    UGANDA ROAD FUND

    Guidance on Programme Management &

    Physical Accountability

    Presented at the URF National Training Workshop

    April 2011

    Andrew NaimanyeMSc(Eng), BEng, CEng, MICE, MIHT

    Programme Manager

    02/05/2013 1URF National Training Workshop April 2011

  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    2/13

    Purpose of Presentation

    To provide guidance on programme management

    To discuss what agencies should provide inphysical accountability

    To discuss works that are eligible for funding,Annual and quarterly workplan formats

    To present URFs Physical Accountability reportingformats

    02/05/2013 URF National Training Workshop April 2011 2

  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    3/13

    Outline of Presentation

    Background/Policy

    Eligible Works

    Annual and quarterly Workplan formats Physical Accountability

    Conclusions

    02/05/2013 3URF National Training Workshop April 2011

  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    4/13

    Background/Policy

    Funds shall only be expended on activities andassets specifically permitted by the Act, withpriority given to:

    efficient and effective routine and periodicmaintenance of public roads

    control of overloading of vehicles on public roads;

    operational costs of the Fund and of the UgandaNational Roads Authority

    targeted research in road and bridge maintenance

    02/05/2013 URF National Training Workshop April 2011 4

  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    5/13

    Eligible Works

    Routine Maintenance

    Designated agencies should use a rational method toestimate cost of routine maintenance based on theclassification of road, terrain and other factors

    Unsupported adoption of historic values isunacceptable

    Workplans must show for each road: length of the road to receive routine maintenance

    the cost / kilometre for off-pavement routine maintenance

    the cost / kilometre for pavement routine maintenance

    the total cost for routine maintenance for the road.

    02/05/2013 URF National Training Workshop April 2011 5

  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    6/13

    Eligible Works

    Contd...Periodic Maintenance

    Rehabilitation or reconstruction do not qualify

    Road formation widening is permitted if it is necessary to: accommodate the overlay thickness where such an increase is required

    give lateral support to the pavement

    make drainage improvements essential to the structural integrity of thepavement.

    Widening in excess of the above shall not normally qualify forfunding

    All road sections/bridges to be treated and the treatment type shall

    be individually listed The required format for reporting periodic maintenance activities

    was provided

    02/05/2013 URF National Training Workshop April 2011 6

  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    7/13

    Workplan formats

    Annual and Quarterly Workplans

    Ms Excel forms have been designed for making Annualand Quartery workplan summary. These can be usedalongside the RAMPS. Information from RAMPS shouldbe summarized and fed into the excel files.Programming Tables.xls

    District and Town Council plans should be presented inthe one document but with clear distinction.

    Sub county work plans should be presented showingworks to be undertaken in each sub county.

    02/05/2013 URF National Training Workshop April 2011 7

    http://localhost/var/www/apps/conversion/tmp/scratch_4/Programming%20Tables.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_4/Programming%20Tables.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_4/Programming%20Tables.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_4/Programming%20Tables.xls
  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    8/13

    Physical Accountability

    Quarterly reporting will have a quarter lag in accordance withMoFPED guidance, please note that accountability for Quarter1 will be the trigger for Q3 funds and accountability forQuarter 2 funds will be the trigger for Quarter 4 funds and so

    on.The Accountability statement shall show for each activity: The physical achievement (kilometres maintained etc)

    Actual, Programmed and Variance (quantity andpercentage).

    The expenditure during the period Actual, Programmed

    and Variance (amount and percentage)

    A variance report stating reasons for variances andmitigation measures to deal with them.Physical & FinancialAccountability Forms.xls

    02/05/2013 URF National Training Workshop April 2011 8

    http://localhost/var/www/apps/conversion/tmp/scratch_4/Physical%20&%20Financial%20Accountability%20Forms.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_4/Physical%20&%20Financial%20Accountability%20Forms.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_4/Physical%20&%20Financial%20Accountability%20Forms.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_4/Physical%20&%20Financial%20Accountability%20Forms.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_4/Physical%20&%20Financial%20Accountability%20Forms.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_4/Physical%20&%20Financial%20Accountability%20Forms.xls
  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    9/13

    Physical Accountability

    contd

    For each Contract with a value in excess of Ushs200,000,000:

    The scope of work involved

    The value of the contract

    Progress to date against programme

    Value of any variations

    Nature and value of any claims

    Accountability statement signed by the District Engineerof the designated agency and authorised by the ChiefAdministrative Officer

    02/05/2013 URF National Training Workshop April 2011 9

  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    10/13

    Programme Changes

    Designated agency may reallocate budgets betweenactivities within same district and work sub-categorywithout approval from Board if: allocation for individual activity in approved Annual Road

    Maintenance Programme is not increased by more than 15%,

    and overall allocation for the work sub-category within district for

    financial year is not changed, and

    performance objectives in district for financial year not changed.

    All other reallocations require approval of Board

    No expenditure in excess of approved allocations arecommitted by the designated agency until and unlessapproval has been given by Board.

    02/05/2013 URF National Training Workshop April 2011 10

  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    11/13

    Programme Changes

    Contd If it is anticipated that expenditure for an activity will exceed allocation for that

    activity by 15% or more, or new activities not foreseen at all in Annual RoadMaintenance Programme , designated agency prepares a programme adjustmentrequest for approval by Board

    Programme adjustment requests will be considered for: Abandoned activities: to suspend/abandon activities (accompanied by an explanation)

    Cash flow adjustments:

    to adjust timing of expenditures (either advancement or delay by more than twomonths compared with that given in the implementation plan) or

    reprogramming approved allocations from the current year into subsequent years(or vice versa)

    Work sub-category cost adjustments: cost increases or decreases changing totalallocation for a work sub-category within district (supported by detailed explanation)

    New activities: requests for new activities not submitted in the Annual Road

    Maintenance Programme (with all required supporting information)

    Requests for programme adjustments must be submitted to Secretariat onappropriate form

    02/05/2013 URF National Training Workshop April 2011 11

  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    12/13

    Conclusion

    Agencies should respond promptly to ourrequirements both in form of physical andfinancial accountability

    URF should be contacted in case of ProgrammeChanges

    URF will undertake M & E to check the accuracyof the physical accountabilities provided

    Non compliance with URF requirements willaffect future releases

    Rehabilitation or reconstruction do not qualify

    02/05/2013 URF National Training Workshop April 2011 12

  • 7/30/2019 Guidance on Programme Mgmt - Physical Accountability_170610

    13/13

    Thank You

    Uganda Road Fund

    Programming Department

    Andrew Naimanye Tel: 0754 190 053

    Ronald Namugera Tel: 0782 381 112

    02/05/2013 URF National Training WorkshopSeptember 2010