Green Datacenters solution March 17, 2009 By: Sanjay Sharma
description
Transcript of Green Datacenters solution March 17, 2009 By: Sanjay Sharma
Green Datacenters solution
March 17, 2009
By: Sanjay Sharma
Green Datacenters solution
March 17, 2009
By: Sanjay Sharma
2 2
Energy Facts• Of all the potential electricity available in an energy source, only 30
percent reaches consumers
• An estimated 170 billion kilowatts are wasted by consumers each year due to insufficient power usage information
• US Datacenters and servers consumed about 670 billion kWh in 2008 with an estimated total electricity cost of $ 5.0 Billion
DATA CENTER
100%
30% 16%
Generation & Distribution Cooling
Power Supplies, UPS
ServersSiliconMission
Critical Apps 1%.003%
3 3
Where Does Power Go?
IT Equipment = 30%
Energy Equipments = 25%
Cooling = 45%
Total number of servers installed increased by factor 100 in one decade
Number of server/processors per rack increased by factor 10 in ten years
Power and thermal waste per server increased by factor 5 in ten years
Total number of servers installed increased by factor 100 in one decade
Number of server/processors per rack increased by factor 10 in ten years
Power and thermal waste per server increased by factor 5 in ten years
Source: APC ViewSource: APC View
4 4
I.T damage to the environment
Billions of KW/hrsMillions of Tons of CO2
• I.T Does as much damage to environment as Airline Industry
• 2% of CO2 Emitted comes from I.T Industry
• For every 1 spent powering systems 0.5 to 1 spent on cooling I.T is the focus of GREEN lobby! Source: EPA ReportSource: EPA Report
5 5
Green Buildings
IBM Example
Enhancing existing buildings to be more energy efficient typically reduces total energy consumption by 20-50%...
…while new “green” buildings have the potential to reduce energy consumption by 80% or more. Benefits Average achievable energy savings
greater than 40%;
Average payback of <2 years in Data Center Energy Efficiency assessments;
Asset utilization rates increasing 2x-4x;
Deferral of massive capital investments in new datacenter builds
$1 energy savings drives another $6-8 operational savings on average
Benefits Average achievable energy savings
greater than 40%;
Average payback of <2 years in Data Center Energy Efficiency assessments;
Asset utilization rates increasing 2x-4x;
Deferral of massive capital investments in new datacenter builds
$1 energy savings drives another $6-8 operational savings on average
Source: IBM Client SurveySource: IBM Client Survey
6 6
Case Study
Energy Management Solutions for Bharti’s Telecom Towers
7 7
Conventional solutions & associated problems
• Unhealthy Grid• High DG running costs• Higher capacity DG’s
• Operational problems• Low efficiency in Power utilization (85%)
– Leading to Heat losses• Slow Voltage regulation time leading to
– SMPS Failure– High maintenance
• Large foot print• Excessive cabling • Frequent breakdowns with no monitoring
of passive infrastructure elements
• Shelter• High solar gain• Non modular• Rusting problem
• Air Conditioning• Oversized AC’s• Very High Inrush Current• No Free Cooling
Problems with Conventional systems
15/25 KVA DG
IT, Servo, AMF, Alarm box ACDB etc
GI:GI
Shelter
1.5x2 2.0x2 Tr AC’s
Conventional systems
8 8
Addressing ChallengesChallenges Contributor/Reasons Innovative ‘s Solutions
Site Operation Cost
• Various AC/DC Conversion Cost• Backup Cost• Environment Conditioning Cost• D.G. running cost due to
unhealthy grid• Over-design Infrastructure for
Peak Load (like 15KVA DG for 3KW load)
• Less/low AC/DC Conversion • Low backup cost • Low Air-Conditioning Cost • Wide range PIU to maximize low
cost grid usage• Low back up power cost with DC
power house of 5kw
Site Downtime
Main Reasons• Battery• Generator• Air-Conditioner
• NextGen thin Plate Technology• Aviation grade very high MTBF
DC Generator• Compressor less N + 2
redundancy
Project , Operation and Maintenance Cost
• Installation Time• Expandability• IT Interface for critical and
operational need monitoring
• Installation time (24-48 hours)• Expandability modular • Energy metering for each
operator and their individual load• Detailed NMS
9 9
Use of technology for reducing energy costs
• Air Conditioning– Next Generation Cooling solutions (for Indoor BTS)– Battery Cooler (for Outdoor BTS)
• Battery back-up power– High efficiency and cycle life batteries– Float Mode operation for extended life
• DG based power– Cost of DG running to be reduced– Move site to DC Power architecture which creates future proof
site– Explore Alternative technologies like wind/ solar or fuel cells
• Energy losses in SMPS & PIU– New products offering high efficiency– Wide operating range to reduce DG running
• Integrated NMS– Integrate Tower Management (Through SMS and GPS) with
overall NOC
10 10
Conventional Telecom Approach
Mains
AC1.4 kW
SMPS250 W10%
BTS1.5 kW
DG
PIU250 W
3%
3.4 kW
Battery300 AH50 W
Leakage
3.15 kW
Note: Per hour energy usage / energy losses
Every IT Companies were focusing at this
point
IT and Datacenters are in similar position like telecom was few years back
11 11
Our Green Solution for Telecom
Mains
AC0.45 kW
SMPS250 W10%
Battery15 W
Leakage
BTS1.5 kW
DC Power House
PIU150 W
3%
2.4 kW
Note: Per hour energy usage / energy losses
1
2
43
PCM TechnologyPCM Technology
12 12
Current IT Datacenter set up
Transformer
Transformer
Switch
Yard
Switch
Yard
Regulator
Regulator
AMF
Panel
AMF
PanelDistributi
on
Panel
Distribution
Panel
ACAC
AirAir
LightingLighting
Misc. Load
Misc. Load
Synchronization
Panel
Synchronization
Panel
Generator
1
Generator
1Generat
or
2
Generator
2Generat
or
3
Generator
3
Distribution
1
Distribution
1
Distribution
2
Distribution
2
Precision
AC1
Precision
AC1
Precision
AC2
Precision
AC2
UPSUPS
UPS 2
UPS 2
UPS 1
UPS 1
UPSUPS
Loss 3%
Loss 3%
Loss 5%
Loss 5%
1 MW1 MW Loss 0.5%
Loss 0.5%
Loss 10%
Loss 10%
15% (no Load)
15% (no Load)
915 kW
915 kW
366 kW
366 kWn
+2
Red
un
dan
cy
n+
2 R
ed
un
dan
cy
Mains 366 kW
Mains 366 kW
Cooling for Server
Cooling for Server
13 13
ACME’s Green Datacenter Solution
Line Conditioner
+ Isolation Transfer +
Lightning Protection
Line Conditioner
+ Isolation Transfer +
Lightning Protection
Mains
Mains
Mains Synchronized Micro turbine
(500 kW) in n+2 configuration
Mains Synchronized Micro turbine
(500 kW) in n+2 configuration
MainsDistributi
on
MainsDistributi
on
ElectronicDistributi
onN+1
ElectronicDistributi
onN+1
Servers &
Electronics
Servers &
Electronics
Mirror Server & Electroni
cs
Mirror Server & Electroni
cs
970 kW (rarely
used)
970 kW (rarely
used) 970 kW970 kW350 kW350 kW
N + 1N + 1
Fuel Tank 1
Fuel Tank 1
Fuel Tank 2
Fuel Tank 2
Multi Fuel
Multi Fuel
VAMVAM
Electrical Chiller
(Redundancy)
Electrical Chiller
(Redundancy)
470 kW (used in
emergency)
470 kW (used in
emergency)
Precision AC
Distribution
N+1
Precision AC
Distribution
N+1
PrecisionAC
PrecisionAC
Redundant
PrecisionAC
Redundant
PrecisionAC
75 kW75 kW
LightingLighting
1 MW1 MW
75 kW75 kWNormal CoolingNormal Cooling
N + 1N + 1
Hot air
14 14
Macro level Savings• On site power generation 24x 7
• No separate expenditure on Air Conditioners
• Elimination of various AC-DC conversion losses
• Energy generation at low cost in cogeneration mode
• Carbon credit benefit
• No operation and maintenance expenditure of DG
15 15
Making green solution profitable• ACME can built clean energy infrastructure for new IT Datacenter
set up and reduce– 20% Capex (approx.)– 15% Opex – 30% Carbon Emission
• ACME can take up existing infrastructure and reduce – 10% Opex– 20% Carbon emission
16 16
Thank You !!Thank You !!Partnership Contact:Partnership Contact:Email: Email: [email protected]:+919810159777Mobile:+919810159777