Presentation to the Guam Legislature
On the DOD FEIS and Discussions to date
August 23, 2010
Presentation Outline Presentation Outline
CONSOLIDATED COMMISSION ON UTILITIESCONSOLIDATED COMMISSION ON UTILITIES Simon A. Sanchez, II, ChairmanSimon A. Sanchez, II, Chairman
GUAM POWER AUTHORITYGUAM POWER AUTHORITY Joaquin C. Flores, P.E. GMJoaquin C. Flores, P.E. GM
GUAM WATERWORKS AUTHORITYGUAM WATERWORKS AUTHORITY John Benavente, P.E. GMCUSJohn Benavente, P.E. GMCUS
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 33
FEIS proposes $740M for Guam Infrastructure
From the start, CCU, GPA and GWA Position: Civilian ratepayers should be shielded from direct and
indirect cost impacts resulting from the proposed buildup.
DoD remains a GPA customer The northern aquifer and our environment shall be
protected for the long term. Mandatory shared responsibility The existing GWA NWWTP shall be the only WW plant over the
aquifer
FEIS proposes $740M for Guam Infrastructure
In 2006: NO commitments to fund off-base civilian infrastructure.Since 2006, we have engaged in hundreds of hours of meetings and extensive exchange of data to determine best solutions, estimated costs and “who pays”.
FEIS proposes $740M for Guam Infrastructure
Today, FEIS “preferred alternatives”:Provide $740 Million for water,
wastewater and power improvements to serve civilian and military needs, AT NO CAPITAL COSTS TO CIVILIAN
RATEPAYERS.DOD WILL PAY 100% OF THESE COSTS!
Unresolved Issues Remain Though DoD will be responsible for payments, how
funding assistance will be provided to GPA/GWA is still being determined. First meetings w/ Japan Bank for Intl.
Cooperation (JBIC) held earlier this month. Direct loans or grants, or indirect through
Special Purpose Entities (SPEs) or other types of Public-Private-Partnerships (PPP)?
WHETHER FUNDING COMES FROM JAPAN, DOD OR THE US GOVT., OUR POSITION IS CLEAR: CIVILIAN RATEPAYERS WILL NOT BE BURDENED
BY CAPITAL COSTS RELATED TO THE BUILDUP.
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 77
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 88
FEIS: Power Impacts Summary
FEIS Identifies ~$160 million in available funding for the power infrastructure:
CT upgrade:
25% or ~ $37 million T&D:
75% or ~ $122 million
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 99
FEIS: Power Demand Load requirements for Marine Corps relocation and other
Department of Defense (DOD) upgrades 70 Megawatt (MW) Total Additional Demand
30 MW DOD Firm Load (24/7) 40 MW DOD Transient Load (Intermittent)
DOD remains a GPA customer
New GPA/Navy Utility Services Agreement (USA) Negotiations have started
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 1010
THERE IS ENOUGH POWER GENERATION CAPACITY
GPA Generation Capacity: 552 MW Current Peak: 272 MW Peak after Build Up: 342 MW (est) Excess Generation Capacity after
build up: = 210 MW GPA & DOD agree there is sufficient
generation capacity to support the build up
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 1111
Preferred Alternative Recondition up to 5 existing GPA permitted
facilities to provide peaking power/reserve capacity
Yigo, 2 @ Dededo, Marbo, Macheche FEIS states “Planning indicates that new power
generation capacity would not be required to meet the planned demand increase.” (Vol 6, 2-9)
No Additional Long Term Alternatives - All other power alternatives in the DEIS to address additional load and capacity were “deemed unnecessary” (Vol 6, 2-3)
“This showed that adequate power would be fairly easily provided in time to accommodate the proposed military relocation.” (Vol 6, 2-3)
FEIS: Generation
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 1212
GENERATION SOLUTIONS GPA & DOD agree that 3 GPA CT’s should be
refurbished to support construction phase Estimated at $37 million (paid by DOD) CT’s located at Dededo & Yigo (~60 MW) Start by 2012
Navy has completed assessment for refurbishment of 5 CT’s
DOD to pay 100% of $37 million cost to refurbish CT’s
All existing civilian ratepayers will benefit from this improvement in generation reliability
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 1313
FEIS: Renewable Energy
OTECGeothermalWind
May be considered in the
future, but not addressed in this
FEIS
SolarBiomassFuel CellsWave/Tidal
Eliminated as viable source to serve direct load
of Build Up
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 1414
Alternative Energy & Fuel Diversification - Ongoing
Discussions GPA is pursuing 80MW of renewable energy sources, primarily from wind and solar
GPA and DOD have been working collaboratively on renewable efforts
GPA will not support renewable power generation solutions that only serve on-base needs. All renewable generation benefits must be shared with the entire island grid via GPA
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 1515
T&D System Upgrades and new T&D Infrastructure needed to mitigate direct, indirect, and induced impacts of Build Up
DOD remains a transmission level customer of GPA
Agreement reached between DoD & GPA on $122 million of T&D projects (transmission lines and substations) directly related to Build Up
FEIS:Transmission &
Distribution
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 1616
Unresolved IssuesGENERATION – New Base Load
To insure continued generation reliability, GPA believes buildup accelerates the need for the next base load generator from 2022 to 2017
GPA believes DOD should pay for induced impacts caused by accelerating the need for the new base load
GPA and DOD have yet to determine and agree on induced impact
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 1717
New Base Load: Buildup accelerates need from 2022 to
2017 60 MW Base Load requirement
$150 million for conventional oil fired $120 million for the plant + $30 million for
additional fuel storage
$300 million for Liquefied Natural Gas (LNG) system (includes fuel storage)
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 1818
Unresolved Issues T&D and Funding Sources
GPA is still concerned about other indirect impacts on T&D assets in the civilian sector caused by the buildup $30 million of T&D projects necessary to mitigate
indirect impacts of the Build Up have been estimated Responsibility of costs related to mitigating these
impacts on T&D assets have yet to be determined Other cost requirements to resolve:
Program Management Office (PMO), Environmental Studies and Archaeological Services
Water
Aquifer YieldAquifer Yield
Aquifer can yield 80 million gallons/day Aquifer can yield 80 million gallons/day (MGD)(MGD)11
Peak during construction surge is 53 Peak during construction surge is 53 MGDMGD
Post construction (base open) will be Post construction (base open) will be less less
Current professional consensus; Current professional consensus; sufficient water to meet buildup growthsufficient water to meet buildup growth
1 – Theoretical Sustainable Yield from 1992 Groundwater Study by Barrett/Mink. 2009 1 – Theoretical Sustainable Yield from 1992 Groundwater Study by Barrett/Mink. 2009 Review by UOG-WERI. Concurred by GWA, DoD, GEPA.Review by UOG-WERI. Concurred by GWA, DoD, GEPA.
FEIS: Protecting the AquiferFEIS: Protecting the Aquifer
Parties will cooperate in all aspects Parties will cooperate in all aspects of water resource development on of water resource development on Guam to ensure the long term and Guam to ensure the long term and sustainable management of the sustainable management of the Northern Guam Lens Aquifer (NGLA).Northern Guam Lens Aquifer (NGLA).
Updated comprehensive study of the Updated comprehensive study of the Aquifer funded by DoD is underway, Aquifer funded by DoD is underway, led by UOG/WERI and supported by led by UOG/WERI and supported by USGS, USEPA, DoD, GEPA and GWA.USGS, USEPA, DoD, GEPA and GWA.
FEIS: Water Supply SolutionFEIS: Water Supply Solution
$165 million for a new northern water $165 million for a new northern water system of wells, treatment, transmission system of wells, treatment, transmission and distribution assets.and distribution assets. DOD WILL PAY 100% OF THESE COSTSDOD WILL PAY 100% OF THESE COSTS
The new northern system will be inter-The new northern system will be inter-connected to the existing GWA and DoD connected to the existing GWA and DoD systems so that the three systems can systems so that the three systems can eventually work as an integrated whole. eventually work as an integrated whole.
Water Supply Ongoing Water Supply Ongoing DiscussionsDiscussions
DoD transmission and distribution DoD transmission and distribution systems Loop design and connection systems Loop design and connection pointspoints
Price for DoD water during Price for DoD water during construction phase construction phase
Price of DoD Transfer and exchange Price of DoD Transfer and exchange of excess water. of excess water.
Wastewater
FEIS: Wastewater (WW) FEIS: Wastewater (WW) SolutionsSolutions
NDWWTP 12MGD Primary Treatment UpgradesNDWWTP 12MGD Primary Treatment Upgrades $65M$65M
NDWWTP 18MGD Secondary Treatment Upgrades $135MNDWWTP 18MGD Secondary Treatment Upgrades $135M
Collection System Improvements Collection System Improvements $85M $85M
Hagatna 12MGD Secondary Treatment Upgrades $150MHagatna 12MGD Secondary Treatment Upgrades $150M
Total : Total : $435M$435M
FEIS: Wastewater (WW) FEIS: Wastewater (WW) AlternativesAlternatives
FEIS Wastewater Alternatives 1a FEIS Wastewater Alternatives 1a & 1b& 1b
FEIS: Northern WW Treatment:FEIS: Northern WW Treatment:
Upgrade and expand NDWWTP with Upgrade and expand NDWWTP with Marines becoming a GWA customer Marines becoming a GWA customer (like AAFB)(like AAFB)
Complete rehab of NWWTP to provide Complete rehab of NWWTP to provide primary treatment to 12 MGDprimary treatment to 12 MGD
Upgrade to secondary treatment to 18 MGDUpgrade to secondary treatment to 18 MGD
FEIS: Central WW FEIS: Central WW Treatment/CollectionTreatment/Collection::
Upgrade Hagatna to 12 MGD primary Upgrade Hagatna to 12 MGD primary treatment treatment
Upgrade Hagatna to 12 MGD Upgrade Hagatna to 12 MGD secondary treatment secondary treatment
Build $82M worth of new WW Build $82M worth of new WW collection systems (new sewer lines) collection systems (new sewer lines) in northern and central Guamin northern and central Guam
FEIS: Figure ES-26 Utilities and Roadway FEIS: Figure ES-26 Utilities and Roadway ProjectsProjects
DoD/GWA on-going DiscussionsDoD/GWA on-going Discussions
• Increase NDWWTP capacity from 6 MGD Increase NDWWTP capacity from 6 MGD to 8-9 MGD with interim upgradesto 8-9 MGD with interim upgrades
Cost of transfer and exchange of DoD Cost of transfer and exchange of DoD excess waterexcess water
Cost of DoD water for construction phase Cost of DoD water for construction phase Design details of DoD transmission and Design details of DoD transmission and
distribution systemsdistribution systems Details of “One Guam” transfer of DoD Details of “One Guam” transfer of DoD
systems to GWAsystems to GWA
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 3333
SUMMARY OF UTILITY ISSUES SUMMARY OF UTILITY ISSUES FACING BUILDUPFACING BUILDUP
GPA/GWA FINAL EIS GPA/GWA FINAL EIS 3434
Summary DOD/US Govt. should pay for its impact, direct and indirect.
$740 million has been proposed to upgrade Guam utility infrastructure at no cost to the people of Guam.
Hold Fed. Officials to their words of “One Guam”, “Green Guam” and that “the buildup cannot be a burden to the people of Guam”.
If funded in a sufficient and timely manner, the “preferred solutions” as summarized in the FEIS are achievable and can provide benefits for existing and future utility customers.
If insufficient funding is provided in an untimely manner, Guam utilities will not be able to permit the construction of facilities that are needed to commence the buildup (e.g. worker housing).
Much work remains to address unresolved issues.