ggg Station Units18 1994 ...@~>hrg O ggg Susquehanna Steam Electric Station Units18 2 1994...
Transcript of ggg Station Units18 1994 ...@~>hrg O ggg Susquehanna Steam Electric Station Units18 2 1994...
@~>hrg
Oggg
Susquehanna Steam Electric StationUnits18 2
1994ANNUALENVIRONMENTALOPERA TING REPORT
(NONRADIOLOGICAL)
Facility Operating License Nos. NPF-14 & NPF-22Docket Nos. 50-387 8 50-388
prepared byEnvironmental ServicesOperations Technology
Pennsylvania Power & Light CompanyAllentown, PA
April 1995
(9505030243 950428PDR ADOCK 05000387R PDR
4k lo Printed on Recycled PaperTgg
SUSQUEHANNA STEAM ELECTRIC STATION
ANNUALENVIRONMENTALOPERA TING REPORT(NONRADIOLOGICAL)
1994
Prepared by:
Sen'erome S. Fieldsnvironmental Scientist - Nuclear
Date: /~ /D
Reviewed by:James . Doxsey
Supervisor-Effluents Manag ent
'eviewed
by:Kenneth E. Shank
Supervisor-Environme tal ServicesNucl a
Date:
.Approved by:John M; lick
SupeIvisor-Operations Technology
Date
I
.I
lC
.l
lt
I
FOREWORD .
The Susquehanna Steam Electric Station (Susquehanna SES) consists of two boilingwater reactors, each with a net electrical generating capacity of 1,100 megawatts. The1,500 acre site is located in Salem Township, Luzerne County, Pennsylvaniaapproximately five miles northeast of Berwick, Pennsylvania. Under terms of,anagreement finalized in January 1978, 90% of the Susquehanna SES is owned by thePennsylvania Power and Light Company (Licensee) and 10% by the Allegheny ElectricCooperative, Inc,
The 1994 Annual Environmental Operating Report (Nonradiological) for Units 1 and 2describes results of programs necessary to meet requirements of Section 2F of theOperating License, Protection of the Environment, and Appendix B, EnvironmentalProtection Plan, as well as commitments in the Final Environmental Statement relatedto operation (NUREG-0564), June 1981. This report discusses environmentalcommitments and impacts from January 1, 1994, through December 31, 1994.
l
IV
I
J'
l~
~
~
~
~
ll
I
I
. TABLE OF CONTENTS
SECTION TITLE PAGE'NO.
1.0
2.0I
Foreword
Table of Contents
OBJECTIVES
ENVIRONMENTALISSUES
2.1 Aquatic Issues2.2 Terrestrial Issues
2.2.1 Studies Previously Completed2.2.2 Maintenance of Transmission Line Corridors
2-1
2-1„2-3
2-32-4 "
3O
4.0
2.3 Cultural Resources Issues
CONSISTENCY REQUIREMENTS
3.1 Plant Design and Operation3.2 Reporting Related to NPDES Permits and State
Certifications3.3 Changes Required for'Compliance with Other
Environmental Regulations
ENVIRONMENTALCONDITIONS
4.1 Unusual or Important Environmental Events4.2 Environmental Monitoring
4.2.1 Maintenance of Transmission Line Corridors
'3-1
3-1
3-2
3-2
4-1
4-14-1
4-1
4.2.1.1 Herbicides Used4.2;1.2 Records4.2.1.3 Types of Maintenance Reported
= 4.2.2 Aquatic Programs
4-14-24-3
4Q
TITLE PAGE NO.
ENVIRONMENTALPROTECTION PLAN REPORTINGREQUIREMENTS
5.1 Review and Audit5.2 Records Retention5.3 Changes in Environmental Protection Plan5.4 Plant Reporting Requirements
5.4.1 Routine Reports5.4.2 Nonroutine Reports
5-1
5-25-2
EXHIBIT
American Shad Impingement Letter
TABLES
Maintenance of Transmission Line Corridors, SelectedHerbicide Application,
Maintenance of Transmission Line Corridors,
'I
FIGURE
Auditing Organization Chart
OBJECTIVES,
The Licensee submitted an Environmental Report-Operating License Stage forthe Susquehanna SES to the U.S. Nuclear Regulatory Commission (NRC) inMay 1978. This report reviewed the results of the preoperational impacts ofconstruction and described the'preoperational and proposed operational
'nvironmental monitorin'g programs: The NRC and other agencies reviewed thisreport and made recommendations for operational environmental monitoring
, programs which were listed in the Final Environmental Statement (FES) relatedto the operation of the Susquehanna SES, Unit 1 and 2, NUREG-0564,June 1981. In addition, the Licensee developed procedures and guidelines toensure that operation of the Susquehanna SES does not adversely affect theenvironment in the vicinityof the station.
Procedures were developed to allocate responsibilities and interfaces necessaryto monitor environmental impacts.'hese include coordination of NRCrequirements and consistency with other federal, state, and local requirementsfor environmental protection. To keep the NRC informed of other agencyactivities, copies of environmental correspondence are routinely provided. In
addition, this 1994 Annual Environmental Operating Report (Nonradiological)provides a summary of both environmental programs and procedures asrequired in the FES and Appendix B - Environmental Protection Plans (EPP) toOperating Licenses,'o. NPF-14 and No. NPF-22. The 1994 report is the 13thAnnual Environmental Operating Report (Nonradiological) submitted to meetEPP requirements.
1-1
t. I
'1 II
I
: I
2.0 ENVIRONMENTALISSUES
2.1 A~tiI
The aquatic monitoring program for operation of the Susquehanna SES isdivided into two phases. Phase 1 includes effluent monitoring required by .
a National Pollutant Discharge Elimination System (NPDES) permitissued by the Pennsylvania Department of Environmental Resources(PaDER). Monthly discharge monitoring reports are submitted to thePaDER as part of the permitting requirements. The station operationalNPDES permit No. PA-0047325 was reissued on January 22, 1990, andwas to expire on January 21', 1995, however, it was administrativelyextended by the PaDER. Phase 2 of the aquatic monitoring programdeals with programs listed in the FES involving environmental monitoring.
The PaDER,in Phase 1 is responsible for regulating the water qualitypermit for the Susquehanna SES. The NPDES permit deals withdischarge parameters for the Susquehanna SES sewage treatment plant,cooling tower blowdown, and miscellaneous low volume wastedischarges. The cooling tower blowdown also includes in-plant process
— streams which discharge to the Susquehanna River. Various low volume,waste sumps discharge to the storm sewers which flow into Lake Took-a-while, and eventually into the Susquehanna River.
The parameters monitored in the sewage treatment plant effluent limitsare as follows:
FlowpHTotal Suspended Solids (TSS)Carbonaceous Biochemical Oxygen Demand (CBOD-5)Fecal Coliforms
In-plant process effluents combine with the cooling tower blowdownbefore being released to the Susquehanna River. These process.effluents are monitored for flow, TSS, and oil and grease. Parametersmonitored in the combined cooling tower blowdown to the SusquehannaRiver are:
FlowpHChromiumZinc
2-1
The parameters monitored in the various low volume waste sumps anddrains that discharge to storm sewers leading to Lake'Took-a-while are:
FlowpHTSSOil and Grease
I
The Licensee has replaced gaseous chlorine at the Susquehanna SESwith Betz Clam-Trol CT-1 as a microbiological control treatment.Approval of the use of this product is included in the station's NPDESpermit. Also, zinc and sulfuric acid are no longer used for treatment ofcirculating water.
Phase 2 of aquatic monitoring progiams, identified in the FES andAppendix B of the Operating License for the Susquehanna SES, includedmonitoring algae and benthic macroinvertebrates both above the intakeand below the discharge to the Susquehanna River. Requirements forthese activities 'were completed in 1988.
The Susquehanna Anadromous Fish Committee administered the captureof a record high 32,330 American shad in the two fish lifts below theConowingo Dam on the Susquehanna River from April22 th'roughJune 12, 1994. Of these, 28,681 shad were transported and stockedupstream of all major dams (Ref. 2.1-1). After these stockings, largenumbers of adult shad were observed in the Juniata,River, but none wererecorded near Sunbury, Pennsylvania, or farther up the Susquehanna
- River. In addition, inflation of the Sunbury fabridam in mid-May wouldhave blocked shad migration beyond Sunbury to the Susquehanna SES
- which is 45 miles farther upriver. Consequently, Mr. Richard St. Pierre,,Susquehanna River Coordinator for the U.S. Fish and WildlifeService,canceled autumn monitoring for impinged juvenile American shad at the-
intake of the Susquehanna SES (Exhibit 1). Monitoring will resume ifthere is any likelihood that substantial numbers of juveniles will out-
" . migrate past the intake in autumn'1995. '.The 1993 agreement to return American shad and other migratory fish,including the American eel, to the Susquehanna River. by the year 2000stipulates the following:
1. Pennsylvania Power 8 Light Company will construct two lifts at theHoltwood Hydroelectric Dam. These lifts are scheduled for completion
22
'9
by 1996 in time for the spring 1997, migration of American shad.
2. Baltimore Gas and Electric Company and Pennsylvania Power & LightCompany will complete one liftat Safe Harbor during construction ofthe Holtwood lifts.
3. Metropolitan Edison willcomplete one liftat the York HavenHydroelectric Station by 1999 for service by 2000.
4
The lifts at Holtwood and Safe Harbor will reopen shad and eel migrationto 35 miles of the Susquehanna River within the next five years. The YorkHaven passage will reopen an additional 200 miles of river for thesefishes three years later. These projects are all on schedule.
The biofouling mollusk monitoring program continued at the Susquehanna9991 1994. Th hh*h 1 (9 1 ~ll )h 9
found repeatedly in samples near Johnson City, New York, about 150miles upriver, and Asiatic clams (corbicula ~fluminea have been confirmed40 miles downriver at Northumberland, Pennsylvania, neither of thesespecies have yet been found in the vicinityof the Susquehanna SES.
The monitoring program currently involves a biweekly schedule ofwater'nd
artificial and natural substrate sampling in the river in the vicinityofthe Susquehanna SES River Intake Building from May through November.Artificialsubstrates are also maintained in side-stream samplers locatedin the Intake Building and on the plant site. In addition, scuba diversperformed inspections of natural substrates in the river on 10 dates inJune through October, and in the Emergency Service Water Spray Pondon August 23 and 24, 1994.
9 '4
2.2 Terrestrial Issues
2.2.1 Studies Previousl Com leted
Terrestrial environmental studies completed prior to 1989 included .
cooling tower bird impaction and sound level surveys.
2-3
2.2.2 Maintenance of Transmission Line Corridors
During 1994, trees and brush in the transmission line corridorswere maintained with herbicides and by manual clearing. Theterrestrial monitoring program for the Susquehanna SES.transmission lines was initiated in response to commitments inSection 5.3.5 of the FES. Three major transmission lines areassociated with the Susquehanna SES: 1) Stanton-SusquehannaNo. 2-500 kV line, 2) Sunbury-Susquehanna No.-2-500 kV line and3) Susquehanna-Wescosville 500 kV line (former Susquehanna-Siegfried line). These lines may be operated at either 230 kV or500 kV. The maintenance program for transmission line corridorsis discussed in detail in subsection 4.2.1 of this report. ~
The schedule for conducting periodic erosion control inspections ofthese lines and access roads is based on the age of the line.Susquehanna's tr'ansmission lines are inspected twice per year byfoot patrols and three times per year by helicopter patrols. Acomprehensive overhead inspection is performed once every five'years.
'I
In 1994, the three transmission lines and corridors were inspectedby helicopter and foot patrols. Areas of minor soil erosion alongthese corridors identified during these inspections have since beenrepaired.
2.3 'ultural Resources Issues \
I I
Environmental Pro(ection Plan actions required to satisfy Title'36, Code of,Federal Regulations Part 800, relating to archeological sites, werecompleted in 1987. The Advisory,Council on Historic Preservation(ACHP), in accordance with 36 CFR 800.6 (a)(1),'approved the NRC'sdetermination of "no adverse effect" for archeological sites SES-3, SES-6,SES-B, and SES-11 located on the Licensee's property (NRC letter dated'October 28, 1987, to ACHP).
As part of the determination of effect process, the Licensee'committed'toand is taking appropriate measures to mitigate impacts from plantmaintenance and operation to sites SES-3, SES-6, SES-8 and SES-11.=
There was no impact to these sites from plant maintenance and operation.in 1994.
2-4
REFERENCES
2.1-1 'estoration'of American Shad to the Susquehanna River, Annual ProgressReport-1994, Susquehanna River Anadromous Fish Restoration Committee,Februarjj 1995.
2-5
N
. I
i
1
I
III.
I
3.0 CONSISTENCY REQUIREMENTS
3.1 Plant Desi n and 0 eration
In accordance with the Environmental Protection Plan (EPP), theLicensee shall prepare and record an environmental evaluation ofproposed changes in plant design, operation, or performance of any testor experiment which may significantly affect the environment. Beforeinitiating such activities, the Licensee shall provide a written evaluationand obtain prior approval from the Director, Officof Nuclear ReactorRegulation. Criteria for the need to perform an environmental evaluationinclude: (1) a significant increase in any adverse environmental
impact'reviouslyevaluated by the NRC or Atomic Safety and Licensing Board,
(2) a significant change in effluent or power level, or (3) a matter notpreviously evaluated which may have a significant adverse enyironmehtal,impact.
The EPP requires that ifan activity meets any of the criteria to perform anenvironmental evaluation, the NRC willbe notified. Ifthe change, test, orexperiment does not meet any of these criteria, the Licensee willdocument the evaluation and allow the activity to occur.
During operation of the Susquehanna SES in 1994, there were threeproposed activities which the Licensee reviewed as part of theunreviewed environmental question program. None of these threeactivities were determined to be an unreviewed environmental question.These were:
An environmental evaluation of the discharge of 450,000 gallons ofwater from the Clarified Water Tank to the storm drains wasconducted. Since the free available chlorine level in the water was<0.05 mg/I, it was determined that any chlorine in the water shouldbe dissipated in the storm drains prior to reaching thesedimentation or recreation ponds.
An evaluation for removal and/or cutting trees around the site's300-foot meteorological tower was conducted. A small grove oftrees approximately 25 to 30 feet high were thought to beinterfering with instruments at the 30-foot level. To minimizeerosion, the trees were to be cut leaving the stumps. Also, thetrunk and branches were to be chipped for mulch. This activity wasconducted in March 1995.
3-1
3. Discharge of Condensate Storage Tank. berm rain water wasevaluated. Options included 1) discharge to the storm drains, '8nd,
-2) collection by tanker and discharge into the Cooling Tower Basinand eventually to the river via cooling tower blowdown. OptionTwo was selected and the water was analyzed for radioactivitybefore being discharged.
3.2 Re ortin Related to NPDES Permits and State Certifications
All reports and information required by the NPDES Permit were submittedto both the NRC,and PaDER. Pennsylvania is a NPDES PermittingAgreement State with the U.S. Environmental Protection Agency,therefore, state certification pursuant to Section 401 of the Clean WaterAct is not required.
Y
, 3.3 Chan es Re uired for Com liance with Other Environmental Re ulations1
During 1994, a renewal application was submitted to the PaDER for .,
NPDES permit no. 0047325. A permit-is expected in 1995.
3-2
4.0 ENVIRONMENTALCONDITIONS
4.1 Unusual or Im ortant Environmental Events
During 1994, three operating occurrences were reviewed as part of thepotentially significant environmental event evaluation.
These events were as follows
1. There was a discharge of halon from the Security Control Ce'nter fireprotection system. Approximately 200 lbs. of this ozone-depletingchemical was discharged into the atmosphere. This discharge wasnot reportable under the Clean AirAct, Superfund, or CommunityRight-to-Know regulations.
f2. An automatic pressure relief valve discharged about 400 lbs. of R-12,
a chlorofluorocarbon, from the Turbine Building Chiller into theatmosphere. The discharge was below regulatory reportingrequirements and, like the halon release, was not considered to besignificant.
3. Approximately 520 lbs. of 50% ethylene glycol solution was spilled intoa bermed area. The solution then leaked through a joint into thesurrounding soil. Since this was a reportable spill, the NationalResponse Center, PaDER, Luzerne County Emergency ManagementAgency, and the U.S. Nuclear Regulatory Agency, was contacted.The area affected was approximately 45 square feet. Even thoughthis event was reportable, it was of negligible environmentalsignificance. Ethylene glycol is used as a commercial de-icing agentfor the road.
The joints of the bermed areas have been refurbished and re-caulked.
4.2 Environmental Monitorin
4.2.1 Maintenance of Transmission Line Corridors
4.2.1:1 Herbicides Used
All herbicides utilized to control undesirable vegetationwithin the Susquehanna SES transmission line corridorsare approved for use by the U. S. EnvironmentalProtection Agency. In addition, all major manufacturersor formulators have had these products registered for
4-1
distribution by the Commonwealth of Pennsylvania underthe authority of the Pennsylvania Pesticide Control'Act of1973:
The following herbicides are specified for use in the'Licensee's programs and are applied according to theinstructions on the label.
Krenite UT
Tordon 101
Pathwa
Garlon 3A
Access
Garlon 4
Accord
Escort
.7;,':;,"'..".", „: 4%3„'A' ',."',;j'!';.'.:".lm"",.',
<',.6'~-,'K4%5ln redierit's~:4:::::4;'-.g><
Fosamine Ammonium
2, 4-D, Picloram
2, 4-D, Picloram
Triclo rTriclo r, Picloram
Triclo rGl hos ate
Metsulfuron Meth '
352-395
464-306
62719-31
62719-37
464-576
464-554524-326-AA
352-439
I
4.2:1.2'dditional
herbicides may be needed ifthe level ofcontrol (i.e., new/different species, sudden increases inresistance to established chemicals) changes.
Records
Records of herbicide use are maintained for a period ofat least five years in appropriate Region Offices of theLicensee. These records include the following:.
2.
Copies of labels of specified herbicides whichdesignate commercial names, active ingredients,rates of application, warnings, and storage andhandling requirements
Concentrations of active ingredient formulationsdiluted for field use
3. Diluting substances (carriers)~ 8.
4. Rates of application
5. Methods of application
6. Locations and dates of application.
4.2.1.3. T es of Maintenance Re orted
" A. Selective Herbicide Applications
ln 1994, herbicides were applied on the Sunbury-.Susquehanna No. 2 and the Susquehanna-Wescosville lines. Herbicides used, their active
. ingredient, acid equivalent (where applicable),amount of concentrate in a designated carrier, driftretardant, and wetting agents are summarized inTable 4.2-1.
Application data for this line, are presented bynumber of acres on which herbicides were applied,total amount of solution used, rate of application ingallons or ounces per acre, total amount ofconcentrate used, average, gallons of concentrateapplied per acre, total pounds of acid equivalent(where applicable), and average pounds per acreapplied. Dates and locations by grid number. of allapplications are listed with the title of theresponsible Region Manager, the phone number,and the mailing address. J
'. Vegetation Maintenance'by Manual Methodsl
Maintenance of Transmission Line Corridors,Table 4.2-'2, summarizes vegetation maintenanceactivities other than the utilization of herbicides.The manual activity used in 1994 was SelectiveReclearing (Selective Reclearing - cutting .
incompatible vegetation where herbicideapplications are restricted).
4-3
h
4.2.2 A uaticPro rams/
The aquatic monitoring requirements, identified in the FES andAppendix B of the operating license for the Susquehanna SES,have been completed and confirm that effects on aquatic biota andwater quality due to plant operation. were no greater than predicted.
4-4
TABLE 4.2-1
SUSQUEHANNA SESMaintenance ofTrarismission Line Cooridors
Selective Herbicide A lication
Sheet 1 of 4
1994Year
Herbicides.
'Sunbu -Sus uehanna ¹2Line Names
Additives
Sus 'uehannaRe ion
Carrier
Alt. CommercialNo. Name5 Garlon 3A
Escort
4 Accord
Active~ln redient
TriclopyrMetsulfuron-MethylGlyphosate-
Acid~Euiv.
3¹/Gal.N/A
3¹/Gal.
Spec. Amt.Per 100 Gal.
Solution3 Qts.1 Oz.
5 Qts.
CommercialName
Cleancut
A'quatic-Surfactant
Spec. Amt.Per 100 Gal
Solution1Qt,
2 Qt.
NameWater
Water
Spec. AmtPer 100 Gal
Solution99 Gal.
98-1/4 Gal,
AltNo.5
No. ofAcres270.10
151.714
TotalGallonsSolution
15,690
9,709
ApplicationRate
Gal. A58.1
64.0
A lication DataTotal
Gallons/oz.Concentrate
Garlon 117.675Escort 156.9 oz.Accord 121.365 Gal.
~Rate Ac.44 Gal./Ac.58 oz./Ac.799 Gal./Ac
Total PoundsAcid
~Euivalent353.025N/A
364.087
PoundsPer
Acre1.302N/'A2.39
AltNo. A lication Date Location b Grid No.
54
From6 2 947194
To9 14 94915 94
From.44109N3379940843N31 802
To25824N24146=26041N23926
Distribution ForesterTitle
71 368-5219- Phone
P.O. Box 158 Montoursville PA 17754Address
l
l
,1
S ,II:l
I1
l
.~- tRR Rf
TABLE 4.2-1SUSQUEHANNA SES
Maintenance ofTransmission Line CooridorsSelective Herbicide A lication
Sheet 2 of 4
1994Year
Herbicides
Sus uehanna-Wescosville 500 KV-Line Names
Additives
S~hRe ion
Caner
Alt.No.5
Commercial- Name
Garlon 3AEscort
Active Acid~In redient ~Euiv.
Triclopyr 3¹/Gal.MetsulfuronMethyl
Spec: AmtPer 100 Gal.
Solution3 Qts.1 oz.
Spec. AmtCommercial Per 100 Gal
Name ~ SolutionClean Cut ' Qt
NameWater
Spec. AmtPer 100 Gal
Solution99 Gal.
AltNo.5--
No. of, Acres28.716
'otalGallonsSolution
1,725
ApplicationRate
Gal. A60.07
A lication DataTotal
Gallons/Oz.Concentrate
Garlon 12.9375 Gal/AcEscort 17.25 Oz./Ac
~Rate Ac.450/Gal/Ac
.60 oz./Ac
, Total Pounds PoundsAcid Per
Eguivalent . - Acre38.812 - .- 1.35N/A
AltNo. A lication Date Location b Grid No.From
6 6 94To
6794From
441 20N33799To
44657N33205
Distribution ForesterTitle
717-368-5219Phone
P.O. Box158 Montoursville PA-17754Address
'I
I
I't lI~
~
~
lt
l
TABLE 4.2-1SUSQUEHANNA SES
Maintenance ofTransmission Line CooridorsSelective Herbicide A lication
Sheet 3 ot 4
1994Year
Herbicides
Sus uehanna-Wescosville 500 KVLine Names
Additives
NortheastRe ion
Carrier
Alt,No.4
CommercialName
. Accord
Active~ln redientGlyphosate
Acid~Huiv..3¹/Gal.
Spec. AmtPer 100 Gal.
Solution5 Qts.
Spec. AmtCommercial Per 100 Gal
Name SolutionAquatic ~ 2Qt.SurfactantLo Drift 4 oz.
NameWater
Spec. Amt .
Per 100 GalSolution.
98-1/4 Gal.
Alt.No..4
No. ofAcres.1185
TotalGallonsSolution
90
ApplicationRate
Gal. A48.65
A lication DataTotal
GallonsConcentrate
1.125Rate Ac
.61
Total PoundsAcid
E~uivslent3.375
PoundsPer
Acre1.82
AltNo. A lication Date Location b Grid No.
44
Fr'om
8 3 948 2 94
To8 3 948 2 94
From53931 N3189545335 N33 610
To54064 N3182945392N33644
Distribution ForesterTitle
717-831-6238Phone
1190 E. Mountain Blvd. Wilkes-B rre PA 18702Address,
P II
J
t
Ii
tI'l
TABLE 4-.2-1
SUSQUEHANNA SESMaintenance ofTransmission Line Cooridors
Selective Herbicide A lication
Sheet 4 of 4
1994Year
Herbicides
Sus uehanna-Wescosville 500 KVLine Names
Additives
~161 6Re ion
Carrier
Alt CommercialNo. Name
5. Garlon 3AEscort
Active~In radiant
TriclopyrMetsulfuronMethyl
Acid~Euiv.
3¹/Gal.N/A
Spec. AmtPer 100 Gal.
Solution3 Qts.1 oz.
CommercialName
ArborChemCleancut
Spec. AmtPer 100 Gal
Solution1 Qt.
NameWater
Spec. AmtPer 100 Gal
Solution99 Gal.
Alt'o.
5
No. ofAcres78.71
TotalGallonsSolution
1550
ApplicationRate
Gal. A19.69
A lication DataTotal
Gallons/oz.Concentrate
11.63 Gal.15.50 oz.
~Rate Ac.15 Gal/Ac.20 Oz./Ac
'otal PoundsAcid
~Euivalent- 34.89
N/A
PoundsPer
Acre.44
N/A
AltNo. A lication Date Location b Grid No.From6 2 946 3 946 6 946794
To From~61666 M135II~61193 353921
61300 S5750861888 S51091
To61168 S5399261336 S5358261394 S53170
To Sub
Distribution ForesterTitle
610-774-3258Phone
P.O. Box 3500 Allentown PAAddress
Il
1
!"
l
II
I l
1
TABLE 4.2-2SUSQUEHANNA SES
Maintenance OfTransmission Line Cooridors
Sheet 1 of 3
1994Year
Selective Reclearin
Stanton-Su's uehanna ¹2 230 KVLine Names
Side To Trimmin
NortheastRe ion
'DatesFro'm To
6/1/94 6/2/946/3/94 6/3/946/6/94 6/7/948/10/94 8/10/948/11/94 - 8/12/948/15/94 8/16/94
Grid LocationFrom To
52675N44324 52641N4428052302N43994 52335N4391252451N44133 52302N4409449708 N40838 49598 N4069 0
496 63N40780 49598 N4069049598 N4069 0 49547N40 620
Acres1.890.110.780.843.363.10
DatesFrom
Grid Location - .
To From ToTrees ~
DatesFrom To
Dan er Tree RemovalsGrid Location
From To TreesDates
From To
Screen TrimminGrid Location
From To
Distribution ForesterTitle
717-831%238 ~
Phone1190-8. Mountain Blvd. Wilkes-Barre PA 18702
Address
/
)
lt
V,
Iq
TABLE. 4. 2-2
SUSQUEHANNA SESMaintenance OfTransmission Line Cooridors
Sheet 2 of 3
1994Year
Selective Reclearin
Sus uehanna-Wescosville 500 KVLine Names
Side To .Trimmin
Northe'astRe 'on
Dates — = Grid LocahonFrom To'rom,, To Acres
7/18/94 '/21/94 59317N27540 59231N27672 11.197/11/94 7/14/94 59390 N27432 59460 N27134 5.867/7/94 7/8/94 59430N27260 59390N27432 3.677/25/94 7/26/94 59317N27540 59547N26740 11.02
Dates 'rid LocationFrom To From To
Trees
DatesFrom To
Dan er Tree RemovalsGrid Location
From To TreesDates
From To
Screen TrimminGrid Location
From To
Distribution Foreste'rTitle
717-831-6238Phone
1190 E. Mountain Blvd. Wilkes-'Bane PA 18702Address
I. I
S\
I
\
t
TABL -2 Sheet
SUSQUEHANNA SESMaintenance OfTransmission Line Cooridors
1994Year
Selective Reclearin
Sus uehanna-Wescosville 500 KVLine Names
Side To Trimmin
~IN 1
.Re ion
DatesFrom To
3/28/94 3/29/944/6/94 4/8/944/18/94 4/19/944/18/94 4/19/94
Grid LocationFrom TQ
60392/S48184 60457/S4796460499/S47819 61188/S5092960587/S46034 60883/S4673961810/S52380 61528/S53013
Acres6.19
9.0811.043.6
Dates='
Grid LocationFrom To From TQ
Tl'ees
Dan er Tree Removals Screen TrimmiriDates
From. ToGrid Location
From To Tl'eesDates
From TQ FromGrid Location
TQ
Distribution ForesterTitle
610-774-3258Phone
P.O. Box 3500 Allentown PAAddress
I 't
I
Il
~
~l
r
.l
5
5.0 ENVIRONMENTALPROTECTION PLAN REPORTINGREQUIREMENTS
5.1 Review and Audit
The Licensee has established procedures for an independent group toreview and audit compliance with the EPP. Audits of EPP compliance areconducted by'Environmental Management Division (EMD) and NuclearAssessment Services. The Auditing Organizational Chart (Fig. 5.1-1) lists
',, the various groups utilized in environmental reviewing and auditing of theSusquehanna SES environmental monitoring programs. The Manager-'Nuclear Technology is responsible for off-site environmental monitoring
.- and.for providing any related support concerning licensing.-'The Vice'President - Nuclear Operations is responsible for on-site environmentalmatters. The Manager-Nuclear Assessment Services with support fromthe Manager-Environmental Management Division of the System Powerand Engineering Department is responsible for verifying compliance withthe EPP. Additional Nuclear Department responsible positions are alsoincluded in Figure 5.1-1.
Audits of the EPP are conducted every other year. There was an audit ofthe EPP in 1993 and the next audit will be conducted in 1995.
5.2 Records Retentionf
Records and logs relative to environmental aspects of plant operation andaudit activities are retained in the Nuclear Records System. This systemprovides for a convenient review and inspection of environmentaldocuments which are available to the NRC upon request.
All records concerning modifications of plant structures, systems andcomponents which are determined to potentially affect the continued,protection of the environment,.shall be retained for the life of the plant.All other records, data, and logs relating to the environmental programs .
and monitoring shall be retained for at least five years or, whereapplicable, in accordance with the requirements of other agencies.
5.3 Chan es in Environmental Protection Plan
There were no requests for changes in the EPP during 1994.
5'-1
5.4 Plant Re ortin Re uir'ements
5:4.1 ~Rt ~ ~5
This Annual Environmental Operating Report (Nonradiological)was prepared to meet routine reporting requirements of the EPP for1994. It provides summaries and analyses of environmentalprotection activities required in Subsection 4.2 of the EPP for thereporting period.
'
5.4.2 Nonroutine Re orts
There were no events in 1994 that required a nonroutine report.5
5
5-2
Figure 5.1-1
AUDITINGORGANIZATIONCHART
General Manager-
POWER SYSTEM
SUPPORT
Sr. Vice President- NUCLEAR
Manager
ENVIRONMENTAL
MANAGEMENT
Manager
NUCLEARASSESSMENT
SERVICES
Vice President
NUCLEAR ENGINEERING
Vice President
NUCLEAR OPERATIONS
Manager
NUCLEAR TECHNOLOGY
Manager
PLANT SERVICES
Key: -----'upport
I
'I
I
'I~
V
IiI
SUSQUEHANNA RIVER
MembersMaryland DeNew York DiPennsylvaniaPennsylvaniaPhiladelphiaSafe Harbor WSusquehanna River Basin CommissionUnited States Fish and WildlifeServiceYork Haven Power Company
ANADROMOUS FISH RESTORATION COtaVW'JWfKTALsMVlKS
Secretarypanment of Natural Resources Susquehanna River Fisheries Coordinatorvision of Fish and Wildlife U.S. Fish and WildlifeServiceFish and Boat Commission 1721 North Front Street. Suite 105Power &Light Company Harrisbur . PA 17102 =
Electric Company Telephone: 7l7-238~6425ater Power Commission FAX: 717-238-0495
September 27, 1994
Jerry Fields,(A9-3)PA Power Ec Light CompanyTwo North Ninth StreetAllentown, PA 18101
Dear Mr. Fields,
During late Aprilthrough ear!y June, 1994, about 32,300 American shad were collected atConowingo Dam and most ofthese were transported to release sites at Middletown andColumbia, PA. Large numbers ofshad were observed in the Juniata River, but I received norecord offish being taken near Sunbury or points further north. Also, with the inflation oftheSunbury fabridam in mid-May, few shad released below Harrisburg would have had time to reachNorth Branch waters before damming.
Considering these limitations, and the likelihood that little spawning could have occurred nearPPAL's Susquehanna SES at Beach Haven, I do not recommend sampling for shad at that site thisfall. Please call ifwe need to discuss this further.
Sincerely,
Richard St. PierreSusquehanna River Coordinator
/I
<hI
r
Ii
II
. III
I/
t
I