GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE...

14
GWRS Initial Expansion Construction Update OCWD Board of Directors July 1, 2015

Transcript of GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE...

Page 1: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

GWRS Initial Expansion Construction Update

OCWD Board of Directors July 1, 2015

Page 2: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Features of GWRS Initial Expansion

• Existing facility production increased from 70 mgd to 100 mgd (72,000 afy to 103,000 afy)

• GWRS original design allows for two 30 mgd expansions up to 130 mgd, eventually

• Expansion includes 10 new MF cells and 5 new UV trains using identical equipment to existing facility

• Six new RO units include some enhancements over existing RO units: energy recovery devices, interstage EC and flow meters

• New post treatment system design based around Tekkem lime system

Page 3: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Flow Equalization Tanks

Equalization Tanks

Pump Station

Fill/Drain Pipeline

SEJB6

Page 4: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Contract Schedule Status

Notice of Award 9/7/2011 Notice to Proceed 10/20/2011 Time of Completion 1350 Calendar Days Original Contract Completion Date 10/18/2014 Authorized Time Extensions 255 Calendar Days Current Contractual Completion Date 06/30/15*

*Close out activities and paperwork will extend to July 31, 2015

Page 5: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Contract Close Out Activities • Submittal of electronic versions of final approved

submittals by contractor • Submittal of final O&M manuals by contractor • Submittal of final warranties by contractor • Completion of punch lists for all areas • Submittal of red line drawings by contractor and

preparation of final drawings by design engineer

Page 6: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Project Budget Project Item Original Project

Budget Revised Budget

Design Services (Includes Approved Amendments No. 1 – 4) (B&V) $ 6,500,000 $ 6,500,000

Amendment No. 5 - Design Services During Construction (B&V) Approved Amendment No. 6

$ 4,416,000 $ 4,416,000 $ 293,900

Construction (McCarthy Building Co.) Change Orders No. 1 - 23

$ 115,090,000 $ 115,090,000 $ 4,622,966

Construction Management (Parsons) Approved Amendments No. 1- 5

$ 6,693,164 $ 6,693,164 $ 1,541,612

Materials Testing (Converse) Approved Amendment No. 1

$ 1,052,864 $ 1,052,864 $ 73,000

Engineering, Legal, and Administration (ELA) Permit Services (DDB Engineering)

$ 1,100,000

$ 923,160 $ 176,840

Project Contingency $ 7,847,972 $ 1,316,494 Total $ 142,700,000 $ 142,700,000

Page 7: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Change Order Process • 5% contingency added to project budget to cover project changes

during construction • If an issue arises contractor issues a Request for Information (RFI) • If RFI response results in a change in project a Request for Proposal

(RFP) summarizing how issue is to be addressed • Contractor issues a cost estimate for the RFP • The final cost is negotiated between contractor, CM and OCWD • Once cost is finalized a Field Change Order (FCO) is issued • FCOs are combined into a formal change order requiring OCWD

project manager and general manager approval

Page 8: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Change Order Summary • 1287 RFI issued to date • 23 change orders issued to date containing 466

individual FCOs • Largest change was related to contaminated soils issue

(8 FCOs totaling $963,222 issued to contractor) • Total cost of 23 change orders is $4,622,966 • Total savings realized through negotiations between

contractor, CM and OCWD on change orders totals $992,652

• Change orders 1-23 makes up 4.02% of 5% budgeted

Page 9: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Contamination Soils Issue

• SEFE tank site located south of original GWRS site on land leased from OCSD for $1 per year

• Pesticides, DDT (and DDE) and toxaphene, were found in the top 5-feet of soil at the SEFE site in concentrations too high for local landfill disposal

• Staff developed a hazardous waste removal plan and submitted it to OC Health Care Agency (and Regional Water Quality Control Board)

• Contractor developed a industrial hygiene program to protect workers and prevent contaminated soil from being hauled from site without proper testing

Page 10: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Soil Management Removal Plan

• OCHCA agreed that only soil disturbed by construction required testing and remediation

• Excavated soil as part of the construction was tested to determine appropriate landfill disposal site

• Soils that exceeded federal thresholds were trucked to hazardous landfill site in Yuma, Arizona

• Contaminated soil in areas undisturbed during construction were left in place

Page 11: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Microfiltration Area

Page 12: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Reverse Osmosis Building

Page 13: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

SEFE Tanks & Pump Station

Page 14: GWRS Initial Expansion Construction Update...Microfiltration Area Reverse Osmosis Building SEFE Tanks & Pump Station Recommendation Ratify issuance of Change Orders 1-23 for Contract

Recommendation

Ratify issuance of Change Orders 1-23 for Contract No. GWRS-2011-01 (McCarthy Building Companies, Inc.) in the amount of $4,622,966 for additional required work and an additional 255 calendar day extension to the original contract completion date.