GROUND INVESTIGATION REPORT for the site at ... INVESTIGATION REPORT for the site at on behalf of...
Transcript of GROUND INVESTIGATION REPORT for the site at ... INVESTIGATION REPORT for the site at on behalf of...
GROUND INVESTIGATION REPORT
for the site at
*****************
on behalf of
*****************
Land Science (Brighton) Ltd • 28-29 Carlton Terrace • Portslade • Brighton • East Sussex • BN41 1UR
T: 0845 604 6494 • F: 01273 423 216 • W: landscience.co.uk
Ground Investigation Page 2 of 19 *****************
D O C U M E N T C O N T R O L
Title:
GROUND INVESTIGATION REPORT
Site: *****************
Client: *****************
Date: 08/12/2010
Reference: LS0237
Version: v2 (updated to incorporate CP borehole)
Prepared by:
SALLY REDMAN M.Sc., B.Sc. (Hons.), F.G.S., AIEMA
Engineer
Checked by:
ELLIOT TOMS CEnv., M.Sc., B.Sc. (Hons.), F.G.S., MIEnvSci
Managing Director
Land Science (Brighton) Ltd is part of the Land Science Ltd group of companies, specialist
consultants in Geotechnical Engineering and Contaminated Land for construction, regulation,
property ownership, and due diligence. By understanding our client’s needs and appreciating
the role that ground issues play within a wider context, we are able to provide focused,
pragmatic, and technically excellent advice. For more information on how Land Science can
benefit your project, please visit www.landscience.co.uk
Ground Investigation Page 3 of 19 *****************
C O N T E N T S
1.0 INTRODUCTION .......................................................................................................... 5
1.1 General ..................................................................................................................... 5
1.2 The Site ..................................................................................................................... 5
1.3 Form of Development ................................................................................................. 5
1.4 Geotechnical Objectives .............................................................................................. 5
1.5 Geo-Environmental Objectives ..................................................................................... 5
1.6 Scope of Works .......................................................................................................... 5
1.7 Schedule of Work ....................................................................................................... 6
1.8 Standards .................................................................................................................. 6
1.9 Conditions ................................................................................................................. 7
2.0 DESK STUDY ............................................................................................................... 8
2.1 Site Walkover Survey .................................................................................................. 8
2.2 Geology ..................................................................................................................... 8
2.3 Hydrogeology ............................................................................................................. 8
2.4 Hydrology .................................................................................................................. 9
2.5 Sensitive Land Uses ..................................................................................................... 9
2.6 Industrial Land Uses .................................................................................................... 9
2.7 Radon ....................................................................................................................... 9
2.8 Ground Gases........................................................................................................... 10
2.9 Historical Data .......................................................................................................... 10
2.10 Previous Ground Investigations .................................................................................. 11
3.0 CONCEPTUAL SITE MODEL ......................................................................................... 12
3.1 Contamination Sources ............................................................................................. 12
3.2 Identified Receptors .................................................................................................. 12
3.3 Source-Pathway-Receptor Linkages ............................................................................ 13
3.4 Environmental Investigation Strategy .......................................................................... 13
4.0 ENCOUNTERED CONDITIONS ..................................................................................... 14
4.1 Soils ........................................................................................................................ 14
4.2 Groundwater ........................................................................................................... 14
4.3 Obstructions ............................................................................................................ 14
4.4 Geotechnical Field Testing ......................................................................................... 14
4.5 Geotechnical Laboratory Testing ................................................................................ 15
5.0 ENGINEERING CONSIDERATIONS ................................................................................ 16
5.1 Traditional Foundations............................................................................................. 16
5.2 Piled Foundations ..................................................................................................... 17
5.3 Ground Floor Slabs ................................................................................................... 17
continued…
Ground Investigation Page 4 of 19 *****************
5.4 Excavations .............................................................................................................. 17
5.5 Retaining Walls and Slope Stability ............................................................................. 17
5.5 Pavements ............................................................................................................... 18
5.6 Building Materials ..................................................................................................... 18
5.7 Soakaways ............................................................................................................... 19
F I G U R E S
FIGURE 1: Site Location Plan
FIGURE 2: Investigation Layout Plan
A P P E N D I C E S
APPENDIX A: Desk Study
APPENDIX B: Engineering Logs
APPENDIX C: Geotechnical Testing Results
Ground Investigation Page 5 of 19 *****************
1.0 INTRODUCTION
1.1 General
Land Science (Brighton) Limited was instructed by ***************** to undertake a phase I
and phase II geotechnical and geo-environmental investigation in relation to the proposed
redevelopment of the site at ***************** (see figure 1).
1.2 The Site
In summary, the site comprised two residential development plots which were situated on a
steeply sloping land within the grounds of *****************. A site walkover survey is
presented in section 2.0.
1.3 Form of Development
It was understood that the proposed development was to comprise the construction of two
residential properties together with private gardens, areas of car parking, provision of utility
services, and associated infrastructure. The steeply sloping nature of the site required a number of
low retaining walls to be constructed. Figure 2 illustrates the layout of the proposed development.
1.4 Geotechnical Objectives
A geotechnical investigation was required to provide an interpretation of ground conditions with
respect to foundation design, pavement construction, soakaways, concrete specification,
excavation stability, basement construction parameters, and basic slope stability considerations.
1.5 Geo-Environmental Objectives
Furthermore, an investigation into geo-environmental aspects of the site was required, in order to
provide a generic quantitative risk assessment (GQRA) in respect of the proposed redevelopment,
adjacent land uses, and the wider environment, in the context of the planning regime and PPS23.
1.6 Scope of Works
Phase I of the investigation was to comprise a desk study of geotechnical and environmental factors
pertaining to the site, in order to formulate a geo-environmental Conceptual Site Model (‘CSM’),
and to identify areas of geotechnical concern relevant to the proposed redevelopment.
In turn, this information was used in the design of the Phase II intrusive investigation and, within
the constraints of the original appointment, the investigative positions and laboratory testing were
to be targeted to geotechnical and geo-environmental areas of concern as appropriate.
The scope of works initially agreed with the client broadly comprised the drilling of a series of
window sampler boreholes and accompanying dynamic probes, with preliminary falling head
soakage tests undertaken in a number of positions.
Ground Investigation Page 6 of 19 *****************
Soft weak Head Deposits were identified in the location of one of the proposed new dwellings
(lower plot), and Land Science returned to site with the Client to excavate a two further trial holes
in this location. Based on the findings, it was agreed to that a piled foundation solution was likely to
be required in this location, it was agreed to return to site to drill a cable percussive borehole to
obtain pile design parameters.
1.7 Schedule of Work
The following table summarises the dates that the various elements of the investigation works
were conducted:
Element Details
Instruction An instruction to proceed with the investigation was received from
************ on behalf of ************ on 29th
October, 2010.
Desk Study The desk study was commenced immediately upon receipt of the Client’s
instruction to proceed. A site walkover survey was conducted as part of the
field work.
Fieldwork The initial phase of intrusive investigation was completed on 9th
November,
2010. Land Science returned on 29th
November 2010 to excavate two
further trial holes with the Client on the lower plot. Based on the results,
Land Science returned to site on 6th
December 2010 to drill a cable
percussive borehole.
Laboratory Analysis Samples were submitted to the geotechnical laboratory (K4 Soils Ltd)
immediately upon completion of the first phase of fieldwork, with the
analysis completed by 26th November 2010.
Schedule of completion of investigation works
1.8 Standards
Where practicable, the ground investigation and subsequent geotechnical and environmental
assessments were undertaken in accordance with the following documents and guidance:
o CLR11: Model Procedures for the Management of Contaminated Land, DEFRA and
Environment Agency 2004
o Environment Agency Guidance on Requirements for Land Contamination Reports, Version 1
dated July 2005.
o Planning Policy Statement (PPS) 23: Pollution.
o Building Regulations Approved Document C: Site preparation and resistance to contaminants
and moisture.
o NHBC Standards Chapter 4.1 Land Quality - Managing Ground Conditions, September 1999.
Other technical sources have been identified in respect of specific aspects of the investigation, as
referenced throughout the text.
Ground Investigation Page 7 of 19 *****************
1.9 Conditions
Geotechnical and/or environmental interpretations are inherently dependant on the conditions
revealed by a limited set of data and the accepted means of interpreting that data in use at the
time of the investigation. Every effort is made to ensure that such data is accurate and
representative, and that any assessment is performed under current best practice. However, we do
not accept any liability for the scope of the investigation, for conditions that have not been directly
revealed through the investigation, or for the ultimate reliability of any published and current
assessment criteria or procedures adopted in interpreting that data.
Any spatial or temporal extrapolation or inference is conjectural and no liability can be accepted for
its accuracy; in particular, differing conditions may be revealed between or under points of
investigation, and the concentrations or levels of mobile liquid and gaseous materials are likely to
vary over time. It is also an inherent aspect of any investigation that areas of concern not previously
anticipated are identified as works progress, and elements of the project design may vary during or
after completion of the investigation; whilst every effort is made to tailor the investigation to suit
within practical constraints as works progress, it may become necessary to undertake additional
investigation work.
Information contained in this report is intended for the use of the Client and his agents for the
purposes set-out in the text, and Land Science (Brighton) Ltd makes no warranty or representation
whatsoever express or implied with respect to the use of this information by any other party or for
uses other than those described. We do not indemnify the Client or any third parties against any
dispute, claim or consequential losses arising from any finding or other result of this investigation
report. No aspect of this report should be taken as a guarantee that a site is free of hazardous or
potentially contaminative materials.
Ground Investigation Page 8 of 19 *****************
2.0 DESK STUDY
The findings of the Phase I Desk Study are summarised in the following section, with relevant
information obtained presented in Appendix A. Comments made in the following section are based
purely on the desk study.
2.1 Site Walkover Survey
Land Science undertook two formal inspections of the site, once during the fieldwork on 9th
November 2010, and again on 29th
November 2010 to inspect excavations being made as part of
site enabling works.
In summary, the areas under investigation comprised two residential development plots situated
on steeply sloping land within the grounds of *************.
The lower plot was situated adjacent to the *************, with a flat level area (upon which the
new dwelling was to be constructed) and a bank at the rear rising steeply at around 30O to 40
O. The
ground was noted to be soft under foot. The area was heavily wooded; there were numerous tall
mature trees around the perimeter of the plot, and a number of old tree stumps were noted within
the plot itself.
Conditions in this area had broadly remained unchanged by the time of the second visit, with the
exception of a small cut having been made into the toe of the existing slope revealing heavily
weathered light brown Chalk putty with abundant intact Chalk fragments.
Access to the plots was gained via a shared driveway with *************. The driveway
transversed the slope diagonally upwards to the upper plot, before turning back on itself towards
the existing dwelling. The upper plot sloped less steeply than the bank between the two plots, at an
angle in the order of 10O. This plot comprised more formal gardens of the existing dwelling, with
the area being mainly laid to lawn with shrubs and the like.
By the time of the second visit an excavation into the slope to create the working area for the
building construction had been made, with a cut face up-slope approximately 2.00m high standing
near vertically and comprising reasonably unweathered blocky chalk.
2.2 Geology
British Geological Survey 1:50,000 sheet number 300 entitled "Alresford” indicated the geology of
the site to comprise the Lewes Nodular Chalk Member (hard nodular chalk with flints) with a thin
tract of Head Deposits along the lower southern boundary (variable deposits of sandy silty clay,
locally gravelly, chalky and flinty in dry valleys).
2.3 Hydrogeology
The table overleaf summarises the relevant groundwater vulnerability data for the site:
Ground Investigation Page 9 of 19 *****************
Aspect Classification Details
Superficial Deposits
(south of the site)
Secondary Aquifer
(undifferentiated)
Assigned in cases where it has not been possible to
attribute either category A or B to a rock type.
Bedrock geology Principle Aquifer These are layers of rock or drift deposits that have
high intergranular and/or fracture permeability -
meaning they usually provide a high level of water
storage. They may support water supply and/or river
base flow on a strategic scale.
Groundwater vulnerability data
The site has been identified to lie within a Source Protection Zone III. An SPZ is a protection zone
placed around a well or borehole that supplies groundwater of potable quality. An SPZ is divided
into three zones defined as follows:
o Zone I - Travel time (of water) of 50 days or less to the groundwater source.
o Zone II - Either 25% of the source area or a travel time of 400 days whichever is greater.
o Zone III - The total area needed to support the abstraction.
There were no groundwater abstractions identified within 500m of the site.
2.4 Hydrology
There are no major watercourses on site or in the immediate vicinity. The site does not lie within an
area classified as being susceptible to flooding. There were no surface water abstractions, discharge
licenses, or pollution incidents identified within 500m of the site.
2.5 Sensitive Land Uses
No such sensitive land uses were identified within a 250m radius of the site.
2.6 Industrial Land Uses
No potentially contaminative land uses were identified on site or in the immediate vicinity.
2.7 Radon
In accordance with BRE 211:2007, the site lies in an area where between 1% and 3% of homes
exceed the government threshold for Radon gas in residential dwellings. A BGS report obtained by
Land Science confirmed that basic Radon Protection Measures are required at this site. Basic Radon
Protection Measures include the use of a well-constructed damp-proof membrane through wall
cavities and beneath the floor scree. Such details should be shown on proposed construction
drawings, and installation should be verified by the building inspector.
Ground Investigation Page 10 of 19 *****************
2.8 Ground Gases
A search waste treatment and disposal sites was undertaken as part of the desk study. Such sites
may form an artificial source of land gases, such as Carbon Dioxide and Methane, where wastes are
buried or disposed of to landfill. No such waste facilities or landfill sites were identified within a
1km radius of the site. The risk to the site is likely to be generally very low in this respect.
In terms of land gases generated from natural sources, it was noted that the site was underlain by
Chalk. The dissolution of carbonate cements by the infiltration of acidic waters may give rise to the
generation of low levels of Carbon Dioxide.
2.9 Historical Data
Historical maps dating back to 1870 were obtained as part of the desk study. A summary of the
apparent key features noted on the map extracts both on the site and within the local area is
presented on the table below.
Date On Site Off Site
1870 The site comprises open land and a
small area of woodland.
The surrounding area comprises open land
with small areas of woodland. Beech Farm is
located to the north-west. A track runs along
to the south of the site.
1896 No significant changes noted. No significant changes noted.
1910 ************* is indicated; the
dwelling is not in the same location as
the present day and lies within a
parcel of land larger than the present
day. The development plots fall within
the associated gardens.
Residential properties have been developed to
the east and west.
1939 An ancillary building is noted to the
north of the main property and a
possible garage located to the south,
adjacent to the drive.
Further residential properties have been
developed to the north and east. Beech Farm
is now known as The Old Farm.
1977 A further small ancillary building has
been developed adjacent to the north
of the main building. The driveway
appears to have been realigned onto
land to the east.
Further residential properties are indicated in
the immediate vicinity. The track to the south
is now labelled *************.
1993 Insufficient coverage. Insufficient coverage.
1997 The dwelling appears to have been
demolished and replaced with a new
structure, commensurate with the
present day house.
One residential property has been developed
adjacent to the site.
Summary of Historical Map extracts
Ground Investigation Page 11 of 19 *****************
In summary, the site appeared to initially comprise open fields and woodland until c.1910, whereby
the land fell within the grounds of *************. The dwelling was located to the west of the
current existing property, close to the proposed location of the new dwelling on the upper plot. A
number of outbuildings and a garage were shown on subsequent maps. The 1997 map shows the
old dwelling to have been replaced with the current dwelling.
The surrounding area comprised open land with small woodland/scrubland areas, with a farm
(Beech Farm) located to the north-west up until c.1910 (later Beech Place). By c.1910, residential
properties had been developed within the immediate vicinity of the site, with further dwellings
being built after this date.
2.10 Previous Ground Investigations
Land Science (Brighton) Ltd was not aware of any previous investigation that may have been
undertaken on the site.
Ground Investigation Page 12 of 19 *****************
3.0 CONCEPTUAL SITE MODEL
The following sections summarise the anticipated environmental factors likely to impact upon the
site in the context of the proposed redevelopment, in order to provide a justification and rationale
for the subsequent phase II ground investigation.
3.1 Contamination Sources
Possible sources of contamination identified or discounted as part of the desk study are
summarised on the following table:
Source Description Notes
Land Gases Carbon Dioxide generated from the
dissolution of carbonate cements
within the New Pit Chalk Formation.
Possible trace levels of Carbon
Dioxide (CO2).
Radon Gas Naturally occurring Radon gas Basic Radon Protection Measures are
required for new dwellings at this
site.
Possible Sources of Contamination
3.2 Identified Receptors
Furthermore, potential receptors associated with the site and its redevelopment, identified or
otherwise discounted, are summarised on the following table:
Receptor Description Notes
Site Workers Persons involved in construction and
future maintenance.
Major ground works are proposed
including foundation excavation.
End Users Occupants of the proposed
redevelopment.
Residential development with private
domestic gardens.
Soft Landscaping Areas of planting including lawns,
shrubs, trees, etc.
Substantial areas of private soft
landscaping are proposed.
Building Materials Elements of the built environment in
direct contact with the ground.
Buried plastics (e.g. water supplies)
and concrete (e.g. foundations) may
be laid.
Adjacent Land
Users
Sensitive land uses identified within
the immediately vicinity
Residential gardens were identified
immediately adjacent to the site.
Ground Water Controlled Waters contained within
the aquifer(s) beneath the site
The site overlies a major aquifer and
the site lies within a groundwater SPZ
III (total catchment).
Possible Receptors of Contamination
Surface water and ecological receptors have not been identified as significant receptors.
Ground Investigation Page 13 of 19 *****************
3.3 Source-Pathway-Receptor Linkages
Whilst the various possible sources and receptors have been identified, the following matrix
illustrates the identified pathways by which a contaminant linkage might plausibly exist:
Source
Land Gases Radon Gases
Re
cep
tors
Site Workers Asphyxiation None
End Users None None
Soft Landscaping None None
Building Materials None None
Adjacent Land Users Not applicable Not applicable
Ground Water None None
Identified Source-Pathway-Receptor linkages
The proposed dwellings will include basic Radon Protection Measures. Such measures are also
sufficient to protect against low concentrations of Carbon Dioxide. No other sources have been
identified. As such no risks are posed to End Users.
Radon Gas and Land Gases (Carbon Dioxide) will not pose a risk to soft landscaping, building
materials, or groundwater, and pathways between off-site receptors and ubiquitous sources of
contamination that exist both on-site and off-site are not applicable to this assessment.
The concentrations of Radon Gas at this site are such that the workplace exposure limit set at
200Bq.m-3
is unlikely to be exceeded; thus no significant risk is posed in this respect.
Whilst a plausible risk may exist with respect to trace levels of Carbon Dioxide and site personnel
working in confined spaces such as deep excavations, pre-entry monitoring in accordance with
Health and Safety requirements should ensure that any risks posed in this respect are adequately
dealt with.
3.4 Environmental Investigation Strategy
On the basis that no significant plausible source-pathway-receptor linkages have been identified,
no environmental investigation was considered necessary. Deep excavation must be pre-monitored
for Carbon Dioxide and Oxygen (amongst any other gases as identified by a confined space risk
assessment) prior to personnel entry.
Ground Investigation Page 14 of 19 *****************
4.0 ENCOUNTERED CONDITIONS
A factual record of the conditions encountered during the physical investigation of the site is
presented in the following sections.
4.1 Soils
According to published information the anticipated geological succession beneath the site was
indicated to comprise Lewes Nodular Chalk with a thin tract of Head Deposits in the southern lower
part of the site. The investigation generally confirmed the anticipated geological succession.
Topsoil was encountered in all window sampler boreholes, to depths in the range of 0.30m and
0.50mbgl. In summary, these materials generally comprised dark brown clayey sandy gravelly silt
with rootlets.
Head Deposits were encountered on the lower plot within WS2, WS3, the two further trial holes,
and BH1, and were proved to a maximum depth of 2.70mbgl (within the trial holes). Generally
these materials were identified as brown silty, sandy very gravelly CLAY (the gravel being fine to
coarse angular flint).
A further zone of similar materials was also encountered within WS6 to a depth of 2.80mbgl, close
to the location of the garage at the upper plot. These materials may represent localised weathering
of the underlying Chalk.
The Lewes Nodular Chalk was encountered across the site from depths in the range of 0.30m to
2.80mbgl, and was proved to a maximum depth of 15.50mbgl within the cable percussive borehole.
In the lower plot, the Chalk was noted to comprise white to light brown putty CHALK with limited
proportions of gravel sized medium density Chalk fragments. In the upper plot, these materials
were recovered as weak off-white gravel to cobble sized intact CHALK with horizons bearing limited
proportions of weathered Chalk putty; the in-situ Chalk exposed in the ongoing excavation at the
upper plot inspected during the second site visit was noted to be blocky and structured with widely
spaced and open (<3mm) joints and occasional flint beds.
4.2 Groundwater
Groundwater was not encountered during excavation of any of the investigative positions, and was
not anticipated at shallow depth.
4.3 Obstructions
No below ground artificial impenetrable solid obstructions were encountered during the fieldwork.
4.4 Geotechnical Field Testing
Super Heavy Dynamic Probes were undertaken at positions WS1 and WS4.
Ground Investigation Page 15 of 19 *****************
Generally the results from WS1 ranged between DP’N’=1 to DP’N’=13, (predominantly less than
DP’N’=9, and averaging DP’N’=4); the values increased considerably between at 5.70m and 5.90m,
and the probe was terminated at 5.90m upon a flint or similar.
The results from WS4 generally ranged between DP’N’=3 to DP’N’=20 (predominantly less than
DP’N’=12, averaging approximately DP’N’=8); the values increased considerably between 5.50m to
6.00m with the position being terminated at 6.00m.
In-situ SPT tests were undertaken at 1.5m centres within the cable percussive borehole. A test
result of SPT’N’=9 was obtained for the Head Deposits. For the Chalk, two identical results of
SPT’N’=16 were obtained for the more weathered putty, increasing to between SPT’N’=18 and
SPT’N’=41 within the more intact Chalk below 6.00m.
4.5 Geotechnical Laboratory Testing
The results of two Particle Size Distribution determinations undertaken on the New Pit Chalk
indicated the proportion of gravel was 32.9%-38.4%, sand 19.5%-24.6%, and silt/clay 36.9%-47.6 %.
The laboratory description of this material was off white putty CHALK with occasional fine to
medium intact chalk fragments.
The results of two Particle Size Distribution determinations undertaken on the Head Deposits
indicated the proportion of gravel was 43.3%-55.1%, sand 10.7%-12.5%, and silt/clay 34.2%-44.2%.
The laboratory description of this material was brown sandy gravelly CLAY with occasional fine to
medium chalk fragments (gravel is fine to medium and sub rounded to angular).
Atterberg Limit analysis on a sample of the New Pit Chalk gave a plasticity index of 6% (or 3.1%
when modified to account for the proportion passing the 425µm sieve). Within the Head Deposits,
plasticity indexes ranged between 20% and 40%, or between 11.8% and 21.2% when modified to
account for the proportion passing the 425µm sieve.
Water soluble Sulphate determination were undertaken on a total of two samples of soil, with the
results ranging between 0.09g/l and 0.10g/l; the accompanying pH results ranged between pH7.4
and 7.6. Elevated Sulphate and highly acidic soil is not generally associated with Chalk strata.
Ground Investigation Page 16 of 19 *****************
5.0 ENGINEERING CONSIDERATIONS
Subsequent to intrusive investigation of the site and receipt of the laboratory results, the following
interpretative assessments have been made with respect to engineering considerations.
5.1 Traditional Foundations
Based on the ground and groundwater conditions encountered within the boreholes on the upper
(northern) plot, it is considered that traditional foundations are appropriate for the proposed
development in that location.
However, on account of the deep Head Deposits and soft weathered putty nature of the underlying
Chalk, and on account of potential requirements for trench stability and heave precautions, it is
recommended that an alternative foundation such as the use of piles is considered for the Lower
(southern) plot.
The following recommendations in respect of traditional foundations apply to the northern plot
only.
The Chalk should be treated as not being susceptible to volume change as defined by the NHBC
Standards 4.2 (i.e. non shrinkable).
Based on the in-situ testing results and typical settlement parameters for the types of soil
encountered, a maximum net allowable bearing capacity of 150kPa is applicable to trench
foundations taken through any Made Ground, soft or loose zones, or disturbed soils, and wholly
into or onto the intact blocky Chalk of the Lewes Nodular Chalk Formation. This assessment
includes an appropriate factor of safety against shear failure, and total settlements should remain
within tolerable limits.
A zone of Head Deposits was identified at WS6, outside the footprint of the proposed main dwelling
structure but in close proximity to the nearby garage. The foundation excavations for the garage
should be carefully inspected, and where Head Deposits are encountered it is recommended that
either the widths are increased based on a maximum net allowable bearing capacity of 50kPa and
foundation nominally reinforced, or that they are taken down onto the less weathered blocky
Chalk. It should also be noted that the Head Deposits corresponded to a medium volume change
potential as defined by the NHBC Standards, and that heave precautions would be required within
the zone of influence of trees. It might be prudent to set out the foundations in this area and
excavate a number of strategically placed trial holes prior to construction to assess ground
conditions in this area.
No evidence of solution features was noted on the site during the investigation. The site lies within
an area where solution features may be present, and care should be taken during construction to
identify any possible suspect soil conditions. Special precautions may be required where evidence
of solution features is identified.
Ground Investigation Page 17 of 19 *****************
5.2 Piled Foundations
Piled foundations are recommended for the lower (southern) plot on account of the significant
thicknesses of soft shrinkable Head Deposits and weathered Chalk. The construction of piled
foundations is a specialist job and the advice of a reputable local contractor familiar with the type
of ground and groundwater conditions encountered on this site should be sought prior to finalising
the design. The actual working load for proposed piles will depend on the particular type of pile and
method of installation adopted.
The contractor should design piles in accordance with CIRIA Project Report 11, and in particular
should adopt factors of safety of 2.5 and 5 on the skin friction and end bearing working loads
respectively. For pile groups, the bearing value of each individual pile should be reduced by a factor
of 0.8 and a calculation made to check for the factor of safety against block failure. All piles should
be taken at least five times their diameter into the founding strata. Where bored piles are adopted,
casing may be required in the upper sections to prevent necking.
In accordance with the NHBC Standards, heave precautions may be required on the upper portions
of piles and on ground beams within the zone of influence of trees, and the piles should be
designed to resist uplift forces that may develop.
5.3 Ground Floor Slabs
Ground floor slabs on the upper dwelling may be constructed as ground bearing, with a maximum
net allowable bearing capacity of 25kN/m2. The sub-grade should be carefully proof rolled and any
soft or loose zones replaced with compacted granular engineering fill.
The use of a ground bearing floor slab for the garage at the upper plot will depend on ground
conditions exposed at the formation level; where significant thicknesses of Head Deposits are
encountered it would be necessary to adopt a suspended ground floor slab.
On account of the soil conditions at the lower plot, ground floor slabs should be fully suspended.
5.4 Excavations
Excavations within the Head Deposits may be generally stable in the short term, being susceptible
to possible localised spalling and collapse; shallow trenches to be left open for short periods may
simply be battered back to a safe angle, whilst appropriate trench support should be considered for
deeper trenches to be left open for prolonged periods. Excavations within the Chalk should remain
generally stable.
5.5 Retaining Walls and Slope Stability
A number of retaining walls are proposed, independent of the building construction, in order to
accommodate the new dwellings. A full engineering assessment of slope stability issues was outside
the scope of this report, although the following advice is given for preliminary purposes.
Ground Investigation Page 18 of 19 *****************
The excavations for the retaining walls at the upper plot had already been commenced at the time
of the second site visit by Land Science. The cut face was up to approximately 2.00-2.50m in height,
and exposed blocky and structured Chalk with broadly horizontal widely spaced and open (<3mm)
joints and occasional flint beds. Whilst cut faces in structured blocky Chalk can stand near vertically,
there are issues with long-term instability associated with spalling, issues related to weathering and
surface protection, and issues associated with serviceability. Where a cut slope is to be
incorporated into the final landscaping design, the angle should not exceed 60O and faces should be
provided with a basic surface protection to prevent spalling and weathering; above this angle, it is
recommended that a basic form of retaining wall is constructed.
Retaining walls approximately 1.50m in height are also required at the rear of the lower plot,
involving excavation along the toe of the slope, and special care and consideration should be given
when designing the associated temporary and permanent works. Materials in this area comprise a
mixture of weathered putty Chalk and soft Head Deposits, and it is likely that some form of
embedded retaining wall would be most appropriate. With reference to BS8002:2004, parameters
for retaining wall design in Head Deposits have been assessed as follows:
Parameter Value
Co-efficient of active earth pressure (Ka) 0.28
Co-efficient of passive earth pressure (Kp) 5.0
Saturated bulk density (γ) 18.0
Angle of shearing resistance of the soil (φ’) 30O
Preliminary retaining wall design parameters
These values are based on a number of critical assumptions, which must be checked and verified as
part of the actual retaining wall design:
o Angle of shearing resistance between the ground and the wall, δ = 20O
o The surface of the ground level to the rear of the wall is inclined at an angle, ß = 30O
o The retained soil may be characterised as a firm clay
5.5 Pavements
Given the variability of the likely sub-grade, it is recommended that the formation should be
treated as being frost susceptible for pavement design purposes, and therefore a minimum
pavement thickness of 450mm adopted. The formation should be carefully proof rolled and any
soft or loose zones replaced with well compacted granular fill.
5.6 Building Materials
The results of the Sulphate and pH analyses fell into Class DS-1 of the current revision of BRE
Special Digest 1. An ACEC class of AC-1 is appropriate based on the pH results and known site
history. The advice of this publication should be taken for the design and specification of all sub
surface concrete.
Ground Investigation Page 19 of 19 *****************
5.7 Soakaways
Preliminary falling head soakage tests were undertaken within WS3 and WS6, which gave
infiltration rates of 1.4x10-4
m.s-1
and 5.8x10-6
m.s-1
respectively. Both boreholes were drilled
through Head Deposits with Chalk towards the base; the higher result in WS3 may be on account of
more granular materials within the Head Deposits. Given this variability, soakaways constructed
into the Head Deposits should be designed based on the more conservative lower infiltration rate
of 5.8x10-6m.s-1. Higher infiltration rates may be realised within the blocky fissured Chalk. Should
improve infiltration rates be required, it would be necessary to conduct full-scale soakage tests in
accordance with BRE365.
Given the sites location within a groundwater Source Protection Zone, and in order to protect
groundwater resources, the Environment Agency might have special requirements for the design of
soakaways including water seals, closed surface entries or interceptors. The consideration of the
Agency should be sought in this respect.
Concentrated discharges into the Chalk from surface water drainage may cause the dissolution of
carbonate cements within rock matrix, which may in turn lead to voiding, instability, and surface
collapse. Such discharges may also potentially reactivate any inactive dissolution features. It is
therefore recommended that all soakaways be located a minimum of 10m distant from any
sensitive structures.
Finally, soakaways should be carefully positioned so as to avoid concentrated point discharges close
to the existing slope, as this may cause instability.
TITLE: REF:
PROJECT: VERSION
CLIENT: FIGURE:
PREPARED: CHECK: DATE: SHEET No:
page: 1 of 1
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
LS0237
v1
1
SR ET 29/10/2010
Site Location Plans
TITLE: REF:
PROJECT: VERSION
CLIENT: FIGURE:
PREPARED: CHECK: DATE: SHEET No:
page: 1 of 1SR ET 29/10/2010
Investigation Layout Plans
**************************
**************************
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
LS0237
v1
1
WS1
WS2
WS3
WS4 WS5
WS6
BH1
APPENDIX A
TITLE: REF:
PROJECT: VERSION
CLIENT: FIGURE:
PREPARED: CHECK: DATE: SHEET No:
page: 1 of 1
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
LS0237
v1
1
SR ET 30/11/2010
1870 Historical Map 1:2500
**************
**************
TITLE: REF:
PROJECT: VERSION
CLIENT: FIGURE:
PREPARED: CHECK: DATE: SHEET No:
page: 1 of 1
1896 Historical Map 1:2500 LS0237
************** v1
************** 1
SR ET 30/11/2010
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
TITLE: REF:
PROJECT: VERSION
CLIENT: FIGURE:
PREPARED: CHECK: DATE: SHEET No:
page: 1 of 1
1910 Historical Map 1:2500 LS0237
************** v1
************** 1
SR ET 30/11/2010
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
TITLE: REF:
PROJECT: VERSION
CLIENT: FIGURE:
PREPARED: CHECK: DATE: SHEET No:
page: 1 of 1
1939 Historical Map 1:2500 LS0237
************** v1
************** 1
SR ET 30/11/2010
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
TITLE: REF:
PROJECT: VERSION
CLIENT: FIGURE:
PREPARED: CHECK: DATE: SHEET No:
page: 1 of 1
1977 Historical Map 1:2500 LS0237
************** v1
************** 1
SR ET 30/11/2010
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
TITLE: REF:
PROJECT: VERSION
CLIENT: FIGURE:
PREPARED: CHECK: DATE: SHEET No:
page: 1 of 1
1997 Historical Map 1:2500 LS0237
************** v1
************** 1
SR ET 30/11/2010
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
APPENDIX B
REMARKS TITLE: REFERENCE: POSITION:Stability:
Groundwater: PROJECT: ELEVATION: CO-ORDINATES:
Chiselling:CLIENT: METHOD:
Casing/dia:
Backfilling: STARTED: SCALE:
Obstructions:COMPLETED: SHEET No:
Others:
Dark brown SILT with fine to coarse angular gravel and
cobbles, and rootlets. (TOPSOIL)
Weak white and occasional light brown putty CHALK with
layers of gravel sized medium density chalk fragments.
(LEWES NODULAR CHALK MEMBER)
Continued on next page.
No obstructions encountered
Hand excavated to 0.40mbgl
No instability encountered
No groundwater encountered
Not applicable
Not recorded
Position backfilled with arisings
D
D
D
D
D
D
D
D
INPUTTED BY:
SR Page: 1 of 2
Not to scale
Archway "Dart" Windowless Sampler
N/A
LOGGED BY:
SRAA DRILLING
DRILLED BY:
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
**************
**************
Not to scale
WS1
09/11/2009
09/11/2009
LS0237
D
D
ET
0.00
Borehole log
0.00
0.10 0.50
5.00
0.50 0.50
1.501.00 -
1.50 - 2.00
2.00 - 2.50
2.50 - 3.00
3.00 - 3.50
3.50 - 4.00
4.00 - 4.50
4.50 - 5.00
- 1.00 D
0.10
-
FILLWATERDESCRIPTION TESTING SAMPLING
CHECKED BY:
-
REMARKS TITLE: REFERENCE: POSITION:Stability:
Groundwater: PROJECT: ELEVATION: CO-ORDINATES:
Chiselling:CLIENT: METHOD:
Casing/dia:
Backfilling: STARTED: SCALE:
Obstructions:COMPLETED: SHEET No:
Others:09/11/2009 Page: 2 of 2
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
Continued…..Weak white and occasional light brown putty
CHALK with layers of gravel sized medium density chalk
fragments. (LEWES NODULAR CHALK MEMBER)
Borehole complete at 6.00m.
No obstructions encounteredINPUTTED BY: CHECKED BY:
Hand excavated to 0.50mbgl SR ET
Not recorded ************** Archway "Dart" Windowless Sampler
Position backfilled with arisings DRILLED BY: LOGGED BY:
AA DRILLING SR 09/11/2009 Not to scale
No instability encountered Borehole log LS0237 WS1No groundwater encountered
************** N/A Not to scaleNot applicable
6.00
D5.50 - 6.00
D
FILL
5.00 5.00 - 5.50
DESCRIPTION TESTING SAMPLING WATER
REMARKS TITLE: REFERENCE: POSITION:Stability:
Groundwater: PROJECT: ELEVATION: CO-ORDINATES:
Chiselling:CLIENT: METHOD:
Casing/dia:
Backfilling: STARTED: SCALE:
Obstructions:COMPLETED: SHEET No:
Others:
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
Dark brown clayey SILT with rootlets. (TOPSOIL)
Brown silty, sandy gravelly CLAY. (HEAD DEPOSITS)
Borehole complete at 3.00m.
Not to scaleNo obstructions encountered
INPUTTED BY: CHECKED BY:
Hand excavated to 0.30mbgl SR ET 09/11/2009 Page: 1 of 1
Position backfilled with arisings DRILLED BY: LOGGED BY:
AA DRILLING SR 09/11/2009
No groundwater encountered
************** N/A Not to scaleNot applicable
Not recorded ************** Archway "Dart" Windowless Sampler
No instability encountered Borehole log LS0237 WS2
3.00
- 3.00 D2.50
- 2.50 D2.00
- 2.00 D1.50
-1.30 1.50 D1.30
-1.00 1.30 D1.00
- 1.00 D0.50
-0.30 0.50 D0.30
- 0.30 D
SAMPLING WATER FILL
0.00 0.00
Off white slightly weathered CHALK, very weak. Structurless
mélange composed of 70% subangular medium to coarse
gravel sized fragments set in 30% soft, off white chalk matrix;
Grade Dc. (LEWES NODULAR CHALK MEMBER)
Off white CHALK, medium to high density. Discontinuities
very closely spaced (20mm), open (<3mm); medium to high
density Grade B5. (LEWES NODULAR CHALK MEMBER)
DESCRIPTION TESTING
REMARKS TITLE: REFERENCE: POSITION:Stability:
Groundwater: PROJECT: ELEVATION: CO-ORDINATES:
Chiselling:CLIENT: METHOD:
Casing/dia:
Backfilling: STARTED: SCALE:
Obstructions:COMPLETED: SHEET No:
Others:
Borehole complete at 3.00m.
Not to scale
Dark brown wood chippings. (TOPSOIL)
Brown silty, sandy slighty gravelly CLAY with fine to medium
angular chalk. (HEAD DEPOSITS)
Light brown silty sandy very gravelly CLAY. Gravel is fine to
coarse angular flint. (HEAD DEPOSITS)
Brown clayey silty sandy GRAVEL. Gravel is fine to coarse
angular flint. (HEAD DEPOSITS)
Brown silty sandy very gravelly CLAY. Gravel is fine to coarse
angular flint. (HEAD DEPOSITS)
Off white slightly weathered. CHALK, weak. Structureless
mélange composed of 80% subangular to rounded medium to
coarse high density grzel sized fragments set in 20% soft, off
white, silt sized chalk matrix; Grade Dc. (LEWES NODUALR
CHALK MEMBER)
Position backfilled with arisings DRILLED BY:
Hand excavated to 0.40mbgl SR ET
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
09/11/2009 Page: 1 of 1
LOGGED BY:
AA DRILLING SR 09/11/2009No obstructions encountered
INPUTTED BY: CHECKED BY:
No groundwater encountered
************** N/A Not to scaleNot applicable
Not recorded ************** Archway "Dart" Windowless Sampler
No instability encountered Borehole log LS0237 WS3
3.00
-2.80 3.00 D2.80
-2.00 2.50 D2.00
-1.60 2.00 D1.60
- 1.50 D1.00
- 1.00 D0.50
0.40
-0.30 0.40 D0.30
D
FILL
0.00 0.00 - 0.30
DESCRIPTION TESTING SAMPLING WATER
REMARKS TITLE: REFERENCE: POSITION:Stability:
Groundwater: PROJECT: ELEVATION: CO-ORDINATES:
Chiselling:CLIENT: METHOD:
Casing/dia:
Backfilling: STARTED: SCALE:
Obstructions:COMPLETED: SHEET No:
Others:
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
Loose dark brown clayey sandy SILT with rootlets and
occasional fine to coarse gravel sized angular chalk.
(TOPSOIL)
Off white CHALK, weak with high density chalk fragments.
Discontinuities closely spaced (20-60mm), open (<3mm); high
density Grade B5. (LEWES NODUALR CHALK MEMBER)
White CHALK, medium density. Discontinuities very closely
spaced (<20mm), open (<3mm); medium density Grade B5.
(LEWES NODUALR CHALK MEMBER)
Off white CHALK, weak. Structureless mélange composed of
80% subangular to rounded, low density chalk fragments set
in 20% soft, off white, silt size chalk matrix; Grade Dc.
(LEWES NODUALR CHALK MEMBER)
White CHALK, very weak. Structureless mélange composed of
20% subangular to rounded medium sized fragments set in
80% soft, off white/brown silt size chalk matrix; Grade Dm.
(LEWES NODUALR CHALK MEMBER)
Not to scaleNo obstructions encountered
INPUTTED BY: CHECKED BY:
Hand excavated to 0.30mbgl SR ET 09/11/2009 Page: 1 of 2
Position backfilled with arisings DRILLED BY: LOGGED BY:
AA DRILLING SR 09/11/2009
No groundwater encountered
************** N/A Not to scaleNot applicable
Not recorded ************** Archway "Dart" Windowless Sampler
Continued on next page
No instability encountered Borehole log LS0237 WS4
5.00
4.50 - 5.00 D
4.00 - 4.50 D4.00
3.50 - 4.00 D
2.50 - 3.00 D2.50
2.00 - 2.50 D
1.50 - 2.00 D1.50
1.00 - 1.50 D
0.50 - 1.00 D
0.30
D
FILL
0.00 0.00 - 0.30
DESCRIPTION TESTING SAMPLING WATER
REMARKS TITLE: REFERENCE: POSITION:Stability:
Groundwater: PROJECT: ELEVATION: CO-ORDINATES:
Chiselling:CLIENT: METHOD:
Casing/dia:
Backfilling: STARTED: SCALE:
Obstructions:COMPLETED: SHEET No:
Others: Hand excavated to 0.30mbgl
SR
09/11/2009 Page: 2 of 2
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
Continued…White CHALK, very weak. Structureless mélange
composed of 20% subangular to rounded medium sized
fragments set in 80% soft, off white/brown silt size chalk
matrix; Grade Dm. (LEWES NODUALR CHALK MEMBER)
Borehole complete at 6.00m.
No obstructions encounteredINPUTTED BY: CHECKED BY:
N/A
SR ET
Not recorded ************** Archway "Dart" Windowless Sampler
Position backfilled with arisings DRILLED BY: LOGGED BY:
AA DRILLING 09/11/2009 Not to scale
No instability encountered Borehole log LS0237 WS4No groundwater encountered
************** Not to scaleNot applicable
6.00
D
FILL
5.00 5.00 - 6.00
DESCRIPTION TESTING SAMPLING WATER
REMARKS TITLE: REFERENCE: POSITION:Stability:
Groundwater: PROJECT: ELEVATION: CO-ORDINATES:
Chiselling:CLIENT: METHOD:
Casing/dia:
Backfilling: STARTED: SCALE:
Obstructions:COMPLETED: SHEET No:
Others:
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
Loose light brown clayey sandy gravelly SILT with rootlets.
Gravel is fine to coarse chalk and brick. (MADE GROUND)
Off white, slightly weathered CHALK, weak. Structureless
mélange composed of 80% medium to coarse high density
chalk fragments set in 20% soft, brown silt size chalk matrix;
Grade Dc. (LEWES NODUALR CHALK MEMBER)
Off white CHALK, strong, high density. Discontinuities closely
spaced (20-60mm), open (<3mm); High density Grade B4.
(LEWES NODUALR CHALK MEMBER)
Off white/grey very high density gravel of CHALK. (LEWES
NODUALR CHALK MEMBER)
Borehole complete at 3.00m.
Not to scaleNo obstructions encountered
INPUTTED BY: CHECKED BY:
Hand excavated to 0.50mbgl SR ET 09/11/2009 Page: 1 of 1
Position backfilled with arisings DRILLED BY: LOGGED BY:
AA DRILLING SR 09/11/2009
No groundwater encountered
************** N/A Not to scaleNot applicable
Not recorded ************** Archway "Dart" Windowless Sampler
No instability encountered Borehole log LS0237 WS5
3.00
Off white CHALK, strong, high density. Discontinuities very
closely spaced (<20mm), open (<3mm); High density Grade
B4. (LEWES NODUALR CHALK MEMBER) 2.50 - 3.00 D
2.30
1.50 - 2.00 D1.50
1.00 - 1.50 D
0.50 - 1.00 D0.50
0.30 - 0.50 D0.30
D
FILL
0.00 0.00 - 0.30
DESCRIPTION TESTING SAMPLING WATER
REMARKS TITLE: REFERENCE: POSITION:
Stability:
Groundwater: PROJECT: ELEVATION: CO-ORDINATES:
Chiselling:CLIENT: METHOD:
Casing/dia:
Backfilling: STARTED: SCALE:
Obstructions:COMPLETED: SHEET No:
Others:
Borehole complete at 3.00m.
Not to scaleNo obstructions encountered
SR ET 09/11/2009
LOGGED BY:
AA DRILLING SR 09/11/2009
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
Loose dark brown silty sandy gravelly CLAY with rootlets.
Gravel is fine to coarse chalk. (TOPSOIL)
Brown silty sandy very gravelly CLAY with rootlets. Gravel is
fine to coarse angular and sub rounded flint and chalk. (HEAD
DEPOSITS)
Brown very silty sandy slightly gravelly CLAY. Gravel is fine to
coarse angular to sub rounded flint and chalk. (HEAD
DEPOSITS)
Brown silty sandy very gravelly CLAY with rootlets. Gravel is
fine to coarse angular and sub rounded flint and chalk. (HEAD
DEPOSITS)
Off white, slightly weathered CHALK, low density.
Discontinuities very closely spaced (<20mm), open (<3mm);
Low density Grade B5. (LEWES NODULAR CHALK MEMBER)
Page: 1 of 1
Position backfilled with arisings DRILLED BY:
INPUTTED BY: CHECKED BY:
Hand excavated to 0.50mbgl
No groundwater encountered
************** N/A Not to scaleNot applicable
Not recorded ************** Archway "Dart" Windowless Sampler
No instability encountered Borehole log LS0237 WS6
3.00
-2.60 3.00 D2.60
-2.00 2.50 D2.00
- 2.00 D1.50
-1.20 1.50 D1.20
-0.50 1.00 D0.50
D
FILL
0.00 0.00 - 0.50
DESCRIPTION TESTING SAMPLING WATER
Interval DP N100 Interval DP N100
m blows/100mm m blows/100mm
0.0 - 0.1 * 5.0 - 5.1 6
0.1 - 0.2 * 5.1 - 5.2 9
0.2 - 0.3 * 5.2 - 5.3 11
0.3 - 0.4 * 5.3 - 5.4 9
0.4 - 0.5 1 5.4 - 5.5 7
0.5 - 0.6 2 5.5 - 5.6 4
0.6 - 0.7 3 5.6 - 5.7 5
0.7 - 0.8 4 5.7 - 5.8 46
0.8 - 0.9 3 5.8 - 5.9 50
0.9 - 1.0 2 5.9 - 6.0
1.0 - 1.1 3 6.0 - 6.1
1.1 - 1.2 2 6.1 - 6.2
1.2 - 1.3 2 6.2 - 6.3
1.3 - 1.4 3 6.3 - 6.4
1.4 - 1.5 2 6.4 - 6.5
1.5 - 1.6 2 6.5 - 6.6
1.6 - 1.7 2 6.6 - 6.7
1.7 - 1.8 3 6.7 - 6.8
1.8 - 1.9 2 6.8 - 6.9
1.9 - 2.0 2 6.9 - 7.0
2.0 - 2.1 3 7.0 - 7.1
2.1 - 2.2 2 7.1 - 7.2
2.2 - 2.3 3 7.2 - 7.3
2.3 - 2.4 2 7.3 - 7.4
2.4 - 2.5 3 7.4 - 7.5
2.5 - 2.6 3 7.5 - 7.6
2.6 - 2.7 2 7.6 - 7.7
2.7 - 2.8 2 7.7 - 7.8
2.8 - 2.9 2 7.8 - 7.9
2.9 - 3.0 2 7.9 - 8.0
3.0 - 3.1 4 8.0 - 8.1
3.1 - 3.2 5 8.1 - 8.2
3.2 - 3.3 7 8.2 - 8.3
3.3 - 3.4 4 8.3 - 8.4
3.4 - 3.5 2 8.4 - 8.5
3.5 - 3.6 2 8.5 - 8.6
3.6 - 3.7 3 8.6 - 8.7
3.7 - 3.8 7 8.7 - 8.8
3.8 - 3.9 5 8.8 - 8.9
3.9 - 4.0 6 8.9 - 9.0
4.0 - 4.1 5 9.0 - 9.1
4.1 - 4.2 6 9.1 - 9.2
4.2 - 4.3 9 9.2 - 9.3
4.3 - 4.4 5 9.3 - 9.4
4.4 - 4.5 4 9.4 - 9.5
4.5 - 4.6 6 9.5 - 9.6
4.6 - 4.7 8 9.6 - 9.7
4.7 - 4.8 6 9.7 - 9.8
4.8 - 4.9 4 9.8 - 9.9
4.9 - 5.0 13 9.9 - 10.0
Hammer mass 63.5 kg Rod weight 6 kg Date Completed
Gravity constant 9.8 N/kg Base of cone 0.002 m2
Ground level Not available
height of fall 0.750 m Friction correction Drilling rig Archway Dart
Anvil weight 30 kg Friction precautions Contractor AA Drilling
Methodology EN DD1997-3:1999 "Eurocode 7 : Geotechnical Design - design assisted by field testing", Clause 6
Remarks No interuptions. No calibration data.
TITLE: REF:
PROJECT: POSITION:
CLIENT: GRID REF:
OPERATIVES: CHECKED: DATE: SHEET:
*********** WS1
09/11/2010
None
None
Super Heavy Dynamic Probing (SHDP) record LS0237
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
*********** N/A
AJ/TR ET 18/11/2010 1 of 1
0 10 20 30 40 50
fell under own weight
to 0.40m
0 10 20 30 40 50
position terminated
at 5.9m
Interval DP N100 Interval DP N100
m blows/100mm m blows/100mm
0.0 - 0.1 - 5.0 - 5.1 6
0.1 - 0.2 - 5.1 - 5.2 6
0.2 - 0.3 3 5.2 - 5.3 9
0.3 - 0.4 4 5.3 - 5.4 15
0.4 - 0.5 4 5.4 - 5.5 7
0.5 - 0.6 5 5.5 - 5.6 21
0.6 - 0.7 7 5.6 - 5.7 36
0.7 - 0.8 7 5.7 - 5.8 41
0.8 - 0.9 7 5.8 - 5.9 36
0.9 - 1.0 8 5.9 - 6.0 38
1.0 - 1.1 8 6.0 - 6.1
1.1 - 1.2 8 6.1 - 6.2
1.2 - 1.3 5 6.2 - 6.3
1.3 - 1.4 5 6.3 - 6.4
1.4 - 1.5 5 6.4 - 6.5
1.5 - 1.6 5 6.5 - 6.6
1.6 - 1.7 6 6.6 - 6.7
1.7 - 1.8 6 6.7 - 6.8
1.8 - 1.9 6 6.8 - 6.9
1.9 - 2.0 6 6.9 - 7.0
2.0 - 2.1 12 7.0 - 7.1
2.1 - 2.2 10 7.1 - 7.2
2.2 - 2.3 9 7.2 - 7.3
2.3 - 2.4 9 7.3 - 7.4
2.4 - 2.5 9 7.4 - 7.5
2.5 - 2.6 8 7.5 - 7.6
2.6 - 2.7 8 7.6 - 7.7
2.7 - 2.8 7 7.7 - 7.8
2.8 - 2.9 8 7.8 - 7.9
2.9 - 3.0 10 7.9 - 8.0
3.0 - 3.1 9 8.0 - 8.1
3.1 - 3.2 10 8.1 - 8.2
3.2 - 3.3 11 8.2 - 8.3
3.3 - 3.4 9 8.3 - 8.4
3.4 - 3.5 17 8.4 - 8.5
3.5 - 3.6 20 8.5 - 8.6
3.6 - 3.7 10 8.6 - 8.7
3.7 - 3.8 11 8.7 - 8.8
3.8 - 3.9 11 8.8 - 8.9
3.9 - 4.0 10 8.9 - 9.0
4.0 - 4.1 10 9.0 - 9.1
4.1 - 4.2 14 9.1 - 9.2
4.2 - 4.3 15 9.2 - 9.3
4.3 - 4.4 11 9.3 - 9.4
4.4 - 4.5 6 9.4 - 9.5
4.5 - 4.6 6 9.5 - 9.6
4.6 - 4.7 7 9.6 - 9.7
4.7 - 4.8 6 9.7 - 9.8
4.8 - 4.9 6 9.8 - 9.9
4.9 - 5.0 4 9.9 - 10.0
Hammer mass 63.5 kg Rod weight 6 kg Date Completed
Gravity constant 9.8 N/kg Base of cone 0.002 m2
Ground level Not available
height of fall 0.750 m Friction correction Drilling rig Archway Dart
Anvil weight 30 kg Friction precautions Contractor AA Drilling
Methodology EN DD1997-3:1999 "Eurocode 7 : Geotechnical Design - design assisted by field testing", Clause 6
Remarks No interuptions. No calibration data.
TITLE: REF:
PROJECT: POSITION:
CLIENT: GRID REF:
OPERATIVES: CHECKED: DATE: SHEET:AJ/TR ET 18/11/2010
None
None
Super Heavy Dynamic Probing (SHDP) record
***********
***********
09/11/2010
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
LS0237
N/A
1 of 1
WS4
0 10 20 30 40 50
Hand dug to 0.20m
0 10 20 30 40 50
position terminated
at 6.0m
REMARKS TITLE: REFERENCE: POSITION:
Stability:
Groundwater: PROJECT: ELEVATION: CO-ORDINATES:
Chiselling:CLIENT: METHOD:
Casing/dia:
Backfilling: STARTED: SCALE:
Obstructions:COMPLETED: SHEET No:
Others:
FILLWATERDESCRIPTION TESTING SAMPLING
CHECKED BY:
36=9.00 SPT (12,8,8,8)
= (6,7,6,5)227.50 SPT
18=6.00 SPT (4,5,4,5)
= (4,3,4,5)164.50 SPT
16=3.00 SPT (4,4,4,4)
=SPT (2,2,2,3)1.50
10.00
6.00
1.90
ET
0.00
Borehole log
9
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
*******************
*******************
Not to scale
BH1
06/12/2010
06/12/2010
LS 0251
INPUTTED BY:
ET Page: 1 of 2
Not to scale
Light Cable Percussive
N/A
LOGGED BY:
SRPB
DRILLED BY:
150mm, cased to 3.00m
Position backfilled with arisings
Brown silty, sandy gravelly CLAY. (HEAD DEPOSITS)
Off white CHALK, medium to high density. Discontinuities very
closely spaced (20mm), open (<3mm); medium to high density
Grade B5. (LEWES NODULAR CHALK MEMBER)
Weak white and occasional light brown putty CHALK with layers
of gravel sized medium density chalk fragments and scattered
flints. (LEWES NODULAR CHALK MEMBER)
…increasing proportions of intact chalk fragments from 3.00m
No obstructions encountered
Hand excavated to 1.00mbgl
Contnued on next sheet
No instability encountered
No groundwater encountered.
Occasional chiselling through flints (1hr)
REMARKS TITLE: REFERENCE: POSITION:
Stability:
Groundwater: PROJECT: ELEVATION: CO-ORDINATES:
Chiselling:CLIENT: METHOD:
Casing/dia:
Backfilling: STARTED: SCALE:
Obstructions:COMPLETED: SHEET No:
Others:
DESCRIPTION TESTING SAMPLING WATER FILL
10.00
10.50 SPT = 27 (5,6,8,8)
12.00 SPT = 29 (7,7,8,7)
13.50 SPT = 29 (7,8,7,7)
15.00 SPT = 41 (12,12,8,9)
15.50
Not to scaleOccasional chiselling through flints (1hr)
SR 06/12/2010 Not to scale
No instability encountered Borehole log LS 0251 BH1No groundwater encountered.
******************* N/A
Hand excavated to 1.00mbgl ET ET
150mm, cased to 3.00m ******************* Light Cable Percussive
Position backfilled with arisings DRILLED BY: LOGGED BY:
PB
borehole complete at 15.50mbgl
06/12/2010 Page: 2 of 2
CARLTON HOUSE, 28-29 CARLTON TERRACE, PORTSLADE, BRIGHTON, BN41 1UR
TEL: 0845 604 6494 FAX: 01273 423 216 EMAIL: [email protected]
LEWES NODULAR CHALK… continued
…water added from 12.00m to assist drilling
No obstructions encounteredINPUTTED BY: CHECKED BY:
APPENDIX C
Project Name: K4 SOILSK4 SOILSK4 SOILSK4 SOILS
Client: Project no:Our job no: 10218
Borehole No: Sample No:
Depth m
pH Sulphate content (g/l)
WS1 2 1.00 7.6 0.10
WS6 2 0.50 7.4 0.09
Summary of Test Results Checked and
Date Approved
26/11/2010 Initials : kp
Unit 8 Olds Close Olds Approach Watford Herts WD18 9RU
Land Science LS0237
BS 1377 : Part 3 :Clause 5 : 1990 Determination of sulphate content of soil and ground water : gravimetric method
Description
Off white putty CHALK with occasional fm intact chalk fragments
Brown slightly sandy gravelly CLAY with occasional chalk fragments and roots (gravel is fmc angular to sub angular)
Project Name: Samples Received:
Project Started:
Client: Testing Started:
Project No: Our job/report no: Date Reported:
Borehole No:
Sample No:
Depth (m)
Moisture content
(%)
Liquid Limit (%)
Plastic Limit (%)
Plasticity Index (%)
Passing 0.425
mm (%)
WS1 1-30.50 - 2.00
25 32 26 6 53
WS2 20.30 - 0.50
35 80 40 40 53
WS3 3-40.50 - 1.50
27 43 23 20 59
WS6 20.50 - 1.00
33 59 29 30 45
Summary of Test ResultsInitials: K.P
BS 1377 : Part 2 : Clause 5 : 1990 Determination of the plastic limit and plasticity index. Date: 26/11/2010
2519 BS 1377 : Part 2 : Clause 3.2 : 1990 Determination of the moisture content by the oven-drying method.
Test Report by K4 SOILS LABORATORY Unit 8 Olds Close Olds Approach Watford Herts WD18 9RU
Test Results relate only to the sample numbers shown above. Approved Signatories: K.Phaure (Tech.Mgr) J.Phaure (Lab.Mgr)
All samples connected with this report ,incl any on 'hold' will be stored and disposed off according to Company policy.Acopy of this policy is available on request. MSF-11/R2
Off white putty CHALK with occasional fm intact chalk fragments
Checked and Approved
Dark brown sandy gravelly CLAY with occasional fm chalk fragments (gravel is fm and sub rounded to angular)
Brown sandy gravelly CLAY with occasional fm chalk fragments and wood remains (gravel is fm and sub angular to angular)
Description
Land Science
10218LS0237
12/11/2010
15/11/2010
24/11/2010
26/11/2010
K4 SOILS
Remarks
Brown slightly sandy gravelly CLAY with occasional chalk fragments and roots (gravel is fmc angular to sub angular)
BS 1377 : Part 2 : Clause 4.4 : 1990 Determination of the liquid limit by the cone penetrometer method.
Approved Signatories:
Initials: kp
Test results relate only to the sample numbers shown above Date:
All samples connected with this report, incl any on 'hold' will be disposed off according to company policy. A copy of this policy is available on request. Sheet 3/3 MSF-11/R9
90
75
100
100
10218
Borehole / Pit No
WS1BS 1377 : Part 2 : 1990 : Clause 9
K4 SOILS
LocationSample No
PARTICLE SIZE DISTRIBUTION Job/report no:
1-3
Depth 0.50 - 2.00 mVisual Soil Description
Off white putty CHALK with occasional fm intact chalk fragments Sample type D
Sieving Sedimentation Test Method
Particle Size mm
% PassingParticle Size
mm% Passing
BS 1377 : Part 2 : 1990
Sieving Clause
Sedimentation N/A
63 100
125 100
37.5 94
50 100
Sample Proportions
20 74 Cobbles 0.0
28 82
14 68
10 65
Gravel 43.3
Sand 12.5
6.3 61
5 60
Silt & Clay 44.2
2 57
3.35 58
1.18 55
0.6 54
0.212 51
0.3 52
49
D60 5.0
D100 125.0
Grading Analysis
N/A
0.15
D10
0.425 53
Uniformity Coefficient0.063 44
Checked and Approved
2519
K4 SOILS LABORATORYUnit 8 Olds Close Olds Approach Watford Herts WD18 9RU. E-mail: [email protected]
K.Phaure(Tech.Mgr) J.Phaure(Lab.Mgr)
26/11/2010
200
6020620.6
0.2
0.06
0.03
0.006
0.002
0
10
20
30
40
50
60
70
80
90
100
Particle Size - mm
Per
cen
tag
e P
assi
ng
- %
CLAYSILT SAND GRAVEL
COBBLESFine Medium Coarse Fine Medium Coarse Fine Medium Coarse
Approved Signatories:
Initials: kp
Test results relate only to the sample numbers shown above Date:
All samples connected with this report, incl any on 'hold' will be disposed off according to company policy. A copy of this policy is available on request. Sheet 3/3 MSF-11/R9
90
75
100
100
10218
Borehole / Pit No
WS2BS 1377 : Part 2 : 1990 : Clause 9
K4 SOILS
LocationSample No
PARTICLE SIZE DISTRIBUTION Job/report no:
2
Depth 0.30 - 0.50 mVisual Soil Description
Dark brown sandy gravelly CLAY with occasional fm chalk fragments (gravel is fm and sub rounded to
angular)Sample type D
Sieving Sedimentation Test Method
Particle Size mm
% PassingParticle Size
mm% Passing
BS 1377 : Part 2 : 1990
Sieving Clause
Sedimentation N/A
63 100
125 100
37.5 100
50 100
Sample Proportions
20 100 Cobbles 0.0
28 100
14 79
10 75
Gravel 38.4
Sand 24.6
6.3 70
5 67
Silt & Clay 36.9
2 62
3.35 64
1.18 60
0.6 56
0.212 47
0.3 50
43
D60 1.3
D100 125.0
Grading Analysis
N/A
0.15
D10
0.425 53
Uniformity Coefficient0.063 37
Checked and Approved
2519
K4 SOILS LABORATORYUnit 8 Olds Close Olds Approach Watford Herts WD18 9RU. E-mail: [email protected]
K.Phaure(Tech.Mgr) J.Phaure(Lab.Mgr)
26/11/2010
200
6020620.6
0.2
0.06
0.03
0.006
0.002
0
10
20
30
40
50
60
70
80
90
100
Particle Size - mm
Per
cen
tag
e P
assi
ng
- %
CLAYSILT SAND GRAVEL
COBBLESFine Medium Coarse Fine Medium Coarse Fine Medium Coarse
Approved Signatories:
Initials: kp
Test results relate only to the sample numbers shown above Date:
All samples connected with this report, incl any on 'hold' will be disposed off according to company policy. A copy of this policy is available on request. Sheet 3/3 MSF-11/R9
90
75
100
100
10218
Borehole / Pit No
WS3BS 1377 : Part 2 : 1990 : Clause 9
K4 SOILS
LocationSample No
PARTICLE SIZE DISTRIBUTION Job/report no:
3 - 4
Depth 0.50 - 1.50 mVisual Soil Description
Brown sandy gravelly CLAY with occasional fm chalk fragments and wood remains (gravel is fm and sub
angular to angular)Sample type D
Sieving Sedimentation Test Method
Particle Size mm
% PassingParticle Size
mm% Passing
BS 1377 : Part 2 : 1990
Sieving Clause
Sedimentation N/A
63 100
125 100
37.5 100
50 100
Sample Proportions
20 100 Cobbles 0.0
28 100
14 94
10 89
Gravel 32.9
Sand 19.5
6.3 80
5 76
Silt & Clay 47.6
2 67
3.35 72
1.18 64
0.6 61
0.212 55
0.3 58
53
D60 0.5
D100 125.0
Grading Analysis
N/A
0.15
D10
0.425 59
Uniformity Coefficient0.063 48
Checked and Approved
2519
K4 SOILS LABORATORYUnit 8 Olds Close Olds Approach Watford Herts WD18 9RU. E-mail: [email protected]
K.Phaure(Tech.Mgr) J.Phaure(Lab.Mgr)
26/11/2010
200
6020620.6
0.2
0.06
0.03
0.006
0.002
0
10
20
30
40
50
60
70
80
90
100
Particle Size - mm
Per
cen
tag
e P
assi
ng
- %
CLAYSILT SAND GRAVEL
COBBLESFine Medium Coarse Fine Medium Coarse Fine Medium Coarse
Approved Signatories:
Initials: kp
Test results relate only to the sample numbers shown above Date:
All samples connected with this report, incl any on 'hold' will be disposed off according to company policy. A copy of this policy is available on request. Sheet 3/3 MSF-11/R9
26/11/2010
Checked and Approved
2519
K4 SOILS LABORATORYUnit 8 Olds Close Olds Approach Watford Herts WD18 9RU. E-mail: [email protected]
K.Phaure(Tech.Mgr) J.Phaure(Lab.Mgr)
Uniformity Coefficient0.063 34
Grading Analysis
N/A
0.15
D10
0.425 39
36
D60 7.9
D100 125.0
0.212 38
0.3 38
1.18 42
0.6 40
2 45
3.35 49
Silt & Clay 34.26.3 56
5 52
Gravel 55.1
Sand 10.710 65
14 71
Sample Proportions
20 78 Cobbles 0.0
28 91
37.5 100
50 100
Sedimentation N/A
63 100
125 100
Sieving Sedimentation Test Method
Particle Size mm
% PassingParticle Size
mm% Passing
BS 1377 : Part 2 : 1990
Sieving Clause
Visual Soil Description
Off white putty CHALK with occasional fm intact chalk fragments Sample type D
2-3
Depth 0.50 - 1.50 m
K4 SOILS
LocationSample No
PARTICLE SIZE DISTRIBUTION Job/report no: 10218
Borehole / Pit No
WS4BS 1377 : Part 2 : 1990 : Clause 9
90
75
100
100
200
6020620.6
0.2
0.06
0.03
0.006
0.002
0
10
20
30
40
50
60
70
80
90
100
Particle Size - mm
Per
cen
tag
e P
assi
ng
- %
CLAYSILT SAND GRAVEL
COBBLESFine Medium Coarse Fine Medium Coarse Fine Medium Coarse