GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.
-
Upload
denis-poole -
Category
Documents
-
view
214 -
download
0
Transcript of GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.
![Page 1: GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.](https://reader036.fdocuments.us/reader036/viewer/2022072116/56649e885503460f94b8c12b/html5/thumbnails/1.jpg)
Discussion Paper on Terms and Conditions of Tariff
November 12, 2003
![Page 2: GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.](https://reader036.fdocuments.us/reader036/viewer/2022072116/56649e885503460f94b8c12b/html5/thumbnails/2.jpg)
Objective of Tariff Norms
• Provide incentive for investors for realizing the “power for all” target
– Tariff norms that reflect opportunity cost for a given business risk
• To reduce cost of generation in addition to reducing fixed cost
– Reduce taxes
– Reduce fuel cost
![Page 3: GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.](https://reader036.fdocuments.us/reader036/viewer/2022072116/56649e885503460f94b8c12b/html5/thumbnails/3.jpg)
Fixed Cost Recovery
• Fixed cost recovery should be different for coal and gas plants
– Coal plants at [70% ] availability
– Gas and liquid plants at [75%] availability
![Page 4: GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.](https://reader036.fdocuments.us/reader036/viewer/2022072116/56649e885503460f94b8c12b/html5/thumbnails/4.jpg)
Return on Equity
• The current guideline on Return on Equity of 16% may be continued– The ROE method has been in practice and well
understood while ROCE method is complicated to implement
– The ROE is linked to risk of business and not interest on debt
– There is no return during construction (for 3-5 years)– Project finance debt interest rate is about 11% based on
the type of project and risks etc.– Normative Debt: Equity at 70:30 may be continued– FE adjustment for both debt and equity– Interest as a “pass through” may be continued
![Page 5: GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.](https://reader036.fdocuments.us/reader036/viewer/2022072116/56649e885503460f94b8c12b/html5/thumbnails/5.jpg)
Interest on Working Capital
• Existing norms may be continued
• The Coal companies are demanding I (one) month L/C and I (one) month cash advance (equivalent to supply of coal) and the cost of L/C and cash advance should be included for the working capital norm
![Page 6: GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.](https://reader036.fdocuments.us/reader036/viewer/2022072116/56649e885503460f94b8c12b/html5/thumbnails/6.jpg)
Depreciation
• The existing norm of depreciation may be continued
– Allows repayment of loans, tenors are usually for 10-12 years for power projects
– Provides cash for additional capacity
– Advance against depreciation etc. would lead to micro-management by and burden on the Regulatory Commissions
![Page 7: GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.](https://reader036.fdocuments.us/reader036/viewer/2022072116/56649e885503460f94b8c12b/html5/thumbnails/7.jpg)
Operation and Maintenance (O&M)
• The current O&M norm of 2.5% of capital cost is low
• O&M norm should be different for coal (lignite) and gas (liquid) fuel plants
• O&M should escalate on the basis of WPI
• O&M should vary with age
• The suggested base O&M norm as % of capital cost as of COD:
Type 0-5 of COD > 5 of COD
Coal (Lignite) 2.5% 3%
Gas (Liquid Fuels) 5% 5.5%
![Page 8: GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.](https://reader036.fdocuments.us/reader036/viewer/2022072116/56649e885503460f94b8c12b/html5/thumbnails/8.jpg)
Other Operating Parameters
• Heat Rate
– Heat Rate for coal Plants of 2500 Kcal/ kWh to be continued
– Heat Rate for gas/ liquid fuel plants 2000 Kcal/ kWh (Combined Cycle) and 2900 kcal/ kWh (Open) Cycle may be continued
• Justified based on existing data• Also need to account for load fluctuations, degradation (esp.
in case of gas based plants), etc.
– The condition “whichever is less” may be removed to incentivise operations to be efficient
![Page 9: GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.](https://reader036.fdocuments.us/reader036/viewer/2022072116/56649e885503460f94b8c12b/html5/thumbnails/9.jpg)
Other Operating Parameters
• Specific Fuel Oil Consumption and Auxiliary Energy Consumption
– The existing norms may be continued
– The condition “whichever is less” may be removed to incentivise operations to be efficient
• Incentive for higher availability
– The existing norm may be continued
![Page 10: GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.](https://reader036.fdocuments.us/reader036/viewer/2022072116/56649e885503460f94b8c12b/html5/thumbnails/10.jpg)
Additional Points for Reducing Cost of Generation
• Reduction in taxes
– Customs duty on capital goods import: 21.8%
– Customs duty on spares: 50.8
– Sales taxes 12-16%
– Taxes on fuel
– Impact of taxes on capital cost (Base Cost : 100)
Imported Content (60)
Customs Duty
= 60x22%= 13.2
Local Content (40)
Sales tax
=40X16%=6.4
Total increase in cost 20%
![Page 11: GMR Group Discussion Paper on Terms and Conditions of Tariff November 12, 2003.](https://reader036.fdocuments.us/reader036/viewer/2022072116/56649e885503460f94b8c12b/html5/thumbnails/11.jpg)
Additional Points for Reducing Cost of Generation
• Reduction fuel cost
– Fuel cost forms 40-50% of total cost
– Fuel taxes
• Suggestions
– Export parity pricing for liquid fuels
– Cost of coal to be in line with international prices