HALLETTSVILLE ISD 2014 FACILITIES BOND PROJECT
description
Transcript of HALLETTSVILLE ISD 2014 FACILITIES BOND PROJECT
1
HALLETTSVILLE ISD2014 FACILITIES BOND PROJECT
2
TABLE OF CONTENTS
The Vision and Strategic Goal Elementary Need and Solution Junior High Need and Solution Financial Information Election Information
3
The STRATEGIC PLANNING COMMITTEE developed the
following goal related to Safety & Facilities:
HISD has appropriate facilities and a comprehensive plan
providing a safe and secure environment for students,
employees, and community members.
January 19, 2013
The Need
The Shared Vision of HISD developed by the strategic planning committee in January of 2013 states that:
Our learning environment Includes facilities that meet the needs of
students and staff. Provides physical and emotional safety.
4
SAFETY AND SECURITY IS OUR TOP PRIORITY
5
AGE OF ELEMENTARY FACILITIES
Year Age ELEM SCHOOL 1956 58 KINDERGARTEN ADDITION 1984 30 ELEM PE FACILITY 1989 25 ELEM LIBRARY ADDITION 1993 21 ELEM ADDITION 2004 10
The Need
Needs of Elementary
Increase safety and security by enclosing the elementary
from “walk-up” access (34 exterior doors at HES)
Additional classrooms and restrooms to accommodate
growing numbers
Library expansion
Technology, electrical, and air system upgrades
6
7
CURRENT ELEMENTARY FACILITY
Restroom Converted to Classroom Space
8
Open Walkways for Students and Staff Members
9
Portable Currently Leased to Provide Additional Classrooms
10
Small Group Instruction Conducted in Closet Space
11
Elementary Student Walkways Outdoors and Accessible to All
12
Outdated Ceiling Tiles That Can No Longer Be Replaced
13
Exposed Electrical, Gas, and Technology Lines
14
Patched Areas and Exposed Drainage Systems and Wires
15
Outdated Air Systems and Weathered Trim on Buildings
16
Limited Classroom Space in Kindergarten Wing
17
Limited Space in HES Library for Group Lessons and Storage
18
Limited Classroom Space for Increased Enrollment
19
Walk-up Access to Classrooms
20
21
PROPOSED TOTALLY ENCLOSED ELEMENTARY FACILITY
22
23
AGE OF JUNIOR HIGH FACILITIES
Year Age JR HIGH CAFETERIA 1970 44 JR HIGH LIBRARY ADDITION 1992 22 MINI GYM 1996 18 JR HIGH ADDITION/RENOVATION 2007 7
The Need
Needs of Junior High Construction of cafeteria to address
kitchen and dining area space limitations Eliminate cafeteria foundation issues Resolve drainage issues between the
gym and the cafeteria Increase library space Additional classroom space More efficient flow of student traffic in
hallways
24
Storage Building and Cooler Outside of Existing Cafeteria
25
Exterior Mop Storage Area on Cafeteria Porch
26
Foundation Problem in Cafeteria
27
Trip Hazards Created by Foundation Problems
28
Limited Storage for Cafeteria Supplies and Food Products
29
Buckled Floor in the Student Dining Area Along East Wall
30
Area Where Students Wait Outside in Line for Cafeteria Service
31
Safety and Security concerns regarding entrance to HJHS Cafeteria
Students are exposed to the elements while waiting to enter the cafeteria.
School entrance is directly connected to the back parking lot.
Parking lot is also used for deliveries to the cafeteria as well as by the community to deposit recyclable items.
Visitors to the campus through this entrance come in unnoticed by staff.
32
Need to Close Off Food Preparation Area from Testing Area
33
Tables Set up to Create Makeshift Serving Line
34
Limited Seating Space for Projected Enrollment
35
Current seating capacity of cafeteria: 168 students Current number of students per lunch: 142 students Number of lunch groups: 2 Projected number of students per lunch in 2016 –
2017+: 140 Projected number of student per lunch in 2017 -
2018+: 170+ Cafeteria is used as a multipurpose room during the
school year for cafeteria purposes and large group meeting room/testing room.
Drainage Problem Between Gym and Cafeteria Building
36
Limited Library Space for Group Meetings and Circulation
37
Library book space at capacity. Limited library seating area for grade level
activities: 58 chairs Current average class size: 66 Projected average class size in 2016-2017:
70 Projected average class size in 2017 –
2018+: 75 More space would allow a reconfiguration of
shelving and seating to meet campus needs.
3838
PROPOSEDJUNIOR HIGH
FACILITY
39The Solution
HISD’s comprehensive plan for providing a safe and secure environment for ALL students, employees, and community members includes:
• Remodeling the structurally sound HES main building
• Constructing new additional classrooms for HES and HJHS campuses to accommodate growth
• Building a new HJHS cafeteria
This approach would provide safe, appropriate learning environments at ALL campuses in the Hallettsville Independent School District.
Bond Project Timeline
February 2014 - Board Calls Bond Election February-April 2014 – Community Presentations May 2014 – Bond Election May 2014 – Finalize Facilities Plans May/June 2014 – HES Staff Moves to Portables June 2014 – Construction Begins Summer 2015 – Construction is Completed Fall 2015 – HES/HJHS Students and Staff Begin Using
New Facilities
The Solution
Estimated Cost by Area
Totals:Junior High Cafeteria $ 1,290,000Junior High Library Expansion $ 640,000Junior High Classrooms $ 600,000Junior High Re-roof $ 375,000Elementary School Construction $ 7,850,000Temporary Classrooms $ 400,000Furniture Fixtures and Equipment $ 325,000Asbestos Abatement $ 150,000
Total $ 11,630,000
***NEEDS UPDATED***
The Solution
19992000
20012002
20032004
20052006
20072008
20092010
20112012
2013$0.0000
$0.2000
$0.4000
$0.6000
$0.8000
$1.0000
$1.2000
$1.4000
Hallettsville ISD Historical Tax Rates – Before Bond
I&S RateM&O Rate
The Solution
After Bond (if it passes)
The Solution
How are the values distributed in Hallettsville ISD?
Based upon a bond issue of $11,630,000, what is the effect on my taxes?
The tax rate needed would be 13 cents.Based upon conservative values.
Home owners 65 and older WILL NOT have an increase in taxes on their homestead.
The Solution
2013 TAX RATES FOR NEIGHBORING DISTRICTS
The Solution
DISTRICTEdnaWeimarIndustrialEast BernardRiceGanadoGoliadColumbusSchulenburgYoakumCueroHallettsvilleShinerMoultonYorktown
M&O RATE1.040001.040001.170001.170001.040001.170001.040001.040001.040001.040001.040000.960001.040000.980000.96000
I&S RATE.26960.24000.09100.08920.19107.02950.14535.14000.12250.11400.06403.14265.00000.01008.01212
TOTAL1.309601.280001.261001.259201.231001.199501.185351.180001.162501.154001.104031.102651.040000.990080.97120
2013 Bond*
.20 (50 Mil) .33 (75 Mil) .13 (11.63 M)
*Cents to be added if bond passes;
Based on current property values.M&O Rate=Maintenance and OperationsI&S Rate=Interest and Sinking
What is the effect on my taxes?
With a Taxable Value of $100,000 – Per Year $ 130.00 Per Month $ 10.83
Per Week $ 2.50 Per Day $ .36
The Solution
48
ARE BOND FUNDS SUBJECT TO RECAPTURE?
Taxes Paid for Facilities Through Maintenance and Operations (M&O) Budget
This is recapture (Robin Hood)
Taxes Pd to HISD $15,218,529
Amt Pd to State $3,588,529
Amt Available $11,630,000For Project
Project Cost $15,218,529
Taxes Paid for Facilities Through Bonds
(I&S)We keep all taxes for bonds
Taxes Pd to HISD $11,630,000
Amount Pd to State $ 0.00
Amt Available $11,630,000For Project
Project Cost $11,630,000
WHEN FINANCING CAPITAL PROJECTS
Election Information
Board met to call Election- Feb. 10, 2014
Early Voting- April 28th through May 6th, Monday through Friday, 8 a.m. until 5 p.m. at the Lavaca
County Courthouse Annex, 412 N. Texana Street
Election day- Saturday, May 10th at the Lavaca County Courthouse Annex. The polls will be open from 7 a.m. until 7 p.m. All registered voters in HISD are eligible to vote.
The Solution