it may become a “Buy”.
Neutral Take no action. Upside & downside risk/reward is evenly
balanced.
Reduce /
Take profits
It is anticipated to be unlikely that there will be gains over
the investment time horizon but there is a possibility of
some price weakness over that period.
Sell Significant price depreciation anticipated.
No Rating No recommendation.
Speculative
Buy
Share price could be volatile. While it is anticipated that,
on a risk/reward basis, an investment is attractive, there
is at least one identifiable risk that has a meaningful
possibility of occurring, which, if it did occur, could lead to
significant share price reduction. Consequently, the
investment is considered high risk.
Institutional Sales Carrick Ryan +61 8 9268 2864
Justin Stewart +61 8 9268 3062
Simon van den Berg +61 8 9268 2867
Chris Chong +61 8 9268 2817
Digby Gilmour +61 8 9268 2814
Veronika Tkacova +61 8 9268 3053
Wealth Management Nicola Bond +61 8 9268 2840
Bradley Booth +61 8 9268 2873
Adrian Brant +61 8 9268 3065
Nathan Bray +61 8 9268 2874
Sven Burrell +61 8 9268 2847
Simon Casey +61 8 9268 2875
Tony Chien +61 8 9268 2850
Tim Cottee +61 8 9268 3064
David Cross +61 8 9268 2860
Nicholas Draper +61 8 9268 2883
John Featherby +61 8 9268 2811
Ben Fleay +61 8 9268 2844
James Gatti +61 8 9268 3025
John Goodlad +61 8 9268 2890
Andrew Gribble +61 8 9268 2842
David Hainsworth +61 8 9268 3040
Murray Jacob +61 8 9268 2892
Gavin Lehmann +61 8 9268 2895
Shane Lehmann +61 8 9268 2897
Steven Loxley +61 8 9268 2857
Andrew Macnaughtan +61 8 9268 2898
Scott Metcalf +61 8 9268 2807
David Michael +61 8 9268 2835
Jamie Moullin +61 8 9268 2856
Chris Munro +61 8 9268 2858
Michael Munro +61 8 9268 2820
Ian Parker +61 8 9268 2810
Matthew Parker +61 8 9268 2826
Charlie Ransom
(CEO)
+61 8 9268 2868
Mark Sandford +61 8 9268 3066
David Smyth +61 8 9268 2839
Greg Soudure +61 8 9268 2834
Sonya Soudure +61 8 9268 2865
Dirk Vanderstruyf +61 8 9268 2855
Samuel Williams +61 8 9268 3041
Jayme Walsh +61 8 9268 2828
Disclaimer/Disclosure
The author of this publication, Hartleys Limited ABN 33 104 195 057 (“Hartleys”), its Directors and their Associates from time to time may hold
shares in the security/securities mentioned in this Research document and therefore may benefit from any increase in the price of those securities.
Hartleys and its Advisers may earn brokerage, fees, commissions, other benefits or advantages as a result of a transaction arising from any advice
mentioned in publications to clients.
Hartleys has assisted in the completion of capital raisings in the past 12 months for Gascoyne Resources Limited ("Gascoyne"), for which it has
earned fees. Hartleys has also provided corporate advice within the past 12 months and continues to provide corporate advice to Gascoyne, for
which it has earned fees and continues to earn fees.
Any financial product advice contained in this document is unsolicited general information only. Do not act on this advice without first consulting
your investment adviser to determine whether the advice is appropriate for your investment objectives, financial situation and particular needs.
Hartleys believes that any information or advice (including any financial product advice) contained in this document is accurate when issued.
Hartleys however, does not warrant its accuracy or reliability. Hartleys, its officers, agents and employees exclude all liability whatsoever, in
negligence or otherwise, for any loss or damage relating to this document to the full extent permitted by law.