GOVERNMENT OF INDIA MINISTRY OF RAILWAYS - Indian … for... · ISMC 250x 82 2.5 m 2 10. ISMC ......

download GOVERNMENT OF INDIA MINISTRY OF RAILWAYS - Indian … for... · ISMC 250x 82 2.5 m 2 10. ISMC ... nozzle torch to save the time as well as uniform heating of sections as shown ...

If you can't read please download the document

Transcript of GOVERNMENT OF INDIA MINISTRY OF RAILWAYS - Indian … for... · ISMC 250x 82 2.5 m 2 10. ISMC ......

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 1 of 17

    GOVERNMENT OF INDIA

    MINISTRY OF RAILWAYS

    lR;esot;rss

    PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE

    BRN/BRNA/BRNAHS

    ISSUED BY:

    MINISTRY OF RAILWAYS, GOVERNMENT OF INDIA

    RESEARCH DESIGNS & STANDARDS ORGANIZATION

    LUCKNOW-226 011

    MAY, 2015

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 2 of 17

    ITEMS LIST

    S.No. Description Length Quantity

    1. Hex. Hd. bolt M10x100 100 mm 4

    2. Check Nut M10 - 4

    3. Wing Nut M10 - 4

    4. Plain Washer - 8

    5. Piano Wire 14 m 2

    6. M.S. Strip 50x6Th. 200 16

    7. Stopper for central girder - 4

    8. Optical Pyrometer/Heat sensitive

    crayons to measure temperature up to

    750C

    - -

    9. ISMC 250x82 2.5 m 2

    10. ISMC 250x82 830 mm 2

    11. ISMC 250x82 819 mm 4

    12. ISMC 150x76 618 mm 2

    13. ISMC 100x50 2845x2 mm

    14. Rib (Shown as Item No.1 in Fig.1) - 24

    15. Side Bearer Supporting Plate (Shown

    as Item No.2 in Fig.1)

    542x160x20 mm 4

    16. Centre Pivot Supporting Plate (Shown

    as Item No.3 in Fig.1)

    509x390x20 mm 2

    17. M-20 Nut-Bolt with Standard Washer

    for Item No.2 in Fig.1

    90 mm 8

    18. M-22 Nut-Bolt with Standard Washer

    for Item No.3 in Fig.1

    100 mm 8

    19. Suitable Turn Buckle More than 1200mm 2

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 3 of 17

    1. DRAFT PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON

    TYPE BRN/BRNA/BRNAHS INTRODUCTION

    1.1 Railways have been reporting about loss of camber at the centre in Bogie Rail

    Wagon type BRN/BRNA/BRNAHS after a period of service. Due to this

    sagging wagon ends get lift up. Railways experience difficulties in maintaining

    the buffer height.

    1.2 In view of the difficulties faced by the railways to maintain the wagons, a

    procedure for carrying out re-cambering of wagons has been drawn up and is

    given below. The re-cambering of wagons should preferably be done at the

    time when wagons require POH.

    2. PROCEDURE FOR MEASUREMENT OF CAMBER OF INCOMING

    WAGONS

    2.1 Cut the centre pivot top huck bolts/Rivets and side bearer nut bolts and run out

    the wagon bogies. Support the wagon body on trestles of equal height as

    shown in fig.1 and clamp them with nut and bolts at side bearers and centre

    pivot location, so that the body weight is borne equally by the trestles as shown

    in fig.2. Secure the trestles with rails. Also place suitable stoppers below

    headstock of such a height, so that after recambering process headstock does

    not bend below the limit of required CBC height, as shown in fig.2.

    2.2 Weld vertically 8 Nos. of steel plates, each having a slot and of size

    200x50x6mm on the bottom of the sole bar at center line of the body bolsters

    and wagon head stocks as shown in fig.3. The slot of 11x50mm provided in

    each plate is to pass the piano wire through it. The plates so welded should be

    erect and parallel to each other.

    2.3 Place a piano wire along the length of the wagon passing through the

    rectangular slots in the plates welded to the sole bars and head stock. Secure

    the ends of the piano wire to 100mm long hexagonal head screws provided

    with wing and check nuts and washers.

    2.4 Tighten the piano wire adequately to ensure that the piano wire is straight and

    there is no kink or sagging effect at any location along the wire length. This

    can be done by loosening adjusting the check nut.

    2.5 Adjust the height of the screw by moving up or down in the rectangular slot of

    the plates welded at wagon head stock so that the distance between the top of

    the piano wire and bottom of the sole bar at body bolster locations is equal.

    Once it is ensured, tighten the wing nuts without disturbing the distance

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 4 of 17

    between the top of the piano wire and bottom of the sole bar at the center of the

    body bolster locations.

    2.6 Let the height between the top of the piano wire and the bottom of the sole bar

    at body bolster location be 'a'. Rotating the wing nuts without disturbing the

    clearance 'a' mentioned above tighten the piano wire finally. Measure the

    clearance between top of the piano wire and the bottom of the sole bar at the

    center of the under frame on either side. Let this clearance be 'b'. Therefore, the

    camber of the under frame at the center shall be 'b-a'. Likewise the vertical

    distance between the top of the piano wire and the bottom of the head stock at

    the wagon ends on either side is measured. Let this clearance be 'c',d, etc.

    Therefore, the camber (lifting) of the under frame at its ends shall be 'c-a',d-a',

    etc.

    2.7 If the reverse camber is measured at the under frame center by the procedure

    given above. Re-cambering of the under frame at its center shall be carried out

    as per the procedure detailed below.

    3. PROCEDURE OF THE RECAMBERING (LIFTING) OF WAGON BY

    APPLICATION OF HEAT AND FORCE AT WAGON UNDERFRAME

    MEMBERS

    3.1 Follow instructions given at Para 2.1 above to run out the bogies and placing of

    the wagon body on trestles of equal heights as shown in fig.2. Place load of 8

    ton on wagon floor near headstock.

    3.2 Place 4 No. stoppers under the central girder (2 Nos. on either side of the

    wagon) at locations shown in fig.2. Place stoppers i.e. 4 Nos. below the central

    girders up to they are tight with central girder bottom flange. Provision of

    securing at the wagon body bolsters would ensure that the level of the under

    frame at these locations remain undisturbed during the process of lifting the

    wagon under frame and also it will not droop while heating the girders.

    3.3 The heat source can be oxyacetylene mixtures. The torch nozzle should be a

    medium to large "rosebud" type. But it would be preferential to select a multi

    nozzle torch to save the time as well as uniform heating of sections as shown in

    fig.9. The temperatures shall be monitored by optical pyrometer/heat-sensitive

    crayons in the real time as the heating progresses.

    3.4 Heat cambering should be limited to low carbon steels. IS:2062 Fe410CuWA

    steel should not be heated above 600C, during the cambering process. The

    consequences of overheating are not readily apparent to the naked eye but

    nonetheless they are present in the form of microstructure changes in the steel.

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 5 of 17

    Most heat cambering is accomplished by heating wedge-shaped segments at

    intervals along the length of the member. If the member is over-heated beyond

    the transformation temperature, there will occur "islands" of altered

    microstructure; in other words, the steel will be non-homogenous. This is to be

    avoided at all costs.

    3.5 Remove floor plate of width of about 1.5 feet in entire width just upon the

    location of heating zone. This will facilitate the removal of heat of cutting

    flame as well as the resistance of underframe for recambering. Then cut the slit

    at the cross-section of Side Rail at the location where floor plate has been

    removed as shown in fig.2. Fix two, any suitable Turn Buckles at the location

    of Head Stock and Rails with the help of suitable brackets.

    Schematic Diagram of Differential Heating

    3.6 Start the flame spreader at point A as shown in figure above. Heat spot A to a

    light red colour 600C. Proceed slowly in a serpentine path in the direction of

    the arrow. Direct the torch toward that direction, moving slowly, bringing each

    area to a light red colour. The area of differential heating B A C should be

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 6 of 17

    roughly the shape of an isosceles triangle with the angle at A varying from 20

    to 40, the larger number producing more movement. It is not necessary to

    return to point A to reheat. When the web heating is finished, start the flange

    heating at point D and proceed toward the center. (The flange heating may be

    started, using an additional torch, as the web heating is nearing completion.)

    Always advance the torch along the path bringing the steel to a light red colour

    as it proceeds. The flange to be heated is on the concave side of the camber

    curve; consequently, point A should be about 50mm, in from the convex side

    of the camber curve. Heating zone shall be the girder and solebar locations as

    shown in fig.2&5. These all locations shall be in straight line of underframe

    cross-section. And floor plate shall be removed above these locations only. All

    the prescribed locations shall be heated simultaneously to ascertain uniform

    heating of underframe cross section. During heating, turn the screws to tighten

    both turn buckles to facilitate the lowering of head stock. Continue this process

    of heating and lowering of Head Stock with the help of Turn Buckles upto 10-

    15mm lower than the standard limit of 1105mm, so as to compensate the

    spring-back tendency of underframe when all loads are removed. Take the

    measurements of respective locations to ascertain that adequate camber is

    achieved, after that heating process should be stopped. For best results, let the

    heated member cool by itself. Now, properly weld both slits of side rails, then

    weld and grind flush the floor plate at its location. Note that the heat wedges

    do not necessarily have to be equally spaced, but they should be symmetrical

    about the centre line of the span (see Fig. 5&6). Care should be taken in

    spacing the supports so that the member will not sag too much as the heating

    progresses (see Fig. 2). For best results, allow the beam to cool naturally. If the

    initial heating does not provide enough camber, additional wedges may be

    heated until the desired results are obtained. In order to cut down the time

    expended on heat cambering, several wedges can be heated simultaneously, as

    required.

    3.7 Once the heating starts, it should not be interrupted until the serpentine path

    described below is completed. As the heating proceeds, the member may start

    to bend in the direction opposite to that intended. However, after the heating is

    finished and the beam starts to cool, the beam will commence to straighten and

    then continue to bend in the desired direction.

    3.8 As these members would get cooled, under frame camber should be gained.

    Tight the Turn Buckles as needed.

    3.9 As a precautionary and strengthening measure, weld channel pieces vertically

    at web from top to bottom at the centreline of wagon, at both the girders and

    also weld a channel below the floor plate throughout the width at 300 mm

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 7 of 17

    offset, both sides from wagon centre line as shown in fig.10. This will help to

    prevent the buckling of centre girder and floor plate during service.

    3.10 Measure the camber at the centre of the under frame and CBC height at Head

    stock during the process of lifting till a positive camber of at least 13 mm and

    CBC height of 1105 mm is achieved. Then release the turn buckles and remove

    the stoppers and load.

    4. CRITERIA FOR ASSESSMENT OF PROCEDURE

    After the recambering procedure is done, following points should be

    observed:-

    4.1 Deflection of wagon under frame shall not be more than 132 mm under

    vertical load condition and once the load is removed the under frame should

    come back to its original position.

    4.2 Structural members, member joints, central girders on visual examination

    should not show cracks or permanent distortion during tests.

    4.3 Since joining knees between bolster and central girder & centre sill and

    bolsters are vulnerable to cracks during this process. They should be properly

    checked for their efficacy. Gusset plates should also be checked.

    4.4 Re welding of knees or joining members may be needed.

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 8 of 17

    ISM

    C 2

    50

    x 8

    2

    20

    TH

    . P

    LA

    TE

    20

    TH

    .PLA

    TE

    3

    1

    22

    3

    20

    TH

    . P

    LA

    TE

    6

    6 66

    66

    ITE

    M N

    O.

    DE

    SC

    RIP

    TIO

    N

    CE

    NT

    RE

    PIV

    OT

    SU

    PP

    RO

    TIN

    G P

    LA

    TE

    SID

    E B

    EA

    RE

    R

    SU

    PP

    RO

    TIN

    G P

    LA

    TE

    RIB

    321

    737

    737

    513

    737

    737

    513

    14

    74

    20

    321

    R35

    542

    100

    100

    160

    462

    23

    .54

    38

    509

    235

    390

    25

    00

    819

    830

    819

    fig.1

    : S

    chem

    atic d

    iagra

    m o

    f tr

    estle to s

    upport

    underf

    ram

    e

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 9 of 17

    C.L

    . O

    F B

    OLS

    TE

    R

    8 TONNE

    9144

    650650

    1474

    648

    fig.2: recambering procedure diagram

    (showing underframe support arrangement and location of

    lifting jacks at the central girder portion of the wagon)

    xy

    8 TONNE

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 10 of 17

    fig.3: camber measuring arrangement

    'X'

    = =

    50

    16

    11

    50

    15

    200

    6

    100

    41

    41

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 11 of 17

    TU

    RN

    BU

    CK

    LE

    FA

    ST

    EN

    ED

    BE

    TW

    EE

    N

    HE

    AD

    ST

    OC

    K A

    ND

    RA

    IL

    R.L

    .

    fig

    .4:

    turn

    bu

    ckle

    tie

    d b

    etw

    een

    he

    adsto

    ck a

    nd

    ra

    ils

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 12 of 17

    fig

    .5:

    he

    atin

    g z

    on

    es o

    n c

    entr

    al girder

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 13 of 17

    fig.6

    : heating z

    ones o

    n s

    ole

    bar

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 14 of 17

    fig

    .7:

    ca

    mb

    er

    me

    asurin

    g lo

    ca

    tio

    ns

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 15 of 17

    fig.8:Schematic Arrangement of weights

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 16 of 17

    fig.9:Multi Nozzles heating torch

  • Document No:

    Technical Pamphlet No. G-107 Version No: Nil Date Issued: May-2015

    Document Title: PROCEDURE FOR RECAMBERING OF BOGIE RAIL WAGON TYPE BRN/BRNA/BRNAHS

    Page 17 of 17

    fig.10: Welding of channels at central girder and below floor plate

    ISMC-150 CHANNEL TO

    BE WELDED AT WEB

    AT THE CENTRELINE

    OF WAGON, AT BOTH

    THE GIRDERS

    ISMC-100 CHANNEL TO BE

    WELDED BELOW FLOOR

    PLATE THROUGHOUT THE

    WIDTH AT 300 mm OFFSET,

    BOTH SIDES FROM WAGON

    CENTRE LINE