Skagit County Public Works www.skagitcounty.net Guemes Island Ferry Replacement Project Preliminary Design Update Tuesday, March 16, 2021

Transcript of Guemes Island Ferry Replacement Project Preliminary …

Skagit County Public Workswww.skagitcounty.net

Guemes Island Ferry Replacement ProjectPreliminary Design UpdateTuesday, March 16, 2021

Agenda• Design Update 10 min• Electrical Operations 10 min• Terminal Modifications 5 min• Project Schedule 5 min• Design Contract Amendment 5 min• Integrator Selection 5 min• Cost Estimates and Funding 5 min• Questions 45 min (throughout)

Crew Feedback

Hull Optimization

Baseline Design

Improved Performance

Improved Performance

Optimized Design

Hull Optimization - Cost Savings

• $50,000 subconsultant fee to perform optimization

• $100,000 savings on vessel batteries alone

• $14,000 annual savings on electrical energy

• Nearly $1M savings over 40 year lifetime

Electrical Systems

Shore Batteries

Automatic Charger Plug Ship

Batteries

Thrusters

Utility Power

208/120VAC SHIP SERVICE DISTRIBUTION

DC PROPULSIONDISTRIBUTION(700-1000VDC)

PROPULSIONBATTERYBANK

SESSHORE ELECTRICAL SYSTEM

VESVESSEL ELECTRICAL SYSTEM

480VACSUPPLEMENTALDISTRIBUTION

STANDBYGENERATOR

PROPULSIONMOTOR

TERMINAL POWER DISTRIBUTION

SHORE POWERRAMPAUTOMATIC SHORE

CONNECTION SYSTEM

DC/DC CONVERTER

SHIP SERVICEINVERTER

PROPULSION MOTORDRIVE

CHARGINGSWBD

208/120VAC SHIP SERVICE DISTRIBUTION

DC PROPULSIONDISTRIBUTION(700-1000VDC)

PROPULSIONBATTERYBANK

SESSHORE ELECTRICAL SYSTEM

VESVESSEL ELECTRICAL SYSTEM

480VACSUPPLEMENTALDISTRIBUTION

STANDBYGENERATOR

PROPULSIONMOTOR

TERMINAL POWER DISTRIBUTION

SHORE POWERRAMPAUTOMATIC SHORE

CONNECTION SYSTEM

DC/DC CONVERTER

SHIP SERVICEINVERTER

PROPULSION MOTORDRIVE

CHARGINGSWBD

208/120VAC SHIP SERVICE DISTRIBUTION

DC PROPULSIONDISTRIBUTION(700-1000VDC)

PROPULSIONBATTERYBANK

SESSHORE ELECTRICAL SYSTEM

VESVESSEL ELECTRICAL SYSTEM

480VACSUPPLEMENTALDISTRIBUTION

STANDBYGENERATOR

PROPULSIONMOTOR

TERMINAL POWER DISTRIBUTION

SHORE POWERRAMPAUTOMATIC SHORE

CONNECTION SYSTEM

DC/DC CONVERTER

SHIP SERVICEINVERTER

PROPULSION MOTORDRIVE

CHARGINGSWBD

Normal Operation

208/120VAC SHIP SERVICE DISTRIBUTION

DC PROPULSIONDISTRIBUTION(700-1000VDC)

PROPULSIONBATTERYBANK

SESSHORE ELECTRICAL SYSTEM

VESVESSEL ELECTRICAL SYSTEM

480VACSUPPLEMENTALDISTRIBUTION

STANDBYGENERATOR

PROPULSIONMOTOR

TERMINAL POWER DISTRIBUTION

SHORE POWERRAMPAUTOMATIC SHORE

CONNECTION SYSTEM

DC/DC CONVERTER

SHIP SERVICEINVERTER

PROPULSION MOTORDRIVE

CHARGINGSWBD

Reliability

• Safely finish trip, always

• Continue operations for most single faults

• Maximize use of utility power vs. generator

208/120VAC SHIP SERVICE DISTRIBUTION

DC PROPULSIONDISTRIBUTION(700-1000VDC)

PROPULSIONBATTERYBANK

SESSHORE ELECTRICAL SYSTEM

VESVESSEL ELECTRICAL SYSTEM

480VACSUPPLEMENTALDISTRIBUTION

STANDBYGENERATOR

PROPULSIONMOTOR

TERMINAL POWER DISTRIBUTION

SHORE POWERRAMPAUTOMATIC SHORE

CONNECTION SYSTEM

DC/DC CONVERTER

SHIP SERVICEINVERTER

PROPULSION MOTORDRIVE

CHARGINGSWBD

Batteries

Shore Electrical and Terminal

Terminal Improvements

Terminal Improvements

Overall Program Schedule

Design Contract Amendment

• New environmental consultant• Expanded scope of terminal modification (PND)• New scope for contracting support, integrator selection• Total increase requested: $470,000

Contracting Challenges

We must have a single electrical systems integrator

We want to select the ESI during contract design

Specifying VES: now vs later

Air-CooledBatteries

Electrical, Thrusters,

etc.Central FW System

Large Battery Room

AC Units

Water Cooled

BatteriesCentral FW System

Seawater Heat

Exchanger

Small AC

Selection depends on ESI

(both acceptable)

ESI-specific selections impact system sizing

Exhaust Design

Exhaust Design

Specifying VES: now vs later

Concept Design Prelim COTP Discussions Battery Safety

Grid capacity, pricing

Contract Design Electrical Concept Load Analysis Reliability

Power Quality Connection/metering

Construction Detailed Approvals QFA/DVTP/PSTP Certificate of Inspection

Utility-side modifications Final connection/test

USCG/Utility Engagement

Shore Electrical System

Automatic Charger Plug

ShipElectrical System

A single integrator is essential

Control Signals

Safety Automation

Energy Optimization

Integration and testCommissioning

Project Management

Shore Electrical System

Automatic Charger Plug

ShipElectrical System

A single integrator is essential

Integration and testCommissioning

Project Management

Terminal Project Ship Project

Integration and testCommissioning

Project Management

Integrator Selection: Options

• Shipyards choose integrators when bidding• Owner-furnish electrical systems• Competitive ESI selection (without contract)

Preliminary construction cost estimate• Vessel Construction $ 13,557,000• Terminal Improvements $ 2,000,001• Shore Side Electrical System $ 3,953,000

Total $ 19,510,001

Funding secured/pending• Funding awarded (1) $ (9,989,521)• County road fund $ (989,521)• Pending WA Capital Budget Ask $ (473,958)• Pending Transportation Package Ask $ (7,000,000)

Remaining $ 1,057,001

(1) WA Capital Budget Appropriation (2019) - $1.5MCounty Ferry Capital Improvement Program (2019) - $7.5 (payable over 20 years)Dept. of Commerce ETS grant (2020) - $989,521 (requiring a 1:1 county match)

Funding