Class SummaryHKM (Huettenwerk Krupp Mannesmann) is specialized in the input material production of steel with all necessary process steps—from pig iron production, including the coking plant and sintering plant—up to production of steel, steel slabs, and round steel bars in the continuous casting process. Today, HKM is a steel enterprise which is setting new, worldwide standards within production and environmental protection. HKM is setting standards in the IT, too—by implementing a true intelligent model of the whole plant, HKM is number one in the industry, having a complete 3D model of their factory site, including inside and outside equipment. This class describes best practice workflows using AutoCAD® Plant 3D, AutoCAD®
Civil 3D®, Autodesk® Revit® Structure, Autodesk® Inventor®, and AutoCAD® Map 3D software for creating a database-driven 3D model in Autodesk® Infrastructure Modeler software.
11/5/2012
2
© 2012 Autodesk
Learning Objectives
At the end of this class, you will be able to:
� Understand the benefit the Autodesk Infrastructure Design Suite offers for typical, daily workflows
� Use AutoCAD Map 3D for network planning, design, analysis and maintenance� Play through, how the different Autodesk software solutions can work together� Produce high-quality 3D visualizations with Autodesk Infrastructure Modeler.
© 2012 Autodesk
Agenda for next 60 min.1. Short introduction of Man and Machine
2. Introduction of HKM in figures
3. Why this project? Compelling Event4. Planing, Design, Analysis and Maintenance � Workflows in 2D� Workflows in 3D
5. Switch to Suites….
6. Outlook: What`s next?
7. Summary
8. Q&A
11/5/2012
3
© 2012 Autodesk
Short introduction ofMan and Machine
© 2012 Autodesk
MuM Business model (Status today)
� Geographical markets:� Direct Value Added Reseller for Autodesk
in 16 European countries� Sales offices for CAM Business
in Japan, APAC and USA (MuM Software only)
� Headcount:663 (PY: 607)
� 63% VAR Business� 37% Software Developement
Introduction
11/5/2012
4
© 2012 Autodesk
Business model since FY 2012:
MuMSoftware
Development of CAD/CAM Software Worldwide sales
Autodesk
End customers
MuMVAR Europe
Value Added Reselling of CAD Software / Service
� Higher added value (gross yield ~50% from 2012) and return from revenue (EBITDA margin est. >10% from 2013)
Introduction
© 2012 Autodesk
Business model
� Mechanical: ~50% share
� Infrastructure: ~15%
� Good segment balance:
� Electrical Engineering: ~10%
� Installed base:� over 50,000 end customers� over 500,000 seats installed
(>50,000 new per year)
� ~2/3 new / 1/3 recurring business
� AEC/Building services: ~25%
� Interdisciplinary: PDM, Industrial design / Visualization, Plant / Factory design
Introduction
11/5/2012
5
© 2012 Autodesk
Our Partnership with Autodesk:
� Man and Machine Inc.Autodesk Platinum Partner, who sells and counsel th e complete Autodesk product portfolio.
*Autodesk Platinum Tier (see: www.autodesk.com )The new Platinum Tier is a clear indication to Autodesk customers that Platinum Partners provide the highest level of service and industry expertise. This tier recognizes partners who deliver the highest level of value to customers. Autodesk reseller partners earn Platinum Tier status by demonstrating deep industry expertise, completing training and certification requirements and meeting the highest Customer Satisfaction requirements.
Introduction
© 2012 Autodesk
More information:
http://www.manandmachine.se
11/5/2012
6
© 2012 Autodesk
Frank Markus
degreed engineer for Geography (core area: GIS)
‘90-97 Man and Machine, Business Development
‘97-99 Smallworld (today: GE Inc.)
‘97-05 c-plan AG, Managing Director Germany
‘05-09 Autodesk Inc., Sales Manager and Business Development CE
‘09-today: Man and Machine, Managing Director (Infrastructure)
married, Hobby: making music
Introduction
© 2012 Autodesk
Huettenwerk Krupp Mannesmann (HKM)Customer Introduction
11/5/2012
7
© 2012 Autodesk
HKM facts� Integrated Steel factory with 2 Furnace, coking plant
and basic oxygen steel plant� located in the Ruhr Area� 3300 Employees� Production capacity: 5,3 Mill. Tons Steel� more than 1000 steel grades� 12% share of all German steel production� Facility area: ca. 2,5 km²
� Share holder:
© 2012 Autodesk
100 Years experience with „Geodata“
From the drawing pen to ISyDiF
11/5/2012
8
© 2012 Autodesk
100 Years experience with Mechanical Design
More than 500.000 Drawings, skeches etc. today in SAP-DVS
For Architecture, Structural steel engineering and
Mechanical Design
More than 500.000 Drawings, skeches etc. today in SAP-DVS
For Architecture, Structural steel engineering and
Mechanical Design
© 2012 Autodesk
�SAP-PM:Object-oriented encryption possible (functional locations) of the buildings and production facilities. Generation of BOM, reports and graphics by trained users.
�SAP-DVS:Drawing archive with more than 500,000 drawings, statistics, documents related to "technical courses.“
�Tables, Databases, human knowledge:Not spontaneously available expertise that is also lost due to fluctuation and retirement of employees. (Approx. 1000 employees in the next 10 years)Stored on local computers tables and databases that could be used for many applications and intersections, but the network is not available.
Much more data without spatial reference ...
11/5/2012
9
© 2012 Autodesk
Why this project?
Compelling Event
© 2012 Autodesk
Why this project?
Starting position and „Compelling Event“:
� Aging workforce/ loss of knowledge� Know-how transfer to the „Rookies“� „Pipe Bridge“ accident� missing linkage of data/ missing synergies/ missing meta data� redundant Data� no department-wide information� change the existing GIS (no further development)� at any time available, at any place, mobile
© Copyright 2010 Reliabilityweb.com. All rights reserved.
11/5/2012
10
© 2012 Autodesk
Sketch of customer`s idea, May 2010
© 2012 Autodesk
Definition: Building Information Modeling (BIM)A digital representation of physical and functional characteristics of a facility. A BIM is a shared knowledge resource for information about a facility forming a reliable basis for decisions during its life-cycle.*
BIM
* Copyright: Wikipedia.org
11/5/2012
11
© 2012 Autodesk
BIM – an intelligent process based on 3D models
© 2012 Autodesk
Layers of a Digital Factory*
*Copyright: Fraunhofer Institut für Produktionstechnik und Automatisierung, Stuttgart
DigitalMockup
11/5/2012
12
© 2012 Autodesk
The HKM digital Factory: All Software components of ISyDiF
© 2012 Autodesk
Planning, Design, Analysis, Maintenance
11/5/2012
13
© 2012 Autodesk
The HKM digital Factory: ISyDiF in 2D
© 2012 Autodesk
The HKM digital Factory: ISyDiF in 2D
� Video
11/5/2012
14
© 2012 Autodesk
ISyDiF Spatial reference for "Technical Courses"
Create a unique spatial reference, i.e. Documentation of the unique situation in the locality:• Building• buildings Improvements• Production zones• Cranes• pipe bridges• .......
© 2012 Autodesk
Migrate existingGeoData from
CAD400 System intoOracle/
GUI AutoCADMap
Combine data fromother databases, DWG drawings,
Excel tables ect. intoOracle DB
Launch all relevant data in the HKM
wide Intranet, bidirectional link toSAP R3 technical
courses
Manage all data(including meta
data) in one singleOracle DB with
AutoCAD Map 3D and AIMS/MapEdit
as GUI
The HKM digital Factory: ISyDiF 2D Workflow
11/5/2012
15
© 2012 Autodesk
ISyDiF 2D GIS: Landing page at HKM Intranet
© 2012 Autodesk
Benefit of the 2D Data� Solution is based on world wide standard software components
� easy to use, scalable through the entire enterprise, secure� customizable without programming, open data model� good references with comparable customers
11/5/2012
16
© 2012 Autodesk
BIM – an intelligent process based on 3D models
© 2012 Autodesk
The HKM digital Factory: ISyDiF in 3D
11/5/2012
17
© 2012 Autodesk
Workflow: 3D Data collection
• Terrestrial Laserscanning• Midrange Scanner Riegl: 2 m-1000 m• Accuracy : 10 mm
© 2012 Autodesk
Workflow: 3D Data collection
Video
11/5/2012
18
© 2012 Autodesk
Workflow: Visualization of existing assets
• Data: Existing 2D data from GIS• 3D structure: Height calculation in LOD2• Areal photos: Google Earth• Terrain model: Google Earth
• Autodesk Product: Autodesk Infrastructure Modeler
© 2012 Autodesk
Video
Workflow: Visualization of existing assets
11/5/2012
19
© 2012 Autodesk
• Data: Combines different graphical databases• Laserscans • 2D-Cadaster + 3D Objects, overground and underground• areal photos and raster data• attribute data
• Autodesk Product: Autodesk Plant3D
Workflow: Above-ground Pipeline Management
© 2012 Autodesk
Video
Workflow: Above-ground Pipeline Management
11/5/2012
20
© 2012 Autodesk
Workflow: Facility Management
• Combine different graphical and non-graphical DB incl. „spatial facility data“• Covers the complete lifecycle of a building• Autodesk Product: Autodesk Architecture + Revit, Rev it Structure + Apps
© 2012 Autodesk
Video
Workflow: Facility Management
11/5/2012
21
© 2012 Autodesk
The HKM digital Factory: ISyDiF for DP
© 2012 Autodesk
Video
Workflow: Factory Design Process
11/5/2012
22
© 2012 Autodesk
High-quality 3D visualization for project review
© 2012 Autodesk
High-quality 3D Visualization for Project review
11/5/2012
23
© 2012 Autodesk
Autodesk® Infrastructure Design Suite Premium 2013 � enhances the customers ability to implement BIM for infrastructure, � helping them design smarter and faster with intelligent model–based
design tools, � evaluate project performance with integrated analysis and simulation, � and communicate with visualization throughout the project lifecycle.
Autodesk Infrastructure Design Suites
© 2012 Autodesk
AutoCAD ® Civil 3D ®
Autodesk ® 3ds Max ® Design
Autodesk ® Revit ® Structure
AutoCAD ® Raster Design
AutoCAD ® Map 3D
AutoCAD ® Utility Design
Autodesk ® Navisworks ® Simulate
Autodesk ® Navisworks ® Manage
Autodesk ® Infrastructure Modeler
AutoCAD ®
Autodesk Infrastructure Design Suite Ultimate
11/5/2012
24
© 2012 Autodesk
ISyDiF What´s next: Augmented Reality
© 2012 Autodesk
Video
ISyDiF What´s next: Augmented Reality
11/5/2012
25
© 2012 Autodesk
ISyDiF What´s next: 3D visualization w/ AIM-Viewer
© 2012 Autodesk
Summary
� Efficient project collaboration, 2D and 3D coordination and communication in planning, execution and maintenance
� Interdisciplinary work from mechanical engineering to the electrical engineering, from building management to plant design and GIS capabilities
� Seamless, integrated, fast, secure, reliable, mobile
and, last but not least:
� One-face-(partner)-to-the-customer: Man and Machine
11/5/2012
26
© 2012 Autodesk
The HKM digital Factory: All Software components ISyDiF
© 2012 Autodesk
� Q&A
11/5/2012
27
© 2012 Autodesk
Contact:
Frank MarkusMan and Machine Inc.BU Infrastructure
Christophstrasse 7D-70178 StuttgartTel. +49 711 933 4830Email: [email protected]
© 2012 Autodesk
Autodesk, AutoCAD* [*if/when mentioned in the pertinent material, followed by an alphabetical list of all other trademarks mentioned in the material] are registered trademarks or trademarks of Autodesk, Inc., and/or its subsidiaries and/or affiliates in the USA and/or other countries. All other brand names, product names, or trademarks belong to their respective holders. Autodesk reserves the right to alter product and services offerings, and specifications and pricing at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document. © 2012 Autodesk, Inc. All rights reserved.