Great Park Development Report
Transcript of Great Park Development Report
![Page 1: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/1.jpg)
Great Park, September 28, 2021
Great Park Development Report
Joel Belding, Deputy Director of Great Park Planning and Development
![Page 2: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/2.jpg)
In Today’s Presentation
Status of previously approved City projects• Cultural Terrace Reuse Plan
Status of previously approved private party projects
New Pursuits
![Page 3: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/3.jpg)
Status of Previously Approved City Projects
![Page 4: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/4.jpg)
Previously Approved Public Development
Visitors Center Plaza
Maintenance Building
Volleyball Improvements
Parkwide Shade
Concessions
Parking Lot 8
Western Sector Improvements
![Page 5: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/5.jpg)
Visitor Center Plaza
90% drawings complete
Ready for Community Development review for permits
Out to bid by the end of the year
Construction in early 2022
![Page 6: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/6.jpg)
Sports Park Enhancement Projects
Reflecting pond fountains
Entry monuments at gateway locations
Soccer Field lighting Plans and Specs
complete Finalizing Engineers
estimate Ready to bid by end
of year
![Page 7: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/7.jpg)
Shade Improvements
Six locations 15 new shade
structures
![Page 8: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/8.jpg)
Shade Improvements
• Community Development Approval: Fall 2021
• City Council Approval: End of 2021/Early 2022
• Contract Bidding and Contract Award: Spring 2022
• Start Construction: Summer 2022
• Complete Construction: Fall/Winter 2022
![Page 9: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/9.jpg)
Concessions Upgrades
• Concept plans for 4 concessions were approved by the Board in April 2021
• Baseball annex design being refined to match existing buildings
• CS and PW will prepare Final Design documents
•Construction in 2022
![Page 10: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/10.jpg)
Volleyball Upgrades
Volleyball Courts
• 2.4-acre site
• $125,000 for Player Safety (funded)
• Reviewing options for additional courts for tournament play
• $1,650,000 additional funding in budget
![Page 11: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/11.jpg)
Western Sector Development Status
• FivePoint/Heritage Fields finalizing designs for Aquatics and Field House buildings
• Preliminary drawings in October/November
• Design, costs and operations plan require Council approval
![Page 12: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/12.jpg)
Maintenance Building status• Westerly Corner of Skyhawk and Marine Way
• Program and general design is completed
• Will provide office, storage, garage, and shop space for Community Services and Public Works staff
• Refining final design
![Page 13: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/13.jpg)
Public Safety Joint Training Facility
• Examining alternative sites across the City
• Approved Budget (OCFA settlement): $20,500,000
• Evaluating funding sources and phasing for total project
• Evaluating revenue and expenditure models
![Page 14: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/14.jpg)
Aviation Beacon Site• Working with FAA to allow
agriculture and other low impact uses on the restricted 70 acres
• Looking for collaborative uses for land adjacent to area
• Possible relocation site for Farm & Food Lab
![Page 15: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/15.jpg)
TVI Relocation
• Evaluating minimum functional size for relocated facility
• Evaluating sites within the Great Park as a long-term temporary option
![Page 16: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/16.jpg)
Timeline Repainting
• Timeline repainting to be completed by October 2021
• Enhancing visibility and durability of text
• Second phase 1991-2020 will occur after Visitor Center Plaza project completion
![Page 17: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/17.jpg)
Electric Vehicle Charging Stations
• RFP issued for installer/operator
• (72) Level 2 chargers at Cultural Terrace parking lot (Lot 8)
• Approximately 185 additional chargers on four other parking lots through SCE program
• Goal is to have contractor selection to Board in November
![Page 18: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/18.jpg)
Great Park Renaming
• Zoning Ordinance and General Plan Amendment to update naming to Planning Commission September 16
• Zoning Ordinance, General Plan Amendment and Municipal Code Amendment to City Council in October
• Bylaws update to Great Park Board in October
• Website update is completed
• Signage and ephemera updates ongoing
![Page 19: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/19.jpg)
Great Park Signage
Preparing schedule and estimates for update of Great Park signs to reflect renaming
Identifying additional sign opportunities on key facilities including the Great Park Ice
Developing designs for park gateways
![Page 20: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/20.jpg)
Cultural Terrace Reuse Plan
![Page 21: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/21.jpg)
Cultural Terrace Architectural and Engineering Contract
• 18 proposals (14 firms with fixed prices)
• Pricing range: $4,930,200 - $18,000,000
• Average contract price: $8,431,431
• IBI price: $7,236,935 ($1,194,496 below average)
• $16.45 per square foot for 440,000 sq. ft. of building area
![Page 22: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/22.jpg)
Cultural Terrace Architectural and Engineering Contract
Great Park Administration Building• A&E design: $1,923,003 for a 28,500 sq. ft. building• $67.47 per sq. ft.
OSF and Animal Care renovation and construction• A&E design: $2,045,662 for 95,924 sq. ft. of rehab and construction• $21.33 per sq. ft.
Quail Hill Community Center (2009)• A&E design: $950,000 for a 12,500 sq. ft. building• $76 per sq. ft.
![Page 23: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/23.jpg)
Cultural Terrace Architectural and Engineering Contract
Building demolition $ 9.8Paving demolition $ 13.1Site grading: $ 52.0Utilities: $ 30.7Circulation: $ 35.6Total Costs $141.1
Current Funding AllocationDesign Contract $ 7.3Building 369 $13.7Hangar 296 $14.6Hangar 297 $13.7Events Space $12.04Plex Plaza $ 4.0Total Reuse Costs: $65.3
Proposed Reuse Funding
Redevelopment Reserve: $92.8**To fund grading, utilities, circulation, and Phase 2 development**Includes $17M from Admin Building CIP
Savings and reallocation for Reuse Option
*All dollars in millions.
![Page 24: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/24.jpg)
Building 369 Events Center
![Page 25: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/25.jpg)
Building 297: Library & Cultural Center
![Page 26: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/26.jpg)
Building 296: Aviation Museum & Innovation Center
• Marine Corps is still reviewing Leathernecks proposal
• Flying Leathernecks are working to form local advisory board
![Page 27: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/27.jpg)
Cultural Terrace Reuse Plan
• Staff and FivePoint will resume joint studies of area to assist with reactivating Cultural Terrace
• Process and funding already established under the ALA II Agreement
• Studies will evaluate grading, reestablishment of utilities, traffic and circulation of the site with retention of FourPlex site and Building 369
• This process will allow refinement of expected development costs
![Page 28: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/28.jpg)
Status of Previously ApprovedPrivate Party Projects
![Page 29: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/29.jpg)
Previously Approved Private Development
Pretend City
Wild Rivers
![Page 30: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/30.jpg)
Wild Rivers
• Under construction
• Anticipated opening May 2022
![Page 31: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/31.jpg)
Pretend City
• Developing plans for City review
• Entitlement application due to City by end of 2021
• Site to be graded by FivePoint
![Page 32: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/32.jpg)
Additional Private Development Status
Lifetime Fitness
FivePointX
Pop Up Village
![Page 33: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/33.jpg)
Pop-Up Village
• 2,000 sq. ft. of food, coffee and bar area
• Introduces new food options for the Great Park and neighborhoods
![Page 34: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/34.jpg)
Amphitheater Lease Extension
• FivePoint proposing to approve a one or two year lease extension while working with City on a permanent location
• Alternative parking arrangements needed in Year 2 as neighborhoods to the east are developed
• Permanent amphitheater locations, funding options, and general terms being evaluated
![Page 35: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/35.jpg)
New Pursuits
![Page 36: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/36.jpg)
Great Park Master Plan Update
• Planned for Fall 2021
• Public input solicited on key development opportunities
• Outreach proposal and schedule is a subsequent agenda item
![Page 37: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/37.jpg)
• Cricket• Amphitheater• Botanic Garden: Including veterans memorial• CSU Fullerton Cooper Center collection• Western Whitewater• TopGolf• New Farm & Food Lab• All will be discussed in context of Master Plan
Long Term Uses
![Page 38: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/38.jpg)
• Mountain biking/pump track courses
• Outdoor sports pop-ups
• Large private events
• 3-5 year durations
Short Term Uses
![Page 39: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/39.jpg)
• Traffic safety and landscape maintenance on Bosque
• Enhanced coordination between Irvine Public Safety and GPN security contractors
Great Park Neighborhood Coordination
![Page 40: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/40.jpg)
• Cultural Terrace Design Contract
• Public Engagement
• Master Planning Process
Upcoming Agenda Items
![Page 41: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/41.jpg)
•Receive and file report and presentation
• Direct staff to proceed with Cultural Terrace Building Reuse
Recommendations
![Page 42: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/42.jpg)
Great Park, September 28, 2021
Great Park Development Report
Joel Belding, Deputy Director of Great Park Planning and Development
![Page 43: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/43.jpg)
Cultural Terrace Architectural and Engineering Contract
Previously estimated costsEnvironmental remediation and demolition - Buildings $9.8Environmental remediation and demolition - Sub-Surface $13.1Earthwork and terraforming $52.0Utility Infrastructure $30.7Circulation – roadways, trails, and parking $35.6
Total estimated cost $141.1
• Demolition, remediation and grading funding can be repurposed to reuse efforts
• Additional savings from consolidating $17M Administration Building into new facilities
![Page 44: Great Park Development Report](https://reader031.fdocuments.us/reader031/viewer/2022013001/61cadfbd634a672124517193/html5/thumbnails/44.jpg)
Cultural Terrace Reuse Plan
• Rehabilitation of the buildings is cost effective, feasible and expeditious
• Seeking direction to begin lead and asbestos remediation for all buildings
• Seeking direction to begin planning and design for full rehabilitation of Building 369 and Hangars 296 and 297
Year Built Size Rehabilitation Cost New Construction Cost
Hanger 296 1944 140,000 $13,670,957 $28,700,000
Hangar 297 1944 140,000 $14,602,660 $28,700,000
Building 369 1594 28,425 $13,708,758 $10,447,118