Green Datacenters solution March 17, 2009 By: Sanjay Sharma

16
Green Datacenters solution March 17, 2009 By: Sanjay Sharma

description

Green Datacenters solution March 17, 2009 By: Sanjay Sharma. DATA CENTER. 16%. 100%. 30%. .003%. 1%. Energy Facts. Of all the potential electricity available in an energy source, only 30 percent reaches consumers - PowerPoint PPT Presentation

Transcript of Green Datacenters solution March 17, 2009 By: Sanjay Sharma

Page 1: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

Green Datacenters solution

March 17, 2009

By: Sanjay Sharma

Green Datacenters solution

March 17, 2009

By: Sanjay Sharma

Page 2: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

2 2

Energy Facts• Of all the potential electricity available in an energy source, only 30

percent reaches consumers

• An estimated 170 billion kilowatts are wasted by consumers each year due to insufficient power usage information

• US Datacenters and servers consumed about 670 billion kWh in 2008 with an estimated total electricity cost of $ 5.0 Billion

DATA CENTER

100%

30% 16%

Generation & Distribution Cooling

Power Supplies, UPS

ServersSiliconMission

Critical Apps 1%.003%

Page 3: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

3 3

Where Does Power Go?

IT Equipment = 30%

Energy Equipments = 25%

Cooling = 45%

Total number of servers installed increased by factor 100 in one decade

Number of server/processors per rack increased by factor 10 in ten years

Power and thermal waste per server increased by factor 5 in ten years

Total number of servers installed increased by factor 100 in one decade

Number of server/processors per rack increased by factor 10 in ten years

Power and thermal waste per server increased by factor 5 in ten years

Source: APC ViewSource: APC View

Page 4: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

4 4

I.T damage to the environment

Billions of KW/hrsMillions of Tons of CO2

• I.T Does as much damage to environment as Airline Industry

• 2% of CO2 Emitted comes from I.T Industry

• For every 1 spent powering systems 0.5 to 1 spent on cooling I.T is the focus of GREEN lobby! Source: EPA ReportSource: EPA Report

Page 5: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

5 5

Green Buildings

IBM Example

Enhancing existing buildings to be more energy efficient typically reduces total energy consumption by 20-50%...

…while new “green” buildings have the potential to reduce energy consumption by 80% or more. Benefits Average achievable energy savings

greater than 40%;

Average payback of <2 years in Data Center Energy Efficiency assessments;

Asset utilization rates increasing 2x-4x;

Deferral of massive capital investments in new datacenter builds

$1 energy savings drives another $6-8 operational savings on average

Benefits Average achievable energy savings

greater than 40%;

Average payback of <2 years in Data Center Energy Efficiency assessments;

Asset utilization rates increasing 2x-4x;

Deferral of massive capital investments in new datacenter builds

$1 energy savings drives another $6-8 operational savings on average

Source: IBM Client SurveySource: IBM Client Survey

Page 6: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

6 6

Case Study

Energy Management Solutions for Bharti’s Telecom Towers

Page 7: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

7 7

Conventional solutions & associated problems

• Unhealthy Grid• High DG running costs• Higher capacity DG’s

• Operational problems• Low efficiency in Power utilization (85%)

– Leading to Heat losses• Slow Voltage regulation time leading to

– SMPS Failure– High maintenance

• Large foot print• Excessive cabling • Frequent breakdowns with no monitoring

of passive infrastructure elements

• Shelter• High solar gain• Non modular• Rusting problem

• Air Conditioning• Oversized AC’s• Very High Inrush Current• No Free Cooling

Problems with Conventional systems

15/25 KVA DG

IT, Servo, AMF, Alarm box ACDB etc

GI:GI

Shelter

1.5x2 2.0x2 Tr AC’s

Conventional systems

Page 8: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

8 8

Addressing ChallengesChallenges Contributor/Reasons Innovative ‘s Solutions

Site Operation Cost

• Various AC/DC Conversion Cost• Backup Cost• Environment Conditioning Cost• D.G. running cost due to

unhealthy grid• Over-design Infrastructure for

Peak Load (like 15KVA DG for 3KW load)

• Less/low AC/DC Conversion • Low backup cost • Low Air-Conditioning Cost • Wide range PIU to maximize low

cost grid usage• Low back up power cost with DC

power house of 5kw

Site Downtime

Main Reasons• Battery• Generator• Air-Conditioner

• NextGen thin Plate Technology• Aviation grade very high MTBF

DC Generator• Compressor less N + 2

redundancy

Project , Operation and Maintenance Cost

• Installation Time• Expandability• IT Interface for critical and

operational need monitoring

• Installation time (24-48 hours)• Expandability modular • Energy metering for each

operator and their individual load• Detailed NMS

Page 9: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

9 9

Use of technology for reducing energy costs

• Air Conditioning– Next Generation Cooling solutions (for Indoor BTS)– Battery Cooler (for Outdoor BTS)

• Battery back-up power– High efficiency and cycle life batteries– Float Mode operation for extended life

• DG based power– Cost of DG running to be reduced– Move site to DC Power architecture which creates future proof

site– Explore Alternative technologies like wind/ solar or fuel cells

• Energy losses in SMPS & PIU– New products offering high efficiency– Wide operating range to reduce DG running

• Integrated NMS– Integrate Tower Management (Through SMS and GPS) with

overall NOC

Page 10: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

10 10

Conventional Telecom Approach

Mains

AC1.4 kW

SMPS250 W10%

BTS1.5 kW

DG

PIU250 W

3%

3.4 kW

Battery300 AH50 W

Leakage

3.15 kW

Note: Per hour energy usage / energy losses

Every IT Companies were focusing at this

point

IT and Datacenters are in similar position like telecom was few years back

Page 11: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

11 11

Our Green Solution for Telecom

Mains

AC0.45 kW

SMPS250 W10%

Battery15 W

Leakage

BTS1.5 kW

DC Power House

PIU150 W

3%

2.4 kW

Note: Per hour energy usage / energy losses

1

2

43

PCM TechnologyPCM Technology

Page 12: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

12 12

Current IT Datacenter set up

Transformer

Transformer

Switch

Yard

Switch

Yard

Regulator

Regulator

AMF

Panel

AMF

PanelDistributi

on

Panel

Distribution

Panel

ACAC

AirAir

LightingLighting

Misc. Load

Misc. Load

Synchronization

Panel

Synchronization

Panel

Generator

1

Generator

1Generat

or

2

Generator

2Generat

or

3

Generator

3

Distribution

1

Distribution

1

Distribution

2

Distribution

2

Precision

AC1

Precision

AC1

Precision

AC2

Precision

AC2

UPSUPS

UPS 2

UPS 2

UPS 1

UPS 1

UPSUPS

Loss 3%

Loss 3%

Loss 5%

Loss 5%

1 MW1 MW Loss 0.5%

Loss 0.5%

Loss 10%

Loss 10%

15% (no Load)

15% (no Load)

915 kW

915 kW

366 kW

366 kWn

+2

Red

un

dan

cy

n+

2 R

ed

un

dan

cy

Mains 366 kW

Mains 366 kW

Cooling for Server

Cooling for Server

Page 13: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

13 13

ACME’s Green Datacenter Solution

Line Conditioner

+ Isolation Transfer +

Lightning Protection

Line Conditioner

+ Isolation Transfer +

Lightning Protection

Mains

Mains

Mains Synchronized Micro turbine

(500 kW) in n+2 configuration

Mains Synchronized Micro turbine

(500 kW) in n+2 configuration

MainsDistributi

on

MainsDistributi

on

ElectronicDistributi

onN+1

ElectronicDistributi

onN+1

Servers &

Electronics

Servers &

Electronics

Mirror Server & Electroni

cs

Mirror Server & Electroni

cs

970 kW (rarely

used)

970 kW (rarely

used) 970 kW970 kW350 kW350 kW

N + 1N + 1

Fuel Tank 1

Fuel Tank 1

Fuel Tank 2

Fuel Tank 2

Multi Fuel

Multi Fuel

VAMVAM

Electrical Chiller

(Redundancy)

Electrical Chiller

(Redundancy)

470 kW (used in

emergency)

470 kW (used in

emergency)

Precision AC

Distribution

N+1

Precision AC

Distribution

N+1

PrecisionAC

PrecisionAC

Redundant

PrecisionAC

Redundant

PrecisionAC

75 kW75 kW

LightingLighting

1 MW1 MW

75 kW75 kWNormal CoolingNormal Cooling

N + 1N + 1

Hot air

Page 14: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

14 14

Macro level Savings• On site power generation 24x 7

• No separate expenditure on Air Conditioners

• Elimination of various AC-DC conversion losses

• Energy generation at low cost in cogeneration mode

• Carbon credit benefit

• No operation and maintenance expenditure of DG

Page 15: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

15 15

Making green solution profitable• ACME can built clean energy infrastructure for new IT Datacenter

set up and reduce– 20% Capex (approx.)– 15% Opex – 30% Carbon Emission

• ACME can take up existing infrastructure and reduce – 10% Opex– 20% Carbon emission

Page 16: Green Datacenters solution March 17, 2009 By: Sanjay Sharma

16 16

Thank You !!Thank You !!Partnership Contact:Partnership Contact:Email: Email: [email protected]:+919810159777Mobile:+919810159777