Grinder Pump Installation and Testing Detail

1
To be installed by property owner. To be installed by HSWA. 4’L x 1.25”Dia. HDPE whip included with Grinder Pump below frost line. 1.5”x1.25” Coupler included with Grinder Pump. 1.5” Dia. HDPE DR11 or Gasketed SDR21 PVC Lateral. 6” Settling Loop. CO Pressure Testing Requirements are as follows: 1.) Gravity: All under slab and/or underground/buried plumbing from structure to Pump must pass a 5 PSI, 15 Min. duration test with no allowable loss of pressure. 2.) Pressure: The completed line from the Pump to the Curb Stop must pass a 80 PSI, 15 Min. duration test with no allowable loss of pressure. A 1.5” Compression Coupler will be the customer connection point and will be marked with a 2”x4” board. Grinder Pump Installation and Testing Detail 4”Dia. SCH40 must be used between Grinder Pump and undisturbed soil. The 4” SCH40 may be transitioned to 4” SDR35 with a gasketed coupler if a longer run is needed. A 4”Dia. Clean out is required within 3’ of the outside or inside of the foundation wall. This is accomplished by using a gasketed 4” SDR35 straight Tee on the outside or a 4” SCH40 glued Tee on the inside. No glue joints will be permitted outside of the foundation. *Please see the attached Specifications for Sanitary Sewer Installation regarding additional rules for Building Drain/Building Sewer Installation.

Transcript of Grinder Pump Installation and Testing Detail

Page 1: Grinder Pump Installation and Testing Detail

To be installed by property owner.

To be installed by HSWA.

4’L x 1.25”Dia. HDPE whip included with Grinder Pump below frost line.

1.5”x1.25” Coupler included with Grinder Pump.

1.5” Dia. HDPE DR11 or Gasketed SDR21 PVC Lateral.

6” Settling Loop.

CO

Pressure Testing Requirements are as follows: 1.) Gravity: All under slab and/or underground/buried plumbing from structure to Pump must pass a 5 PSI, 15 Min. duration test with no allowable loss of pressure. 2.) Pressure: The completed line from the Pump to the Curb Stop must pass a 80 PSI, 15 Min. duration test with no allowable loss of pressure.

A 1.5” Compression Coupler will be the customer connection point and will be marked with a 2”x4” board.

Grinder Pump Installation and Testing Detail

4”Dia. SCH40 must be used between Grinder Pump and undisturbed soil. The 4” SCH40 may be transitioned to 4” SDR35 with a gasketed coupler if a longer run is needed. A 4”Dia. Clean out is required within 3’ of the outside or inside of the foundation wall. This is accomplished by using a gasketed 4” SDR35 straight Tee on the outside or a 4” SCH40 glued Tee on the inside. No glue joints will be permitted outside of the foundation.

*Please see the attached Specifications for Sanitary Sewer Installation regarding additional rules for Building Drain/Building Sewer Installation.