GROUND IMPROVEMENT TREATMENT BY PRELOADING IN …igs/ldh/conf/2011/articles/Theme - Q 15.pdf ·...
Transcript of GROUND IMPROVEMENT TREATMENT BY PRELOADING IN …igs/ldh/conf/2011/articles/Theme - Q 15.pdf ·...
Proceedings of Indian Geotechnical Conference
December 15-17,2011, Kochi (Paper No. Q-356)
GROUND IMPROVEMENT TREATMENT BY PRELOADING IN THE ENLARGEMENT
OF ALICANTE PORT (SPAIN)
Roberto Rodríguez Escribano. Geological and geotechnical department manager. Prointec, S.A.. [email protected]
Margarita Díaz-Toledo García. Geological and geotechnical dept project manager. Prointec, S.A.. [email protected]
Javier Escartín García. Ports department manager. Prointec, S.A.. [email protected]
Marta Estefanía López Sierra. Geological and geotechnical department project manager. Icyfsa. [email protected]
Claudio Olalla Marañón. Professor, ETSICCP of the Technical University of Madrid (UPM). [email protected]
ABSTRACT: Port extension works present important challenges, on having possessed compressible materials with
deficient geotechnical characteristics as foundation level. In this respect, the geotechnical case of study is focused on the
compressibility analysis of satured soils under static loads, orienting it to the design of the soil improvement treatment by
preloading in the enlargement of Alicante Port (Spain). The research carried out shows the developed methodology, both
project phase and construction, so that it has been possible on the one hand, to estimate the foreseeable settlements and the
design of the ground improvement treatment by preloading, and on other hand, the most important one, compare the
estimated settlements with the real behaviour of the soil by means of auscultation of the improvement process on the site.
INTRODUCTION
Alicante Port enlargement refers to the construction of three
new terminals for the docks 21, 23 and 25, which will
provide wide use surfaces to satisfy the shipping demand.
To achieve this goal it has been necessary to carry out a
great volume earth filling in order to extend the port surface
towards the sea and therefore carry out the esplanade over
which will be placed the pavement. Fig. 1. (Note: in this
paper the decimal sign used is the comma “,” and the
thousands separator is the full point “.”)
Fig. 1 Aerial photograph of the portuary filling process.
IDENTIFIED PROBLEMATIC
The paved esplanade to execute in the new Alicante Port
East docks, present, same as in other enlargement ports
cases the inconvenient related to the high compresibilty
materials (new fills over sea muds and sands), which
constitute these esplanades foundation.
These kind of materials are usually characterized by
relevant long term settlements. This situation can be
aggravated depending to the percentage of organic matter.
In the case this percentage is relevant the settlement can be
developed in a long time (several years), as the organic
matter. keeps decomposing.
This way, an important settlement is expected to be
generated due to the thickness and geotechnical
characteristics of these kind of compressible materials (sea
sand and muds plus port fills). The magnitude of this
settlement is likely to exceed the limits defined by the
ROM 4.1-94 [1].
This is the reason why the determination of the settlement
magnitude beside the soil consolidation process duration,
function of the use load estimated (30 y 60 kPa) is needed.
METHODOLOGY
To aproach the study for the esplanade geotechnical
viability, it´s necessary to develop several investigation
phases which allow:
The geotechnical characterization of the terrain with
the purpose to estimate the deformability.
Determinate, depending on the use loads, the
settlement magnitude, comparing this to the maximum
stipulated by the ROM 4.1-94 (1994), Guidelines for
the design and construction of port pavements.
In case in which the settlement magnitude exceeds the
service use limits, design an improvement and
reinforcement treatment for the terrain which lets to
reduce the post-constructive settlement.
1047
R. Rodríguez Escribano, M. Díaz-Toledo García, J. Escartín García, M. E. López Sierra & C. Olalla Marañón
At last, in case in which an improvement treatment will
be needed, auscultate during the process, comparing
the real-field data to the calculated settlement.
To achieve these tasks properly, the project is developed in
to main steps:
Phase 1, Project. Related to the investigation,
characterization, determination and design.
Phase 2, Work; It will allow to control the movements,
compare them to the magnitude estimated in Phase 1
and adjust the soil behavior models.
Each Phase has the same importance, although most of the
times both are totally disconnected and it is not possible to
develop a back-analysis study in order to adjust the
analyzed situation to the real measured settlements.
This study is relevant as it has been possible to reach these
two main points (Phase 1 and Phase 2).
PHASE 1. PROJECT PHASE
Geological-Geotechnical Characterization
Starting from the compilation and analysis, both from the
site available geotechnical information and the field and
laboratory complementary investigation, it was able to
identify the fills and sea sand and muds geotechnical
parameters. There were established the following
geological-geotechnical units, Table 1.
Table 1 Geological-Geotechnical units
Geological-Geotechnical Unit
Thickness (m)
N30 E (MPa)
Cv
(cm2/sg)
Level 1, Anthropic fills
2,8-12,4 12
7,2
Level 2, Muds and silts
0,8-7 5
2,5 3·10-3
Level 3, Sand with gravels
0,4-6,4 50
45
Level 4, Marls, sandstones, conglomerates,
calcarenites
-
R
1.000
Note: N1+N2, Cv = 2·10-2 cm2/sg according to the preload
tests.
Due to the important variability in the stratigraphic profile
and in order to reach the best adjustment for the settlement
estimation, it was decided to identify and to zone areas with
a similar stratigraphy and carry out different stratigraphic
profiles for each area defined, Fig. 2.
Fig. 2 Sectorization related to the geotechnic profile.
Esplanade Viability Analysis
To verify the esplanade viability as foundation level it is
essential to check it is not reached the geotechnical failure
situations, it means sinking, sliding and the use related to an
inadmissible settlement.
These checks have been achieved by applying classic
methodology and also with finite element methods based in
Plaxis code.
According to these results is observed how for the
considered use loads are not reached the requirements
imposed in the guideline for the design and construction of
port pavements, ROM 4.1-94 [1], as the final settlement is
not admissible (superior to 0,10 m along 10 years).
Ground Improvement Methodology Design
Within the wide range of possibilities concerning to the
ground improvement, the treatment which best fits to the
site characteristics and to the technical and economical
requirements, is the embankments preload. According to
the soil grain size and considering the limits proposed by
Queyroi et al (1985) there wont be necessary to combine
preload plus drains.
The improvement treatment by using preloads was designed
for 1,5 times the use loads, therefore the minimum
embankments dimensions (equivalent to an infinite load)
for areas designed for 30 Kpa use load, were 40x80 m and
for areas designed for 60 Kpa use loads, were 60x120 m,
with consolidation periods between 15 and 90 days.
Stability of the Construction Process
For the embankment stability assessment there have been
considered the safety factor values proposed in the ROM
0.5-05 [2] and since it can be considered an accidental and
transitory situation in a short term these values will be
within the following range 1,1<S.F. 1,3. To analyze the
1048
Ground improvement treatment by preloading in the enlargement of Alicante Port (Spain)
sliding situation it has been used the program Slide
(Rocscience), considering the Mohr-Coulomb lineal failure
criterion, Fig. 3.
Fig. 3 Limit equilibrium stability calculus.
Preload Settlement Assessment
In order to carry out the design of the preload treatment,
calculation has been made of the foreseeable settlements
under the preload stresses and, a posteriori, once the
overburden of earth has been eliminated when the use loads
are applied, with the aim of checking that the regulations on
port pavements ROM 4.1-94 [1] are complied with.
The estimation of the settlements has been done by
comparing classical methods, based on the theory of
elasticity and on one-dimensional consolidation, and finite
element methods by means of Plaxis software, Fig. 4.
Fig. 4 Deformation under the preload embankment.
Also, on the basis of the evolution of the expansion works
on the port, with filled wharfs, others that are partially
filled and others waiting to be filled, and depending on the
moment the preload is located, two settlement calculation
hypotheses have been considered:
Hypothesis A: preload immediately on execution of the
fill. Settlements originated by the fill and compressible
natural ground, due to the effect of the actual weight of
the port fill and due to the effect of the preload.
Hypothesis B: preload a posteriori in time, with fill and
natural ground now consolidated due to the actual
weight of the port fill. Settlements corresponding to the
fill and compressible natural ground due to the effect
of the preload.
Estimation of the Settlements in the Service Phase
It was confirmed that, following the execution of the
preload, the settlements that are going to take place in the
ground when the use overloads are applied will be produced
as a function of the reload modules so long as they do not
exceed loads of 30 and 60 kPa, reducing the settlements to
admissible values.
PHASE 2. WORK PHASE
Auscultation constitutes a valuable tool since it guarantees
the proper and safe evolution of the process, and permits
the real behaviour of the ground to be determined, in
addition to any estimation method in the project.
Test Embankment
In the work, before commencing the improvement
treatment, a preload test embankment has been created,
having a triangular shape in plan view and approximate
dimensions of 45 x 93 m, which has been instrumented with
6 settlement plates and measurements taken periodically,
Fig. 5.
On the basis of the analysis of the settlements produced by
the preload embankment, a retrospective analysis has been
made of the behaviour of the materials by means of various
methods, with the aim of estimating the deformational
parameters of the ground, especially the coefficients of
vertical consolidation (Cv), for the estimation of which
three different methods have been applied: the Casagrande
method or time logarithm method, the Taylor method or
square root of time method, and the Asaoka method [3].
This has allowed the values of the deformation modulus to
be adjusted for the compressible levels (Levels N1+N2).
1
21
28 35
42 48 55 62 69 87 94 108 179
-60,000
-50,000
-40,000
-30,000
-20,000
-10,000
0,000
10,000
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190
SE
TT
LEM
EN
T (
cm
)
TIME (days)
HEIGHT (m) - SETTLEMENTS (cm) - TIME (days)
Base 1. Embankment
Height
Base 1. Settlements
Base 2. Embankment
Height
Base 2. Settlements
Base 3. Embankment
Height
Base 3. Settlements
Base 4. Embankment
Height
Base 4. Settlements
Base 5. Embankment
Height
Base 5. Settlements
Base 6. Embankment
Height
Base 6. Settlements
EM
BA
NK
ME
NT
HE
IGH
T (
m)
NOTE.-Preload settlements plates:- H=4 m: 1 and 3- H=6 m: 2 and 4- H=8 m: 5 and 6
Fig. 5 Graph of height – settlements – time of the preload
test embankment.
Auscultation of Preload Process
The monitoring of the preload has been done by means of
various control devices (settlement plates or inclinometers)
monitoring the vertical and horizontal movements
generated by the preload embankments, increasing safety
and correct evolution.
1049
R. Rodríguez Escribano, M. Díaz-Toledo García, J. Escartín García, M. E. López Sierra & C. Olalla Marañón
In general, the stabilization of the settlement has been
achieved in advance of the time planned in the project, with
settlement values similar to the estimated ones, considering
hypothesis A, Fig. 6.
Fig. 6 Map of settlement isolines.
In general the settlements have, by a large percentage with
regard to the total, been generated practically
instantaneously and simultaneous with the construction
process (load), with a clear reduction being seen of the
settlement in the plates located around the zones regarded
as already preloaded (zones that have historically supported
overloads of stockpiles, fills, etc.), while the bases located
in the last fill area where a major accumulation of mud
could be seen show settlements clearly greater than the
estimated values.
CONCLUSIONS
The results of the settlements obtained by means of the
auscultation conducted during the preload treatment agree
with the estimates both in the value of the settlement
reached, Fig. 7, and the time of duration of the
consolidation, with the stabilization of the settlements in
general being achieved more rapidly and, in an important
percentage of cases, almost instantaneously with the
loading process.
This reduction in the consolidation times can be produced
by a lesser thickness of the mud layer and, on a
complementary basis, by the displacement of that mud
when the fill is carried out by means of direct pouring,
giving rise to alternating small cohesive layers within the
granular materials being poured, which will facilitate the
drainage or dissipation of the interstitial pressure,
generating a much faster consolidation since the minimum
travel for the drainage of the clay packet becomes reduced.
At the same time, it has to be borne in mind that these
variations can be due to a greater or lesser accuracy in
estimating the coefficient of consolidation.
PT-1.1
PT-1.2
PT-2.1
PT-2.2
PT-2.3PT-2.4
PT-3.1 PT-3.2
0
5
10
15
20
25
30
35
40
45
50
0 5 10 15 20 25 30 35 40 45 50
Re
al S
ett
lem
en
t(c
m)
Estimated Settlement (cm)
CLOSURE AREAOF THE LASTPORT FILLS
HISTORICALPRELOADS AREA
Fig. 7 Adjustment between the estimated settlement values
and those measured on site.
As final conclusions, the following can be stated:
On the basis of the results obtained, the applied
methodology constitutes a valid process for estimating
the compressibility of the ground, in spite of the
limitations caused by the lack of field or laboratory
trials aimed at obtaining the deformational parameters
of the ground which would permit a proper check to be
made of the adopted values.
There exists a good fit between the classical methods
of calculating settlements (theory of on-dimensional
consolidation and the theory of elasticity) and the finite
element method.
The retrospective analysis conducted on the basis of
the auscultation results of the preload test embankment
has allowed a determination to be made of the real
modulus of deformation of the ground (Young’s
modulus) and the coefficient of consolidation, with the
latter showing a certain variation with respect to that
obtained by theoretical methods.
REFERENCES
1. ROM 4.1-94 (1994), Guidelines for the design and
construction of port pavements. State Ports Board.
Ministry of Public Works, Transport and Environment.
Government of Spain.
2. ROM 0.5-05 (2008), Geotechnical Recommendations on Maritime and Port Works. State Ports Board.
Ministry of Public Works, Transport and Environment.
Government of Spain.
3. Asaoka, A. (1978), Observational procedure of
settlement prediction. Soils and Foundations.
1050