Goddard Space Flight Center HST Program · PDF fileAperture door Secondary ... Soft Capture...
Transcript of Goddard Space Flight Center HST Program · PDF fileAperture door Secondary ... Soft Capture...
Hubble Space Telescope Program
1101907_PMB_STUC.ppt
Goddard Space Flight Center
HST Program StatusPresentation to:
Space Telescope User’s Committee
Preston M. BurchProgram Manager
October 19, 2007
Hubble Space Telescope Program
2101907_PMB_STUC.ppt
Goddard Space Flight Center Topics
● Program Update
● Observatory Health
● SM4 Preparations and Status
Hubble Space Telescope Program
3101907_PMB_STUC.ppt
Goddard Space Flight Center
HST Program Status(Since April 13, 2007)
● HST SM4 launch date moved up one month to August 2008 (was September 10, 2008)
– Still manifested on OV-104 (Atlantis)– SM4 development work on schedule– We are now at L minus 10 months
● HQ Science Mission Directorate reviewed HSTP recommended SM4 manifest content and priorities, directed minor change (FGS)
● EVA Working Group developed new EVA timeline– EVA days 1 and 2 are swapped– NOBL 5 removed from timeline
● Recently conducted NBL 07.3 (6 EVA days of runs), SM4 Crew Familiarization #1, Safety TIM, POWG, Flight Techniques Panel Meeting, Sim #1 (Rendezvous/Capture), Sim #2 (Gyros & Batteries), Sim #3 (WFC3 & Batteries), Sim #4 (COS & ACS-R), and Center Directors’ Quarterly Review
● Conducting Mini-POP 08-1 to assess FY09 Budget submission to OMB guidelines for SM4 development and post-SM4 operations
● Completed recovery from safemode events:– Gyro #2 failure on August 31– NICMOS safemode on September 1
Hubble Space Telescope Program
4101907_PMB_STUC.ppt
Goddard Space Flight Center
Hubble Space Telescope Program
5101907_PMB_STUC.ppt
Goddard Space Flight Center Major Mission Integration Milestones
● Preliminary Avionics Review June 28, 2007 Complete
● Baseline in Flight Definition/Requirement Doc. (FDRD) June 29, 2007 Complete
● Final Bay IPT Aug 15, 2007 Complete
● Cargo Integration Review Dry (CIRD)-Run (IPT) Sept 12, 2007 Complete
● Cargo Integration Review (CIR) Oct 15-19, 2007
● Flight Planning/Stowage Review (FPSR) (IPT) Nov 14, 2007
● Flight Operations Review (FOR) Feb 25, 2008
● Crew Equipment Interface Test (CEIT) May 9, 2008
● Bench Review June 26, 2008
● Payload Readiness Review (PRR) June 28, 2008
● Flight Readiness Review (FRR) July 24, 2008
● Payload End-to-End Pad test Aug 1, 2008
● Launch Aug 7, 2008
Hubble Space Telescope Program
6101907_PMB_STUC.ppt
Goddard Space Flight Center
HST Servicing Mission 4Planned Mission Manifest and Priorities
Manifest in Priority Order1. RSUs (Gyros)2. WFC33. COS4. Battery Modules5. FGS2RR6. STIS Repair7. ACS Repair8. NOBL 89. NOBL 510. NOBL 7
Note: SCM and Reboost are parallel activities that do not contend with other EVA tasks and, therefore, do not affect priorities
Hubble Space Telescope Program
7101907_PMB_STUC.ppt
Goddard Space Flight Center SM4 Manifest Rationale
Restores unique functionality of STIS: Imaging spectroscopy at full angular resolution of HST, high-resolution UV spectroscopy from 115 to 320nm; resolving power as high as 200,000; high-time-resolution (128 µs) UV spectroscopy and imaging, very high S/N visible spectrophotometry
STIS Repair
Replaces FGS-2R which has degraded star selector encoder LED (predicted unusable in 2011); FGS-3 bearings predicted usable until 2017; operational work-arounds available if only two, or even one, FGS available
FGS2RR
Provides additional margin to science altitude floorReboost
Provides cooperative docking system for future spacecraft to increase probability of eventual de-orbit mission success
SCM
Prevents further degradation of MLI from impacting temps of equipment in Bay 7 and adjacent bays
NOBL 7
Provides cooling of SSRs and MATs that will allow relaxation of roll restrictions and high data volume; more options for operational management of equipment in Bay 5 than Bay 8
NOBL 5
Provides cooling of PSEA that will extend life and allow use of +V3 sunpoint; very limited options for operational management of equipment in Bay 8; pointing restrictions would seriously impact science scheduling
NOBL 8
Restores unique functionality of ACS CCDs: Unexcelled performance in visible-red, best-ever coronagraph on HST
ACS Repair
Current capacity (304 Ah) approximately 58% of nameplate capacity (528 Ah); batteries will be 20 years old at SM4 (5 year on-orbit spec.); present capacity trend is flat
Batteries
Superb point-source, low- and medium-resolution UV spectrographCOS
HST’s first UV-IR panchromatic wide-field camera and wide-field IR imager; discovery efficiencies 40x over ACS in UV/blue,15-20x over NICMOS in IR
WFC3
Replaces failed gyros #2, #3 & #5, anomalous gyro #6, high run time gyros #1 and #4RSUs
Hubble Space Telescope Program
8101907_PMB_STUC.ppt
Goddard Space Flight Center
HST SM4 EVA TimelineFor HST Program Planning Development Only
Priority Task Times1. RSUs (3) 3:152. WFC3 3:053. COS 2:254. Battery Modules (2) 1:50 ea5. FGS 2 3:056. STIS Repair 3:157. ACS - part I 2:15
- part II 0:308. NOBL 8 0:509. NOBL 5 0:5010. NOBL 711. SCM 0:1512. Reboost
Hubble Space Telescope Program
9101907_PMB_STUC.ppt
Goddard Space Flight CenterHST Servicing Mission 4
Shortened Mission Scenarios
RSUs (3), WFC3, COS, Batteries (2 modules), ACS Repair, STIS Repair, NOBLs (8, 5), SCM4.5**
RSUs (2+), WFC3, COS, Batteries (1 module), STIS Repair, NOBL 8,SCM(2)
RSUs (3), WFC3, COS, Batteries (2 modules), ACS Repair, STIS Repair, NOBL 8, FGS2, NOBL 5, SCM5
RSUs (3), WFC3, COS, Batteries (2 modules), STIS Repair, NOBLs (8, 5), SCM(2)
RSUs (3), WFC3, COS, Batteries (2 modules), ACS Repair, NOBL 8, FGS2, SCM(1)4*
RSUs (2+), WFC3, COS, Batteries (1 module), ACS Repair, NOBLs (8, 5), SCM(1)3*
RSUs (2+), WFC3, COS, Batteries (1 module), SCM2
RSUs (2 or more), WFC3, SCM1
ORU/ORI Change-OutEVA Days
* Choice between ACS and STIS repair in 3 and 4 EVA scenarios to be made NLT FOR** 4.5 EVA scenario may be required by OBSS focused inspection
Hubble Space Telescope Program
10101907_PMB_STUC.ppt
Goddard Space Flight CenterShortened Mission Scenarios
EVAs R
emaining
Nominal PlanACS-R pt. 2, FGSCOS, NOBLs 8, 5
WFC3, 2nd BMA, NOBL 82 RSUs, WFC3, SCM1
Nominal PlanCOS, (ACS-R &
FGS or STIS-R & NOBL 5), NOBL 8
WFC3, COS, ACS-R, NOBL 8
2 RSUs, WFC3, COS, 1 BMA, SCM2
Nominal PlanWFC3, COS, (ACS-R & FGS or STIS-R & NOBL 5), 2nd BMA,
NOBL 8
2 RSUs, WFC3, COS, 1 BMA, (ACS-R &
NOBL 5 or STIS-R), NOBL 8, SCM
3
Nominal Plan3 RSUs, WFC3, COS,
2 BMAs, (ACS-R & FGS or STIS-R & NOBL 5),
NOBLs 8, SCM4
Nominal Plan5
4(3 RSUs, WFC3,
COS, 2 BMAs, ACS-R pt. 1, STIS-R, NOBL 8, SCM)
3(3 RSUs, WFC3, COS, 2 BMAs, ACS-R pt. 1,
SCM)
2(3 RSUs, WFC3, 2
BMAs, SCM)
1(3 RSUs, 1 BMA,
SCM)
0
Planned EVAs Completed
Hubble Space Telescope Program
11101907_PMB_STUC.ppt
Goddard Space Flight Center
HST Spacecraft HealthHigh gain antenna
Aperture doorSecondary
mirror
Primary mirror
Equipment Section– Degraded MLI:
Install NOBLs on Bays 5, 7, 8 in SM4
Fine Guidance Sensors– FGS2R: degrading servo LED– FGS3: degrading bearings– Replace one FGS on SM4
Axial Scientific Instruments
– STIS, failed 8/04– STIS Repair on SM4– ACS CCD Imaging
failed 1/07– ACS Repair on SM4– Install COS on SM4
Rate Sensor Units– Gyros 2, 3, and 5 failed:
replace all 6 gyros on SM4
Solar Arrays
Batteries– Charge capacity trending downward;
replace all 6 batteries on SM4Radial Scientific Instrument
– Replace WFPC2 w/ WFC3 on SM4
Aft Shroud– Higher power
instruments causing warming
Hubble Space Telescope Program
12101907_PMB_STUC.ppt
Goddard Space Flight Center Run Times of HST Gyros at 9/17/07
Hubble Space Telescope Program
13101907_PMB_STUC.ppt
Goddard Space Flight Center SM4 Flight CrewScott
AltmanGreg
JohnsonMegan
McArthur
MikeMassimino
DrewFeustel
Mike Good
John Grunsfeld
Hubble Space Telescope Program
14101907_PMB_STUC.ppt
Goddard Space Flight Center HST Servicing Mission 4 (SM4) Configuration
Cosmic Origins Spectrograph
Wide Field Camera 3
Fine Guidance Sensor
Rate Sensor Units
Batteries
Flight Support System
Super Lightweight Interchangeable
Carrier
Orbital Replacement Unit Carrier
Multi-use Logistic
Equipment Carrier
Soft Capture Mechanism
IMAX
Hubble Space Telescope Program
15101907_PMB_STUC.ppt
Goddard Space Flight Center SM4 Flight Hardware Status
● Cosmic Origins Spectrograph (COS)– Completed EMI and VEST testing, metrology verification, SMGT, and ORUC and Hi Fi
Mechanical Simulator fit checks
– Aluminum grating performance issue investigation concluded
● Wide Field Camera 3 (WFC3)– Thermal Vac Test #2 completed
• UVIS-2 and IR-1 detectors are in WFC3
• IR channel thermal instability problem resolved
– Glinting problem identified on UVIS-2 during T/V #2
– Stopped UVIS-1 ATP to address glinting• Removed outer (vacuum) housing to install baffle
– IR-3 detector received at Goddard September 28• IR-4 completing ATP
– Replacement engineering and flight calibration lamps received and are in testing• Calibration system to be removed and modified after EMI testing
– IR channel throughput performance degradation resolved
Hubble Space Telescope Program
16101907_PMB_STUC.ppt
Goddard Space Flight Center SM4 Flight Hardware Status (cont’d)
● New Batteries at Goddard in cold storage– Recent test of flight spare battery shows no sign of degradation
– New battery procurement at Eagle-Picher terminated
● Gyros (aka Rate Sensor Units (RSUs); 1 RSU = 2 gyros)– RSUs 1005, 1006, and 1007 at GSFC
– RSU 1004 in development; to be delivered December 2007
● Fine Guidance Sensor (FGS)– Delivered to Goddard
● New Outer Blanket Layers (NOBLs 5, 7, and 8)– Modifications in work
● Space Telescope Imaging Spectrograph (STIS) Repair– Development work on track
Hubble Space Telescope Program
17101907_PMB_STUC.ppt
Goddard Space Flight CenterOverall WFC CEB/LVPS-Replacement
Implementation
New WFC CEB Module is inserted into and clamps to CEB box
New LVPS module clamps to handrail standoff
Cable conducts power and signals between WFC CEB and LVPS
Cable conducts power between ACS input harness and LVPS
Hubble Space Telescope Program
18101907_PMB_STUC.ppt
Goddard Space Flight Center
Teledyne(ASIC/ Design & Fab)
J&T (CEB-R PWA/ Design, Fab,
Assy, Test)
Ball (CEB-R Chassis/ Mech. Design and Fab)
Ball (LVPS-R/ Box Level)
GSFC(441/FSW)
GSFC(441/FSW)
GSFC (442/I&T)
Key Products Responsibilities
Hubble Space Telescope Program
19101907_PMB_STUC.ppt
Goddard Space Flight Center Key Demonstrations Provide Design Validation
● At PDR (June 20-21), we demonstrated a CEB Breadboard that performed all CCD clocking and video processing functions using the SIDECAR ASIC
– Checks CEB-R to WFC CCD interface– A revised version of this breadboard implements the exact flight design to
enable detailed performance testing without a full CEB-R
● At CDR (October 3-4), we demonstrated the Pre-EM hardware that implements all the FPGA and ASIC functions that are seen by the ACS MEB
– Checks the CEB-R to MEB interface– Being used for early FSW development and testing
● HRC Backpowering Tests demonstrated ability to restore HRC imaging by backpowering the HRC CEB through the flight power harnesses
– Two tests performed with HRC 2 Flight Spare Detector– Detector noise showed no significant differences from nominal performance– On-orbit success with HRC remains dependent on condition of on-orbit
hardware (possible collateral damage from failures)
Hubble Space Telescope Program
20101907_PMB_STUC.ppt
Goddard Space Flight Center
-- Backup Charts --
Hubble Space Telescope Program
21101907_PMB_STUC.ppt
Goddard Space Flight Center
HST Observatory StatusStatus as of 9/4/07 Last changed 9/4/07
Color Code
● Tailor attitude and equipment usage as needed● Consider conditional limitations on operations in
order to retain flexibility● Install Bays 8 and 5 NOBLs on SM4
● MLI degradation assumed to be continuing; may accelerate during coming Solar Min
● Slow warming of aft shroud and equipment bays
● Operations has realized a 38% decrease in SSAT cycles [2044 (7/05-7/06) vs. 3281 (7/03-7/04)]
● 1st year of MAT power cycling LEI yielded a 24.7% reduction [7599 (2/06-2/07 vs. 10089 (2/05-2/06)]
● No performance liens● On/off cycles for the Multi-access & S Band
Single-access transmitters are accumulating
Communications
● ExcellentData Mgmt System
● Two-Gyro Science Mode ops began 8/29/05● FGS-2R acceleration limit K-factor lowered to
ameliorate loss of performance. Effectivenessdecreases with servo-loop gain loss; remainingmargin uncertain. Periodic tests show thatperformance is slowly worsening
● FGS-3 use reduced to preserve bearings● Hybrid HST 486/FGE acquisition mode being
developed
● Gyros 1, 6 operating well; Gyro 4 in reserve, and should be used with primary heaters off
● Gyro 2 failed 8/31/07● FSW compensation of Gyro 6’s bias
instability is being recalibrated● FGS-1R Excellent● FGS-2R Degraded (Anomalous A-Servo
LED suspected)● FGS-3 Degraded (Bearing performance
sub-par; higher torques required)
● Software taper charge continues● 2006 capacity testing completed 8/25/06● 2 additional amps of array output shorted
on 8/31/07
● Batteries are aging ● System-level battery charge capacity
increased ~ 6 Ahr from 2004 to 2006● SA3 performing very well (~77 of 80 strings)
● Highly competitive Cycle 15 and Cycle 16 Science Programs will maintain a 1st rate science program with the remaining SIs
● ACS SBC science resumed February 20● NICMOS recovered 9/4 from 9/1 safing
● WFPC2 Excellent● ACS Redundant electronics failed 1/27/07
SM4 recovery of WFC/HRC pending● NICMOS Excellent● STIS Failed 8/3/04, SM4 repair pending
Changes in Status/Accomplishments/Life-Extension MeasuresSummarySubsystem
G
G
G
G
G
GScience Instruments
Electrical Power System
Pointing Control System
Thermal Performance
Hubble Space Telescope Program
22101907_PMB_STUC.ppt
Goddard Space Flight Center
NOTES:
ORBITAL REPLACEMENT UNITS (ORU's) (TO GSFC I&T)
GROUND SYSTEMS
FLIGHT SYSTEMS
OPS & GND SYSTEMS DEVELOPMENT
PROGRAM MILESTONES
J A S OMILESTONES
1
2
3
4
11
13
14
GODDARD SPACE FLIGHT CENTER
APPVL RESP
BASELINE AS OF
LAST SCHED CHG
STATUS AS OF
HUBBLE SPACE TELESCOPE SM4 MASTER SCHEDULEP. BURCH
FLIGHT INSTRUMENTSCOSMIC ORIGINS SPECTROGRAPH (COS)
SPACE SUPPORT EQUIPMENT (SSE)
LAUNCH
SHUTTLE
PROJECT
0 - 1
1 2
MISSION MANAGEMENT/EVA VERIF.
J3 4 F
2006A M JM
7
8
6
5
- HST 486 FLT SW
- CTL CTR SYS
- OPS SYS DEV
9
SR-3.1
- NSSC-1 FLT SW
SYSTEM TESTING & TRAINING
12
EVA SYSTEMS & CREW TRAINING
MISSION H/W INTEG & TEST @ GSFC
KSC PRE LAUNCH/LAUNCH OPS
2.7 486/R1
JN D F
START SMGTs
ALIVENESS FUNC TEST
START JSC TESTING
09/30/07
PIP/ BL
ICD/ BL
QUEEN V5
J AA M JM
2007
COMPL SMGTs
S O N
WIDE-FIELD CAMERA 3 (WFC3)
FORCIR
486/R2
8.6
10/04/07
CRITICAL PATH
CDR/TRR
5.4.2 5.4.3
8.4
BATTs
2008JD F J AA M JM S
SR-2.1SR-3.2
ARCHIVE 1.0
5.4.4
9.0
O N
KSC FRR
SMOV
SHIP TO KSC
GSFC FRR
GND SYS FREEZE
S/W FREEZE
S/W FREEZE
DELIV TO KSC COMPL
COMPL ETEs
SHIP TO KSC
SHIP TO KSC
LAUNCH OPS
2/09
EVA VERIF COMPLETE
8.5
FGSRSU 1005
5.4.5
LAUNCH
10
DEL TO SYS I&T
RSU 1006
COS ACOUSTIC
RAAS/HOMS DELV
PRE ENV'T FUNC
MULE ACSTCSLIC STRENGTH TESTHP PALLET TO GSFC
GND SYS FREEZE
ACOUSTIC TEST
EMI/ EMC#1
T/V CALIB TEST#2
IR2@ GSFC
2.8 486/R4
RSU 1007
CREW ASSIGN
CF#1 CF#2 CF#3 CF#4 CF#5
JISsGSFC SIMS
FUNC TEST
T/VAC COMPL
PIP SUBMIT
NBL 06.1
486/3.1A 1 GYRO
PH-2 FLT SAF REV
PH-2 GND SAF REV
PH-3 FLT SAF REV
PH-3 GND SAF REV
NBL 06.2
ARCHIVE 1.1
MSO
(LAUNCH DATE 08/07/08)
FUNC TEST
IR2@ BALL
DEINTEG COMPLT
RE-INTEG COMPLT
SSE CDR
5.4.6 GSRR 5.4.6
RSU 1004
RSU 1007
PERR
T/V CALIB TEST#3
PER-2
SLIC PER
FSS ACSTC
NBL 06.3
NBL 07.4
NBL 08.1
NBL 08.2
NBL 08.3
NBL 08.4
NBL 07.5
NBL 07.6
NBL 07.2
NBL 07.3
NBL 07.1
2005
8.6.1
NBL 08.5
5.4.7
PSR
PRR
QUEEN V5.1
SR-4.1 SR-4.2
486/R3
INSTALL FLT
DETECTEMI/
EMC#2
SLIC ACSTC
START KSC TESTING
NBL 08.6
NBL 08.7
- ACS- STIS
CDR PERCEB-R DELV ACS-RREPAIRS
15
SRR PDR PER LVPS DELV
COMPL JISs
ORUC ACSTC
IMAX DEL TO CARRIER
08/10/07
PDR
CVR DEL
LVPS DELV
Line 2 - WFC3 T/V CALIB TEST #2 and EMI/EMC #1 moved one to two months to the right. SCR pending
Line 3 - STIS REPAIR LVPS DELV moved two months to the right. SCR pending
5.4.7.1
Hubble Space Telescope Program
23101907_PMB_STUC.ppt
Goddard Space Flight Center
Hubble Space Telescope Program
24101907_PMB_STUC.ppt
Goddard Space Flight CenterSummary of SM4 Work Remaining
(Major Work Elements)● WFC3 and gyros● Soft Capture and Rendezvous System● STIS replacement hardware, repair tools, and techniques● Shuttle/payload analytical and physical integration● Flight hardware environmental test● Ground system and flight software changes● Mission operations plans and procedures● Mission level integration and test
– Includes end-to-end system verification/validation
● Simulations and Training● Payload processing (KSC)● Launch and mission execution● Post flight de-integration● Servicing mission observatory verification
Hubble Space Telescope Program
25101907_PMB_STUC.ppt
Goddard Space Flight Center ACS Failure History
MEB1 / LVPS2
MEB2 / LVPS1
CEB
● Side 1 failure on June 19, 2006– LVPS1 failure left CEB inoperable
from Side 1
– Most likely cause of ACS failure resides within LVPS1 Board #3, component U2-7, MFL2815D Interpoint DC-DC converter
– Next most likely cause is short to ground in +35V step-up transformer T6 on same LVPS board
● Side 2 failure on January 27, 2007– ACS PDU Side 2 fuse is open
– Failure most likely in LVPS2 Hold section electronics
• Specific component failure likely will remain unknown
APB
Hubble Space Telescope Program
26101907_PMB_STUC.ppt
Goddard Space Flight Center
MEB2 / LVPS1
CEB
Vicinity of TPS
MEB1 /LVPS2Inside Possible ESM
Interference For Panel Removal
HRCCEBInside
WFC CEB Inside
ESM
ACS Mockup
MEB1 / LVPS2
Thermal Saddle (Heat Pipes Inside)
ACS Worksite Accessibility and AccessPanel Locations
APB
+V1
Hubble Space Telescope Program
27101907_PMB_STUC.ppt
Goddard Space Flight Center
ACS Present ConfigurationCurrent State of ACS (post Bus C Test)
Hubble Space Telescope Program
28101907_PMB_STUC.ppt
Goddard Space Flight CenterConcept for ACS Repair
(Not yet Approved by NASA Headquarters)
Repaired State Simplified Electrical Block Diagram
MEB
Side 1
APB
LVPS OOPERATE Bus
HOLD Bus
+15, -15, +35
+5
WFC CEB
WFC CCD
HRC CEB
HRC CCD
LVPS H LVPS H
MEB
Side 2
APB
LVPS O
HOLD Bus
OPERATE Bus
+5
Failed Element
Suspect Element
PDU 20 Amp FusePDU 20 Amp Fuse
Side 1 used to operate the entire instrument except for the CEBs which are
replaced/powered by a new boxSide 2 is inoperable
+15, -15, +35
New Element
New Power Supply
Hubble Space Telescope Program
29101907_PMB_STUC.ppt
Goddard Space Flight Center
Concept for ACS Repair(Not yet Approved by NASA Headquarters)
ACS Repair Architecture - Replace CEB Cards
CEB Replacement Module
Power Supply Module