GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001 W Neil Johnson 1 Gamma-ray...
-
Upload
alexandra-gray -
Category
Documents
-
view
217 -
download
2
Transcript of GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001 W Neil Johnson 1 Gamma-ray...
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 1
Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope
GLAST Large Area Telescope:GLAST Large Area Telescope:
Calorimeter (WBS 4.1.5)
W. Neil JohnsonNaval Research LabCalorimeter Subsystem Manager
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 2
Calorimeter Subsystem
Outline
Programmatic Status
Lehman Review Recommendation Status
Technical Progress
Assembly & Test
Resources
Issues / Concerns
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 3
Programmatic StatusProgrammatic Status
In France the CNES Scientific Program committee issued positive recommendation and re-confirmed the French participation in GLAST.
A CNES Preliminary Requirements Review will occur in October to authorize the technical approach and French organization. This review will secure the budget for the implementation phase.
Management activities have focused on creating CAL WBS, revised plans, schedules, and costs for the development and fabrication of the calorimeter
Interim Design Review held in Paris, June 11 – 13, focused on detailed review of the Swedish and French responsibilities, interfaces, work flow and schedules.
Financial problems in France for this FY have been resolved and, as a result, the PIN photodiode procurement (US) for EM diodes was released.
Significant efforts have been placed in improving or creating CAL documentation for PDR – required specifications, plans and procedures have been identified and responsible persons have been assigned.
Completed CAL Subsystem Peer Design Review on July 27.
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 4
Lehman Review Recommendation StatusLehman Review Recommendation Status
Sign and implement international agreements– Drafts exist of MoA among participating laboratories and of NASA-CNES
International LoA. – MoA has been updated by US and French participants; no apparent
action on LoA. Successful PRR should permit French signatures. Organize French efforts and commitment to roles and responsibilities
– Done. Documented in MoA and WBS. Develop bottoms up resource-loaded schedule
– Done. Delivered to PMCS on 7/20/01. Revisions continue. Update the cost estimate and assign adequate contingency
– Bottoms up costing completed. Contingency analysis on-going. Overall funding and profile are problems.
Resolve PIN diode glue problems– Resources have been applied. Test and selection program identified.
Backup solution identified. Tests are continuing. Define responsibilities for procurement, qualification and testing of
ASICs– Done. SLAC designs and tests prototypes. NRL does the rest.
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 5
Technical ProgressTechnical Progress
CsI Crystals– The first two crystal optical test benches have
been completed at NRL and have been shipped to Sweden.
– First metrology test bench has been completed in Sweden.
– First 24 crystals from Amcrys-H have been received and tested in Sweden.
• The crystals were generally as expected although several crystals were slightly out of specification. These out of spec conditions were generally either over sized or incorrect light tapering along the crystal.
PIN Photodiode– 1st photodiode delivery expected Aug 15th. – Flex cable design for connection of PIN to
readout electronics has been iterated with mechanical and electrical engineering.
13 CsI Crystals from Amcrys-H
BTEM PIN diode and flex cable
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 6
Technical Progress (2)Technical Progress (2)
Crystal Detector Elements (CDE)
– New baseline for CDE includes optical wrapping (VM2000) attached to CsI crystal rather than applied to structure walls.
– Mylar tape on corner bevels holds 4 VM2000 strips.
Mylar tape
VM 2000 film strip
Dual PIN diode
Flex cable
CsI Crystal
Glue
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 7
Technical Progress (3)Technical Progress (3)
PIN Photodiode – CsI Crystal Bonding– Studies of potential bonding material continue at IN2P3 and NRL.– IN2P3 contract with CETIM to model the bonding problem
• Rejects hard epoxies• Soft epoxy and silicone are OK.
– Bonding Plan• Test soft epoxy & silicone elastomer with primer• A vacuum gap is the backup solution.• Thermal (-30°C to +50°C) cycling in vacuum environment tests
between glass and CsI with surface preparation.• The type of bonding for the EM will be chosen after 12 thermal-
vac cycles. A set of photodiodes that are larger than CAL diode will be bonded on CsI and ultimately tested for 100 cycles.
• Aging tests ( thermal cycling and irradiation) are performed on these glues with particular attention to transparencies
• Bonding for FM will be reviewed after completion of test program and experience with EM fabrication.
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 8
Technical Progress (4)Technical Progress (4)
Pre Electronics Module (PEM)– Verification Model 2 (VM2)
tooling has been designed and is being fabricated
– Baseplate design has been modified to meet LAT Grid stiffness requirements.
– Preliminary thermal and structural analysis have been completed.
– VM2 will contain 12 CDE and 84 mass dummies
– Science performance evaluation before LAT PDR
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 9
Technical Progress (5)Technical Progress (5)
First prototype GCFE1 ASIC received at SLAC in June 01– Contains all functionality
• Analog: Multi-gain amplification, shaping, auto-range gain selection, trigger discriminators, five 7-bit DAC’s
• Digital: VHDL synthesized and auto place&routed digital circuits (~10,000 gates) for configuration/mode registers, write&read state-machine, data-acquisition state-machine & logic, etc.
– Digital circuits are fully functional, tested up to limit of test-box, 40 MHz, (f=20 MHz is nominal)
– Found capacitor-to-capacitor short of calibration-circuit to gain-selection circuit. Bug discovered in linear capacitor extract software
– Analog amplifier and shaper are functional after cut of trace on chip– Single range calibration, charge-amplifier with external gain select, shaping,
post-amplification, auto-ranging, acquisition sequence, rail-amplifiers, trigger discriminators are fully operational. Performance tests are in progress.
2nd Version GCFE2 received last week, has Single-Event Upset hardened registers incorporated
3rd version GCFE3 with short fixed to be submitted July 28.
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 10
Assembly & Test in EuropeAssembly & Test in Europe
CsI crystals delivered to Sweden at rate of 200 per month.– Starts early. Last crystals delivered ~ 5 months before
needed. PIN photodiodes delivered to France at rate of 600 per 5 weeks.
– Delivery rate not a problem for Hamamatsu. CDE Assembly and Test at rate of ~ 200 per month (~ 6 days per
crystal) PEM Assembly in France requires 7 weeks per module
– Assembly, Metrology
– Cosmic muons
– Environmental: Thermal vac & vibration (TBR)
– Final test (cosmic muons)
Total Processing Time ~ 9 weeks per module
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 11
Module Assembly and Test ScheduleModule Assembly and Test Schedule
Phase Module
EM QM, 1-2 3-6 7-16
PEM Acceptance 14 9 8 5
Elect Integration 25 14 10 9
Calibration 12 6 5 4
Environmental 28 17 11 11
Pre-ship Verification
10 7 6 6
Margin 5 5 8 8
Total per Module 94 58 48 43
The challenge – sustained receipt, assembly, test and delivery of a module every two weeks.
– One PEM arrives at NRL every two weeks. – Five Modules in process at once.– One Module ships to LAT Integration Site (SLAC) every two weeks.
• (but last Module arrives at SLAC five weeks before required date.)
• Duration of assembly and test phases (working days for each Module)
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 12
Assembly and Test ScheduleAssembly and Test Schedule
Module Planned Module
Delivery Date
LAT Schedule Integration
Date
Weeks delivery is
early
Qual Model (FM A) 13 May 03 15 Aug 03 13
Flight Spare (FM B) 03 Jun 03 15 Aug 03 10
Flight Model 1 29 Jul 03 03 Nov 03 14
Flight Model 2 19 Aug 03 03 Nov 03 11
Flight Model 3 27 Aug 03 02 Jan 04 18
Flight Model 4 10 Sep 03 02 Jan 04 16
Flight Model 5 24 Sep 03 15 Jan 04 17
Flight Model 6 08 Oct 03 15 Jan 04 14
Flight Model 7 15 Oct 03 29 Jan 04 15
Flight Model 8 29 Oct 03 29 Jan 04 13
Flight Model 9 12 Nov 03 12 Feb 04 13
Flight Model 10 26 Nov 03 12 Feb 04 11
Flight Model 11 10 Dec 03 26 Feb 04 11
Flight Model 12 24 Dec 03 26 Feb 04 9
Flight Model 13 07 Jan 04 10 Mar 04 9
Flight Model 14 21 Jan 04 10 Mar 04 7
Flight Model 15 04 Feb 04 24 Mar 04 7
Flight Model 16 18 Feb 04 24 Mar 04 5
Delivery for integration into LAT
– Instrument integration schedule specifies required Ready For Integration (RFI) dates.
– RFI rate: Two Modules every two weeks.
• Too much work in parallel, so we’ll start earlier and stretch deliveries.
Typical delivery rate: One Module every two weeks.
– Plan: FMs arrive at LAT Integration Site 5 to 18 weeks earlier than required.
• Some margin for slippage.
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 13
Resources - Mass EstimateResources - Mass Estimate
Component Mass in Kg
per ModuleComposite Structure 3.363Structure shell 7.090Dampers 0.320Fasteners 0.500Crystal Detector Element 79.132Printed Circuit Boards(AFEE) 1.690Miscellaneous 0.100
Total Mass of CAL Module (kg) 92.195CAL Allocation Per Module (kg) 93.250
Mass (kg)
SRR Est. (Adj.) 1482.1
ANSI/ AIAA Reserve Recom'd
101.8
Subsystem Reserve Allocation
9.9
Subsystem Budget Allocation
1492.0 (93.25 /module)
Mass Reserve Analysis
90% of reserve held at LAT level
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 14
Resources - Power EstimateResources - Power Estimate
Item Quantity Each Total
GCFE 48 8 384ADC Max145 (no sleep) 48 4 192Digital Controller ASIC 4 80 320DAC 1 6 6DAC Buffers 4 5 20References 2 5 10LV Biasing 48 1 24PIN Bias 1 1 1
TOTAL Power per AFEE (mW) 957TOTAL Power per Module (mW) 3,828Allocated Power per Module (mW) 5,688
Power (mW)
Power (Watts)
SRR Est. (Adj.) 87.0
ANSI/ AIAA Reserve Recom'd
12.0
Subsystem Reserve Allocation
4.0
Subsystem Budget Allocation
91.0
(5.69 / module)
Power Reserve Analysis
75% of reserve held at LAT level
Conditioned Power at 3.3 & 70 VFor each AFEE board (4 / Module)
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 15
Resources - Cost EstimateResources - Cost Estimate
4.1.5 CalorimeterFY99 $ FY00 FY01 FY02 FY03 FY04 FY05 FY06 Total
Total Labor 1,038,582 792,375 1,819,014 2,154,173 1,535,554 868,956 253,158 8,461,812Total Material 137,187 222,000 1,119,600 808,375 231,525 39,500 8,750 2,566,937Total Travel 25,000 44,500 157,350 240,100 139,500 133,900 32,400 772,750
0 0 0 0 0 0 0Grand Total FY99 $ 1,200,769$ 1,058,875$ 3,095,964$ 3,202,648$ 1,906,579$ 1,042,356$ 294,308$ 11,801,499$
Inflation Factor (from FY99) 4.10% 8.16% 12.38% 16.76% 21.31% 26.05% 31.00%
Grand Total RY $ 1,250,000$ 1,145,278$ 3,479,187$ 3,739,440$ 2,312,957$ 1,313,846$ 385,543$ 13,626,253$
4.1.D Science Analysis SoftwareFY99 $ FY00 FY01 FY02 FY03 FY04 FY05 FY06 Total
Total Labor - - 198,557 198,557 198,557 198,557 99,278 893,506
Total FY99 $ -$ -$ 198,557$ 198,557$ 198,557$ 198,557$ 99,278$ 893,506$
Inflation Factor (from FY99) 4.10% 8.16% 12.38% 16.76% 21.31% 26.05% 31.00%
Total RY $ -$ -$ 223,134$ 231,837$ 240,878$ 250,273$ 130,055$ 1,076,177$
4.1.5 & 4.1.D Total (Current Estimate)FY99 $ FY00 FY01 FY02 FY03 FY04 FY05 FY06 Total
Total FY99 $ 1,200,769$ 1,058,875$ 3,294,521$ 3,401,205$ 2,105,135$ 1,240,913$ 393,586$ 12,695,004$
Inflation Factor (from FY99) 4.10% 8.16% 12.38% 16.76% 21.31% 26.05% 31.00%
Total RY $ 1,250,000$ 1,145,278$ 3,702,321$ 3,971,277$ 2,553,836$ 1,564,119$ 515,598$ 14,702,429$
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 16
Cost Comparison w/ ProposalCost Comparison w/ Proposal4.1.5 & 4.1.D Total (Current Estimate)FY99 $ FY00 FY01 FY02 FY03 FY04 FY05 FY06 Total
Total FY99 $ 1,200,769$ 1,058,875$ 3,294,521$ 3,401,205$ 2,105,135$ 1,240,913$ 393,586$ 12,695,004$
Inflation Factor (from FY99) 4.10% 8.16% 12.38% 16.76% 21.31% 26.05% 31.00%
Total RY $ 1,250,000$ 1,145,278$ 3,702,321$ 3,971,277$ 2,553,836$ 1,564,119$ 515,598$ 14,702,429$
Proposal Costs - CalorimeterFY99 $ FY00 FY01 FY02 FY03 FY04 FY05 FY06 Total
Total Labor 1,038,513 922,847 1,719,538 2,406,522 1,285,468 450,791 - 7,823,679Total Material 137,187 132,603 1,174,387 401,732 104,757 26,562 1,977,228Total Travel 24,300 44,550 66,075 134,300 109,775 43,380 422,380
Grand Total FY99 $ 1,200,000$ 1,100,000$ 2,960,000$ 2,942,554$ 1,500,000$ 520,733$ -$ 10,223,287$
Inflation Factor (from FY99) 4.10% 8.16% 12.38% 16.76% 21.31% 26.05% 31.00%
Grand Total RY $ 1,249,200$ 1,189,759$ 3,326,393$ 3,435,752$ 1,819,718$ 656,362$ -$ 11,677,184$
(Current - Proposal) RY$ 800$ (44,481)$ 375,929$ 535,525$ 734,117$ 907,757$ 515,598$ 3,025,245$
Changes in Work Scope from Proposal to Current Estimate
FY99 $ FY00 FY01 FY02 FY03 FY04 FY05 FY06 Total
Analog ASIC Devel - moved from France - 106,581 117,462 215,000 - - - 439,043Increased Monitoring of French Program - - 91,275 105,800 - - - 197,075Increased Env Testing - - - 95,000 89,000 - - 184,000Additional Sys Engineering - - 72,000 72,000 160,000 80,000 40,000 424,000Additional I&T Support - - - - 150,000 275,000 - 425,000Program Stretch - - - - - 210,000 283,000 493,000Grand Total FY99 $ -$ 106,581$ 280,737$ 487,800$ 399,000$ 565,000$ 323,000$ 2,162,118$
Inflation Factor (from FY99) 4.10% 8.16% 12.38% 16.76% 21.31% 26.05% 31.00%
Grand Total RY $ -$ 115,278$ 315,487$ 569,560$ 484,045$ 712,159$ 423,130$ 2,619,659$
Cost Growth RY $ 800$ (159,759)$ 60,442$ (34,035)$ 250,072$ 195,598$ 92,468$ 405,586$
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 17
Issues / ConcernsIssues / Concerns
CAL project is working hard to make up for lost time. Additional personnel are being added in US and France to support engineering development.
Near term schedule to CDR will be a challenge. Critical near term milestones include
– Determination of the PIN diode bonding solution and verifying its ability to meet the performance and environmental requirements.
– Completion of VM2 prototype, demonstrating science performance (before PDR) as well as mechanical design verification (post PDR).
– Completion of GCFE analog ASIC performance testing and obtaining completely functional parts for EM fabrication.
– Completion of EM fabrication and test program prior to CDR. Revised CAL cost and schedule have just recently (7/20) been
submitted to SLAC. – CAL funding is insufficient and profile is not optimal. Resources lost in FY
’02 reappear too late (FY ’04) to be of much use. – More iterations are required – Environmental test plan needs more consideration.
• Cost issues• Over-testing issues
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 18
Backup MaterialBackup Material
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 19
Test MatrixTest Matrix
HARDWARE MECHANICAL ELECTRICAL THERMAL OTHER
LEV
EL
COMPONENT (ITEM)
QU
AN
TIT
Y
TY
PE
SU
PP
LIE
R
ST
AT
IC L
OA
D
SIN
E B
UR
ST
SIN
E S
WE
EP
RA
ND
OM
VIB
AC
OU
ST
IC
PR
ES
SU
RE
PR
OF
ILE
MA
SS
PR
OP
ER
TIE
S
INT
ER
FA
CE
VE
RIF
EM
C/E
MI
ES
D C
OM
PA
TA
BIL
ITY
(G
ND
ING
)
MA
GN
ET
ICS
FU
NC
TIO
NA
L
TH
ER
MA
L V
AC
UU
M
TH
ER
MA
L B
AL
AN
CE
TH
ER
MA
L C
YC
LE
HU
MID
ITY
RA
DIA
TIO
N
BA
KE
OU
T
BE
AM
TE
ST
– E
M S
HO
WE
RS
BE
AM
TE
ST
- H
AD
RO
NS
BE
AM
TE
ST
– H
EA
VY
IO
NS
COMMENTS
C VM2 CsI Det Elements (CDE) 12 Q F A A M T A A A T TQ TQ T
C VM2 PreElect Modules (PEM) 1 Q F T TQ TQ TQ TQ M T T TQ TQ T
C VM Electronics Prototype 1 Q N T
EM CsI Det Elements (CDE) Q F T TQ TQ TQ M T T TQ TQ M TQ TQ applies to sample batches
C EM PreElect Modules (PEM) 1 Q F M TQ TQ TQ TQ M T T TQ TQ M A
C EM Front End Elect (AFEE) 4 Q N A A A A M T A A A T TQ TQ M A A
S EM CAL Module 1 Q N TQ TQ TQ M T T T T T TQ TQ M A A T T T
QM CsI Det Elements (CDE) Q F T TQ TQ TQ M T T TQ TQ M TQ TQ applies to sample batches
C QM PreElect Modules (PEM) 1 Q F M TQ TQ TQ TQ M T T TQ TQ M A
C QM Front End Elect (AFEE) 4 Q N A A A A M T A A A T TQ TQ M A
S QM CAL Module 1 Q N TQ TQ TQ M T T T T T TQ TQ M A A
FM CsI Det Elements (CDE) F F TQ TQ TQ M T T TQ M TQ TQ applies to non-flight samples
C FM PreElect Modules (PEM) F F M TA TA TA TA M T T TA M A
C FM Front End Elect (AFEE) F N QS QS QS QS M T QS QS QS T QS M A
S FM CAL Module 17 F N QS QS TA M T QS QS QS T TA M A QS
Calorimeter Verification plan & Environmental Specification, TBD System Level Electrical Requirements, TBD Contamination Control Plan, TBD Grounding checked for each component prior to S/C integration
LEVEL OF ASSEMBLY: S = Subsystem C = Component SUPPLIER: F = France N = NRL
UNIT TYPE: PF = ProtoFlight F = Flight S = Spare Q = Qual. unit
VERIFICATION METHOD: T = Test QS = Qual by Similarity A = Analysis TQ = Test, Qual level M = Measurement TA = Test, Acceptance level I = Inspection
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 20
Thermal Simulation of Bonding to CsIThermal Simulation of Bonding to CsI
• Thermal (-30°,20°) simulation of constraints on different glues curing at 20°C by CETIMThermal (-30°,20°) simulation of constraints on different glues curing at 20°C by CETIM
Masterbond EP29 Hard epoxy
Masterbond EP37 3FLF Soft epoxy
Dow corning 93500 with primer
E(tensile modulus)
2600 MPa 490 MPa
?
Tensile strength 45 MPa 28 MPa
7 Mpa
Elastic limit 30 MPa 15-20 MPa Elongation at break
180%
? Elongation at break 140%
Max Von Mises constraints inside the glue (#thickness)
1 mm : 50 MPa 2 mm : 37 MPa
1 mm :13 MPa
1 mm : 0.31 MPa
Hard epoxy does not fit
EP 37 stands the dilatation safety margin : 1.2
93500 stands the dilatation safety margin > 7
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 21
Development ProgramDevelopment Program
PEM VM2 Prototype
– Mechanical Model w/ 12 CDE and 84 dummy crystals
– CDE Performance testing before LAT PDR
– Environmental testing completed by Dec ‘01 Front End Electronics
– GCFE Test Board – Radiation Testing - Nov ‘01
– VM Board, GCFE + GCRC FPGA
– Functional testing with CDE
– Radiation testing – Jan ‘02 Engineering Model (EM)
– Form and function of flight units, commercial grade parts where required, fully populated PEM
– Functional testing
– Environmental testing
– Beam tests
– Delivered to SLAC for T&DF, software development
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 22
VM2 & EM DevelopmentVM2 & EM DevelopmentID Task Name Duration Start Finish
4 VM Plan 41.8 wks Thu 3/1/01 Tue 12/18/01
5 Xtal (15+1) delivery to F 0 days Fri 6/29/01 Fri 6/29/01
6 Xtal metrology 5 days Fri 6/29/01 Thu 7/5/01
7 Light yield test 10 days Fri 7/6/01 Thu 7/19/01
8 NRL PIN delivery to F 0 days Fri 8/24/01 Fri 8/24/01
9 PIN acceptance 2 days Fri 8/24/01 Mon 8/27/01
10 French PINs delivery 0 days Sun 9/2/01 Sun 9/2/01
11 F PIN acceptance 3 days Mon 9/3/01 Wed 9/5/01
12 Preliminary Bonding Procedure available 0 days Tue 8/14/01 Tue 8/14/01
13 CDE assembly 10 days Thu 9/6/01 Wed 9/19/01
14 CDE Test 8 days Thu 9/20/01 Mon 10/1/01
15 VM2 structure development 141 days Thu 3/1/01 Thu 9/13/01
16 VM2 structure available 0 days Fri 9/14/01 Fri 9/14/01
17 VM2 PEM Integration and Light Yield Test - ISSUE 6 days Tue 10/2/01 Tue 10/9/01
18 VM AFEE 162 days Thu 3/1/01 Fri 10/12/01
19 PDR prep / margin 14 days Wed 10/10/01 Mon 10/29/01
20 LAT IPDR 0 days Mon 10/29/01 Mon 10/29/01
21 VM2 PEM Env Test - ISSUE 50 days Wed 10/10/01 Tue 12/18/01
22 EM plan 52.4 wks Tue 8/14/01 Wed 8/14/02
23 EM PEM 29.4 wks Tue 8/14/01 Wed 3/6/02
24 EM Structure available 0 days Fri 12/21/01 Fri 12/21/01
25 PINs diodes available 0 days Tue 10/9/01 Tue 10/9/01
26 Bonding Procedure finalized ?? Same as preliminary0 days Tue 8/14/01 Tue 8/14/01
27 Xtal delivery to F (>96 logs) date? 5 wks Mon 9/17/01 Fri 10/19/01
28 CDE assembly & test 54 days Mon 10/22/01 Thu 1/3/02
29 Clean room ready 1 day Mon 12/31/01 Mon 12/31/01
30 EM PEM assembly (logs insert) 16 days Fri 1/4/02 Fri 1/25/02
31 EM PEM assembly (closeouts) 1 day Mon 1/28/02 Mon 1/28/02
32 EM PEM test (muon, light yield (Poly) why this long? 54-->2222 days Tue 1/29/02 Wed 2/27/02
33 Transportation F-NRL 5 days Thu 2/28/02 Wed 3/6/02
34 EM A&T 43.6 wks Mon 10/15/01 Wed 8/14/02
35 EM AFEE development 100 days Mon 10/15/01 Fri 3/1/02
36 EM AFEE available (-digital ASIC?) 0 days Mon 3/4/02 Mon 3/4/02
37 EM PEM available @ NRL 0 days Fri 3/15/02 Fri 3/15/02
38 PEM acceptance 10 days Mon 3/18/02 Fri 3/29/02
39 EM assembly 30 days Mon 4/1/02 Fri 5/10/02
40 EM test 10 days Mon 5/13/02 Fri 5/24/02
41 EM Env Test 28 days Mon 5/27/02 Wed 7/3/02
42 Beam Test (hadrons) 30 days Thu 7/4/02 Wed 8/14/02
43 CAL CDR 0 days Wed 6/5/02 Wed 6/5/02
44 I-CDR 0 wks Mon 8/5/02 Mon 8/5/02
6/29
8/24
9/2
8/14
9/14
10/29
12/21
10/9
8/14
3/4
3/15
6/5
8/5
J F M A M J J A S O N D J F M A M J J A S O N D2001 2002
GLAST LAT Project DOE/NASA Review of the GLAST/LAT Project, Aug. 14, 2001
W Neil Johnson 23
Current Estimate vs FundingCurrent Estimate vs Funding
4.1.5 & 4.1.D Total (Current Estimate)FY00 FY01 FY02 FY03 FY04 FY05 FY06 Total
Total RY $ 1,250,000$ 1,145,278$ 3,702,321$ 3,971,277$ 2,553,836$ 1,564,119$ 515,598$ 14,702,429$
Funding Profile
Funding - NASA (RY $) 1,250,000 1,030,000 3,326,393 3,435,752 1,819,718 656,362 - 11,518,226Funding Delta 3/24/01 - - (666,393) - 719,385 - - 52,992Funding - SLAC (RY $) - 115,000 99,000 - - - - 214,000Total Funding (RY $) 1,250,000$ 1,145,000$ 2,759,000$ 3,435,752$ 2,539,104$ 656,362$ -$ 11,785,218$
Funding Short Fall RY $ (Current Est - Funding) 0$ 278$ 943,321$ 535,525$ 14,732$ 907,757$ 515,598$ 2,917,211$