Gloucester, MA Deep Energy Retrofit · Project Cost Breakout (approximate) Lumber & materials:...
Transcript of Gloucester, MA Deep Energy Retrofit · Project Cost Breakout (approximate) Lumber & materials:...
1
Gloucester, MADeep Energy Retrofit
John Livermore, Livermore Energy Associates03-05-10
Thousand Home ChallengeCASE STUDY
January 2010
2
Answer the Questions…
Why we did it?What we did?
What we learned?
3
John Livermore…“The motivation for taking action to reduce our family’scarbon footprint was the understanding that carbonemissions need to be reduced by about 90% by 2030in order to stabilize the earth’s climate (at 350 ppm),and the realization that I needed to take personalresponsibility for reducing our emissions. Also, I’d beenin the energy efficiency business for over 20 years &I felt it was time to put my money where my mouth was(to walk the talk), taking everything I’d learned aboutbuilding science & had dreamed about doing over theyears, & applying it toward retrofitting my own house.”
4
John continued…“The purpose of performing the energy retrofit &renewable energy installations on the Livermoreresidence was primarily to demonstrate what can bedone to reduce the carbon footprint of a suburbanhomeowner on a budget of approximately $50,000. Theoverall goal is to reduce our home’s carbon footprint by90%, & in doing so to help others by changing thecurrent paradigm of what is possible.”
5
The retrofit strategy has struck abalance between three objectives:1. Make it affordable2. Make it feasible (use off-the-shelf technologies)3. Make it replicableThe sweet spot in the middle, where the three circles overlap, iswhere we primarily focused our strategy.
Affordability
FeasibilityRepeatability
6
Project Cost Breakout(approximate)
Lumber & materials: $9,000Closed-cell foam insulation: $7,000Thermotech windows/doors: $19,000Solar hot water system: $11,500Solar PV system: $9,000Bill’s labor: $4,000Total: $59,500
Note: Costs do not include John’s time, but do factor in all rebates & taxcredits.
7
Project Team
Caleb EwingLead Carpenter
Bill HallarenProject Assistant
John LivermoreProject Designer &Owner
MarcRosenbaum, P.E.
Project Engineer
8
Other Team Members
John’s daughters,Alix & Samantha
John’s 93-year-oldfather
Jasmine,“the supervisor”
9
Starting Point:Typical 1973 Garrison Ranch
• Finished floor area:2,480 ft2
• Walls: R-13 FG batt• Attic: R-19 FG batt• Windows: DH single-pane
w/storms• Basement: Uninsulated• Air sealing?: ...Ha ha
ha…None! (3,000 cfm50)• Lighting: All incandescent• Appliances: Vintage
10
Interim Projects (2001-2007)• Replaced oil furnace
w/87 AFUE gas boilerw/indirect-fired DHWtank
• R-76 attic insulationw/air sealing & radiantbarrier
• Started insulatingbasement slab &foundation walls
• R-5 foam on north wall
11
Project Target Specs• Walls: R-43 (5” closed-cell foam added)• Attic: R-76 w/radiant barrier• Windows: Triple-pane, low-E, argon (R-
5)• Bsmt: Slab (R-7.5), Walls (R-22)• Air Sealing: Reduce to 300 cfm50• Lighting: All LED/SSL & CFL• Appliances: All ENERGY STAR®• Renewables: 4.3 kW solar electric
system & 3-panel solar hot water system
12
Goal: DramaticPerformance Improvement
13
Meeting theThousand Home Challenge
• This home’s customized threshold to meet or exceed is11,247 kWh/Yr (Threshold Allowance OPTION B)
• This household will officially meet the THC when theapplication is completed, & documentation of 1 year ofhousehold consumption verifies that energy use is lessthan 11,247 kWh (net total site household energy)
• This household is on track for exceeding itsthreshold by a factor of two!
NOTE: THC OPTION A (75% reduction from previous use) cannot be used becausethe energy value of the previous year’s wood use is not verifiable. OPTION B is notrelative to previous use; inputs include weather, house size, number of occupancy andtype of fuel used for heating
14
Thousand Home ChallengeThreshold compared with
Usage/Production (kWh/yr by use)
1 Approximate Pre-Consumption: Averaged over several previous years
0 500010000
15000
20000
25000
30000
35000
09-10 Actual / Predicted
(Net; including PV credit)
09-10 Actual / Predicted
(excluding PV)
THC Option A
(75% reduction)
THC Option B
Pre-Consumption1
Heat
Cooling
Water Htg
Everything Else
Net
15
Thousand Home ChallengeThreshold Compared with our
Usage/ProductionTHC Option A (75% Reduction): 6,730 kWh/Yr (Equiv.)
THC Option B1: 11,247 kWh/Yr (Equiv.)
Actual/Projected Usage 2009-10: 5663 kWh/Yr (Equiv.)
1. Option B Assumptions: 6,594 DD, 3 occupants, wood/fossil heat, 2480 Ft2 FFA• For more information on the Threshold Allowance: www.ThousandHomeChallenge.org
Select Energy Source Enter annual use MMBtu kWh
Nat Gas - therms 30.0 3.0 879Electricity - kWh -1986.0 -6.8 -1,986
Wood pellets - lbs. 2817.0 23.1 6,770
Other 0.0 0
TOTALS 19.3 5,663
16
Pre1(red) & Predicted2 (blue)Peak Heating Loads (Btu/Hr)
0 10002000
30004000
50006000
70008000
9000
Above Grade
North Wall
Above Grade Base
Wall (unfinished)
Below Grade
Base Wall (heated)
Frame Walls
Windows
Flat Ceiling
Glass Door
Infiltration
1 Existing in 2008, before basement partially insulated2 Predicted Final Condition, with DER, SDHW, & PV
17
Design Heat Loss (Btu/Hr) Predicted Final Condition, w DER, SDHW, & PV
0
500
1000
1500
2000
2500
3000
3500
Above Grade North Wall
Above Grade Base Wall (u
nfinished)
Below Grade Base Wall (h
eated)
Slab on grade (heated)
Fireplace Wall
Frame Walls
Floor over 0
utdoors
Windows
Sloped Ceiling
Flat Ceiling
Opaque Door
Glass Door
Infiltration
18
Pre-condition vs. Predicted Final
33129kWh/Meter2
06,000Electric Use (kWh/Yr)
3.815.2DHW MMBtu/Yr
21.463.7Heating MMBtu/Yr
6.216.1Design Heat Loss/Ft2 (Btu/hr/Ft2)
4.611.5Design Heat Loss (kW)
15,71239,352Design Heat Loss (Btu/hr)
PredictedPre (08)
19
Construction details designed &drawn by Marc Rosenbaum, P.E.
20
21
22
Meditating onMarc’s Sketches
23
Getting the Building Permit• The code officials began as skeptics (“You want to do WHATto the house?!”) but we were able to turn them intosupporters.
Excerpt from my journal entry, July 24, 2008:“This is your house, right?” Bill asked. I knew he didn’t wantme experimenting on someone else’s home. “I like theapproach,” Bill said, with a skeptical thought bubble almostvisible over his head saying, “But I want you to show/convinceme that it’s going to work.” By the end of our chat, we allshook hands & Bill wished me luck & asked me to keep himposted on how the project is going.
24
Creating theSpirit of Experimentation
Poster created byJohn’s daughter, Samantha
25
Extending the Utilities
Boiler Intake & Exhaust
Gas Meter & Spigots
26
Gable RoofExtensions
August 2008
27
Re-roofing
Prep forthe PVsystem
28
Slider to Clerestory
Reduced area of glass & maximizedopportunity for insulation
29
Wall Truss System(aka ‘Larsen Trusses’)
Rip a 2x4 down themiddle & nail togetherwith plywood gussetsthe thickness of thedesired wall cavity
30
Trusses & More Trusses
Installeddirectly overexistingsiding tominimizeconstructionwaste
31
Deep Energy Retrofits can be FUN
32
Window Frame Extensions
Trimmed 2x6s with9” TimberLokTM screws
33
Window Frame Extension on Foundation Wall
34
John…“One of the most satisfying experiences during theconstruction was the evolving reactions of my neighbors.I had prepped them prior to construction about what wasgoing to happen so it wouldn’t be a surprise to them. Atone point, I think they pretty much thought I had fallen outof a tree & hit my head way too hard. As the truss wallsbegan to take shape, however, & the first phase of sprayfoam was installed, several of them came over and, almostto a word, said, ‘Wow, NOW I get it. This is great! Imight consider this for my own house.’ They needed tosee it to understand it.”
The Neighbors
35
Closed-Cell Foam
R-6 per Inch
36
Prepping for Foam
37
Spraying Foam
38
Scraping Foam
39
WindowsThermotechTM, triple-pane, Low-E, argon-filled,
foam-filled fiberglass frame, R-5
40
Sequencing of Job: Trusses/Windowframes/Windows/Head flashing/More trusses
41
Wall Drainage System
Aluminum mesh strips nailed to bottom plate, bent into a U-shape to hold CobraTM vent material. Surface of foam acts asthe wall drainage plane, & sill flashing directs any moisture
out through the ½” mesh area.
42
Primed Outer Truss Face
43
‘The Yellow Cake’
44
Siding Begins
45
It’s December…Cold hands, dull saw blade, tired bodies
46
Siding Last (rear) Wall
December 2008
47
January 2009
48
January 2009
49
June 2009
A big hunk ofmasonry & apiece of paper
50
Insulating the Chimney
51
RoxulTM mineralwool (2 2/8”, R-10)
52
Reflections on the Chimney
“We should havetorn it down!”
MarcRosenbaum
53
BasementFloorInsulationsystem
2 coats ofDryLokTM
paint
Install 2’x3’grid
Cut & fit1½” EPSfoam board
Install ¾”T&Gplywood
54
Foundation WallInsulation System
55
Interior WallInsulation System(North wall -Basement)
56
Interior WallInsulation System(North wall -Bedroom)
57
Lighting
All LEDs & CFLs
58
AppliancesGave away dryer
Other appliances areENERGY STAR®-rated
59
Ventilation
17-watt PanasonicTM fan (50 cfm) on ventilationschedule controlled by digital timer
60
Solar Hot Water System
3-panel SchucoTM
system with110 gallon stainlesssteel storage tank
61
Solar Hot Water Production-UsageJan 2009 - Nov 2009
• 110 gallon solar tank heats upto 145° F
• Estimated annual gas usage:30 therms (previous baselineabout 180 therms)
• Offset approximately 150therms of gas annually
• 4 therms of gas usage over7-month period (Apr-Oct)
HP is hours the 70 watt pump operated
Solar DHW Cumul (KWH) is electricity offsetassuming DHW is electric resistance (it is not)
62
Hot Water Usage
• BricorTM 1.125gpm showerhead
• Could take a2-hour showeron 1 full tank ofsolar hot water
63
Solar PV System 4.3 kW system(14) 310-watt SchottTM panels
Inverter
64
Electricity Production-UsageOct 2008 - Sept 2009
• Ann. Prod: 4,889 kWh• Ann. Use: 2,903 kWh
(previous baseline:6,000 kWh)
• Produced 146% ofelectricity needs!
• Rainy June: 476 kWh
65
ScanWoodstovew/Biobrick
Sole heat sourcefor house
66
Heating• 2009-2010 heating season
will be the ‘after’ test case• Previous heating energy
usage: Approx. 700 thermsof gas per year
• Estimated 1 ton of Biobricksfor the heating season (orapproximately 231 thermsgas equivalent)
67
Carbon Reductions:Closing in on Net Zero Energy
68
A Boatload of Other Benefits
• Higher comfort at lower airtemps (heating season)
• Easy to maintain good RH• Significantly fewer colds &
viruses than previouswinters
• Quiet interior• More durable home: No
ice dams & lessmaintenance (with newbuilding exterior)
• Wide window sills
• Keeps money in the localeconomy (green jobs)
• Reduces U.S.dependence on foreignenergy supplies,strengthening nationalenergy security
• Provides buffer againstenergy price increases
69
Lessons Learned - Start earlier than August
- It takes longer than you think - Planning, planning, planning
- Understand what you’re doing deeply before you start - Break down into individual tasks for planning &
ordering materials - Educate both code officials & neighbors
- Larsen trusses hard to make level over lap siding,& hard to find studs
- 3½” deck screws worked well for attaching trusses - 9” TimberlokTM screws worked well for attaching window
frames, which were built as a unit & attached as such - Next time, steel L brackets instead of trusses (save time)
70
www.greenbuildessexcounty.org (click on ‘Gloucester residence’)
www.thousandhomechallenge.org
www.powerofaction.com/der/
For More Information